Contract & Estimating is a study of construction industry including tender procedure, contract procedure and measurement method.

Discover the best professional documents and content resources in AnyFlip Document Base.
Search
Published by haslizaaa789, 2021-04-15 03:06:09

CONTRACT & ESTIMATING

Contract & Estimating is a study of construction industry including tender procedure, contract procedure and measurement method.

Keywords: construction industry

Lintel- concrete ,steel lintel

steel

Lintel door

WALL

Taking off :
1. Internall wall
2. Externall wall

Internal wall Luar
225/2=113
5
5 Dalam
113/2=57
5

wall

Notes on brickwork:
 Front – 1 brickwork in facing bricks. (225)
 Rear -1 brickwork with common bricks and facing bricks

externally.(225)
 Left & right - 1 brickwork in common bricks(225)
 Internal - ½ brickwork in common bricks(113)

Given:
 D5 – 900mm X 2100mm
 D6 – 750mm X 2100mm
 Air brick = 200 x 200
 Roof beam = 300 x 300mm
 Tebal lintel= 150mm

Calculate wall

1. internal wall
Area of wall
- Minus Lintel door
- Minus door
- Stiffener
2. External wall
Area of wall
- Minus Lintel door
- Minus door
- Minus air bricks
- Column
3. No of air brick
- Calculate total of airbrick

Roof beam

3 113
01200 w16 4Y-10

0 R6-150
0w10

roof beam w10 1200 3
H=300mm w16 0
0
0

1200 1000 1600 1600

D9- 1500 X2100

W10 W11

W2

Taking off list Internal wall

No Item Unit

1. Concrete in stiffener m3

2. Formwork to stiffener m2

3. Reinforcement bars in stiffener m

4. Links in stiffener m

5. Half brickwall in common brick m2
(internal & external) m

6. 113mm wide d.p.m

INTERNAL WALL

300

3000 wall

7200

Wall thickness 225

EXTERNALL 1 2700+1800+2700=7200
WALL 300 +600+1200+900=3000

+

1/ ½ / 225= 113 2
113/2 = 57 3&4

1/ ½ / 225= 113
113/2 = 57

Bil door

- Add
2/113=226

Height/tebal
150

add 33

Height/tebal
150

113

/Dpm m
/Damp prove course(or 12
membrane)

Ambil panjang asal
Refer slip ; 7200-(2x225/2)=6975

wc ; 2700-(225/2)-(113/2)
=2531

BR&lobby ; 3000-(225/2)-(113/2)
15.17 =2831

Taking off list: External

Measure Quantity for External Wall based on drawing below
Taking off list of brick wall – External wall

No Item Unit
1. 1 brickwall in common brick m2
2. 1 brickwall in facing brick m2
3. Air brick no
4. 113mm wide d.p.m m

W10- 1200mm X 1800mm
W11- 600 X 1800
W2- 600 X 1200(tingkap angin)
Airbrick- 1600 X 200(store) , 1200 x 200(store), 1000 x 200(atas pintu)
W16- 600 X600(tingkap angin)
D9- 1500 X2100

Left & right

33

W2 dan w16 xde lintel sbb
tingkap kecil, if nak letak
pun boleh. Dah hampir
dengan roof beam.

airbrick

Rear / back

16.67 16
15.62
Column yang
berada di
tengah

front

Atas
pintu

27

(front) Length 7200

Less Brickwall 225
2 x 225/2 6975

Di tengah2
(rear)



Bilangan 2
2



CHAPTER 7(5) :
THE QUANTITY MEASUREMENT

Finishing works ITEM
- The end of - Floor
construction activity - wall
- Ceiling
function

- ……………………….
- ……………………….
- ……………………….
- ……………………….
- ……………………….

Parket

Tiles

INTRODUCTION

 Finishing is to apply decoration to the
internal or external perimeter of rooms and
spaces such as wall, floor, and ceilings.

 It is running at the end of construction
activity and it needs a good skill in doing
this job to make sure it is in a good
performance.

 Building finishes including internal and
external finishes and consists of ceiling
finishes, wall finishes and floor finishes.

INTRODUCTION

 Function of building finishes is:

➢ To reduce the amount of light penetration
➢ For decoration and nice arrangement.
➢ To provide a flat and smooth surface
➢ To protect slab and concrete
➢ To make sure the construction building is high in

quality.

FLOOR FINISHES

 Floor finishes are provide to improve the appearance,
cleanliness, noiselessness and damp proofing of the floors.

 There are various types of materials used for floor finishes such
as cement render, tile, marble, mosaic, painting and many more.

 All types of floor finishes are measured in square meter and an
area that is measured is in contact with the base (S.2.2).

 Area is measured between the face of the wall and including the
width of the bottom of the door finishes (S.1.8) as shown in the
figure below.

finishing at the bottom of the door are wall
included in floor finishes

 Finishes at drop, between two different floor levels as
shown below, is measured separately. It measured the same as
finishes the curb and fillets, in linear meters and height stated.

Floor level

Finishes at the drop is
measured separately

SCREEDING

 Screeding by definition means the proper leveling of the
materials that are placed on the floors or even on the walls in
any type of construction work which may include plastering or
even concrete work.

 Every material used in creating the wall or the floors require a
proper leveling to reflect the beauty of the design and the
material.

 Floor screeding has various types of which the most commonly
used is cement and sand screed or concrete screed.

 Screeded layer has a very rough surface, is made by scratching
the surface of the plaster layer to create a grip on
finishes installed on it.

 This underlay is suitable or in situ finishes or hard finishes that
is installed using mortar.

 Floated layer was prepared with wood trowel and has rough
surface, suitable for hard finishes fitted with adhesive. While
trowelled layer was prepared with steel

cement and sand screed or concrete screed.
- rough surface

Example calculation
Quantity measurement for floor finishes

Measure quantity of floor finishes based on drawing below.

A BC Given: Thick of brick wall = 225mm
8000 7000 Length door, D1 = 1000mm
Length drop, DP2 = 1500
Thick of beds & backing= 19mm
Drop = 100mm high
Skirting = 80mm high

1

6500 D1 Living 2
(carpet)

DP2 Dining Room 6500
(ceramic)

2

D1 a

3

Taking-off list Unit
m2
No Item m2
1 Screed to carpet m2
2 Carpet m2
3 Screed to ceramic tiles m
4 Ceramic tiles m
5 Screed to Drop m
6 Ceramic tiles to drop m
7 Screed to ceramic skirting
8 Ceramic skirting

Finishing:
Living room - Carpet
Dinning room - Ceramic tiles

Drawing No. Bill No. Element: Slip No.:
Floor Finishes 1

Heading Unit
Screed to carpet m2
Description Quantity
19mm thick c&s (1:3) floated bed to receive carpet to floor level
49 50
Living

7.78 Living
6.28
Length Width
48.86 8000 6500

Less bwl 225 225
2 / ½ / 225 7775 6275

1.00 Finishes under door, D1
0.23
Length Width
0.23
1000 225
1.50
0.23 0.35 DP2

49.44 Length Width

1500 225

Drawing No. Bill No. Element: Slip No.:
Floor Finishes 2

Heading Unit
m2
Carpet Quantity
Description
Approved rubber underlay fitted with adhesive to floor level on floated bed. 49 50

Living Width
6500
7.78 Living
6.28 Length 225
8000 6275
48.86
Less bwl 225
2 / ½ / 225 7775

1.00 Finishes under door, D1
0.23 0.23
Length Width
1.50
0.23 0.35 1000 225

49.44 DP2

Length Width

1500 225

Dining area

Screed
Tiles
Screed to drop
Tiles to drop
Screed to skirting
Tiles to skirting

43

Ceramic tile

43

screed 42.8
19mm thick c&s…….to receive ceramic tiles



2 side
DP 2



CEILING FINISHES

 Type of ceiling finishes :
asbestos cement, gypsum board, plaster ceiling

and painting.
 Ceilings are taken from wall to wall for each room
 measured in square meters

gypsum board
ceiling

Asbestos
cement fiber

plaster ceiling



An approved 1200mmX600mm thick asbestos-free ceiling sheet out symmetrically from 98
center of the room area fixed to timber framing

6.5 Living
8.0

52

7.0 dining
6.5

45.5
97.5

EXERCISE

Based from plan given, calculate quantity measurement for Internal Floor Finishes for kitchen, W/C, dining and
living. Quantity measurement is including backing screeded, floor finishes, dividing strip, skirting and drop.

4500 2000 Note:
•Toilet and kitchen – 150mm x 150mm ceramic tile
4500 Kitchen W/C 1500 2000 2000 •Dining and living – broken marble
2500 •Bedroom – 150mm x 150mm parket
3500 Dining D1 W/C •Utility – cement render
D1 •19mm thick screeded bed to receive floor finishing
Living D1 •19mm thick cement render
Utility •12mm thick screeded bed to receive floor skirting
D2 •DP50 – drop 50mm high, 800mm width
Bedroom 3500 •D1 – 600mm x 2400mm
6000 •D2 – 1200mm x 2400mm
D1 •Stairs – 2000mm x 800mm
•Brickwall – 113mm

3500

Dividing strip

Strip wood to tile

THE END