Ground slab
Earthwork
1. Site clearance
- Removing trees(unit:no)
- Removing hedges( unit: m)
- Clearing undergrowth/shrubs(unit:m2)
- Tree stumps(unit:no)
- Lifting turf(m2)
- Top soil(unit:m2)
2. Cut & fill
Clearing undergrowth/shrubs
Tree stump
Lifting turf Removing hedges
Top soil
Removing hedges
20000 • example:
• total length = 20 + 20
•
= 40.0 m
20000
Excavating top soil
- The depth of top soil removed is 150mm to 300mm
- The unit of top soil excavation is square meter(m2)
Excavating top soil
A
B
solution
DRWG NO. BILL NO. ELEMENT : SLIP NO : 1
Work Below Lower Floor Finish UNIT
m2
HEADING QUANTITY
Excavation top soil
DESCRIPTION
Excavation top soil for preservn. Avg. 150mm deep
15.00 Excavation top soil commencing from ground
15.00 level not exceeding 1.50m depth,
5.00 A]
12.00
225
B] 20 000-15 000 = 5000
60
Cut and fill
Cutting and filling
i. Square method
ii. Triangle method
Question: refer grid given calculate cutting and filling
1. Formation level is 4m
2. Top soil is 150mm
Cutting and filling: Square Method
60m
A 8.52 B 8.73 C 7.69 D 8.67 E 8.67
F 5.32 G 7.98 H 7.50 I 5.78 J 7.98
O 9.23
30m
K 8.56 L 7.75 M 6.89 N 7.78
P 6.95 Q 7.29 R 4.90 S 7.70 T 5.75
Nilai ketinggian adalah aras laras sebenar yang dikira dalam ukur aras
Cut and fill Top soil
00..1155m
GL= 8.52m 4.40.m0
Depth = 8.52- 0.15- 4.0 = + 4.37m Formation level
Formation level means the final earthwork
level after cutting or filling.
solution
Ground Reduce Formation Depth (A) Weighting (B) Weighting depth Weighting depth
Level level Level AxB AxB
Location Top soil Cutting Filling No of square (Cut) (Fill)
8.52 8.37 4.00 (+) (-)
A 8.73 0.15 8.58 4.00 1 4.37
B 7.69 0.15 7.54 4.00 4.37 2 9.16
C 8.67 0.15 8.52 4.00 2 7.08
D 8.67 0.15 8.52 4.00 4.58 2 9.04
E 7.98 0.15 7.83 4.00 1 4.52
F 7.98 0.15 7.83 4.00 3.54 2 7.66
G 7.50 0.15 7.35 4.00 4 15.32
H 5.78 0.15 5.63 4.00 4.52 4 13.4
I 7.98 0.15 7.83 4.00 4 6.52
J 8.56 0.15 8.41 4.00 4.52 2 7.66
K 7.75 0.15 7.6 4.00 2 7.7
L 6.89 0.15 6.74 4.00 3.83 4 15
M 0.15 7.63 4 10.95
N 7.78 0.15 9.08 4.00 3.83 4
O 0.15 6.8 3.35 2 14.52
P 9.23 0.15 7.14 4.00 1.63 1
Q 6.95 0.15 4.75 4.00 2 10.16
R 7.29 0.15 7.55 4.00 3.83 2 2.8
S 4.90 0.15 5.6 4.00 2 6.28
T 7.70 0.15 4.00 3.85 1 1.5
5.75 4.00 48 7.1
3.75 1.6
162.34
2.74
3.63
5.08
2.8
3.14
0.75
3.55
1.6
TOTAL
AVERAGE
VOLUME OF SOIL
Calculation:
Average height = total weighting depth
total weighting
= 162.34/ 48
= 3.38
Volume of soil = area x average of height
= (60x 30) x 3.38
= 6087m3
Cutting and filling: triangle method
60m
A 8.52 B 8.73 C 7.69 D 8.67 E 8.67
F 5.32 G 7.98 H 7.50 I 5.78 J 7.98
O 9.23
30m
K 8.56 L 7.75 M 6.89 N 7.78
P 6.95 Q 7.29 R 4.90 S 7.70 T 5.75
solution
Ground Reduce Formation Depth (A) Weighting (B) Weighting depth Weighting depth
Level level Level AxB AxB
Location Top soil Cutting Filling No of triangle (Cut) (Fill)
8.52 8.37 4.00 (+) (-)
A 0.15 2 8.74
8.73 0.15 8.58 4.00 4.37
B 3 13.74
7.69 0.15 7.54 4.00 4.58 10.62
C 8.67 0.15 8.52 4.00 3 13.56
D 8.67 0.15 8.52 4.00 3.54 3 4.52
E 7.98 0.15 7.83 4.00 4.52 1 11.49
F 7.98 0.15 7.83 4.00 4.52 3 22.98
G 7.50 0.15 7.35 4.00 3.83 6 20.1
H 5.78 0.15 5.63 4.00 3.83 6 9.78
I 7.98 0.15 7.83 4.00 3.35 6 11.49
J 8.56 0.15 8.41 4.00 1.63 3 11.55
K 7.75 0.15 7.6 4.00 3.83 3 22.5
L 6.89 0.15 6.74 4.00 3.85 6 16.44
M 7.78 0.15 7.63 4.00 3.75 6
N 9.23 0.15 9.08 4.00 2.74 6 21.78
O 6.95 0.15 6.8 4.00 3 15.24
P 7.29 0.15 7.14 4.00 3.63 1
Q 4.90 0.15 4.75 4.00 3 2.8
R 7.70 0.15 7.55 4.00 5.08 3 9.42
S 5.75 0.15 5.6 4.00 2.8 3 2.25
T 3.14 2 10.65
0.75 72 3.2
3.55
1.6 242.85
TOTAL
AVERAGE
VOLUME OF SOIL
Calculation:
Average height = total weighting depth
total weighting
= 242.885/ 72
=3.37
Volume of soil = area x average of height
= (60x 30) x 3.37
= 6071m3
Exercise 1
100mm
4.8m
Exercise 2
180mm
5m
Exercise 3
According to the figure, estimate the quantity of
earthwork to be cut and filled using the triangle
method.
Data given:
1. Interval is 10 m
2. Formation level is 4m
3. Top soil is 150mm
exercise 150.35 151.20
148.52 150.5
150 151.50
151 151.2
151.4 149.2 149.62 15085
151.75 148.25 147.52 150.3
151.95 147.85 148.50 150.82
Answer
1. Average height
……………………………….
Volume of soil
(40x30)x ……………= ………………..m3
2. Average height
………………………………..
volume of soil
(40x30)x ………………….=…………………….m3
Piling Work Deep foundation
- Piling is a type of ground treatment which is
driving a pile into the ground below ground level
- It’s used to strengthen the soil so that the ground
able to support the load of the building
- Shallow foundations are defined as those where the depths are less than 3 m below the
finished ground level
- Deep foundations are defined as those where the depths are more than 3 m below
the finished ground level.
Pile
Types of piles
- Pre-Cast Reinforced Concrete Piles
- Cast Insitu Reinforced Concrete Piles
- Timber pile
- Steel pile
Ground level Column
Pile cap
pile
pile
Types of pile
Pre-Cast Reinforced Concrete Piles
Cast In situ Reinforced Concrete Piles
Timber pile Types of pile
steel pile
steel pile
Extension
Point
-Number of holes in the pile cap
1 hole 2 holes 4 holes
Refer standard method of measurement (smm)
SECTION E : PILING
E.5 piling description and mesurement
.
Question:
Based on drawing PSAS/JKA/PILING/01;
a) Prepare taking off list
b) Schedule of pile cap
c) Calculate quantity all the piling works.
Berdasarkan lukisan PSAS/JKA/PILING/01;
a) Sediakan senarai pengukuran kuantiti
b) Jadual cerucuk
c) Kirakan kuantiti bagi semua kerja-kerja cerucuk
Example: taking off pile
PSAS/JKA/PILING/01
Figure: Point of pile
Data
NOTES:
All pile is precast reinforced concrete pile
All pile should be in 300mm diameter
Supply length of pile shall be:
Starter pile: 6.00 m long
Extension pile: 6.00 m long
Estimated penetration depth is 35 meter
Working load: 30 tones per pile
The test load to twice working load shall be maintained for
48 hours.
Legend:
P1 – pile cap with 1 point
P2 – pile cap with 2 point
P3 – pile cap with 3 point
solution
i. Taking off list
ii. Schedule of pile cap
iii. Mobilization of piling plant (unit:item)
iv. Initial piles(unit:No)
v. Driven depth (unit: m)
vi. Pile extension(unit:No)
vii. Pile extension exceed x.00 m long (unit :m)
viii. Jointing of piles (unit:No)
ix. Cut of piles(unit:No)
x. Testing of piles(item)
Taking off list
DRAWING NO BILL NO ELEMENT SLIP NO
HEADING
DESCRIPTION UNIT
QUANTITY
Answer for question (a)
TAKING OFF LIST:
1. Mobilisation of piling plant – item
2. Initial pile – no
3. Driven depth – m
4. Pile extention – no
5. Pile extention exceed 3.00 meter long – m
6. Jointing of pile – no
7. Cutting of top pile and prepare for pile head – no
8. Testing of pile – item
(4 marks)
Answer for question (b)
Schedule of pile cap:
(4 marks)
Location Type of pile cap
A/ 1 – 5 P1 P2 P3
B/1–5 1
C/1–5 2
D/1–5 1
TOTAL 2 3
21
2
55
Example: taking off pile
PSAS/JKA/PILING/01
Figure: Point of pile
i. Mobilization of piling plant
DRAWING NO BILL NO ELEMENT SLIP NO
PSAS/CC301/JULY 1 mark PILING 1
2011/PILING
HEADING
Mobilisation of piling plant
DESCRIPTION UNIT
Item
Bringing in and removing from site all plant required for this section 1 mark
of work
& 1 mark QUANTITY
Maintaining on site all plant ditto.
Item 1 mark
Item
Item P1,p2,& p3
1 mark
(total 5 marks)
ii. Initial pile
DRAWING NO BILL NO ELEMENT SLIP NO
PSAS/CC301/JULY PILING 2
2011/PILING
1 mark
HEADING
Initial pile
DESCRIPTION UNIT
Supply, deliver and unload on site 6.00 meter long with 300mm No 1 mark
diameter initial precast reinforced concrete pile.
QUANTITY
1 mark 27 1 mark
1/ 2 P1
2
2 P2
5
10
3 P3
5
Point of pile – 15 (total 7 marks)
27
(Refer Total pile
legend:p1,p2,p3) 3 marks initial
Total types of pile/pile cap
(schedule of pile cap)
iii. Driven depth
DRAWING NO BILL NO ELEMENT SLIP NO
PSAS/CC301/JULY 2011/PILING PILING 3
HEADING 1 mark UNIT
Driven depth m 1 mark
QUANTITY
DESCRIPTION 945 1 mark
Driven only vertical 300mm diameter precast reinforced concrete pile
Penetration 1 mark
depth
1/ 2 P1
35.00
70.00
2 35.00 P2
5
350.00
3 P3
5 525.00
945.00
35.00 (total 7
3 marks marks)
Total driven
iv. Pile extension (no of pile)
DRAWING NO BILL NO ELEMENT SLIP NO
PSAS/CC301/JULY 1 mark PILING 4
2011/PILING
HEADING
Pile extention
DESCRIPTION UNIT
Supply, deliver and unload on site 6.00m long with 300mm diameter
extension precast reinforced concrete pile. No 1 mark
1 mark QUANTITY
135 1 mark
1/ 2 P1 5 6m
4 6m
5 3 6m Bil ext pile
10
P2
2
5
5
50
P3
Bil extention pile=5 2 6m (total 7 marks)
3 5 1 6m Note:
5 75 6m penetration = 35 m
Initial pile Length =6 m
Bil ext pile 135
36 m- 35m =1 m(cut)
3 marks
Total ext pile
v. Extension of pile exceed 6m long
DRAWING NO BILL NO ELEMENT SLIP NO
PSAS/CC301/JULY 2011/PILING PILING 5
HEADING 1 mark
Extention of pile exceed 3.00 m long
DESCRIPTION UNIT
Total length of pile extension for pile length exceeds 3.00 meters long.
m 1 mark
1 mark
QUANTITY
810 1 mark
1/ 2 6.00 60.00 P1 point Bil ext
6.00 300.00 P2
5 P3 2/5/5
2 Bil pile cap
5
5
3 (total 7
5 marks)
5
6.00
450.00
Bil ext of pile Length of 810.00 Total ext of pile
pile
3 marks
vi. Jointing of pile
DRAWING NO BILL NO ELEMENT SLIP NO
PSAS/CC301/JULY 1 mark PILING 6
2011/PILING
HEADING 1 mark UNIT
Jointing of pile
No 1 mark
DESCRIPTION
Total no of jointing of pile
QUANTITY
135 1 mark
1/ 2 P1
5
10
P2 Jointing=5
2 (total 7 marks)
5
5
50 P3
3 75
5
135
5
3marks
Jointing=bil extention
vii. Cutting of top pile and prepare for pile head
DRAWING NO BILL NO ELEMENT SLIP NO
PILING 7
PSAS/CC301/JULY
1 mark
2011/PILING
HEADING
Cutting of top pile and prepare for pile head
DESCRIPTION UNIT
Total no cutting of top pile and prepare pile head for pile capping
No 1 mark
QUANTITY
1 mark 27 1 mark
1 2 21 P1
22 2
5 51 P2
33
55 10 P3
15
1 (total 7 marks)
point Total Pile 27
3 marks
viii. Testing of
pile
DRAWING NO BILL NO ELEMENT SLIP NO
PSAS/CC301/JULY 1 mark PILING 8
2011/PILING
HEADING
Testing of pile
DESCRIPTION UNIT 1 mark
Item
60Allow 2 no. testing on a single and group pile to a total load of 140
QUANTITY
tonnes
Item
1 mark
1 mark
Ite P1 , P2 and P3
m
1 mark
(total 5 marks)
2 x 30(working load)= 60
Total marks:
= 52/52 x 22
= 22 marks
exercise
12 3 4
P3
A P3 P2 P2 P2
B P2 P1 P1 P3
C P3 P1 P1
D P4 P4
Figure 1: Point of pille
Refer to the data and figure 1 given prepare taking off list, schedule of pile cap and calculate quantity all the
piling works.
ITEM DESCRIPTION
TYPE OF PILE REINFORCED CONCRETE PILE 200X200MM
DRIVEN 28 m
DEPTH/penetration
WORKING LOAD 25 TONNES
THE TEST LOAD TO TWICE WORKING LOAD SHALL BE MAINTAINED FOR 48 HOURS
STATERS PILES/initial 3.00 m LONG
EXTENTION PILES 5m LONG
LEGEND P1- 1 PILE POINT
P2- 2 PILE POINT
P3- 3 PILE POINT
P4- 4 PILE POINT
Refer to the data and figure 1 given prepare taking off list, schedule of pile cap and calculate quantity all the
piling works.
ITEM DESCRIPTION
TYPE OF PILE REINFORCED CONCRETE PILE 200X200MM
DRIVEN DEPTH 23 m
WORKING LOAD 25 TONNES
STATERS PILES THE TEST LOAD TO TWICE WORKING LOAD SHALL BE MAINTAINED FOR 48 HOURS
3.00 m LONG
EXTENTION PILES 3m LONG AND 6 m LONG
LEGEND P1- 1 PILE POINT
P2- 2 PILE POINT
P3- 3 PILE POINT
P4- 4 PILE POINT
Solution :Perlu ada 2 form untuk
1. Extension of pile exceed 3m long and 6m ……………..unit m
2. Pile extension 3 m and 6 m ………………….unit NO
Pile foundation
Pile foundation
CHAPTER 7(2) :
THE QUANTITY MEASUREMENT