Contractor and supplier
Main contractor
Sub contractor
Domestic sub contractor
Nominated sub contractor
Nominated supplier
STRUKTUR ORGANISASI DALAM TENDER
KONVENSIONAL
Klien
Pasukan Perunding
⚫Arkitek
⚫ Jurutera Awam & Struktur
⚫Jurutera Mekanikal &
Elektrikal
⚫ Juruukur Bahan
Kontraktor Utama
Menggunakan khidmat perunding
Atau kendalian jabatan
STRUKTUR ORGANISASI DALAM TENDER REKA
DAN BINA (DESIGN AND BUILD)
Klien
Kontraktor Utama
Pasukan Perunding
⚫Arkitek
⚫ Jurutera Awam & Struktur
⚫Jurutera Mekanikal &
Elektrikal
⚫ Juruukur Bahan
Kontraktor bertanggungjawab untuk mengemukakan harga tawaran di dalam dokumen pre bidding berdasarkan kepada
kehendak penyata klien tersebut serta akan menyediakan rekabentuk dan mengawasi kerja sehingga projek siap.
Main contractor
- An individual that signs a contract to perform a part or
all of the obligations.
- Direct contractual relationship between the client.
- Obligation : refer to Standard Form Of Contract
Public Work Department (PWD) 203 ( Revision 2007)
Definition of Subcontractor
A subcontractor is an individual that signs a
contract to perform a part of the obligations of
another's contract.
Domestic Sub –contractor
A subcontractor is hired by a general contractor (or
prime contractor, or main contractor) to perform a
specific task as part of the overall project.
Payment by the main contractor
Types of domestic subcontractor :
i. Material – supply goods(nominated supplier)
ii. Labour - skilled, semi-skilled and unskilled
Nominated Sub-contractor
Direct contractual relationship between the client.
Payment by the owner
Special work- Pile work, electrical work, water supply,
air condition work, fire prevention and others.
Payment by the owner
Nominated Supplier
Appointed by owner to supply material and
construction item to main contractor for the
project.
Contract with main contractor
Payment by the main contractor
exercises
Explain the Contract principles are made according to
Contract Act 1950 (Amendments 1974)
Explain the Relationship between Contract and
Tender
Explain briefly the types of contract.
State the differences between Domestic Sub contractor
and Nominated Sub Contractor
State the reason of nominated supplier appointed.
State the purpose of standard forms
CHAPTER 4 :
THE STANDARD CONDITION OF
CONTRACT
(refer to the standard form of contract)
Standard form of contract
Document or form containing the
terms and conditions of the
contract.
Purpose:
- To provide basic legal framework
- The legal relationship between
the parties
Standard Forms of contract
(government/public sector)
JKR form 2003
Two types of standard form of contract which are usually
used for contract works in public work department.
i. Standard Form Of Contract Public Work Department
(PWD) 203 ( Revision 2010) (Based on DRAWING
AND SPESIFICATION)-Projek segera,x sempat
sediakan BQ
ii. Standard Form of Contract Public Work
Department(PWD) 203A ( Revision 2010) (Based on
BILLS OF QUANTITIES)- Projek2 besar
Private sector
PAM(Pertubuhan Arkitek Malaysia)
IEM(Institution of engineers Malaysia)
Standard Form of Contract
Purpose of standard forms
To provide basic legal framework evidencing the legal
relationship between the parties.
To put in place the administrative procedure to effect the
legal and commercial relationship between the parties for
achieving the purposes of the contract
To establish the ambit of the powers and duties of contract
administration under the contract between parties.
To furnish mechanism for regulating the conduct of
commercial relationship between parties.
CONTENT
Clause 1 : Definition.
Clause 2: Contract period.
Clause 3 : The S.O and S.O representative.
Clause 4: S.O’s Right To Take Action
Clause 5: S.O instruction.
Clause 10: Obligation Of the contractor.
Clause:14,15,16,21,23,28,35,40,44,51,53,79….
…………………..81
Clause 1: Definition
Contract Documents:
- Means the documents forming the tender including:
1. Form of Tender;
2. Letter of Acceptance of Tender;
3. Contract Drawings;
4. Bill of Quantities and others
Continue Clause 1: Definition
"S.O.“ : The Superintending Officer
"S.O.'s Representatives“ : Any person or persons
delegated in writing by the S.O.
"Works“ : The works specified in the Contract
Documents and shall include temporary works.
Site: ………………………………………………………….
Contractor: ………………………………………………...
Defect liability period:……………………………………….
Clause 2.0: Contract period
Start finish
Contract period
Clause 3: S.O. and S.O.'S Representative
S.O
Responsible for the overall supervision and
direction of the Works
S.O.'s Representative
Responsible to the S.O
Watch and supervise the Works and to test
and examine any materials or goods
Continue clause 3:
S.O.'s Authority to Delegate
From time to time in writing delegate to the
S.O.'s Representative
If the Contractor is not satisfied with any
decision of the S.O.'s Representative, the
Contractor shall refer the matter to the S.O
Clause 5: S.O Instructions
Refer to the drawings, details and/or written instructions
in regard to:
- Variation refer to clause 24
- Any discrepancy in or between the Contract
Documents as referred to in clause 8.2(b)
- The removal from the Site of any materials
or goods
Continue Clause 5:
- The removal and/or re-execution of any
works executed by the Contractor
- Opening up for inspection of any work
covered up
Instructions procedure
All instructions issued by the S.O. shall be in writing.
If such instruction is given orally, the S.O. shall then issue a
written instruction within seven (7) days from the date of
such oral instruction is given.
If within seven (7) days after receipt of a written notice
from the S.O , the Contractor does not comply, the S.O.
without prejudice to :
1. undertake the work
2. pay another Contractor to continue the work
3. The cost will be deduct from any money( performance
bond)
4. The Contractor shall be responsible for all costs of work
under clause 5.3
Clause 9: Representations, Warranties, and
Undertaking of the contractor.
Clause 9: Perwakilan, Jaminan,Akujanji kontraktor.
The Contractor represents and warrants to the
Government that:
1. Corporation validly existing under the laws of Malaysia
2. The Contractor has obtained a valid registration with the
Construction Industry Development Board
3. Perform its obligations under this Contract
4. It has necessary financial and technical capability to undertake the
Works
Contractor undertakes :
1. Comply all requirement
2. Pay all taxes
3. Ensure all employees comply with all law
Clause 10: Obligations of the contractor
The Contractor shall:
Construct, complete, test and commission the Works in
accordance with the Contract
Perform the Works with good management practice
and to the best advantage of the Government;
Ensure that the Works comply with the requirements of
this Contract
Perform the Works by exercising professional judgment
and practice, requisite skill, care and diligence.
Continue clause 10
At all times perform the Works in such manner. as will
always safeguard and protect the Government's
interest
Inform the Government immediately in writing of the
occurrence of any factor or event, which is likely to
affect the Works.
Provide and maintain throughout the Contract Period
, categories of qualified and competent personnel
necessary to perform the Works;
Continue Clause 10
Provide and maintain at its own cost and expense all
equipment and materials necessary for the proper and
effective performance of the Works;
instruct and supervise its staffs and sub-contractor in
carrying out the Works' repairs and other works in
relation to the Works;
make good any defect, imperfection, shrinkage or any
other fault whatsoever which may appear during the
Defects Liability Period
carry out any other obligations and responsibilities
under this Contract.
Exercise
1.With your own group.....
Refer to the Standard Form of Contract P.W.D
(Rev.2007), clause 5
provide mind map of instructions procedure…
2. Individual
- Discuss clearly responsibility of S.O.'s Representative
- The…………shall be responsible for the overall supervision and
direction of the works.
- To perform a good work and protect the Government's
interest , what should contractor do……………………...refer to
standard form of contract P.W.D(Rev.2007)
- Explain clearly contractor obligation
Refer to Clause 1 Standard Form of Contract P.W.D (Rev.
2007), Restate the terms below;
Contractor
Contract document
Site
S.O Representatives
Work
CHAPTER 5 :
PRELIMINARY
ESTIMATING METHODS
DEFINITION
Preliminary estimation is to estimate the cost of
project.
An estimate is a calculation of the quantities of
various items of work.
The estimation is done based on drawings and
technical information.
Preliminary Estimation is usually done after an
architect’s drawing is completed.
Purpose Of Preliminary Estimation
o To obtain the clients budget.
o Contractors tendering project.
o To know the profit rate.
o Quotation from subcontractor to general
contractor.
o To know the percentage and types of
building elements.
The Method Of Preliminary Estimation
Unit Valuation Method
Floor Area Method
Cubic Content Method
Unit Valuation Method
Estimate : Students, patients, beds and
others
= Standard Units X Cost/Unit
existing prices
Example 1
The construction cost of the existing school which
was completed two years ago is RM 100,000.00 and
can accommodate 100 students. Estimate the cost of
new school which can accommodate 200 students.
SOLUTION
Cost of a completed school building = RM 100,000.00
accommodate = 100 students
Therefore,
cost per unit (students) = RM 100,000.00 / 100
= RM 1, 000.00/student
Therefore, = 200 x RM 1, 000.00
estimated new cost = RM 200,000.00
EXAMPLE 2
Refer to the table below, calculate the cost of new
hostel which can accommodate 3000 students.
Given the factor of cost increment is 20%.
Type Construction Number of
Costs (RM) students
Hostel A 3,000,000.00
Hostel B 1700
2,500,000.00
1500
SOLUTION
Cost per unit (Hostel A) = 3000000 / 1700 = RM 1764.71
Cost per unit (Hostel B) = 2500000/ 1500 = RM 1666.67
Average cost per unit = RM 1764.71+RM 1666.67 =RM 1715.69
2
Increment of 20% = RM 1715.69 x 20/100
= RM 343.14
Total cost per unit = RM 1715.69 + RM 343.14 = RM 2058.83
New hostel cost = RM 2058.83x 3000
= RM 6176490.00
Floor Area Method
formula
Estimate :
= floor area X price/meter2
Area = length X width
Garage or porch = ½ ( length X width)
Floor Area Method
Refer to the diagram below, calculate the cost of the building
using the Floor Area Method. Assume cost rates as RM250.00/ m
2.
10.0m
25.0m
SOLUTION
Building Area = Length x width
= 25.0 m x 10.00m
= 250.00 m2
Building Cost = Floor Area x price rate / sq meter
= 250.00 x RM 250.00
= RM 62 500.00
example
Base on the diagram below, calculate the
cost of the building, assume cost rate as Rm
350m2
8.2 m
Room 1 Living area 3.2 m
4.5 m
5.2 m
Room 2 garaj
Garaj
5m
solution
8.2 m
y 3.2 m
Room 1 X
5.2 m Garage 4.5 m
Room 2
5m
garaj
solution
Area 1
Room 1,room 2 & X area = 5 x 5.2
= 26 m
Area 2
Y area = ( 8.2-5)x 3.2m
= 10.24 m
Area 3
Garage area = ½ (4.5 x 3.2)
= 7.2 m
cost
Building cost = floor area x price rate
= (26 + 10.24 +7.2) x rm 250.00
= 43.44 x rm 250.00
= Rm 10 860.00
Cubic content method
Estimate = Volume x unit cost (cost/m3)
Volume= length x width x height
However, the height of the building depends on the types of roof which is:
i. Flat roof
ii. Pitched roof
Types of Roof ii. Pitched roof
i. Flat roof