Flat roof
Roof with less than 10 0 pitch is categorized as flat roof
Two types of flat roof which is :
1. Fully flat roof
2. Flat roof with parapet walls
Parapet wall
Concept of height FLAT ROOF
FULLY FLAT ROOF
T= 0.6m
Building height = H + 0.6m
H
T= Height of parapet wall
Building height = H+ T
H
If parapet wall < 600mm
❖Height = H + 0.6 m
If parapet wall > 600mm
❖Height = H + T(parapet height)
PITCHED ROOF
PITCHED ROOF
Roof with more than 10 0 pitch is categorized as pitched roof
FORMULA
Building height= H + T/2
Roof height = T
H
Ground
level
Example 1
Refer to the data below, calculate the cost of the building using the
Cubic Content Method. Assume cost rates as RM100.00/ m3
Building Length, L = 45.00 m
Building Width, W = 15.00 m
Building Height, H = 20.00 m
Solution:
Building Volume = LxWxH
= = 45.00 x 15.00 x 20.00
13, 500 m3
Building Cost = Building Volume x price rate / meter
= 13, 500 m3 x RM 100.00 /m3
= RM 1,350,000.00
Example 2
Refer to the figure, calculate the Rear view
cost of the building using the
Cubic Content Method.
Assume cost rates as RM350.00/
m3
1500
Plan view
solution 9.5-6.5-2.5= 0.5
0.5 +6.5 = 7m
Flat roof volume area
= 7.00 x 4.50 x (9.5 + 0.60)
=7.00 x 4.50 x 10.10
=318.15 m3
Pitch roof volume area
=4.00 x 1.50 x (7.00 + 2.50/2)
=4.00 x 1.50 x 8.25
=49.00 m3
Building Cost =(318.15 + 49.00) x RM 350.00
=367.65 x RM 350.00
=RM 128, 677. 50
EXERCISE
Exercise 1
Calculate the cost of new school building which
accommodate 4000 students. Given the factor of
cost increment is 15%.
Type Construction Costs (RM) Number of
students
School A 4,000,000.00
1500
School B 5,000,000.00
2100
School C 6,500,000.00
2800
Exercise 2
Base on diagram below, calculate the cost of the
building, assume cost rate as Rm 350/m2
18 m garaj
ANSWER: RM 52500
Room 2 Room 1
10 m
Area 3
12 m
Exercise 3 600
7500
Base on diagram below, calculate the cost of the building, assume cost rate as Rm 300/m3
800
8600
REAR VIEW
20 m
wc Room 2 wc
Room 3
13 m
Area 2
Room 1 Area 1
15 m
PLAN VIEW
ANSWER: RM 688350.00
Exercise 4
A= RM 1932.22 B= RM 3 956 470.00
ANSWER: RM 50 352.00
Section A Final exam question
1. List four types of engineering work in construction industry
2. Name four types of head system based on the scope of work in construction
3. List and briefly explain three main catergories of contractors
4. List four importance of organization chart in contractor firm
5. State two duties of Contractor Service Centre
6. Identify two diferences between Domectic and nominated sub-contractor
7. Explian two activities related to construction
8. State two types of work which are involved in the construction industry
9. State two roles of CIDB
10.Complete the table below regarding Garade and Tendering capasity by CIDB
grade Tendering capasity
G1 RM
Section B
1. Explian the role of each member of builder team as listed below
i. Contractors
ii. Architects
iii. Civiland Structural Engineer/electrical and Mechanical Engineer
iv.Quantity Surveyor
2. Explian seven activities involved in construction
3. Explian the role of CIDB
4. Identify the roles of each member in design team and builder team members.
5. Describe the relationship between consturction industry and economic growth.
CHAPTER 6 :
BUIL-UP RATE METHOD
What is rate
Price per unit of measurement
Example:
Price rate for 1 m3
RM 4.14/ m3 unit of
measurement
It is the list of rates of various items
of work.
The schedule is prepared by the
Public Work Department / JKR.
The purposes Of The Built-Up Rate Methods
Know the financial allocation employer.
Know the suitability design based on limit
allocation.
As information and record for reference and
estimate projects for the future.
Types of built up work
1. Excavation work(manual & machine)
2. Concreting work(manual & machine)
3. Brick work
4. Reinforcement work
Types Of Cost
Material cost
Labour cost
Plant and equipment costs
Overhead cost and Profit
1.0 Material Cost
- Material cost such a brick, roof, tile, glass, iron, cement
and sand.
- Estimated price depends on:
i. The original cost of the material
ii. Transportation cost
iii. Storage cost
iv. Wastage cost
2.0 Labour Cost
Labour cost is a fee or wages to the workers after
work has been completed. In the construction
industry, workers are divided into two classes:
i. Skilled worker
Workers who are skilled in their own field such as bar
bender, carpenter and bricklayer.
ii. General worker
Workers who carry out general work such as transporting
dumping and clearing of site.
Types of labour
Craftsman
Carpenter, blacksmith, bricklayer, craftsman plaster,
plumber and others
Semi-skilled Labour
Craftsman’s assistant
Labourer
Craftsman or semi-skilled labour assistant
Head
Somebody which lead a group of craftsman, semi-
skilled labour and labourer.
3.0 Plant and equipment costs
Contractor can purchase or hire plant and equipment as
follows;
i. Non-machinery plant and equipment such as scaffolding,
ladder, wheelbarrow, pails and others.
ii. Machinery plant and equipment such as lorry, bulldozer,
concrete mixer, concrete vibrator equipment and others.
4.0 Overhead/operating cost and profit
Overhead cost and profit:
Percentage of materials, labour, plant and equipment
costs and others.
Include management/operation cost:
Electricity, water and telephone bills related to office and
workshop operations.
Cost of office and workshop furniture and purchase of
stationery.
Allowances for company’s board of directors.
Salary of management personnel
SOCSO
office rental and others.
1) Built Up Cost for Excavation Work
They are two ways of conducting excavation work ;
i. Manual excavation work
- Using hand equipments such as hoe and shove.
- Suitable for small work and limited working area.
ii. Excavation work using machinery
- Using machineries such as tractor, bulldozer, backhoe
and excavator.
- Suitable for large excavation work.
Calculation should include:
Excavation
Transporting and dumping of the excavated soil
Backfilling and compacting
Constructing temporary trench support on the
sides of excavated trench if necessary.
excavation Unit : m3 (>100mm)
m2 for topsoil (<100mm)
Table 1: Increasing volume
types Increase (%)
Sand 10
Clay 20
Natural soil 25
gravel 50
Table 2: labour constant/Angkatap Buruh
Example 1
Excavation by hand
Example:
Built up cost for manual excavation work, as follows:
Manual excavation of ditch, not exceeding 1.5 meter deep
and dumping to an average distance 100m from the site.
Important information :
- Excavating trench/ditch not exceeding 1.5m deep : 1.74hour/m₃(refer table 2)
- Dumping of soil 100m away from site. : 1.00 hour/m₃(refer table 2)
- Increased volume of soil after excavation : 25% (refer table 1)
- Overhead cost and profit. :10%
- Labour cost for excavating and dumping trench/ditch per day (8 hours) : RM 40
(refer price rate-jkr)
1. Labour Cost solution
- Excavating trench not exceeding 1.5m deep :1.74 hour /m₃
:1.00 hour/m₃
- Dumping of soil 100m away from site. :25%
:0.25 hour /m₃
- Increased volume of soil after excavation
2.99 hour /m₃
= 25 x 1.00 hour /m₃
100
Total labour constant
1.74+1.00+0.25 =2.99
Labour rates for excavate, remove and disposal of 1 m₃ : RM 14.95
2.99 hour x RM40 = RM 14.95/hour RM 1.50
------------
8 RM 16.45
=========
2. Overhead cost and profit ( 10 % )
= 10 x 14.95=1.50
100
Total excavation cost for trench for every 1 m₃
Excavation By Machine ( rental)… (1 m3 )
Calculate in 1 m3 excavation work, starting from ground
level more than 1.50m but not exceeding 3.00m depth.
Important information :
- Rental rate RM 50.00/ hour
- Machine operator 1 person
- Labour 1 person
- Machine operator cost RM 4.00/hour
- Labour cost RM 2.50/hour
- Diesel consumed 4.55 liter/hour
- Lubricant oil consumed 0.24 liter/hour
- Cost of Diesel RM 2.05/liter
- Cost of lubricant oil RM 25/ liter
- Production capability 19.11 m3 /hour
- Overhead cost and profit. 10%
Excavation By Machine = 1 person x RM 4.00 Example 2
= 1 person x RM 2.50
Solution: RM 50.00
1. Machinery cost RM 4.00
RM 2.50
Rental rate per hour RM 6.50
2. Labour Cost RM 9.33
RM 6.00
Machine operator ( 1 person ) RM 15.33
Laborers
3. Oil cost = 4.55 liter x RM 2.05
= 0.24 liter x RM 25
Diesel
Lubricant oil
solution
Total machinery cost per hour = Machinery cost + Labour cost + Oil cost
= RM 50.00 + RM 6.50 + RM 15.33
= RM 71.83/hour
4. Production capability
Production capability 19.11 m3/hour
Machinery costs for 19.11m3 soil :
19.11 m3 /hour = RM 71.83/hour
1 m3 =RM 71.83 x 1 hour = RM 3.76/ m3
hour 19.11 m3
Excavation costs for 1 m3 = RM 3.76
5. Overhead cost and profit ( 10%) RM0.38
= 10 x 3.76
100
6. Price rate for 1 m3 RM 4.14/ m3
RM 3.76 + RM0.38
EXERCISE
Calculate in 1 m3 excavation work, starting from ground level more than
1.50m but not exceeding 3.00m depth.
Important information :
- Rental rate RM 20.00/ hour
- Machine operator 1 person
- Labour 1 person
- Machine operator cost RM 4.00/hour
- Labour cost RM 2.50/hour
- Diesel consumed 4.55 liter/hour
- Lubricant oil consumed 0.24 liter/hour
- Cost of Diesel RM 2.05/liter
- Cost of lubricant oil RM 25/ liter
- Production capability 12.30 m3 /hour
- Overhead cost and profit. 10%
3:00 PM
Excavation debris, throw from site at average distance of 50.00m from excavation site. Example 3
1. Machinery costs RM 20.00
Rental rate per hour
RM 4.00
2. Labour costs = 3.41 liter x RM 0.70 RM 2.39
Machine operator ( 1 person ) = 0.11liter x RM 3.60 RM 0.40
= 1 person x RM 4.00 RM 2.79
3. Oil costs
Diesel
Lubricant oil
Total machinery cost per hour
= Machinery cost + Labour cost + Oil cost
= RM 20.00 + RM 4.00 + RM 2.79
= RM 26.79/ hour
4. Production capability Solution
Production capability 12.30 m3/hour
Machinery costs for 12.30m3/hour = RM 26.79/hour = RM 2.18/m3
= RM 26.79 x 1hour
12.30 m3
Excavation costs for 1 m3
5. Overhead cost and profit ( 10%) = RM 0.22
= 10 x 2.18 = RM 2.40/ m3
100
6. Price rate for 1 m3
RM 2.18 + RM 0.22
Built Up Cost for Concreting Work
Two ways of mixing :
1. Manual concreting work
- Using light equipment such as hoe, shovel and pail.
- Suitable for small quantity.
2. Mixing concrete using machinery
- Using special machine.
- Suitable for large scale work.
Calculation should include
Material Price
- Cement
- Sand
- Aggregate.
Shrinkage and Wastage
- Shrinkage : volume change.
- The volume of concrete reduces when the concrete
mixes with water.
- Most of the concrete will waste during mixing,
removing and pouring concrete.
- 50 % increment due to shrinkage
3:00 PM
Manual Concreting Work ( 1m3) Example 1
Built up cost of mixing concrete manually, as follows:
“Solid concrete (1:2:4-aggregates 20mm) for ground beam;
transport and cast into the formwork”. (unit m3)
Important information:
1 m3 cement 28.7 bags
Price of a bags of cement RM 10.00
Price of 1 m3 sand RM 15.00
Price of 1 m3 coarse aggregate 28.7 bags RM 25.00
Increase in volume due to shrinkage, wastage and compaction of concrete 50 %
Overhead cost and profit 20%
RM 40.00
Labour cost for 1 worker per day (8 hours) RM 40.00 7.75 hour/m3
Labour costant for mixing, transporting, casting and 7.75 hour/m3
compacting concrete into formwork per day (8 hours)
1. Material Cost RM 287.00
1 m3 of cement x 28.7 bags x RM 10.00 RM 30.00
2 m3 of sand x RM 15.00 RM 100.00
4 m3 of coarse aggregate x RM 25.00
7 m3 concrete material RM 417.00
50 % increment due to shrinkage, wastage and compaction
50 x RM 417.00 = 208.50 RM 208.50
100
Total cost of materials for 7 m3 of concrete RM 625.50
417.00+208.50
therefore, 1 m3 of concrete = RM 625.50 RM 89.36/ m3
7
2. Labour Cost
Labour costant for mixing, transporting, casting and 7.75 hour/ m3
RM 38.75 / m3
compacting 1 m3 of concrete
RM128.11/ m3
= 7.75 hour/ m3 x RM 40.00 =38.75
8 hours
3. Total Cost
Total material cost + labour cost
RM89.36 + RM38.75= RM128.11
4. Overhead cost and profit
= 20 x RM128.11
100
= RM 25.62/ m3
5. Manual cost rate for concreting work per 1 m3 RM153.73/ m3
RM128.11 + RM25.62= RM153.73/ m3
Example 4
Mixing Concrete Using Machinery (beli jentera)
Built up cost of mixing concrete using concrete mixer
, as follows: “Mass concrete (1:2:4-aggregates 19mm)”.
(unit m3)
Material cost refer to example 1 = RM 89.36/ m3
3:00 PM
Example 4
Price of concrete mixer RM6000.00
3.44 m3/hour
Production capability of concrete mixer 1/20 of the original
price
Rates of transport machinery to the construction site for 5 10 %
years 10 %
150
Bank interest costs a year 3.41 litre/hour
0.50 litre/day
Cost of repairing machines for 5 years 1 person
4 person
The number of days using the machine for a year 10 %
8 h/day
Diesel consumed per hour 1 h/day
RM1.04/litre
Lubricant oil consumed per day RM5.00/litre
RM2.00/hour
Operator needs
Assistants needs
Overhead cost and profit
Working period
Duration of cleaning and maintenance machines
Cost of diesel
Cost of lubricant oil
Labour cost per hour
Solution:
1. Material cost RM 89.36/ m3
RM 6000.00
2. Capital cost
Price of concrete mixer RM 3000.00
Interest on capital
= 10 x 5 year x RM 6000 RM 300.00
RM 9900.00
100
= RM 3000.00 RM 1980.00
Repairing machines cost RM 13.20
= 10 x RM 6000 = RM600
RM 600.00
100
Transport costs
= 1 x RM 6000 = RM 300.00
20
Total capital cost for 5 year
Rm 6000+Rm3000+Rm600+ Rm 300 = RM 9900
Total capital cost per year
=RM 9900.00/5 = RM 1980.00
Total capital cost per day
=RM1980.00/150= RM 13.20
3. OPERATING COST 8 + 1(maintenance)
Labour cost
Labour operator (1 person)
= 1 person x 9 hour x RM 2.00= RM 18.00 RM 18.00
RM 64.00
Labour assistant rm 28.37
= 4 person x 8 hour x RM 2.00= RM 64.00 rm 2.50
Rm 112.87
4. FUEL
Diesel Rm 126.07/day
3.41L x Rm1.04x 8= Rm 28.37
Lubricant
0.5L x Rm5.00= Rm2.50
5. Daily operating cost
Rm18.00+Rm64.00+Rm28.37+Rm2.50
= Rm 112.87
6. Daily Machine Cost
=Capital cost + Operating Cost
=Rm13.20 + Rm 112.87
=Rm 126.07
7. PRODUCTION COST 27.52 m3
Production capability (3.44 m3/hour)
Daily production capability (8hour) RM 4.58
= 3.44m3/h x 8 hour/1 d = 27.52 m3 / day
Mixing costs for 27.52 m3 /d concrete= RM 126.07/d RM 93.94
1 m3 = RM 126.07 = Rm 4.58 Rm 9.39
Rm 103.33/m3
27.52 m3
Mixing costs for 1 m3 concrete = RM 4.58
Total mixing cost for 1 m3 concrete
=Material Cost + mixing cost for 1 m3
=RM 89.36/ m3 + RM 4.58 /m3
= RM 93.94 /m3
8. Overhead cost and profit
= 10 x RM 93.94 = Rm 9.39
100
9. Cost 1 m3 concrete
Mixing cost for 1 m3 concrete
=RM 93.94 + RM 9.39 = Rm 103.33
Built Up Cost for Brick Work
- Brickwork is calculated based on square metre(m2) .
- The unit price per square metre of brickwork is
calculated based on the following:
Materials: brick and mortar
Labour costs
Overhead cost and profit
Brick size
102.5