SL_Edwards LifeSciences RFP_10.5.18

Discover the best professional documents and content resources in AnyFlip Document Base.
Search
Published by nfarighi, 2019-03-27 17:17:33

Test

SL_Edwards LifeSciences RFP_10.5.18

2019 2020

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Finish Paint

Door Hardware

Mechanical Trim

Fire Sprinkler Trim

Electrical Trim

Low Voltage Trim

Tile (Restrooms)

Plumbing Fixtures (Restrooms)

Toilet Accessories (Restrooms)

Cleanup & Prepunch Interior

3RD FLOOR CORE

Overhead Mechanical Rough-in

Overhead Plumbing Rough-in

Overhead Fire Sprinkler Rough-in

Overhead Electrical Rough-in

Wall Framing & Furring

Wall Plumbing Rough-in

Wall Electrical Rough-in

Wall Low Voltage Rough-in

Wall MEP & Framing Inspections

Wall Insulation (dry-in)

Drywall Walls

Hard Ceiling Framing

Hard Ceiling Mechanical Rough-in

Hard Ceiling Fire Sprinkler Rough-in

Hard Ceiling Electrical Rough-in

Hard Ceiling MEP Inspections

Drywall Ceilings

Tape Drywall Walls & Ceilings

Prime & Paint

Electrical Panels & Pull Wire

Door Frames

Suspended & Surface Mounted Fixtures

Flooring

Base

Hang Doors

Finish Paint

Door Hardware

Mechanical Trim

Fire Sprinkler Trim

Electrical Trim

Low Voltage Trim

Tile (Restrooms)

Plumbing Fixtures (Restrooms)

Toilet Accessories (Restrooms)

Cleanup & Prepunch Interior

es Campus Expansion Remaining Level of Effort
ule - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work

Activity ID Activity Name Dur Current Start Current
Finish
Aug Sep Oct Nov Dec
INTERIOR STAIRS 50 02/10/20 04/17/20
Edwards Lifescience
1B-70000 Drywall & Tape Stairs 30 02/10/20 03/20/20 Proposal Schedu
20 03/02/20 03/27/20 Snyder L
1B-70010 Handrails 20 03/09/20 04/03/20
20 03/16/20 04/10/20
1B-70020 Prime & Paint 20 03/23/20 04/17/20
56 03/02/20 05/18/20
1B-70030 Flooring
10 03/02/20 03/13/20
1B-70040 MEP Trim 5 03/16/20 03/20/20
5 03/23/20 03/27/20
ELEVATORS 3 03/30/20 04/01/20
3 04/02/20 04/06/20
1B-71000 Elevator Pre-Check List & Corrections 5 04/07/20 04/13/20
5 04/27/20 05/01/20
1B-71010 Elevator Rails (#1) 5 03/30/20 04/03/20
5 04/06/20 04/10/20
1B-71020 Elevator Equipment (#1) 3 04/13/20 04/15/20
3 04/16/20 04/20/20
1B-71030 Elevator Temp Platform (#1) 5 04/21/20 04/27/20
5 05/04/20 05/08/20
1B-71040 Elevator Door Frames (#1) 5 04/13/20 04/17/20
5 04/20/20 04/24/20
1B-71050 Elevator Cab & Finishes (#1) 3 04/27/20 04/29/20
3 04/30/20 05/04/20
1B-71060 Elevator Test & Adjust (#1) 5 05/05/20 05/11/20
5 05/12/20 05/18/20
1B-72010 Elevator Rails (#2) 06/08/20
322 03/04/19
1B-72020 Elevator Equipment (#2) 03/29/19
20 03/04/19 04/26/19
1B-72030 Elevator Temp Platform (#2) 20 04/01/19 12/10/19
20 11/08/19 01/09/20
1B-72040 Elevator Door Frames (#2) 20 12/11/19 05/06/20
120 11/15/19 06/08/20
1B-72050 Elevator Cab & Finishes (#2) 40 04/13/20 07/07/20
70 03/30/20
1B-72060 Elevator Test & Adjust (#2) 04/24/20
20 03/30/20 06/22/20
1B-73010 Elevator Rails (#3) 20 05/26/20 06/22/20
40 04/27/20 07/07/20
1B-73020 Elevator Equipment (#3) 10 06/23/20 07/07/20
06/08/20
1B-73030 Elevator Temp Platform (#3) 0 07/07/20
2 06/05/20 07/07/20
1B-73040 Elevator Door Frames (#3) 20 06/09/20 05/28/20
0
1B-73050 Elevator Cab & Finishes (#3) 295 04/01/19

1B-73060 Elevator Test & Adjust (#3)

SITEWORK

1B-80000 Site Wet Utilities

1B-80100 Site Dry Utilities

1B-80200 Hardscape (Parking Aisle)

1B-80210 Landscape/Irrigation (Parking Aisle)

1B-80400 Hardscape (Main Courtyard)

1B-80410 Landscape (Main Courtyard)

INSPECTIONS / PUNCHLIST

1B-89000 Permanent Power

1B-90000 Final Inspections

1B-90005 Commissioning/LEED Approval

1B-90010 Inclement Weather Allowance

1B-90020 Substantial Completion

1B-90100 Prepare Punchlist

1B-90110 Punchlist Corrections

1B-90120 Final Completion

CONSTRUCTION - PHASE 1 - BLDG A (PAVILION/MUSEUM)

EARTHWORK 16 04/08/19 04/29/19
0 04/08/19
1A-10000 Start Construction

Project Start 09/10/18 Page 8 of 18
Project Finish 07/23/20 TASK filter: All Activities
Data Date 09/01/18
Run Date 10/05/18

2019 2020

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

INTERIOR STAIRS

Drywall & Tape Stairs

Handrails

Prime & Paint

Flooring

MEP Trim

ELEVATORS

Elevator Pre-Check List & Corrections

Elevator Rails (#1)

Elevator Equipment (#1)

Elevator Temp Platform (#1)

Elevator Door Frames (#1)

Elevator Cab & Finishes (#1)

Elevator Test & Adjust (#1)

Elevator Rails (#2)

Elevator Equipment (#2)

Elevator Temp Platform (#2)

Elevator Door Frames (#2)

Elevator Cab & Finishes (#2)

Elevator Test & Adjust (#2)

Elevator Rails (#3)

Elevator Equipment (#3)

Elevator Temp Platform (#3)

Elevator Door Frames (#3)

Elevator Cab & Finishes (#3)

Elevator Test & Adjust (#3)

SITEWORK

Site Wet Utilities

Site Dry Utilities

Hardscape (Parking Aisle)

Landscape/Irrigation (Parking Aisle)

Hardscape (Main Courtyard)

Landscape (Main Courtyard)

INSPECTIONS / PUNCHLIST

Permanent Power

Final Inspections

Commissioning/LEED Approval

Inclement Weather Allowance

Substantial Completion

Prepare Punchlist

Punchlist Corrections

Final Completion

CONSTRUCTION - PHASE 1 - BLDG A (PAVILION/MUSEUM)

EARTHWORK
Start Construction

es Campus Expansion Remaining Level of Effort
ule - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work

Activity ID Activity Name Dur Current Start Current
Finish
Aug Sep Oct Nov Dec
1A-10010 Survey 1 04/08/19 04/08/19
5 04/09/19 04/15/19 Edwards Lifescience
1A-10020 Demo 1 04/09/19 04/09/19 Proposal Schedu
5 04/16/19 04/22/19 Snyder L
1A-10050 Pre-Grade Meeting with City 5 04/23/19 04/29/19
154 04/30/19 12/09/19
1A-10100 Earthwork

1A-10110 Certify Pad

FOUNDATIONS / STRUCTURE

1A-15000 Drill/Rebar/Pour Piles (144) 15 04/30/19 05/20/19
10 05/21/19 06/04/19
1A-15100 Form/Rebar/Pour Pilecaps 10 05/21/19 06/04/19
10 06/05/19 06/18/19
1A-15200 Excavate/Form/Pour Elevator Pit 20 06/19/19 07/17/19
20 07/18/19 08/14/19
1A-15300 Form/Rebar/Pour Gradebeams 20 08/15/19 09/12/19
10 09/13/19 09/26/19
1A-16000 Form/Rebar/Pour/Strip CIP Walls (Pour 1) 15 09/27/19 10/17/19
10/24/19
1A-16100 Form/Rebar/Pour/Strip CIP Walls (Pour 2) 5 10/18/19 10/31/19
5 10/25/19 11/07/19
1A-16110 Form/Rebar/Pour/Strip CIP Walls (Pour 3) 5 11/01/19 11/07/19
5 11/01/19 11/12/19
1A-17000 Erect Structural Steel 2 11/08/19 11/14/19
2 11/13/19 11/21/19
1A-17010 Weld Structural Steel 5 11/15/19 11/07/19
5 11/01/19 11/15/19
1A-17100 Metal Deck/Edge Metal/Shear Studs (2nd Floor) 5 11/08/19 12/02/19
5 11/22/19 12/09/19
1A-17110 Metal Deck/Edge Metal/Shear Studs (Low Roof) 5 12/03/19 11/22/19
20 10/25/19 04/15/20
1A-17120 Metal Deck (High Roof) 90 12/10/19
12/31/19
1A-18000 Underslab Plumbing Rough-in 15 12/10/19 12/31/19
5 12/24/19 01/15/20
1A-18100 Fine Grade for SOG 12/31/19
10 01/02/20 01/22/20
1A-18110 Sand/Vapor Barrier for SOG 15 12/10/19

1A-18120 Form/Rebar/Pour SOG 5 01/16/20

1A-18200 MEP/Rebar/Pour Concrete on Metal Deck (2nd Floor)

1A-18300 MEP/Rebar/Pour Concrete on Metal Deck (Low Roof)

1A-18400 Fireproofing 1st Floor

1A-18410 Fireproofing 2nd Floor

1A-19000 Prep/Pour Ramp & Precast Stairs

EXTERIOR SKIN

1A-30000 Exterior Framing

1A-30010 Exterior MEP Rough-in

1A-30020 Exterior Sheathing

1A-30050 Intumescent & High Performance Paint at Exposed Steel

1A-30200 Waterproofing for Wood Panel System

1A-30210 Wood Panel System 20 01/23/20 02/19/20
40 01/02/20 02/26/20
1A-30300 Curtainwall 10 01/30/20 02/12/20
10 02/27/20 03/11/20
1A-30350 Storefront Framing 03/18/20
5 03/12/20 02/12/20
1A-30360 Storefront Glazing 20 01/16/20 01/22/20
02/19/20
1A-30370 Storefront Doors 5 01/16/20 04/01/20
20 01/23/20
1A-30400 Steel & Glass Guardrails 30 02/20/20

1A-30500 Weatherproofing for Aluminum Panels

1A-30510 Field Measure & Fab Aluminum Panels

1A-30520 Install Aluminum Panels

1A-30550 Composite LED Screen 10 03/19/20 04/01/20
5 04/02/20 04/08/20
1A-30600 MEP Trim 5 04/09/20 04/15/20

1A-30900 Cleanup & Prepunch

Project Start 09/10/18 Page 9 of 18
Project Finish 07/23/20 TASK filter: All Activities
Data Date 09/01/18
Run Date 10/05/18

2019 2020

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Survey

Demo

Pre-Grade Meeting with City

Earthwork

Certify Pad

FOUNDATIONS / STRUCTURE

Drill/Rebar/Pour Piles (144)

Form/Rebar/Pour Pilecaps

Excavate/Form/Pour Elevator Pit

Form/Rebar/Pour Gradebeams

Form/Rebar/Pour/Strip CIP Walls (Pour 1)

Form/Rebar/Pour/Strip CIP Walls (Pour 2)

Form/Rebar/Pour/Strip CIP Walls (Pour 3)

Erect Structural Steel

Weld Structural Steel

Metal Deck/Edge Metal/Shear Studs (2nd Floor)

Metal Deck/Edge Metal/Shear Studs (Low Roof)

Metal Deck (High Roof)

Underslab Plumbing Rough-in

Fine Grade for SOG

Sand/Vapor Barrier for SOG

Form/Rebar/Pour SOG

MEP/Rebar/Pour Concrete on Metal Deck (2nd Floor)

MEP/Rebar/Pour Concrete on Metal Deck (Low Roof)

Fireproofing 1st Floor

Fireproofing 2nd Floor

Prep/Pour Ramp & Precast Stairs

EXTERIOR SKIN

Exterior Framing

Exterior MEP Rough-in

Exterior Sheathing

Intumescent & High Performance Paint at Exposed Steel

Waterproofing for Wood Panel System

Wood Panel System

Curtainwall

Storefront Framing

Storefront Glazing

Storefront Doors

Steel & Glass Guardrails

Weatherproofing for Aluminum Panels

Field Measure & Fab Aluminum Panels

Install Aluminum Panels

Composite LED Screen

MEP Trim

Cleanup & Prepunch

es Campus Expansion Remaining Level of Effort
ule - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work

Activity ID Activity Name Dur Current Start Current Aug Sep Oct Nov Dec
Finish
ROOF MEP Penetrations & Roof Drains
Mechanical Curbs 41 11/01/19 01/03/20
LOW ROOF Roof Hatch
1A-40000 Sheetmetal Flashing 41 11/01/19 01/03/20
1A-40010 Roofing 3 11/01/19 11/05/19
1A-40020 Set Mechanical Equipment 3 11/01/19 11/05/19
1A-40030 Hookup Mechanical Equipment 3 11/01/19 11/05/19
1A-40100 Operable Skylight 3 11/06/19 11/08/19
1A-40200 Sheetmetal Trim & Finish 5 11/12/19 11/18/19
1A-40210 Cleanup & Prepunch Roof 2 11/19/19 11/20/19
1A-40300 12/06/19
1A-40400 Overhead Mechanical Rough-in 10 11/21/19 12/18/19
1A-40900 Overhead Plumbing Rough-in 20 11/19/19 12/26/19
Overhead Fire Sprinkler Rough-in 01/03/20
INTERIOR Overhead Electrical Rough-in 5 12/19/19 04/29/20
Wall Framing & Furring 5 12/27/19
1ST FLOOR Wall Plumbing Rough-in 105 12/03/19 04/22/20
1A-50000 Wall Electrical Rough-in 12/09/19
1A-50010 Wall Low Voltage Rough-in 100 12/03/19 12/16/19
1A-50020 Wall MEP & Framing Inspections 5 12/03/19 12/16/19
1A-50030 Wall Insulation (dry-in) 5 12/10/19 12/16/19
1A-50100 Drywall Walls 5 12/10/19 12/16/19
1A-50110 Hard Ceiling Framing 5 12/10/19 12/23/19
1A-50120 Hard Ceiling Mechanical Rough-in 5 12/10/19 12/23/19
1A-50130 Hard Ceiling Fire Sprinkler Rough-in 5 12/17/19 12/23/19
1A-50140 Hard Ceiling Electrical Rough-in 5 12/17/19 12/26/19
1A-50150 Hard Ceiling MEP Inspections 5 12/17/19 01/17/20
1A-50160 Drywall Ceilings 2 12/24/19 01/24/20
1A-50200 Tape Drywall Walls & Ceilings 2 01/16/20 12/19/19
1A-50210 Prime & Paint 5 01/20/20 12/24/19
1A-50220 Electrical Panels & Pull Wire 3 12/17/19 12/24/19
1A-50230 Door Frames 3 12/20/19 12/24/19
1A-50240 Ceiling Grid 3 12/20/19 12/27/19
1A-50250 Mechanical Fixtures in Grid 3 12/20/19 01/29/20
1A-50260 Fire Sprinkler Drops in Grid 2 12/26/19 02/12/20
1A-50300 Electrical Fixtures in Grid 3 01/27/20 02/19/20
1A-50310 Ceiling Grid & MEP Inspections 03/04/20
1A-50320 Ceiling Tile 10 01/30/20 02/24/20
1A-50400 Suspended & Surface Mounted Fixtures 5 02/13/20 02/26/20
1A-50410 Millwork/Cabinetry/Wall Finishes 03/04/20
1A-50420 Countertops 10 02/20/20 03/04/20
1A-50430 Flooring 3 02/20/20 03/04/20
1A-50440 5 02/20/20 03/06/20
1A-50450 5 02/27/20 03/13/20
1A-50460 5 02/27/20 03/20/20
1A-50500 5 02/27/20 03/11/20
1A-50510 2 03/05/20 03/16/20
1A-50600 5 03/09/20 03/27/20
5 03/16/20

10 02/27/20
3 03/12/20
5 03/23/20

Project Start 09/10/18 Page 10 of 18 Edwards Lifescience
Project Finish 07/23/20 TASK filter: All Activities Proposal Schedu
Data Date 09/01/18 Snyder L
Run Date 10/05/18

2019 2020

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

ROOF

LOW ROOF

MEP Penetrations & Roof Drains

Mechanical Curbs

Roof Hatch

Sheetmetal Flashing

Roofing

Set Mechanical Equipment

Hookup Mechanical Equipment

Operable Skylight

Sheetmetal Trim & Finish

Cleanup & Prepunch Roof

INTERIOR

1ST FLOOR

Overhead Mechanical Rough-in

Overhead Plumbing Rough-in

Overhead Fire Sprinkler Rough-in

Overhead Electrical Rough-in

Wall Framing & Furring

Wall Plumbing Rough-in

Wall Electrical Rough-in

Wall Low Voltage Rough-in

Wall MEP & Framing Inspections

Wall Insulation (dry-in)

Drywall Walls

Hard Ceiling Framing

Hard Ceiling Mechanical Rough-in

Hard Ceiling Fire Sprinkler Rough-in

Hard Ceiling Electrical Rough-in

Hard Ceiling MEP Inspections

Drywall Ceilings

Tape Drywall Walls & Ceilings

Prime & Paint

Electrical Panels & Pull Wire

Door Frames

Ceiling Grid

Mechanical Fixtures in Grid

Fire Sprinkler Drops in Grid

Electrical Fixtures in Grid

Ceiling Grid & MEP Inspections

Ceiling Tile

Suspended & Surface Mounted Fixtures

Millwork/Cabinetry/Wall Finishes

Countertops

Flooring

es Campus Expansion Remaining Level of Effort
ule - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work

Activity ID Activity Name Dur Current Start Current
Finish
Aug Sep Oct Nov Dec
1A-50610 Base 2 03/30/20 03/31/20
1A-50620 Hang Doors 3 03/30/20 04/01/20 Edwards Lifescience
1A-50630 Finish Paint 5 04/02/20 04/08/20 Proposal Schedu
1A-50640 Door Hardware 3 04/09/20 04/13/20 Snyder L
1A-50650 Mechanical Trim 5 04/09/20 04/15/20
1A-50660 Fire Sprinkler Trim 5 04/09/20 04/15/20
1A-50670 Electrical Trim 5 04/09/20 04/15/20
1A-50680 Low Voltage Trim 5 04/09/20 04/15/20
1A-50800 Tile (Restrooms) 5 02/20/20 02/26/20
1A-50820 Plumbing Fixtures (Restrooms) 3 02/27/20 03/02/20
1A-50840 Toilet Accessories (Restrooms) 3 03/03/20 03/05/20
1A-50900 Cleanup & Prepunch Interior 5 04/16/20 04/22/20
2ND FLOOR 100 12/10/19 04/29/20
1A-55000 Overhead Mechanical Rough-in 5 12/10/19 12/16/19
1A-55010 Overhead Plumbing Rough-in 5 12/17/19 12/23/19
1A-55020 Overhead Fire Sprinkler Rough-in 5 12/17/19 12/23/19
1A-55030 Overhead Electrical Rough-in 5 12/17/19 12/23/19
1A-55100 Wall Framing & Furring 5 12/17/19 12/23/19
1A-55110 Wall Plumbing Rough-in 5 12/24/19 12/31/19
1A-55120 Wall Electrical Rough-in 5 12/24/19 12/31/19
1A-55130 Wall Low Voltage Rough-in 5 12/24/19 12/31/19
1A-55140 Wall MEP & Framing Inspections 2 01/02/20 01/03/20
1A-55150 Wall Insulation 2 01/20/20 01/21/20
1A-55160 Drywall Walls 5 01/27/20 01/31/20
1A-55200 Hard Ceiling Framing 3 12/24/19 12/27/19
1A-55210 Hard Ceiling Mechanical Rough-in 3 12/30/19 01/02/20
1A-55220 Hard Ceiling Fire Sprinkler Rough-in 3 12/30/19 01/02/20
1A-55230 Hard Ceiling Electrical Rough-in 3 12/30/19 01/02/20
1A-55240 Hard Ceiling MEP Inspections 2 01/03/20 01/06/20
1A-55250 Drywall Ceilings 3 02/03/20 02/05/20
1A-55260 Tape Drywall Walls & Ceilings 10 02/06/20 02/19/20
1A-55300 Prime & Paint 5 02/20/20 02/26/20
1A-55310 Electrical Panels & Pull Wire 10 02/27/20 03/11/20
1A-55320 Door Frames 3 02/27/20 03/02/20
1A-55400 Ceiling Grid 5 02/27/20 03/04/20
1A-55410 Mechanical Fixtures in Grid 5 03/05/20 03/11/20
1A-55420 Fire Sprinkler Drops in Grid 5 03/05/20 03/11/20
1A-55430 Electrical Fixtures in Grid 5 03/05/20 03/11/20
1A-55440 Ceiling Grid & MEP Inspections 2 03/12/20 03/13/20
1A-55450 Ceiling Tile 5 03/16/20 03/20/20
1A-55460 Suspended & Surface Mounted Fixtures 5 03/23/20 03/27/20
1A-55500 Millwork/Cabinetry/Wall Finishes 10 03/05/20 03/18/20
1A-55510 Countertops 3 03/19/20 03/23/20
1A-55600 Flooring 5 03/30/20 04/03/20
1A-55605 Walkway Pedestal Pavers 10 02/27/20 03/11/20
1A-55610 Base 2 04/06/20 04/07/20

Project Start 09/10/18 Page 11 of 18
TASK filter: All Activities
Project Finish 07/23/20

Data Date 09/01/18

Run Date 10/05/18

2019 2020

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Base

Hang Doors

Finish Paint

Door Hardware

Mechanical Trim

Fire Sprinkler Trim

Electrical Trim

Low Voltage Trim

Tile (Restrooms)

Plumbing Fixtures (Restrooms)

Toilet Accessories (Restrooms)

Cleanup & Prepunch Interior

2ND FLOOR

Overhead Mechanical Rough-in

Overhead Plumbing Rough-in

Overhead Fire Sprinkler Rough-in

Overhead Electrical Rough-in

Wall Framing & Furring

Wall Plumbing Rough-in

Wall Electrical Rough-in

Wall Low Voltage Rough-in

Wall MEP & Framing Inspections

Wall Insulation

Drywall Walls

Hard Ceiling Framing

Hard Ceiling Mechanical Rough-in

Hard Ceiling Fire Sprinkler Rough-in

Hard Ceiling Electrical Rough-in

Hard Ceiling MEP Inspections

Drywall Ceilings

Tape Drywall Walls & Ceilings

Prime & Paint

Electrical Panels & Pull Wire

Door Frames

Ceiling Grid

Mechanical Fixtures in Grid

Fire Sprinkler Drops in Grid

Electrical Fixtures in Grid

Ceiling Grid & MEP Inspections

Ceiling Tile

Suspended & Surface Mounted Fixtures

Millwork/Cabinetry/Wall Finishes

Countertops

Flooring

Walkway Pedestal Pavers

Base

es Campus Expansion Remaining Level of Effort
ule - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work

Activity ID Activity Name Dur Current Start Current
Finish
Aug Sep Oct Nov Dec
1A-55620 Hang Doors 3 04/06/20 04/08/20
5 04/09/20 04/15/20 Edwards Lifescience
1A-55630 Finish Paint 3 04/16/20 04/20/20 Proposal Schedu
5 04/16/20 04/22/20 Snyder L
1A-55640 Door Hardware 5 04/16/20 04/22/20
5 04/16/20 04/22/20
1A-55650 Mechanical Trim 5 04/16/20 04/22/20
5 04/23/20 04/29/20
1A-55660 Fire Sprinkler Trim 35 02/03/20 03/20/20

1A-55670 Electrical Trim 10 02/03/20 02/14/20
10 02/17/20 02/28/20
1A-55680 Low Voltage Trim 03/06/20
5 03/02/20 03/13/20
1A-55900 Cleanup & Prepunch Interior 5 03/09/20 03/20/20
5 03/16/20 04/09/20
INTERIOR STAIRS 36 02/20/20
03/04/20
1A-70000 Drywall & Tape Stairs 10 02/20/20 03/11/20
5 03/05/20 03/18/20
1A-70010 Handrails 5 03/12/20 03/23/20
3 03/19/20 03/26/20
1A-70020 Prime & Paint 3 03/24/20 04/02/20
5 03/27/20 04/09/20
1A-70030 Flooring 5 04/03/20 05/06/20

1A-70040 MEP Trim 280 04/01/19 04/26/19
05/24/19
ELEVATOR 20 04/01/19 04/08/20
20 04/29/19 05/06/20
1A-71000 Elevator Pre-Check List & Corrections 60 01/16/20 05/28/20
20 04/09/20
1A-71010 Elevator Rails 55 03/12/20 04/01/20
05/13/20
1A-71020 Elevator Equipment 15 03/12/20 05/13/20
10 04/30/20 05/28/20
1A-71030 Elevator Temp Platform 40 03/19/20 05/28/20
10 05/14/20 04/29/20
1A-71040 Elevator Door Frames 05/28/20
0 05/28/20
1A-71050 Elevator Cab & Finishes 2 04/28/20 07/22/20
20 04/30/20
1A-71060 Elevator Test & Adjust 0
313 04/29/19
SITEWORK

1A-80000 Site Wet Utilities

1A-80100 Site Dry Utilities

1A-80400 Hardscape (Entry/Museum)

1A-80410 Landscape (Entry/Museum)

INSPECTIONS / PUNCHLIST

1A-89000 Permanent Power

1A-90000 Final Inspections

1A-90005 Commissioning/LEED Approval

1A-90010 Inclement Weather Allowance

1A-90020 Substantial Completion

1A-90100 Prepare Punchlist

1A-90110 Punchlist Corrections

1A-90120 Final Completion

CONSTRUCTION - PHASE 1 - BLDG C (CAFE/CONFERENCE)

EARTHWORK 21 06/25/19 07/24/19

1C-10000 Start Construction 0 06/25/19 06/25/19
1 06/25/19 07/17/19
1C-10010 Survey 15 06/26/19 07/24/19
5 07/18/19 12/19/19
1C-10020 Earthwork 102 07/25/19 08/28/19
09/12/19
1C-10030 Certify Pad 25 07/25/19
15 08/22/19
FOUNDATIONS / STRUCTURE

1C-15000 Drill/Rebar/Pour Piles (246)

1C-15100 Form/Rebar/Pour Pilecaps

Project Start 09/10/18 Page 12 of 18
Project Finish 07/23/20 TASK filter: All Activities
Data Date 09/01/18
Run Date 10/05/18

2019 2020

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Hang Doors

Finish Paint

Door Hardware

Mechanical Trim

Fire Sprinkler Trim

Electrical Trim

Low Voltage Trim

Cleanup & Prepunch Interior

INTERIOR STAIRS

Drywall & Tape Stairs

Handrails

Prime & Paint

Flooring

MEP Trim

ELEVATOR

Elevator Pre-Check List & Corrections

Elevator Rails

Elevator Equipment

Elevator Temp Platform

Elevator Door Frames

Elevator Cab & Finishes

Elevator Test & Adjust

SITEWORK

Site Wet Utilities

Site Dry Utilities

Hardscape (Entry/Museum)

Landscape (Entry/Museum)

INSPECTIONS / PUNCHLIST

Permanent Power

Final Inspections

Commissioning/LEED Approval

Inclement Weather Allowance

Substantial Completion

Prepare Punchlist

Punchlist Corrections

Final Completion

CONSTRUCTION - PHASE 1 - BLDG C (CAFE/CO

EARTHWORK

Start Construction
Survey

Earthwork
Certify Pad
FOUNDATIONS / STRUCTURE

Drill/Rebar/Pour Piles (246)
Form/Rebar/Pour Pilecaps

es Campus Expansion Remaining Level of Effort
ule - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work

Activity ID Activity Name Dur Current Start Current
Finish
Aug Sep Oct Nov Dec

1C-15200 Excavate/Form/Pour Elevator Pit 10 08/29/19 09/12/19
15 09/06/19 09/26/19
1C-15300 Form/Rebar/Pour Gradebeams 10 09/27/19 10/10/19
15 10/04/19 10/24/19
1C-17000 Erect Structural Steel 10 10/18/19 10/31/19
10 10/18/19 10/31/19
1C-17010 Weld Structural Steel 10 11/01/19 11/15/19
10 11/08/19 11/22/19
1C-17020 Erect BRB's 10 11/08/19 11/22/19
11/26/19
1C-17100 Metal Deck/Edge Metal/Shear Studs (2nd Floor) 2 11/25/19 12/05/19
5 11/27/19 12/19/19
1C-17110 Metal Deck/Edge Metal (Roof) 10 12/06/19 12/03/19
15 11/08/19 04/27/20
1C-18000 Underslab Plumbing Rough-in 95 12/13/19

1C-18050 Complete Rebar/Pour Gradebeams at Moment Frames

1C-18100 Fine Grade for SOG

1C-18110 Sand/Vapor Barrier for SOG

1C-18120 Form/Rebar/Pour SOG

1C-18200 MEP/Rebar/Pour Concrete on Metal Deck (2nd Floor)

EXTERIOR SKIN

1C-30000 Exterior Framing 15 12/13/19 01/06/20
1C-30010 Exterior MEP Rough-in 10 12/20/19 01/06/20
1C-30020 Exterior Sheathing 10 12/30/19 01/13/20
1C-30200 Waterproofing for Wood Rain Screen 01/20/20
1C-30210 Wood Rain Screen 5 01/14/20 02/17/20
1C-30300 Curtainwall 20 01/21/20 03/30/20
1C-30350 Storefront Framing 60 01/07/20 03/16/20
1C-30360 Storefront Glazing 10 03/03/20 03/30/20
1C-30370 Storefront Doors 10 03/17/20 04/06/20
1C-30400 Steel & Glass Guardrails 02/10/20
1C-30500 Weatherproofing for Aluminum Panels 5 03/31/20 01/27/20
1C-30510 Field Measure & Fab Aluminum Panels 20 01/14/20 03/02/20
10 01/14/20
30 01/21/20

1C-30520 Install Aluminum Panels 40 02/18/20 04/13/20
1C-30600 MEP Trim 5 04/14/20 04/20/20
1C-30900 Cleanup & Prepunch 5 04/21/20 04/27/20
05/26/20
ROOF MEP Penetrations & Roof Drains 132 11/18/19
Sheetmetal Flashing
ROOF DECK Waterproofing 122 12/04/19 05/26/20
1C-40000 Topping Slabs 5 12/04/19 12/10/19
1C-40030 Roof Deck Pavers & Finishes 5 12/11/19 12/17/19
1C-40100 Cleanup & Prepunch Roof Decks 04/13/20
1C-40110 10 03/31/20 04/20/20
1C-40300 MEP Penetrations & Roof Drains 10 04/07/20 05/18/20
1C-40900 Mechanical Curbs 20 04/21/20 05/26/20
MAIN ROOF Sheetmetal Flashing 02/13/20
1C-41000 Roofing 5 05/19/20 11/22/19
1C-41010 Set Mechanical Equipment 60 11/18/19 11/22/19
1C-41030 Hookup Mechanical Equipment 12/03/19
1C-41100 Roof Screen Panels 5 11/18/19 12/17/19
1C-41200 5 11/18/19 12/24/19
1C-41210 5 11/25/19 01/23/20
1C-41300 10 12/04/19 01/16/20
5 12/18/19
20 12/26/19
20 12/18/19

Project Start 09/10/18 Page 13 of 18 Edwards Lifescience
Project Finish 07/23/20 TASK filter: All Activities Proposal Schedu
Data Date 09/01/18 Snyder L
Run Date 10/05/18

2019 2020

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Excavate/Form/Pour Elevator Pit

Form/Rebar/Pour Gradebeams

Erect Structural Steel

Weld Structural Steel

Erect BRB's

Metal Deck/Edge Metal/Shear Studs (2nd Floor)

Metal Deck/Edge Metal (Roof)

Underslab Plumbing Rough-in

Complete Rebar/Pour Gradebeams at Moment Frames

Fine Grade for SOG

Sand/Vapor Barrier for SOG

Form/Rebar/Pour SOG

MEP/Rebar/Pour Concrete on Metal Deck (2nd Floor)

EXTERIOR SKIN

Exterior Framing
Exterior MEP Rough-in

Exterior Sheathing
Waterproofing for Wood Rain Screen
Wood Rain Screen
Curtainwall
Storefront Framing
Storefront Glazing
Storefront Doors
Steel & Glass Guardrails
Weatherproofing for Aluminum Panels
Field Measure & Fab Aluminum Panels

Install Aluminum Panels
MEP Trim
Cleanup & Prepunch
ROOF

ROOF DECK
MEP Penetrations & Roof Drains

Sheetmetal Flashing
Waterproofing
Topping Slabs
Roof Deck Pavers & Finishes
Cleanup & Prepunch Roof Decks

MAIN ROOF
MEP Penetrations & Roof Drains
Mechanical Curbs

Sheetmetal Flashing
Roofing
Set Mechanical Equipment
Hookup Mechanical Equipment
Roof Screen Panels

es Campus Expansion Remaining Level of Effort
ule - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work

Activity ID Activity Name Dur Current Start Current
Finish
Aug Sep Oct Nov Dec

1C-41400 Sheetmetal Trim & Finish 10 01/24/20 02/06/20
5 02/07/20 02/13/20
1C-41900 Cleanup & Prepunch Roof 06/04/20
122 12/13/19
INTERIOR

1ST FLOOR CORE 109 12/13/19 05/15/20
10 12/13/19 12/27/19
1C-50000 Overhead Mechanical Rough-in 10 12/20/19 01/06/20
10 12/20/19 01/06/20
1C-50010 Overhead Plumbing Rough-in 10 12/20/19 01/06/20
10 12/20/19 01/06/20
1C-50020 Overhead Fire Sprinkler Rough-in 10 12/30/19 01/13/20
10 12/30/19 01/13/20
1C-50030 Overhead Electrical Rough-in 10 12/30/19 01/13/20
5 01/09/20 01/15/20
1C-50100 Wall Framing & Furring 5 01/13/20 01/17/20
10 01/15/20 01/28/20
1C-50110 Wall Plumbing Rough-in 10 01/07/20 01/20/20
10 01/14/20 01/27/20
1C-50120 Wall Electrical Rough-in 10 01/14/20 01/27/20
10 01/14/20 01/27/20
1C-50130 Wall Low Voltage Rough-in 5 01/23/20 01/29/20
10 01/27/20 02/07/20
1C-50140 Wall MEP & Framing Inspections 10 02/10/20 02/21/20
10 02/17/20 02/28/20
1C-50150 Wall Insulation (dry-in) 20 02/24/20 03/20/20
5 02/24/20 02/28/20
1C-50160 Drywall Walls 20 03/02/20 03/27/20
10 03/30/20 04/10/20
1C-50200 Hard Ceiling Framing 10 04/06/20 04/17/20
2 04/20/20 04/21/20
1C-50210 Hard Ceiling Mechanical Rough-in 5 04/20/20 04/24/20
5 04/27/20 05/01/20
1C-50220 Hard Ceiling Fire Sprinkler Rough-in 5 05/04/20 05/08/20
5 05/04/20 05/08/20
1C-50230 Hard Ceiling Electrical Rough-in 5 05/04/20 05/08/20
5 05/04/20 05/08/20
1C-50240 Hard Ceiling MEP Inspections 5 05/04/20 05/08/20
15 02/24/20 03/13/20
1C-50250 Drywall Ceilings 5 03/09/20 03/13/20
5 03/16/20 03/20/20
1C-50260 Tape Drywall Walls & Ceilings 5 05/11/20 05/15/20
112 12/30/19 06/04/20
1C-50300 Prime & Paint 15 12/30/19 01/20/20
15 01/07/20 01/27/20
1C-50310 Electrical Panels & Pull Wire 15 01/07/20 01/27/20
15 01/07/20 01/27/20
1C-50320 Door Frames

1C-50400 Ceiling Finishes

1C-50460 Suspended & Surface Mounted Fixtures

1C-50600 Flooring

1C-50610 Base

1C-50620 Hang Doors

1C-50630 Finish Paint

1C-50640 Door Hardware

1C-50650 Mechanical Trim

1C-50660 Fire Sprinkler Trim

1C-50670 Electrical Trim

1C-50680 Low Voltage Trim

1C-50800 Tile (Restrooms)

1C-50820 Plumbing Fixtures (Restrooms)

1C-50840 Toilet Accessories (Restrooms)

1C-50900 Cleanup & Prepunch Interior

2ND FLOOR CORE

1C-55000 Overhead Mechanical Rough-in

1C-55010 Overhead Plumbing Rough-in

1C-55020 Overhead Fire Sprinkler Rough-in

1C-55030 Overhead Electrical Rough-in

Project Start 09/10/18 Page 14 of 18 Edwards Lifescience
Project Finish 07/23/20 TASK filter: All Activities Proposal Schedu
Data Date 09/01/18 Snyder L
Run Date 10/05/18

2019 2020

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Sheetmetal Trim & Finish

Cleanup & Prepunch Roof

INTERIOR

1ST FLOOR CORE

Overhead Mechanical Rough-in

Overhead Plumbing Rough-in

Overhead Fire Sprinkler Rough-in

Overhead Electrical Rough-in

Wall Framing & Furring

Wall Plumbing Rough-in

Wall Electrical Rough-in

Wall Low Voltage Rough-in

Wall MEP & Framing Inspections

Wall Insulation (dry-in)

Drywall Walls

Hard Ceiling Framing

Hard Ceiling Mechanical Rough-in

Hard Ceiling Fire Sprinkler Rough-in

Hard Ceiling Electrical Rough-in

Hard Ceiling MEP Inspections

Drywall Ceilings

Tape Drywall Walls & Ceilings

Prime & Paint

Electrical Panels & Pull Wire

Door Frames

Ceiling Finishes

Suspended & Surface Mounted Fixtures

Flooring

Base

Hang Doors

Finish Paint

Door Hardware

Mechanical Trim

Fire Sprinkler Trim

Electrical Trim

Low Voltage Trim

Tile (Restrooms)

Plumbing Fixtures (Restrooms)

Toilet Accessories (Restrooms)

Cleanup & Prepunch Interior

2ND FLOOR CORE

Overhead Mechanical Rough-in

Overhead Plumbing Rough-in

Overhead Fire Sprinkler Rough-in

Overhead Electrical Rough-in

es Campus Expansion Remaining Level of Effort
ule - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work

Activity ID Activity Name Dur Current Start Current
Finish
Aug Sep Oct Nov Dec

1C-55100 Wall Framing & Furring 15 01/07/20 01/27/20
15 01/14/20 02/03/20
1C-55110 Wall Plumbing Rough-in 15 01/14/20 02/03/20
15 01/14/20 02/03/20
1C-55120 Wall Electrical Rough-in 02/05/20
5 01/30/20 02/07/20
1C-55130 Wall Low Voltage Rough-in 5 02/03/20 02/18/20
10 02/05/20 02/03/20
1C-55140 Wall MEP & Framing Inspections 10 01/21/20 02/10/20
10 01/28/20 02/10/20
1C-55150 Wall Insulation (dry-in) 10 01/28/20 02/10/20
10 01/28/20 02/10/20
1C-55160 Drywall Walls 10 01/28/20 02/17/20
5 02/11/20 02/26/20
1C-55200 Hard Ceiling Framing 10 02/13/20 03/11/20
10 02/27/20 03/18/20
1C-55210 Hard Ceiling Mechanical Rough-in 10 03/05/20 04/08/20
20 03/12/20 03/18/20
1C-55220 Hard Ceiling Fire Sprinkler Rough-in 5 03/12/20 04/15/20
20 03/19/20 04/29/20
1C-55230 Hard Ceiling Electrical Rough-in 10 04/16/20 05/06/20
10 04/23/20 05/08/20
1C-55235 Operable Wall Tracks 2 05/07/20 05/13/20
5 05/07/20 05/20/20
1C-55240 Hard Ceiling MEP Inspections 5 05/14/20 05/28/20
5 05/21/20 05/28/20
1C-55250 Drywall Ceilings 5 05/21/20 05/28/20
5 05/21/20 05/28/20
1C-55260 Tape Drywall Walls & Ceilings 5 05/21/20 05/28/20
5 05/21/20 05/28/20
1C-55300 Prime & Paint 5 05/21/20 04/08/20
20 03/12/20 04/15/20
1C-55310 Electrical Panels & Pull Wire 10 04/02/20 04/22/20
10 04/09/20 06/04/20
1C-55320 Door Frames 5 05/29/20 04/29/20
35 03/12/20
1C-55400 Ceiling Finishes

1C-55460 Suspended & Surface Mounted Fixtures

1C-55600 Flooring

1C-55610 Base

1C-55620 Hang Doors

1C-55630 Finish Paint

1C-55640 Door Hardware

1C-55650 Mechanical Trim

1C-55660 Fire Sprinkler Trim

1C-55670 Electrical Trim

1C-55680 Low Voltage Trim

1C-55690 Operable Wall Panels

1C-55800 Tile (Restrooms)

1C-55820 Plumbing Fixtures (Restrooms)

1C-55840 Toilet Accessories (Restrooms)

1C-55900 Cleanup & Prepunch Interior

INTERIOR STAIRS

1C-70000 Drywall & Tape Stairs 15 03/12/20 04/01/20
10 03/26/20 04/08/20
1C-70010 Handrails 10 04/02/20 04/15/20
10 04/09/20 04/22/20
1C-70020 Prime & Paint 10 04/16/20 04/29/20
40 03/12/20 05/06/20
1C-70030 Flooring

1C-70040 MEP Trim

ELEVATORS

1C-71000 Elevator Pre-Check List & Corrections 10 03/12/20 03/25/20
5 03/26/20 04/01/20
1C-71010 Elevator Rails 5 04/02/20 04/08/20
3 04/09/20 04/13/20
1C-71020 Elevator Equipment

1C-71030 Elevator Temp Platform

Project Start 09/10/18 Page 15 of 18 Edwards Lifescience
Project Finish 07/23/20 TASK filter: All Activities Proposal Schedu
Data Date 09/01/18 Snyder L
Run Date 10/05/18

2019 2020

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Wall Framing & Furring

Wall Plumbing Rough-in

Wall Electrical Rough-in

Wall Low Voltage Rough-in

Wall MEP & Framing Inspections

Wall Insulation (dry-in)

Drywall Walls

Hard Ceiling Framing

Hard Ceiling Mechanical Rough-in

Hard Ceiling Fire Sprinkler Rough-in

Hard Ceiling Electrical Rough-in

Operable Wall Tracks

Hard Ceiling MEP Inspections

Drywall Ceilings

Tape Drywall Walls & Ceilings

Prime & Paint

Electrical Panels & Pull Wire

Door Frames

Ceiling Finishes

Suspended & Surface Mounted Fixtures

Flooring

Base

Hang Doors

Finish Paint

Door Hardware

Mechanical Trim

Fire Sprinkler Trim

Electrical Trim

Low Voltage Trim

Operable Wall Panels

Tile (Restrooms)

Plumbing Fixtures (Restrooms)

Toilet Accessories (Restrooms)

Cleanup & Prepunch Interior

INTERIOR STAIRS

Drywall & Tape Stairs

Handrails

Prime & Paint

Flooring

MEP Trim

ELEVATORS

Elevator Pre-Check List & Corrections

Elevator Rails

Elevator Equipment

Elevator Temp Platform

es Campus Expansion Remaining Level of Effort
ule - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work

Activity ID Activity Name Dur Current Start Current
Finish
1C-71040 Elevator Door Frames 3 04/14/20 Aug Sep Oct Nov Dec
5 04/17/20 04/16/20
1C-71050 Elevator Cab & Finishes 5 04/30/20 04/23/20 Edwards Lifescience
293 04/29/19 05/06/20 Proposal Schedu
1C-71060 Elevator Test & Adjust 06/23/20 Snyder L
20 04/29/19
SITEWORK 20 05/28/19 05/24/19
100 01/07/20 06/24/19
1C-80000 Site Wet Utilities 40 04/28/20 05/26/20
73 04/09/20 06/23/20
1C-80100 Site Dry Utilities 07/22/20
15 04/09/20
1C-80400 Hardscape (Cafe/Conference) 10 06/24/20 04/29/20
40 05/12/20 07/08/20
1C-80410 Landscape (Cafe/Conference) 10 07/09/20 07/08/20
07/22/20
INSPECTIONS / PUNCHLIST 0 07/22/20
2 06/22/20 06/23/20
1C-89000 Permanent Power 20 06/24/20 07/22/20
0 07/22/20
1C-90000 Final Inspections 278 01/03/19 02/06/20

1C-90005 Commissioning/LEED Approval 278 01/03/19 02/06/20

1C-90010 Inclement Weather Allowance 60 01/03/19 03/27/19
10 03/28/19 04/10/19
1C-90020 Substantial Completion 04/11/19
1 04/11/19 04/18/19
1C-90100 Prepare Punchlist 5 04/12/19 04/25/19
5 04/19/19 05/02/19
1C-90110 Punchlist Corrections 5 04/26/19 05/07/19
3 05/03/19 05/14/19
1C-90120 Final Completion 5 05/08/19 06/05/19
15 05/15/19 06/05/19
CONSTRUCTION - PHASE 1 - OFFSITE 15 05/15/19 06/05/19
15 05/15/19 06/06/19
REDHILL DECELERATION LANE, LEFT TURN LANE, MEDIAN, U/G UTILITIES 1 06/06/19 06/11/19
3 06/07/19 06/14/19
1S-11900 Submit/Approve Traffic Control Plans 3 06/12/19 06/18/19
2 06/17/19 06/20/19
1S-12000 Post Advanced Construction Notification & Street Signage 2 06/19/19 06/27/19
5 06/21/19 07/05/19
1S-12010 Contact Underground Dig Alert & Record Permit Number 5 06/28/19 07/12/19
5 07/08/19 07/15/19
1S-12020 Verify, Document & Submit Existing Conditions Prior to Start 1 07/15/19 06/07/19
2 06/06/19 06/11/19
1S-12030 Survey Demo Limits Prior to Start & Confirm with Contract Documents 2 06/10/19 06/13/19
2 06/12/19 06/20/19
1S-12040 Preconstruction Conference with City of Irvine as Required 5 06/14/19 06/27/19
5 06/21/19 07/02/19
1S-12100 Setup Temporary Traffic Control Measures 3 06/28/19

1S-12110 Setup Temporary BMP's

1S-12112 Construct (N) 16 in ACP Water Main

1S-12114 Construct (N) Fire, Domestic & Irrigation D.I. Laterals

1S-12116 R&R Fire Hydrant & Remove Lateral

1S-12118 Survey & Layout Raised Islands

1S-12120 Sawcut & Demo Hardscapes for Raised Islands

1S-12122 Grade & Compact Subgrades for Raised Islands

1S-12124 Form Raised Islands & Certify Formwork

1S-12126 Pour & Strip Curb Islands

1S-12128 Backfill & Compact Curb Islands

1S-12130 Patch A/C Paving at Curb Islands

1S-12132 Grind & Overlay A/C Paving at Curb Islands

1S-12134 Temporary Striping

1S-12136 Remove & Relocate Construction Fencing

1S-12138 Safe-off & Re-Route Irrigation

1S-12140 Remove & Salvage Signage as Applicable

1S-12150 Remove & Relocate Existing Low Volt Pull Box & Assoc. Cabling

1S-12160 Remove & Protect Existing Bus Bench, Trash Can & Associated Signage

1S-12200 Demo (E) Hardscapes & Landscapes

Project Start 09/10/18 Page 16 of 18
Project Finish 07/23/20 TASK filter: All Activities
Data Date 09/01/18
Run Date 10/05/18

2019 2020

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Elevator Door Frames

Elevator Cab & Finishes

Elevator Test & Adjust

SITEWORK

Site Wet Utilities

Site Dry Utilities

Hardscape (Cafe/Conference)

Landscape (Cafe/Conference)

INSPECTIONS / PUNCHLIST

Permanent Power

Final Inspections

Commissioning/LEED Approval

Inclement Weather Allowance

Substantial Completion

Prepare Punchlist

Punchlist Corrections

Final Completion

CONSTRUCTION - PHASE 1 - OFFSITE

REDHILL DECELERATION LANE, LEFT TURN LANE, MEDIAN, U/G UTILITIES

Submit/Approve Traffic Control Plans
Post Advanced Construction Notification & Street Signage
Contact Underground Dig Alert & Record Permit Number
Verify, Document & Submit Existing Conditions Prior to Start
Survey Demo Limits Prior to Start & Confirm with Contract Documents
Preconstruction Conference with City of Irvine as Required
Setup Temporary Traffic Control Measures
Setup Temporary BMP's
Construct (N) 16 in ACP Water Main
Construct (N) Fire, Domestic & Irrigation D.I. Laterals
R&R Fire Hydrant & Remove Lateral
Survey & Layout Raised Islands
Sawcut & Demo Hardscapes for Raised Islands
Grade & Compact Subgrades for Raised Islands
Form Raised Islands & Certify Formwork
Pour & Strip Curb Islands
Backfill & Compact Curb Islands
Patch A/C Paving at Curb Islands
Grind & Overlay A/C Paving at Curb Islands
Temporary Striping
Remove & Relocate Construction Fencing
Safe-off & Re-Route Irrigation
Remove & Salvage Signage as Applicable
Remove & Relocate Existing Low Volt Pull Box & Assoc. Cabling
Remove & Protect Existing Bus Bench, Trash Can & Associated Signage
Demo (E) Hardscapes & Landscapes

es Campus Expansion Remaining Level of Effort
ule - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work

Activity ID Activity Name Dur Current Start Current
Finish
Aug Sep Oct Nov Dec

1S-12210 Survey (N) Curb & Gutter 1 07/03/19 07/03/19
5 07/05/19 07/11/19
1S-12220 Prepare Subgrade for (N) Deceleration Lane, Curb & Gutter 2 07/12/19 07/15/19
10 07/16/19 07/29/19
1S-12230 Test Subgrade for Compaction 5 07/30/19 08/05/19
5 07/30/19 08/05/19
1S-12240 Install (N) Below Grade Signal Conduit & Associated Pull Boxes 1 08/06/19 08/06/19
5 08/07/19 08/13/19
1S-12242 Relocate Pedestrian Light Pole 3 08/14/19 08/16/19
1 08/19/19 08/19/19
1S-12250 Form (N) Curb & Gutter & EntranceApron 1 08/20/19 08/20/19
5 08/21/19 08/27/19
1S-12260 Survey & Record (N) Curb & Gutter Formwork - Prepour 1 08/28/19 08/28/19
3 08/29/19 09/03/19
1S-12270 Pour (N) Curb & Gutter, Entrance Apron, Strip & Cure 2 09/04/19 09/05/19
3 09/06/19 09/10/19
1S-12280 Backfill & Compact Behind Curb & Gutter, Entrance Apron 1 09/11/19 09/11/19
2 09/12/19 09/13/19
1S-12290 Survey Subgrade for Sidewalks at EntranceApron 10 01/02/20* 01/15/20
5 01/16/20 01/22/20
1S-12300 Install (N) Posts & Signage as Applicable 10 01/23/20 02/05/20
1 02/06/20 02/06/20
1S-12310 Form Sidewalks 110 08/01/19 01/09/20

1S-12320 Survey & Record (N) Sidewalk Formwork

1S-12330 Pour Sidewalks, Strip & Cure

1S-12340 Install Relocated Bus Stop Bench, Trash Can & Associated Signage

1S-12350 Prepare Roadway Subgrade with .65' Aggregate Base & Compact

1S-12360 Test Compaction of A.B.

1S-12370 A/C Paving

1S-12372 Grind & Overlay A/C Paving

1S-12374 Slurry Seal A/C Paving

1S-12376 Striping 1st Pass, Cure & Final Stripe

1S-12380 Final Clean

ALTON PKWY STREET WIDENING & U/G UTILITIES

1S-20000 Post Advanced Construction Notification & Street Signage 10 08/01/19* 08/14/19
1 08/15/19 08/15/19
1S-20010 Contact Underground Dig Alert & Record Permit Number 5 08/16/19 08/22/19
5 08/23/19 08/29/19
1S-20020 Verify, Document & Submit Existing Conditions Prior to Start 5 08/30/19 09/06/19
3 09/09/19 09/11/19
1S-20030 Survey Demo Limits Prior to Start & Confirm with Contract Documents 5 09/12/19 09/18/19
10/09/19
1S-20040 Preconstruction Conference with City of Irvine as Required 15 09/19/19 10/02/19
10 09/19/19 09/20/19
1S-20050 Setup Temporary Traffic Control Measures 09/24/19
2 09/19/19 09/26/19
1S-20060 Setup Temporary BMP's 2 09/23/19 10/03/19
2 09/25/19 10/10/19
1S-20070 Sanitary Sewer Improvements 5 09/27/19 10/17/19
5 10/04/19 10/18/19
1S-20080 Relocate Fire Hydrants 5 10/11/19 10/22/19
1 10/18/19 10/23/19
1S-20090 Remove & Relocate Construction Fencing 2 10/21/19 11/06/19
1 10/23/19 11/08/19
1S-20100 Safe-off & Re-Route Irrigation 10 10/24/19 11/12/19
2 11/07/19 11/14/19
1S-20110 Remove & Salvage Signage as Applicable 1 11/12/19
2 11/13/19
1S-20120 Remove & Relocate Existing Low Volt Pull Box & Assoc. Cabling

1S-20130 Remove & Protect Existing Bus Bench, Trash Can & Associated Signage

1S-20140 Demo (E) Hardscapes & Landscapes

1S-20150 Survey (N) Curb & Gutter

1S-20160 Prepare Subgrade for (N) Street Widening, Curb & Gutter

1S-20170 Test Subgrade for Compaction

1S-20180 Install (N) Below Grade Signal Conduit & Associated Pull Boxes

1S-20190 Form (N) Curb & Gutter & EntranceApron

1S-20200 Survey & Record (N) Curb & Gutter Formwork - Prepour

1S-20210 Pour (N) Curb & Gutter, Entrance Apron, Strip & Cure

Project Start 09/10/18 Page 17 of 18 Edwards Lifescience
Project Finish 07/23/20 TASK filter: All Activities Proposal Schedu
Data Date 09/01/18 Snyder L
Run Date 10/05/18

2019 2020

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Survey (N) Curb & Gutter

Prepare Subgrade for (N) Deceleration Lane, Curb & Gutter

Test Subgrade for Compaction

Install (N) Below Grade Signal Conduit & Associated Pull Boxes

Relocate Pedestrian Light Pole

Form (N) Curb & Gutter & EntranceApron

Survey & Record (N) Curb & Gutter Formwork - Prepour

Pour (N) Curb & Gutter, Entrance Apron, Strip & Cure

Backfill & Compact Behind Curb & Gutter, Entrance Apron

Survey Subgrade for Sidewalks at EntranceApron

Install (N) Posts & Signage as Applicable

Form Sidewalks

Survey & Record (N) Sidewalk Formwork

Pour Sidewalks, Strip & Cure

Install Relocated Bus Stop Bench, Trash Can & Associated Signage

Prepare Roadway Subgrade with .65' Aggregate Base & Compact

Test Compaction of A.B.

A/C Paving

Grind & Overlay A/C Paving

Slurry Seal A/C Paving

Striping 1st Pass, Cure & Final Stripe

Final Clean

ALTON PKWY STREET WIDENING & U/G UTILITIES

Post Advanced Construction Notification & Street Signage

Contact Underground Dig Alert & Record Permit Number

Verify, Document & Submit Existing Conditions Prior to Start

Survey Demo Limits Prior to Start & Confirm with Contract Documents

Preconstruction Conference with City of Irvine as Required

Setup Temporary Traffic Control Measures

Setup Temporary BMP's

Sanitary Sewer Improvements

Relocate Fire Hydrants

Remove & Relocate Construction Fencing

Safe-off & Re-Route Irrigation

Remove & Salvage Signage as Applicable

Remove & Relocate Existing Low Volt Pull Box & Assoc. Cabling

Remove & Protect Existing Bus Bench, Trash Can & Associated Signage

Demo (E) Hardscapes & Landscapes

Survey (N) Curb & Gutter

Prepare Subgrade for (N) Street Widening, Curb & Gutter

Test Subgrade for Compaction

Install (N) Below Grade Signal Conduit & Associated Pull Boxes

Form (N) Curb & Gutter & EntranceApron

Survey & Record (N) Curb & Gutter Formwork - Prepour

Pour (N) Curb & Gutter, Entrance Apron, Strip & Cure

es Campus Expansion Remaining Level of Effort
ule - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work

Activity ID Activity Name Dur Current Start Current Aug Sep Oct Nov Dec
Finish
1S-20220 Backfill & Compact Behind Curb & Gutter, Entrance Apron
1S-20230 Survey Subgrade for Sidewalks 1 11/15/19 11/15/19
1S-20240 Install (N) Posts & Signage as Applicable 1 11/18/19 11/18/19
1S-20250 Form Sidewalks 1 11/19/19 11/19/19
1S-20260 Pour Sidewalks, Strip & Cure 1 11/20/19 11/20/19
1S-20270 Install Relocated Signage 1 11/21/19 11/21/19
1S-20280 Prepare Roadway Subgrade with .65' Aggregate Base & Compact 2 11/22/19 11/25/19
1S-20290 Test Compaction of A.B. 2 11/26/19 11/27/19
1S-20300 A/C Paving 1 12/02/19 12/02/19
1S-20310 Grind & Overlay A/C Paving 2 12/03/19 12/04/19
1S-20320 Slurry Seal A/C Paving 2 12/05/19 12/06/19
1S-20330 Striping 1st Pass, Cure & Final Stripe 2 12/09/19 12/10/19
1S-20340 Final Inspections 10 12/11/19 12/24/19
10 12/26/19 01/09/20

Project Start 09/10/18 Page 18 of 18 Edwards Lifescience
Project Finish 07/23/20 TASK filter: All Activities Proposal Schedu
Data Date 09/01/18 Snyder L
Run Date 10/05/18

2019 2020

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Backfill & Compact Behind Curb & Gutter, Entrance Apron

Survey Subgrade for Sidewalks

Install (N) Posts & Signage as Applicable

Form Sidewalks

Pour Sidewalks, Strip & Cure

Install Relocated Signage

Prepare Roadway Subgrade with .65' Aggregate Base & Compact

Test Compaction of A.B.

A/C Paving

Grind & Overlay A/C Paving

Slurry Seal A/C Paving

Striping 1st Pass, Cure & Final Stripe

Final Inspections

es Campus Expansion Remaining Level of Effort
ule - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work

phasing plans













11.4

Below is the cost for our preconstruction services along with our preconstruction services scope description, which is also
outlined as part of our technical project plan in section 11.6.

Setting the Groundwork for Success in Preconstruction
The preconstruction effort is vital to setting the groundwork for establishing the level of quality and pace of schedule.
Quality standards for this project will be set in collaboration with Edwards, LPA, and Snyder Langston. At all of the phases
of the project, Snyder Langston will implement its construction management software programs, including Prolog,
Primavera P6 CPM scheduling, Modelogix/D-Estimator, and PlanGrid to manage and share project information in real time.
If requested, we can use an Edwards-designated platform at no additional cost. We have designated November 1, 2018
to January 15, 2019 as the preconstruction period for the project. During preconstruction, Snyder Langston will work with
the team to advance the project in the following activities:

Schedule/Logistics/Safety
• Develop and refine the master schedule to incorporate design, permitting and construction activities

consistent with all Edwards’s priorities and with input from Edwards, LPA and selected subcontractors. Snyder
Langston will update monthly or more often as required.
• Prepare/update a detailed logistics plan in coordination with Edwards Environmental, Health & Safety (EHS)
personnel and code enforcement to include site-specific safety reflective of the project schedule and all
applicable phasing, staging, site access, WQMP/SWPPP, and City of Irvine security plan requirements in order
to allow an expedient flow of work.

Design/BIM Coordination/Constructability
• Provide constructability and bidability reviews to facilitate accurate subcontractor bidding and buyout.

See sample below.
• Assist the design team with completion of the documents to reduce the number of RFIs.
• Provide value engineering, life cycle analysis, and early coordination to optimize the design.

See sample below.
• Establish the most favorable plan checking and permitting process for the project.
• Employ a project-specific BIM execution plan to facilitate early MEP system routing, clash detection and

installation coordination to form the basis of a quality installation and eliminate errors and conflicts.
See proposed BIM execution plan following our Technical Project Plan.

Budget
• Provide budgeting and Value Analysis using our Modelogix, D-Profiler and D-Estimator software as required

to assist completing the Construction Documents within the target budget.
• Contract early trade work and long lead time work items necessary to achieve the completion date.

Greg Hurlock SNYDER LANGSTON PR

Vice President, Estimating Georg
Project
Greg McClure
Jenny
Sr. Superintendent Sr. Proje

MEP CMooErdiPnatCi
Erik
Asst.
Ma

Franc
Sr. Proje

RECONSTRUCTION TEAM Team Resources
Stephen Jones
ge Loynd
t Executive Chairman Emeritus

y Walker John F. Rochford
ect Manager
Chairman & CEO
Ctiono/BoIMrdMiannaagtement
Bruner Jason Rich
. Project
anager President & COO
cisco Felix
ect Engineer Richard Cavecche

Sr. Vice President, Operations

David Stelter

Vice President, Field Operations

Cassidy Green

Project Manager, Brightworks

Edwards Lifesciences Project Staffing Date: 5-Oct-18
Project Executive: Loynd
Irvine, CA Harrison / Wallitsch
Lead Estimator: $ 90,000,000
Description Project Cost:
Bldg Area: 345,000

Cost Quantity Rate Extension Notes
Code

PRECONSTRUCTION Duration = 2.5 months 11/1/18 - 1/15/19 26,456 George
26,439 Jim
Project Executive 919005 3.9 weeks 6,783.61 27,361 Jenny
V.P. Estimating 919007 4.3 weeks 6,101.24
Sr. Project Manager 919013 4.8 weeks 5,739.98 4,327 Erik
Asst. Project Manager 919012 1.1 weeks 3,993.90 12,002 Francisco
Sr. Project Engineer 919015 3.3 weeks 3,692.85 13,219 Greg
Senior Superintendent 919025 2.2 weeks 6,101.24 109,803

Total Preconstruction(19002)

Snyder Langston Page 1 of 1 GCs Edwards 10-04-8.xls
10/5/2018 General Conditions

11.5

11.5 – FEE & GENERAL CONDITIONS
1. Detailed summary of the General Conditions cost and the line-­item components it covers; indicate a fixed value
of the General Conditions to be included in the GMP based on your proposed staffing plan and schedule

See following general conditions sheets
2. Weekly cost for General Conditions in the event of delays

$40,978
3. Proposed Fee as a percentage mark-­up over direct costs

2.25%
4. Identify and describe all additional charges or mark-­ups over direct costs (e.g., Insurance, Bond, Sub-­Guard,

Reimbursable Expenses, etc.)

Subguard: 1.25%
General Liability Insurance: 0.90%

Edwards Lifesciences Project Staffing Date: 5-Oct-18
Project Executive: Loynd
Irvine, CA Harrison / Wallitsch
Lead Estimator: $ 90,000,000
Description Project Cost:
Bldg Area: 345,000

Cost

Code Quantity Rate Extension Notes

GENERAL CONDITIONS Construction 18.0 months February, 2019 - July, 2020 (18 mos)
Duration =

Project Manangement & Supervision

Operations Exec Support 919003 2.2 weeks 9,706.61 21,000
27 weeks 6,950.92
Project Executive 919005 90 weeks 5,881.55 188,333
83 weeks 4,092.41
Senior Project Manager 919013 80 weeks 3,783.93 531,197 Jenny
45 weeks 2,632.30
Asst Project Manager / MEP 919012 88 weeks 2,632.30 340,208 Erik - Super, Core, MEP
62 weeks 6,251.72
Senior Project Engineer / BIM 919015 84 weeks 6,251.72 302,914 Francisco - Skin

Project Engineer 919020 66 weeks 5,182.35 118,869 Adam L Site

Project Engineer 919020 5 weeks 5,182.35 232,335 Jose L Erik Asst
6.2 weeks 1,686.32
Senior Superintendent 919025 44 weeks 2,550.04 384,974 Greg M
18 weeks 3,372.64
Senior Superintendent 919025 142 person months 526,131 Scott H

Superintendent 919030 340,398 Brian - Site, Street,
Inspection Mgmnt

Safety Director 919910 25,530

Intern 919050 10,500

Project Coordinator 919052 112,014

Project Accountant 919055 61,613

Total Project Management & Supervision: 3,196,018

Total Project Staffing (19001) 3,196,018

Snyder Langston Page 1 of 2 GCs Edwards 10-04-8.xls
10/5/2018 General Conditions

11.6

SECRET SAUCE OF SUCCESS

“Edwards First”

HIT THE GROUND RUNNING
Snyder Langston is committed to creating success for Edwards and have selected a highly experienced team that will be
dedicated specifically to this project. We understand that success is defined by delivering Building B at the earliest possible
time. We have developed the following plan to achieve this goal. We encourage your review and the opportunity to
include your ideas and suggestions to craft an integrated and thorough work plan.
Setting the Groundwork for Success in Preconstruction
The preconstruction effort is vital to setting the groundwork for establishing the level of quality and pace of schedule.
Quality standards for this project will be set in collaboration with Edwards, LPA, and Snyder Langston. At all of the phases
of the project, Snyder Langston will implement its construction management software programs, including Prolog,
Primavera P6 CPM scheduling, Modelogix/D-Estimator, and PlanGrid to manage and share project information in real time.
If requested, we can use an Edwards-designated platform at no additional cost. We have designated November 1, 2018
to January 15, 2019 as the preconstruction period for the project. During preconstruction, Snyder Langston will work with
the team in the following activities to advance the project:

Schedule/Logistics/Safety
• Develop and refine the master schedule to incorporate design, permitting and construction activities

consistent with all of Edwards’s priorities and with input from Edwards, LPA and selected subcontractors.
Snyder Langston will update monthly or more often as required.
• Prepare/update a detailed logistics plan in coordination with Edwards Environmental, Health & Safety (EHS)
personnel and code enforcement to include site-specific safety reflective of the project schedule and all
applicable phasing, staging, site access, WQMP/SWPPP, and City of Irvine security plan requirements in order
to allow an expedient flow of work.

Design/BIM Coordination/Constructability
• Provide constructability and bidability reviews to facilitate accurate subcontractor bidding and buyout.

See sample below.
• Assist the design team with completion of the documents to reduce the number of RFIs.
• Provide value engineering, life cycle analysis, and early coordination to optimize the design.

See sample below.
• Establish the most favorable plan checking and permitting process for the project.
• Employ a project-specific BIM execution plan to facilitate early MEP system routing, clash detection and

installation coordination to form the basis of a quality installation and eliminate errors and conflicts.
See proposed BIM execution plan following our Technical Project Plan.

Budget
• Provide budgeting and Value Analysis using our Modelogix, D-Profiler and D-Estimator software as required

to assist completing the Construction Documents within the target budget.
• Contract early trade work and long lead time work items necessary to achieve the completion date.

CERTAINTY OF SCHEDULE
Our overall approach includes the requirements of the RFP and is then further defined in our schedule and logistics plans:
Phase 0: 11/5/18 – 1/31/2019
The generator relocation and gate re-configuration work of Phase 0 will take place from November 5, 2018 to January 31,
2019. The logistics plan found in Section 11.3 of our Proposal reflects the approach Snyder Langston will take while
installing the infrastructure for relocating gates, relocating generators and completing the connection of the temporary
access road to reach the HVC building per the current Fire Master Plan.
Phase 1 (Utility Relocation): 1/3/19 – 4/5/19
During the utility relocation work of Phase 1 from January 3, 2019 to April 5, 2019, the focus of the work will be on
relocating the required fire lines, storm drain and the electrical service to the MLE Building. The logistics plan found in
Section 11.3 of our Proposal illustrates Snyder Langston’s plan to complete this work will be performed while maintaining
access to the HVC Building and maintaining fire service to the Community Building by temporarily relocating the fire line
to facilitate future work for Building A.
Phase 1 (Building B, A, and C): 1/3/19 – 7/22/20
During January 3, 2019 to July 22, 2020, we will start construction of Building B and flow into Building A and then into
Building C, per the proposed schedule. The logistics plan found in Section 11.3 of our Proposal takes into account the Fire
Master Plan’s requirements for fire department access, while mitigating inclement weather and controlling dust by
installing gravel access roads and constructing a temporary asphalt parking lot while maintaining access for the HVC
Building.
For all phases of construction, Snyder Langston will accommodate the needs of the active campus and will, when
necessary, utilize trench plates to cover excavations, install temporary gravel or paving, or reschedule work as required to
allow the operations of the HVC building while maintaining the safety of all Edwards personnel.

Long-Lead Items
In our analysis of expediting the delivery of the project, we have identified the following long-lead time items that dictate
early release prior to receiving the building permit and finalizing the GMP. The following trades and award dates are
necessary to maintain our schedule. The following example shows how we identify, schedule, and track long-lead items.

ITEM LEAD TIME AWARD DATE
• Curtain Wall 12 Months 12/13/18
• Architectural Metal Panels 5 Months 2/2/19
• Caissons 3 Months 11/9/19
• Concrete & Rebar 3 Months 1/15/19
• Structural Steel 6 Months 1/15/19
• Elevators 9 Months 2/12/19
• Precast 7 Months 2/12/19
• Stairs 6 Months 2/2/19

Long Lead Time Procurement Schedule:

Material & Manpower Availability/Procurement Strategy
Considering the current market conditions and workload of subcontractors, Snyder Langston will carefully review each
subcontractor for their capability and capacity to perform the work in a manner consistent with the project plan. For
example, given the unique complexity and difficulty of the work, Snyder Langston will carefully study the pros and cons of
awarding curtain wall for Buildings B and C to the same subcontractor.

Pull Planning with Team to Expedite Schedule
Snyder Langston utilizes subcontractor pull planning with key trade foremen to improve the certainty of meeting our
schedule.
We will monitor the schedule daily and issue formal updates no less than once per month. To improve the consistency of
performance, our Superintendents will hold weekly pull planning sessions with our subcontractor foremen and the design
team as appropriate as we have determined that this effort improves schedule outcomes by:

• Obtaining and maintaining schedule buy-in at the subcontractor foreman level.
• Increasing to 85% from 55% the percent of activities promised to be completed by the foremen.
• Improving quality and reducing rework

Construction Site Access Control for Manpower Management
Snyder Langston will utilize an access control system for construction worker access to the project to facilitate accurate
and timely management of manpower on site. This will enable our team to:

• Ensure schedule integrity by preventing subcontractor platooning workers on and off our project.
• Identify workers assigned to our project and ensure they have received safety and project orientation training.
• Maintain consistent workers who know the project and our commitment to schedule, safety, and quality.

Relationship with the City of Irvine
Our Superintendents have developed excellent working relationships with Irvine’s building inspectors by being ready,
honest and transparent. These relationships will benefit the project by expediting the inspection process.

• Brian Coffman will lead the scheduling and coordinating of inspections for the project. See sample below.
• Ensure that pre-requisites required by City of Irvine inspectors are met to avoid delays from re-inspections.
Sample Inspection Schedule:

Approach to Early Delivery for Interior Improvements Construction
Snyder Langston will work with Edwards and the City of Irvine to enable the start of Tenant Improvements to begin as
soon the City of Irvine will issue the permits. We will work with the selected Tenant Improvement contractor to provide
project access, material staging and MEP system connections.
CERTAINTY OF COST
GMP Preparation
To establish early cost certainty, Snyder Langston will prepare the GMP by January 15, 2019 with 80% of major trades
contracted and the remaining 20% bought by the end of February 2019. Using our SmartBidNet software, we will
competitively bid out all the subcontractor trades pursuant to a joint pre-approved subcontractor bid list. Bids will be
received, reviewed, and negotiated by Snyder Langston and then submitted to Edwards for approval.
PROJECT TEAM AND SIMILAR PROJECTS
The Snyder Langston team will deliver certainty of outcome with a dedicated project team who are experienced building
multiple projects in Irvine of similar size and scope to Building B.
Executive Meetings
Snyder Langston’s headquarters are approximately one mile from the project. Our ownership and full executive team will
be available and accessible at all times to support the project team. In addition, we suggest the use of executive meetings
to engage the leadership of all team members based on the following format:

• Regular monthly executive team meetings with Snyder Langston, Edwards, Jeff Gingold and LPA.
• Discuss what is working and what needs improvement regarding our administration of the project.
• Provide for open communication to facilitate a highly functioning team that delivers certainty of outcome.

Institutional Knowledge
Snyder Langston is a leading builder of office buildings in Orange County in general, and Irvine in particular. Our firm’s
institutional knowledge along with the capabilities of the project team is illustrated below. In addition, to create certainty
on achieving LEED Platinum and Gold Certification under Version 4, we have retained Brightworks who worked with us on
Boardwalk and has successfully certified a LEED Platinum project under Version 4.

* Sample Project Savings

Pacific Life Headquarters: $102,753 or 0.14% Savings

Sand Canyon Business Center: $689,175 or 1.5% Savings

The Boardwalk: $1,972,158 or 1.7% Savings

QUALITY CONTROL
Snyder Langston’s Quality Management System
As an ISO 9001:2015 Registered company, Snyder Langston is committed to ensuring quality throughout
all phases of construction and has a Quality Management System that:

• Assures resources assigned to your project are fully trained in Snyder Langston’s systems.
• Focuses on contract document compliance.
• Assures quality through extensive use of mock ups, off-site plant inspections and daily on-site

quality walks.
• Assures all quality discrepancies are tracked and resolved through the use of Quality Action

Reports (QARs).

SAFETY, SECURITY AND SITE LOGISTICS
We will develop an Edwards-specific safety plan to execute the project in an orderly fashion while preventing disruptions
to existing Edwards’s operations. The plan guidelines include the following activities:
• Preparation/updating of a detailed logistics plan reflective of the project

schedule and all applicable phasing, staging, site access, WQMP/SWPPP,
and City of Irvine security plan requirements for coordination and safety
with all parties.

• Preparation of a site-specific safety program for submission and approval
by Edwards Environmental, Health, and Safety (EHS) personnel.

• Development of a site-specific safety plan prepared by each
subcontractor.

• Oversight by Snyder Langston’s Safety Director, Risk Manager and 3rd
party safety inspectors.

Risk Mitigation Mindset

Snyder Langston will create and maintain a risk mitigation matrix throughout the life of the project to help the team
focus on areas of overall risk. Some examples of risk items Snyder Langston has identified are as follows:

• Utility relocation in the access drive north of HVC
• Interruption of utility services to ELS campus or portions of campus during excavations
• Continuity/Disruption of Deliveries to HVC
• Permitting Timelines
• Quality & Extent of Architectural Sheet Metal – finding the right sub(s) to perform this work on A & C
• Rapid ramp-up of project
• Security
• Safety of ELS employees and vendors during work within the ELS campus
• Dust & Erosion Control
• Work in Redhill
• Glass / Glazing and Structural Steel procurement and lead times

sample bim execution plan