Activity ID Activity Name Dur Current Start Current
Finish
Aug Sep Oct Nov Dec

1C-10020 Earthwork 15 06/26/19 07/17/19
5 07/18/19 07/24/19
1C-10030 Certify Pad 12/19/19
102 07/25/19
FOUNDATIONS / STRUCTURE

1C-15000 Drill/Rebar/Pour Piles (246) 25 07/25/19 08/28/19
15 08/22/19 09/12/19
1C-15100 Form/Rebar/Pour Pilecaps 10 08/29/19 09/12/19
15 09/06/19 09/26/19
1C-15200 Excavate/Form/Pour Elevator Pit 10 09/27/19 10/10/19
15 10/04/19 10/24/19
1C-15300 Form/Rebar/Pour Gradebeams 10 10/18/19 10/31/19
10 10/18/19 10/31/19
1C-17000 Erect Structural Steel 10 11/01/19 11/15/19
10 11/08/19 11/22/19
1C-17010 Weld Structural Steel 10 11/08/19 11/22/19
11/26/19
1C-17020 Erect BRB's 2 11/25/19 12/05/19
5 11/27/19 12/19/19
1C-17100 Metal Deck/Edge Metal/Shear Studs (2nd Floor) 10 12/06/19 12/03/19
15 11/08/19 04/27/20
1C-17110 Metal Deck/Edge Metal (Roof) 95 12/13/19

1C-18000 Underslab Plumbing Rough-in

1C-18050 Complete Rebar/Pour Gradebeams at Moment Frames

1C-18100 Fine Grade for SOG

1C-18110 Sand/Vapor Barrier for SOG

1C-18120 Form/Rebar/Pour SOG

1C-18200 MEP/Rebar/Pour Concrete on Metal Deck (2nd Floor)

EXTERIOR SKIN

1C-30000 Exterior Framing 15 12/13/19 01/06/20
10 12/20/19 01/06/20
1C-30010 Exterior MEP Rough-in 10 12/30/19 01/13/20
01/20/20
1C-30020 Exterior Sheathing 5 01/14/20 02/17/20
20 01/21/20 03/30/20
1C-30200 Waterproofing for Wood Rain Screen 60 01/07/20 03/16/20
10 03/03/20 03/30/20
1C-30210 Wood Rain Screen 10 03/17/20 04/06/20
02/10/20
1C-30300 Curtainwall 5 03/31/20 01/27/20
20 01/14/20 03/02/20
1C-30350 Storefront Framing 10 01/14/20 04/13/20
30 01/21/20 04/20/20
1C-30360 Storefront Glazing 40 02/18/20 04/27/20
05/26/20
1C-30370 Storefront Doors 5 04/14/20
5 04/21/20
1C-30400 Steel & Glass Guardrails 132 11/18/19

1C-30500 Weatherproofing for Aluminum Panels

1C-30510 Field Measure & Fab Aluminum Panels

1C-30520 Install Aluminum Panels

1C-30600 MEP Trim

1C-30900 Cleanup & Prepunch

ROOF

ROOF DECK 122 12/04/19 05/26/20
5 12/04/19 12/10/19
1C-40000 MEP Penetrations & Roof Drains 5 12/11/19 12/17/19
04/13/20
1C-40030 Sheetmetal Flashing 10 03/31/20 04/20/20
10 04/07/20 05/18/20
1C-40100 Waterproofing 20 04/21/20 05/26/20
02/13/20
1C-40110 Topping Slabs 5 05/19/20 11/22/19
60 11/18/19 11/22/19
1C-40300 Roof Deck Pavers & Finishes
5 11/18/19
1C-40900 Cleanup & Prepunch Roof Decks 5 11/18/19

MAIN ROOF

1C-41000 MEP Penetrations & Roof Drains

1C-41010 Mechanical Curbs

Project Start 09/10/18 Page 13 of 18 Edwards Lifescience
Project Finish 07/23/20 TASK filter: All Activities Proposal Schedule with C
Data Date 09/01/18
Run Date 10/05/18 Snyder L

2019 2020

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Earthwork

Certify Pad

FOUNDATIONS / STRUCTURE

Drill/Rebar/Pour Piles (246)

Form/Rebar/Pour Pilecaps

Excavate/Form/Pour Elevator Pit

Form/Rebar/Pour Gradebeams

Erect Structural Steel

Weld Structural Steel

Erect BRB's

Metal Deck/Edge Metal/Shear Studs (2nd Floor)

Metal Deck/Edge Metal (Roof)

Underslab Plumbing Rough-in

Complete Rebar/Pour Gradebeams at Moment Frames

Fine Grade for SOG

Sand/Vapor Barrier for SOG

Form/Rebar/Pour SOG

MEP/Rebar/Pour Concrete on Metal Deck (2nd Floor)

EXTERIOR SKIN

Exterior Framing

Exterior MEP Rough-in

Exterior Sheathing

Waterproofing for Wood Rain Screen

Wood Rain Screen

Curtainwall

Storefront Framing

Storefront Glazing

Storefront Doors

Steel & Glass Guardrails

Weatherproofing for Aluminum Panels

Field Measure & Fab Aluminum Panels

Install Aluminum Panels

MEP Trim

Cleanup & Prepunch

ROOF

ROOF DECK

MEP Penetrations & Roof Drains

Sheetmetal Flashing

Waterproofing

Topping Slabs

Roof Deck Pavers & Finishes

Cleanup & Prepunch Roof Decks

MAIN ROOF

MEP Penetrations & Roof Drains

Mechanical Curbs

es Campus Expansion Remaining Level of Effort
ConXtech Steel - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work

Activity ID Activity Name Dur Current Start Current
Finish
Aug Sep Oct Nov Dec

1C-41030 Sheetmetal Flashing 5 11/25/19 12/03/19
10 12/04/19 12/17/19
1C-41100 Roofing 12/24/19
5 12/18/19 01/23/20
1C-41200 Set Mechanical Equipment 20 12/26/19 01/16/20
20 12/18/19 02/06/20
1C-41210 Hookup Mechanical Equipment 10 01/24/20 02/13/20
06/04/20
1C-41300 Roof Screen Panels 5 02/07/20
122 12/13/19
1C-41400 Sheetmetal Trim & Finish

1C-41900 Cleanup & Prepunch Roof

INTERIOR

1ST FLOOR CORE 109 12/13/19 05/15/20
10 12/13/19 12/27/19
1C-50000 Overhead Mechanical Rough-in 10 12/20/19 01/06/20
10 12/20/19 01/06/20
1C-50010 Overhead Plumbing Rough-in 10 12/20/19 01/06/20
10 12/20/19 01/06/20
1C-50020 Overhead Fire Sprinkler Rough-in 10 12/30/19 01/13/20
10 12/30/19 01/13/20
1C-50030 Overhead Electrical Rough-in 10 12/30/19 01/13/20
5 01/09/20 01/15/20
1C-50100 Wall Framing & Furring 5 01/13/20 01/17/20
10 01/15/20 01/28/20
1C-50110 Wall Plumbing Rough-in 10 01/07/20 01/20/20
10 01/14/20 01/27/20
1C-50120 Wall Electrical Rough-in 10 01/14/20 01/27/20
10 01/14/20 01/27/20
1C-50130 Wall Low Voltage Rough-in 5 01/23/20 01/29/20
10 01/27/20 02/07/20
1C-50140 Wall MEP & Framing Inspections 10 02/10/20 02/21/20
10 02/17/20 02/28/20
1C-50150 Wall Insulation (dry-in) 20 02/24/20 03/20/20
5 02/24/20 02/28/20
1C-50160 Drywall Walls 20 03/02/20 03/27/20
10 03/30/20 04/10/20
1C-50200 Hard Ceiling Framing 10 04/06/20 04/17/20
2 04/20/20 04/21/20
1C-50210 Hard Ceiling Mechanical Rough-in 5 04/20/20 04/24/20
5 04/27/20 05/01/20
1C-50220 Hard Ceiling Fire Sprinkler Rough-in 5 05/04/20 05/08/20
5 05/04/20 05/08/20
1C-50230 Hard Ceiling Electrical Rough-in 5 05/04/20 05/08/20
5 05/04/20 05/08/20
1C-50240 Hard Ceiling MEP Inspections 5 05/04/20 05/08/20
15 02/24/20 03/13/20
1C-50250 Drywall Ceilings 5 03/09/20 03/13/20
5 03/16/20 03/20/20
1C-50260 Tape Drywall Walls & Ceilings 5 05/11/20 05/15/20

1C-50300 Prime & Paint

1C-50310 Electrical Panels & Pull Wire

1C-50320 Door Frames

1C-50400 Ceiling Finishes

1C-50460 Suspended & Surface Mounted Fixtures

1C-50600 Flooring

1C-50610 Base

1C-50620 Hang Doors

1C-50630 Finish Paint

1C-50640 Door Hardware

1C-50650 Mechanical Trim

1C-50660 Fire Sprinkler Trim

1C-50670 Electrical Trim

1C-50680 Low Voltage Trim

1C-50800 Tile (Restrooms)

1C-50820 Plumbing Fixtures (Restrooms)

1C-50840 Toilet Accessories (Restrooms)

1C-50900 Cleanup & Prepunch Interior

Project Start 09/10/18 Page 14 of 18 Edwards Lifescience
Project Finish 07/23/20 TASK filter: All Activities Proposal Schedule with C
Data Date 09/01/18
Run Date 10/05/18 Snyder L

2019 2020

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Sheetmetal Flashing

Roofing

Set Mechanical Equipment

Hookup Mechanical Equipment

Roof Screen Panels

Sheetmetal Trim & Finish

Cleanup & Prepunch Roof

INTERIOR

1ST FLOOR CORE

Overhead Mechanical Rough-in

Overhead Plumbing Rough-in

Overhead Fire Sprinkler Rough-in

Overhead Electrical Rough-in

Wall Framing & Furring

Wall Plumbing Rough-in

Wall Electrical Rough-in

Wall Low Voltage Rough-in

Wall MEP & Framing Inspections

Wall Insulation (dry-in)

Drywall Walls

Hard Ceiling Framing

Hard Ceiling Mechanical Rough-in

Hard Ceiling Fire Sprinkler Rough-in

Hard Ceiling Electrical Rough-in

Hard Ceiling MEP Inspections

Drywall Ceilings

Tape Drywall Walls & Ceilings

Prime & Paint

Electrical Panels & Pull Wire

Door Frames

Ceiling Finishes

Suspended & Surface Mounted Fixtures

Flooring

Base

Hang Doors

Finish Paint

Door Hardware

Mechanical Trim

Fire Sprinkler Trim

Electrical Trim

Low Voltage Trim

Tile (Restrooms)

Plumbing Fixtures (Restrooms)

Toilet Accessories (Restrooms)

Cleanup & Prepunch Interior

es Campus Expansion Remaining Level of Effort
ConXtech Steel - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work

Activity ID Activity Name Dur Current Start Current
Finish
Aug Sep Oct Nov Dec

2ND FLOOR CORE 112 12/30/19 06/04/20
15 12/30/19 01/20/20
1C-55000 Overhead Mechanical Rough-in 15 01/07/20 01/27/20
15 01/07/20 01/27/20
1C-55010 Overhead Plumbing Rough-in 15 01/07/20 01/27/20
15 01/07/20 01/27/20
1C-55020 Overhead Fire Sprinkler Rough-in 15 01/14/20 02/03/20
15 01/14/20 02/03/20
1C-55030 Overhead Electrical Rough-in 15 01/14/20 02/03/20
02/05/20
1C-55100 Wall Framing & Furring 5 01/30/20 02/07/20
5 02/03/20 02/18/20
1C-55110 Wall Plumbing Rough-in 10 02/05/20 02/03/20
10 01/21/20 02/10/20
1C-55120 Wall Electrical Rough-in 10 01/28/20 02/10/20
10 01/28/20 02/10/20
1C-55130 Wall Low Voltage Rough-in 10 01/28/20 02/10/20
10 01/28/20 02/17/20
1C-55140 Wall MEP & Framing Inspections 5 02/11/20 02/26/20
10 02/13/20 03/11/20
1C-55150 Wall Insulation (dry-in) 10 02/27/20 03/18/20
10 03/05/20 04/08/20
1C-55160 Drywall Walls 20 03/12/20 03/18/20
5 03/12/20 04/15/20
1C-55200 Hard Ceiling Framing 20 03/19/20 04/29/20
10 04/16/20 05/06/20
1C-55210 Hard Ceiling Mechanical Rough-in 10 04/23/20 05/08/20
2 05/07/20 05/13/20
1C-55220 Hard Ceiling Fire Sprinkler Rough-in 5 05/07/20 05/20/20
5 05/14/20 05/28/20
1C-55230 Hard Ceiling Electrical Rough-in 5 05/21/20 05/28/20
5 05/21/20 05/28/20
1C-55235 Operable Wall Tracks 5 05/21/20 05/28/20
5 05/21/20 05/28/20
1C-55240 Hard Ceiling MEP Inspections 5 05/21/20 05/28/20
5 05/21/20 04/08/20
1C-55250 Drywall Ceilings 20 03/12/20 04/15/20
10 04/02/20 04/22/20
1C-55260 Tape Drywall Walls & Ceilings 10 04/09/20 06/04/20
5 05/29/20 04/29/20
1C-55300 Prime & Paint 35 03/12/20
04/01/20
1C-55310 Electrical Panels & Pull Wire 15 03/12/20 04/08/20
10 03/26/20 04/15/20
1C-55320 Door Frames 10 04/02/20 04/22/20
10 04/09/20 04/29/20
1C-55400 Ceiling Finishes 10 04/16/20

1C-55460 Suspended & Surface Mounted Fixtures

1C-55600 Flooring

1C-55610 Base

1C-55620 Hang Doors

1C-55630 Finish Paint

1C-55640 Door Hardware

1C-55650 Mechanical Trim

1C-55660 Fire Sprinkler Trim

1C-55670 Electrical Trim

1C-55680 Low Voltage Trim

1C-55690 Operable Wall Panels

1C-55800 Tile (Restrooms)

1C-55820 Plumbing Fixtures (Restrooms)

1C-55840 Toilet Accessories (Restrooms)

1C-55900 Cleanup & Prepunch Interior

INTERIOR STAIRS

1C-70000 Drywall & Tape Stairs

1C-70010 Handrails

1C-70020 Prime & Paint

1C-70030 Flooring

1C-70040 MEP Trim

Project Start 09/10/18 Page 15 of 18 Edwards Lifescience
Project Finish 07/23/20 TASK filter: All Activities Proposal Schedule with C
Data Date 09/01/18
Run Date 10/05/18 Snyder L

2019 2020

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

2ND FLOOR CORE

Overhead Mechanical Rough-in

Overhead Plumbing Rough-in

Overhead Fire Sprinkler Rough-in

Overhead Electrical Rough-in

Wall Framing & Furring

Wall Plumbing Rough-in

Wall Electrical Rough-in

Wall Low Voltage Rough-in

Wall MEP & Framing Inspections

Wall Insulation (dry-in)

Drywall Walls

Hard Ceiling Framing

Hard Ceiling Mechanical Rough-in

Hard Ceiling Fire Sprinkler Rough-in

Hard Ceiling Electrical Rough-in

Operable Wall Tracks

Hard Ceiling MEP Inspections

Drywall Ceilings

Tape Drywall Walls & Ceilings

Prime & Paint

Electrical Panels & Pull Wire

Door Frames

Ceiling Finishes

Suspended & Surface Mounted Fixtures

Flooring

Base

Hang Doors

Finish Paint

Door Hardware

Mechanical Trim

Fire Sprinkler Trim

Electrical Trim

Low Voltage Trim

Operable Wall Panels

Tile (Restrooms)

Plumbing Fixtures (Restrooms)

Toilet Accessories (Restrooms)

Cleanup & Prepunch Interior

INTERIOR STAIRS

Drywall & Tape Stairs

Handrails

Prime & Paint

Flooring

MEP Trim

es Campus Expansion Remaining Level of Effort
ConXtech Steel - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work

Activity ID Activity Name Dur Current Start Current
Finish
Aug Sep Oct Nov Dec

ELEVATORS 40 03/12/20 05/06/20

1C-71000 Elevator Pre-Check List & Corrections 10 03/12/20 03/25/20
5 03/26/20 04/01/20
1C-71010 Elevator Rails 5 04/02/20 04/08/20
3 04/09/20 04/13/20
1C-71020 Elevator Equipment 3 04/14/20 04/16/20
5 04/17/20 04/23/20
1C-71030 Elevator Temp Platform 5 04/30/20 05/06/20
06/23/20
1C-71040 Elevator Door Frames 293 04/29/19
05/24/19
1C-71050 Elevator Cab & Finishes 20 04/29/19 06/24/19
20 05/28/19 05/26/20
1C-71060 Elevator Test & Adjust 100 01/07/20 06/23/20
40 04/28/20 07/22/20
SITEWORK 73 04/09/20
04/29/20
1C-80000 Site Wet Utilities 15 04/09/20 07/08/20
10 06/24/20 07/08/20
1C-80100 Site Dry Utilities 40 05/12/20 07/22/20
10 07/09/20 07/22/20
1C-80400 Hardscape (Cafe/Conference) 06/23/20
0 07/22/20
1C-80410 Landscape (Cafe/Conference) 2 06/22/20 07/22/20
20 06/24/20 02/06/20
INSPECTIONS / PUNCHLIST 0
278 01/03/19
1C-89000 Permanent Power

1C-90000 Final Inspections

1C-90005 Commissioning/LEED Approval

1C-90010 Inclement Weather Allowance

1C-90020 Substantial Completion

1C-90100 Prepare Punchlist

1C-90110 Punchlist Corrections

1C-90120 Final Completion

CONSTRUCTION - PHASE 1 - OFFSITE

REDHILL DECELERATION LANE, LEFT TURN LANE, MEDIAN, U/G UTILITIES 278 01/03/19 02/06/20

1S-11900 Submit/Approve Traffic Control Plans 60 01/03/19 03/27/19
10 03/28/19 04/10/19
1S-12000 Post Advanced Construction Notification & Street Signage 04/11/19
1 04/11/19 04/18/19
1S-12010 Contact Underground Dig Alert & Record Permit Number 5 04/12/19 04/25/19
5 04/19/19 05/02/19
1S-12020 Verify, Document & Submit Existing Conditions Prior to Start 5 04/26/19 05/07/19
3 05/03/19 05/14/19
1S-12030 Survey Demo Limits Prior to Start & Confirm with Contract Documents 5 05/08/19 06/05/19
15 05/15/19 06/05/19
1S-12040 Preconstruction Conference with City of Irvine as Required 15 05/15/19 06/05/19
15 05/15/19 06/06/19
1S-12100 Setup Temporary Traffic Control Measures 1 06/06/19 06/11/19
3 06/07/19 06/14/19
1S-12110 Setup Temporary BMP's 3 06/12/19 06/18/19
2 06/17/19 06/20/19
1S-12112 Construct (N) 16 in ACP Water Main 2 06/19/19 06/27/19
5 06/21/19 07/05/19
1S-12114 Construct (N) Fire, Domestic & Irrigation D.I. Laterals 5 06/28/19 07/12/19
5 07/08/19 07/15/19
1S-12116 R&R Fire Hydrant & Remove Lateral 1 07/15/19 06/07/19
2 06/06/19
1S-12118 Survey & Layout Raised Islands

1S-12120 Sawcut & Demo Hardscapes for Raised Islands

1S-12122 Grade & Compact Subgrades for Raised Islands

1S-12124 Form Raised Islands & Certify Formwork

1S-12126 Pour & Strip Curb Islands

1S-12128 Backfill & Compact Curb Islands

1S-12130 Patch A/C Paving at Curb Islands

1S-12132 Grind & Overlay A/C Paving at Curb Islands

1S-12134 Temporary Striping

1S-12136 Remove & Relocate Construction Fencing

Project Start 09/10/18 Page 16 of 18 Edwards Lifescience
Project Finish 07/23/20 TASK filter: All Activities Proposal Schedule with C
Data Date 09/01/18
Run Date 10/05/18 Snyder L

2019 2020

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

ELEVATORS

Elevator Pre-Check List & Corrections

Elevator Rails

Elevator Equipment

Elevator Temp Platform

Elevator Door Frames

Elevator Cab & Finishes

Elevator Test & Adjust

SITEWORK

Site Wet Utilities

Site Dry Utilities

Hardscape (Cafe/Conference)

Landscape (Cafe/Conference)

INSPECTIONS / PUNCHLIST

Permanent Power

Final Inspections

Commissioning/LEED Approval

Inclement Weather Allowance

Substantial Completion

Prepare Punchlist

Punchlist Corrections

Final Completion

CONSTRUCTION - PHASE 1 - OFFSITE

REDHILL DECELERATION LANE, LEFT TURN LANE, MEDIAN, U/G UTILITIES

Submit/Approve Traffic Control Plans
Post Advanced Construction Notification & Street Signage
Contact Underground Dig Alert & Record Permit Number
Verify, Document & Submit Existing Conditions Prior to Start
Survey Demo Limits Prior to Start & Confirm with Contract Documents
Preconstruction Conference with City of Irvine as Required
Setup Temporary Traffic Control Measures
Setup Temporary BMP's
Construct (N) 16 in ACP Water Main
Construct (N) Fire, Domestic & Irrigation D.I. Laterals
R&R Fire Hydrant & Remove Lateral
Survey & Layout Raised Islands
Sawcut & Demo Hardscapes for Raised Islands
Grade & Compact Subgrades for Raised Islands
Form Raised Islands & Certify Formwork
Pour & Strip Curb Islands
Backfill & Compact Curb Islands
Patch A/C Paving at Curb Islands
Grind & Overlay A/C Paving at Curb Islands
Temporary Striping
Remove & Relocate Construction Fencing

es Campus Expansion Remaining Level of Effort
ConXtech Steel - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work

Activity ID Activity Name Dur Current Start Current
Finish
Aug Sep Oct Nov Dec

1S-12138 Safe-off & Re-Route Irrigation 2 06/10/19 06/11/19
2 06/12/19 06/13/19
1S-12140 Remove & Salvage Signage as Applicable 5 06/14/19 06/20/19
5 06/21/19 06/27/19
1S-12150 Remove & Relocate Existing Low Volt Pull Box & Assoc. Cabling 3 06/28/19 07/02/19
1 07/03/19 07/03/19
1S-12160 Remove & Protect Existing Bus Bench, Trash Can & Associated Signage 5 07/05/19 07/11/19
2 07/12/19 07/15/19
1S-12200 Demo (E) Hardscapes & Landscapes 10 07/16/19 07/29/19
5 07/30/19 08/05/19
1S-12210 Survey (N) Curb & Gutter 5 07/30/19 08/05/19
1 08/06/19 08/06/19
1S-12220 Prepare Subgrade for (N) Deceleration Lane, Curb & Gutter 5 08/07/19 08/13/19
3 08/14/19 08/16/19
1S-12230 Test Subgrade for Compaction 1 08/19/19 08/19/19
1 08/20/19 08/20/19
1S-12240 Install (N) Below Grade Signal Conduit & Associated Pull Boxes 5 08/21/19 08/27/19
1 08/28/19 08/28/19
1S-12242 Relocate Pedestrian Light Pole 3 08/29/19 09/03/19
2 09/04/19 09/05/19
1S-12250 Form (N) Curb & Gutter & EntranceApron 3 09/06/19 09/10/19
1 09/11/19 09/11/19
1S-12260 Survey & Record (N) Curb & Gutter Formwork - Prepour 2 09/12/19 09/13/19
10 01/02/20* 01/15/20
1S-12270 Pour (N) Curb & Gutter, Entrance Apron, Strip & Cure 5 01/16/20 01/22/20
10 01/23/20 02/05/20
1S-12280 Backfill & Compact Behind Curb & Gutter, Entrance Apron 1 02/06/20 02/06/20
110 08/01/19 01/09/20
1S-12290 Survey Subgrade for Sidewalks at EntranceApron

1S-12300 Install (N) Posts & Signage as Applicable

1S-12310 Form Sidewalks

1S-12320 Survey & Record (N) Sidewalk Formwork

1S-12330 Pour Sidewalks, Strip & Cure

1S-12340 Install Relocated Bus Stop Bench, Trash Can & Associated Signage

1S-12350 Prepare Roadway Subgrade with .65' Aggregate Base & Compact

1S-12360 Test Compaction of A.B.

1S-12370 A/C Paving

1S-12372 Grind & Overlay A/C Paving

1S-12374 Slurry Seal A/C Paving

1S-12376 Striping 1st Pass, Cure & Final Stripe

1S-12380 Final Clean

ALTON PKWY STREET WIDENING & U/G UTILITIES

1S-20000 Post Advanced Construction Notification & Street Signage 10 08/01/19* 08/14/19
1 08/15/19 08/15/19
1S-20010 Contact Underground Dig Alert & Record Permit Number 5 08/16/19 08/22/19
5 08/23/19 08/29/19
1S-20020 Verify, Document & Submit Existing Conditions Prior to Start 5 08/30/19 09/06/19
3 09/09/19 09/11/19
1S-20030 Survey Demo Limits Prior to Start & Confirm with Contract Documents 5 09/12/19 09/18/19
10/09/19
1S-20040 Preconstruction Conference with City of Irvine as Required 15 09/19/19 10/02/19
10 09/19/19 09/20/19
1S-20050 Setup Temporary Traffic Control Measures 09/24/19
2 09/19/19 09/26/19
1S-20060 Setup Temporary BMP's 2 09/23/19 10/03/19
2 09/25/19 10/10/19
1S-20070 Sanitary Sewer Improvements 5 09/27/19 10/17/19
5 10/04/19 10/18/19
1S-20080 Relocate Fire Hydrants 5 10/11/19 10/22/19
1 10/18/19
1S-20090 Remove & Relocate Construction Fencing 2 10/21/19

1S-20100 Safe-off & Re-Route Irrigation

1S-20110 Remove & Salvage Signage as Applicable

1S-20120 Remove & Relocate Existing Low Volt Pull Box & Assoc. Cabling

1S-20130 Remove & Protect Existing Bus Bench, Trash Can & Associated Signage

1S-20140 Demo (E) Hardscapes & Landscapes

1S-20150 Survey (N) Curb & Gutter

1S-20160 Prepare Subgrade for (N) Street Widening, Curb & Gutter

Project Start 09/10/18 Page 17 of 18 Edwards Lifescience
Project Finish 07/23/20 TASK filter: All Activities Proposal Schedule with C
Data Date 09/01/18
Run Date 10/05/18 Snyder L

2019 2020

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Safe-off & Re-Route Irrigation

Remove & Salvage Signage as Applicable

Remove & Relocate Existing Low Volt Pull Box & Assoc. Cabling

Remove & Protect Existing Bus Bench, Trash Can & Associated Signage

Demo (E) Hardscapes & Landscapes

Survey (N) Curb & Gutter

Prepare Subgrade for (N) Deceleration Lane, Curb & Gutter

Test Subgrade for Compaction

Install (N) Below Grade Signal Conduit & Associated Pull Boxes

Relocate Pedestrian Light Pole

Form (N) Curb & Gutter & EntranceApron

Survey & Record (N) Curb & Gutter Formwork - Prepour

Pour (N) Curb & Gutter, Entrance Apron, Strip & Cure

Backfill & Compact Behind Curb & Gutter, Entrance Apron

Survey Subgrade for Sidewalks at EntranceApron

Install (N) Posts & Signage as Applicable

Form Sidewalks

Survey & Record (N) Sidewalk Formwork

Pour Sidewalks, Strip & Cure

Install Relocated Bus Stop Bench, Trash Can & Associated Signage

Prepare Roadway Subgrade with .65' Aggregate Base & Compact

Test Compaction of A.B.

A/C Paving

Grind & Overlay A/C Paving

Slurry Seal A/C Paving

Striping 1st Pass, Cure & Final Stripe

Final Clean

ALTON PKWY STREET WIDENING & U/G UTILITIES

Post Advanced Construction Notification & Street Signage

Contact Underground Dig Alert & Record Permit Number

Verify, Document & Submit Existing Conditions Prior to Start

Survey Demo Limits Prior to Start & Confirm with Contract Documents

Preconstruction Conference with City of Irvine as Required

Setup Temporary Traffic Control Measures

Setup Temporary BMP's

Sanitary Sewer Improvements

Relocate Fire Hydrants

Remove & Relocate Construction Fencing

Safe-off & Re-Route Irrigation

Remove & Salvage Signage as Applicable

Remove & Relocate Existing Low Volt Pull Box & Assoc. Cabling

Remove & Protect Existing Bus Bench, Trash Can & Associated Signage

Demo (E) Hardscapes & Landscapes

Survey (N) Curb & Gutter

Prepare Subgrade for (N) Street Widening, Curb & Gutter

es Campus Expansion Remaining Level of Effort
ConXtech Steel - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work

Activity ID Activity Name Dur Current Start Current Aug Sep Oct Nov Dec
Finish
1S-20170 Test Subgrade for Compaction
1S-20180 Install (N) Below Grade Signal Conduit & Associated Pull Boxes 1 10/23/19 10/23/19
1S-20190 Form (N) Curb & Gutter & EntranceApron 10 10/24/19 11/06/19
1S-20200 Survey & Record (N) Curb & Gutter Formwork - Prepour 11/08/19
1S-20210 Pour (N) Curb & Gutter, Entrance Apron, Strip & Cure 2 11/07/19 11/12/19
1S-20220 Backfill & Compact Behind Curb & Gutter, Entrance Apron 1 11/12/19 11/14/19
1S-20230 Survey Subgrade for Sidewalks 2 11/13/19 11/15/19
1S-20240 Install (N) Posts & Signage as Applicable 1 11/15/19 11/18/19
1S-20250 Form Sidewalks 1 11/18/19 11/19/19
1S-20260 Pour Sidewalks, Strip & Cure 1 11/19/19 11/20/19
1S-20270 Install Relocated Signage 1 11/20/19 11/21/19
1S-20280 Prepare Roadway Subgrade with .65' Aggregate Base & Compact 1 11/21/19 11/25/19
1S-20290 Test Compaction of A.B. 2 11/22/19 11/27/19
1S-20300 A/C Paving 2 11/26/19 12/02/19
1S-20310 Grind & Overlay A/C Paving 1 12/02/19 12/04/19
1S-20320 Slurry Seal A/C Paving 2 12/03/19 12/06/19
1S-20330 Striping 1st Pass, Cure & Final Stripe 2 12/05/19 12/10/19
1S-20340 Final Inspections 2 12/09/19 12/24/19
10 12/11/19 01/09/20
10 12/26/19

Project Start 09/10/18 Page 18 of 18 Edwards Lifescience
Project Finish 07/23/20 TASK filter: All Activities Proposal Schedule with C
Data Date 09/01/18
Run Date 10/05/18 Snyder L

2019 2020

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Test Subgrade for Compaction

Install (N) Below Grade Signal Conduit & Associated Pull Boxes

Form (N) Curb & Gutter & EntranceApron

Survey & Record (N) Curb & Gutter Formwork - Prepour

Pour (N) Curb & Gutter, Entrance Apron, Strip & Cure

Backfill & Compact Behind Curb & Gutter, Entrance Apron

Survey Subgrade for Sidewalks

Install (N) Posts & Signage as Applicable

Form Sidewalks

Pour Sidewalks, Strip & Cure

Install Relocated Signage

Prepare Roadway Subgrade with .65' Aggregate Base & Compact

Test Compaction of A.B.

A/C Paving

Grind & Overlay A/C Paving

Slurry Seal A/C Paving

Striping 1st Pass, Cure & Final Stripe

Final Inspections

es Campus Expansion Remaining Level of Effort
ConXtech Steel - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work

concrete schedule

Activity ID Activity Name Dur Current Start Current Finish
Aug Sep Oct Nov Dec
Edwards ELS Expansion (10/05/18 proposal w/Concrete B)
471 09/10/18 07/23/20
SUMMARY & MILESTONES
431 11/05/18 07/23/20

OVERALL 431 11/05/18 07/22/20

S1000 Start Construction 0 11/05/18* 07/22/20 Start Con
431 11/05/18 07/22/20 Phase 0 S
S1010 Overall Construction (SUMMARY) 07/22/20
0 07/22/20
S1090 Substantial Completion 60 04/28/20 07/23/20
01/28/19
S1100 Punchlist & Closeout (SUMMARY) 0
431 11/05/18 01/28/19
S1110 Final Completion 01/28/19
54 11/05/18 07/08/20
DETAIL 0 11/05/18 04/05/19

PHASE 0 54 11/05/18 07/07/20
0 10/30/19
S2000 Phase 0 Start Construction
384 01/03/19 07/07/20
S2010 Phase 0 Construction Duration (SUMMARY) 67 01/03/19
0 02/01/19* 07/07/20
S2050 Phase 0 Complete Construction 07/07/20*
363 02/01/19 05/29/20
PHASE 1 (BUILDING B) 0
0 10/31/19 05/28/20
S2190 Utility Relocations (SUMMARY) 0 09/26/19
0 07/08/20
S2200 Phase 1 Start Construction (Building B) 05/28/20
22 06/05/20
S2210 Phase 1 Construction Duration (Building B) (SUMMARY) 0 05/28/20
05/28/20
S2215 Phase 1 Concrete Roof Deck Complete (Building B) 290 04/08/19 07/23/20
0 04/08/19
S2220 Ready for Tenant Improvements (Building B) (by SL) 07/22/20
290 04/08/19 10/10/19
S2250 Phase 1 Substantial Completion (Building B) 0
0 12/03/19 07/22/20
S2255 Ready for Tenant Improvements (Building B) (by Others) 0
0 05/29/20 07/22/20
S2260 Phase 1 Punchlist & Corrections (Building B) (SUMMARY) 07/22/20
22 04/28/20 02/06/20
S2270 Phase 1 Final Completion (Building B) 0
02/06/20
PHASE 1 (BUILDING A) 273 06/25/19 02/06/20
0 06/25/19*
S2100 Phase 1 Start Construction (Building A)
273 06/25/19
S2110 Phase 1 Construction Duration (Building A) (SUMMARY) 0
0 12/13/19
S2115 Phase 1 Steel Erection Complete (Building A) 0
0 07/23/20
S2120 Ready for Tenant Improvements (Building A) (by SL)
22 06/22/20
S2150 Phase 1 Substantial Completion (Building A) 0

S2155 Ready for Tenant Improvements (Building A) (by Others) 218 03/28/19
0 03/28/19
S2160 Phase 1 Punchlist & Corrections (Building A) (SUMMARY)
218 03/28/19
S2170 Phase 1 Final Completion (Building A) 0

PHASE 1 (BUILDING C)

S2300 Phase 1 Start Construction (Building C)

S2310 Phase 1 Construction Duration (Building C) (SUMMARY)

S2315 Phase 1 Steel Erection Complete (Building C)

S2320 Ready for Tenant Improvements (Building C) (by SL)

S2350 Phase 1 Substantial Completion (Building C)

S2355 Ready for Tenant Improvements (Building C) (by Others)

S2360 Phase 1 Punchilst & Corrections (Building C) (SUMMARY)

S2370 Phase 1 Final Completion (Building C)

PHASE 1 (OFFSITE - ALTON PKWY & REDHILL AVE)

S2400 Phase 1 Start Construction (Offsite)

S2410 Phase 1 Construction Duration (Offsite) (SUMMARY)

S2420 Phase 1 Complete Construction (Offsite)

Project Start 09/10/18 Page 1 of 18 Edwards Lifescience
Project Finish 07/23/20 TASK filter: All Activities Proposal Schedule with Buil
Data Date 09/01/18
Run Date 10/05/18 Snyder L

2019 2020

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Edwards ELS Expansion (10/05/18 proposal w/Conc

SUMMARY & MILESTONES

OVERALL

nstruction
Overall Construction (SUMMARY)
Substantial Completion
Punchlist & Closeout (SUMMARY)
Final Completion
DETAIL

PHASE 0
Start Construction

Phase 0 Construction Duration (SUMMARY)
Phase 0 Complete Construction

PHASE 1 (BUILDING B)
Utility Relocations (SUMMARY)
Phase 1 Start Construction (Building B)

Phase 1 Construction Duration (Building B) (SUMMARY
Phase 1 Concrete Roof Deck Complete (Building B)
Ready for Tenant Improvements (Building B) (by SL)

Phase 1 Substantial Completion (Building B)
Ready for Tenant Improvements (Building B) (by Others)
Phase 1 Punchlist & Corrections (Building B) (SUMMAR
Phase 1 Final Completion (Building B)
PHASE 1 (BUILDING A)
Phase 1 Start Construction (Building A)
Phase 1 Construction Duration (Building A) (SUMMARY)
Phase 1 Steel Erection Complete (Building A)
Ready for Tenant Improvements (Building A) (by SL)
Phase 1 Substantial Completion (Building A)
Ready for Tenant Improvements (Building A) (by Others)
Phase 1 Punchlist & Corrections (Building A) (SUMMARY)
Phase 1 Final Completion (Building A)

PHASE 1 (BUILDING C)
Phase 1 Start Construction (Building C)

Phase 1 Construction Duration (Building C) (SUMMA
Phase 1 Steel Erection Complete (Building C)

Ready for Tenant Improvements (Building C) (by SL)
Phase 1 Substantial Completion (Building C)
Ready for Tenant Improvements (Building C) (by Oth
Phase 1 Punchilst & Corrections (Building C) (SUMM
Phase 1 Final Completion (Building C)

PHASE 1 (OFFSITE - ALTON PKWY & REDHILL AVE)
Phase 1 Start Construction (Offsite)

Phase 1 Construction Duration (Offsite) (SUMMARY)
Phase 1 Complete Construction (Offsite)

es Campus Expansion Remaining Level of Effort
lding B Concrete - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work

Activity ID Activity Name Dur Current Start Current Finish

Aug Sep Oct Nov Dec

CONTRACT AWARD 30 09/10/18 10/19/18 CONTRACT

D1000 Prepare Proposal 20 09/10/18* 10/05/18 Prepare Proposal
0 10/05/18 Submit Proposal
D1010 Submit Proposal 5 10/08/18 10/12/18
0 10/12/18 Owner Review
D1020 Owner Review Proposal / Interview 5 10/15/18 10/19/18 Owner Award C
09/12/19
D1030 Owner Award Contract 218 10/29/18 Execute Cont

D1040 Execute Contract

CRITICAL PERMIT MILESTONES

. 113 10/29/18 04/15/19

D2000 Phase 0 Building Permit 0 10/29/18* Phase 0 Bu
0 12/17/18*
D2005 Precise Grading Permit for Building A, B & C 0 01/15/19*
0 02/15/19*
D2010 1st Plan Check Comments from City for Building A & B 0 02/15/19*
0 03/15/19*
D2020 1st Plan Check Comments from City for Building C 0 04/15/19*
0 01/02/19 01/02/19
D2030 Foundation Only Permit (if not bldg) for Building A, B & C
0 01/02/19*
D2040 Full Building Permit for Building A & B 0 01/02/19*
0 01/02/19*
D2050 Full Building Permit for Building C 0 01/02/19*
0 01/02/19*
ONSITE/OFFSITE PERMITS 0 01/02/19*
0 01/02/19*
D2100 Site Electrical Permit 200 11/28/18 09/12/19

D2110 SCE Permit 30 11/28/18 01/14/19
30 08/01/19 09/12/19
D2120 OCFA Permit 298 10/22/18 12/31/19

D2130 Yard Permit

D2140 Civil Permit

D2150 MCE Offsite Encroachment Permit

D2160 IRWD Permit

FAA PERMITS

D2200 Obtain FAA Crane Permit (Generator Relocation)

D2210 Obtain FAA Crane Permit (Steel Erection)

CRITICAL SUBMITTALS & PROCUREMENT

DIVISION 02 - SITE 45 10/22/18 12/28/18

P023000.10 Bid & Award Piles 15 10/22/18 11/09/18 Bid & Aw
10 11/13/18 11/28/18 Prep
P023000.20 Prepare Shop Drawings for Piles 20 11/29/18 12/28/18
10 11/29/18 12/12/18 T
P023000.21 City Review Shop Drawings for Piles 12/19/18
5 12/13/18 12/28/18
P023000.30 Test Piles 5 12/20/18 09/27/19
180 01/16/19
P023000.31 Document Test Piles 02/12/19
20 01/16/19 05/07/19
P023000.32 City Review Test Piles 60 02/13/19 06/05/19
20 05/08/19 09/27/19
DIVISION 03 - CONCRETE 80 06/06/19 08/07/19
167 12/10/18
P034000.10 Bid & Award Precast 01/15/19
23 12/10/18* 01/25/19
P034000.20 Prepare Shop Drawings Precast 8 01/16/19 01/28/19
1 01/28/19 07/24/19
P034000.21 Review/Approve Shop Drawings Precast
125 01/29/19
P034000.29 Fabricate Precast Panels

DIVISION 05 - METALS

P051000.05 Bid Structural Steel

P051000.06 Steel Bidders Review 1st Plan Check & Update Bids (Bldg A & B)

P051000.10 Award Structural Steel

P051000.30 Submittal/Review/Fabricate Steel (Bldg A)

Project Start 09/10/18 Page 2 of 18 Edwards Lifescience
Project Finish 07/23/20 TASK filter: All Activities Proposal Schedule with Buil
Data Date 09/01/18
Run Date 10/05/18 Snyder L

2019 2020

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

T AWARD

al
l
Proposal / Interview
Contract
tract

CRITICAL PERMIT MILESTONES

.

uilding Permit
Precise Grading Permit for Building A, B & C

1st Plan Check Comments from City for Building A & B
1st Plan Check Comments from City for Building C
Foundation Only Permit (if not bldg) for Building A, B & C
Full Building Permit for Building A & B
Full Building Permit for Building C

ONSITE/OFFSITE PERMITS

Site Electrical Permit
SCE Permit
OCFA Permit
Yard Permit
Civil Permit
MCE Offsite Encroachment Permit
IRWD Permit

FAA PERMITS

Obtain FAA Crane Permit (Generator Relocation)
Obtain FAA Crane Permit (Steel Erection)
CRITICAL SUBMITTALS & PROCUREMENT

DIVISION 02 - SITE

ward Piles
pare Shop Drawings for Piles

City Review Shop Drawings for Piles
Test Piles

Document Test Piles
City Review Test Piles
DIVISION 03 - CONCRETE

Bid & Award Precast
Prepare Shop Drawings Precast
Review/Approve Shop Drawings Precast
Fabricate Precast Panels
DIVISION 05 - METALS

Bid Structural Steel
Steel Bidders Review 1st Plan Check & Update Bids (Bldg A & B)
Award Structural Steel
Submittal/Review/Fabricate Steel (Bldg A)

es Campus Expansion Remaining Level of Effort
lding B Concrete - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work

Activity ID Activity Name Dur Current Start Current Finish
Aug Sep Oct Nov Dec

P051000.40 Submittal/Review/Fabricate Steel (Bldg C) 125 02/12/19 08/07/19

DIVISION 07 - THERMAL & MOISTURE PROTECTION 165 01/16/19 09/06/19

P074243.10 Bid & Award Aluminum Panels 20 01/16/19 02/12/19

P074243.20 Submittal/Review/Procure Material to Shop Aluminum Panels (Bldg B) 125 02/13/19 08/08/19

P074243.21 Submittal/Review/Procure Material to Shop Aluminum Panels (Bldg A) 125 02/27/19 08/22/19

P074243.29 Submittal/Review/Procure Material to Shop Aluminum Panels (Bldg C) 125 03/13/19 09/06/19

DIVISION 08 - OPENINGS 290 11/01/18 12/31/19

P084000.10 Bid & Award Glass/Glazing 20 11/01/18* 12/03/18 Bid

P084000.20 Submittal/Review/Fabricate Curtainwall/Glazing (Bldg B) 250 12/04/18 12/02/19

P084000.30 Submittal/Review/Fabricate Curtainwall/Glazing (Bldg A) 250 12/18/18 12/16/19

P084000.40 Submittal/Review/Fabricate Curtainwall/Glazing (Bldg C) 250 01/07/19 12/31/19

DIVISION 14 - ELEVATORS 220 01/16/19 11/25/19

P142000.10 Bid & Award Elevators 20 01/16/19 02/12/19

P142000.20 Prepare Shop Drawings Elevators 60 02/13/19 05/07/19

P142000.21 Review/Approve Shop Drawings Elevators 20 05/08/19 06/05/19

P142000.29 Fabricate Elevators 120 06/06/19 11/25/19

CONSTRUCTION - PHASE 0 - ELECTRICAL IMPROVEMENTS 54 11/05/18 01/28/19

ELECTRICAL / GENERATOR WORK 54 11/05/18 01/28/19

0-10000 Start Construction 0 11/05/18 11/09/18 Start Con
5 11/05/18 11/14/18 Mobilizat
0-10010 Mobilization 2 11/13/18 11/30/18 Notify U
10 11/15/18 11/30/18
0-10020 Notify Underground Dig Alert 10 11/15/18 11/30/18 Dec
0 12/07/18 Con
0-10030 Decorative Fence at Redhill Ave & Alton Pkwy 5 12/03/18 01/03/19 Acc
15 12/10/18 01/03/19
0-10035 Construct Access Road from Alton 15 12/10/18 01/10/19 Co
5 01/04/19 12/11/18
0-10036 Access Road from Alton Available 2 12/10/18 12/13/18 E
2 12/12/18 12/18/18 S
0-10040 Coordination Meeting 3 12/14/18 12/10/18
1 12/10/18 12/26/18 L
0-10050 Relocate (E) Motorized Gate at MLE 10 12/11/18 12/26/18
10 12/11/18 12/28/18
0-10060 (N) Motorized Gate at Access Road 2 12/27/18 01/02/19
1 01/02/19 12/27/18
0-10070 Phase 0 Construction Fencing 1 12/27/18 01/03/19
3 12/28/18 01/04/19
0-10100 Electrical Safe-off 1 01/04/19 01/07/19
1 01/07/19 01/07/19
0-10300 Sawcut/Demo Asphalt 1 01/07/19 01/14/19
5 01/08/19 01/16/19
0-10310 Demo Electrical Conduit/Infrastructure 2 01/15/19 01/16/19
2 01/15/19 01/21/19
0-11000 Layout New Service Yard 3 01/17/19

0-11010 Underground Electrical Ductbank to New Service Yard

0-11020 Pull Box & Underground Electrical Ductbank to Future Lab Bldg

0-11030 Slurry & Backfill Electrical Trench

0-11040 Repair A/C Paving & Remove Trench Plates

0-11100 Fine Grade 2500KV Generator Pad

0-11110 Form/Rebar 2500KV Generator Pad

0-11120 Inspect 2500KV Generator Pad

0-11130 Pour 2500KV Generator Pad

0-11135 Pour 1250KV Generator Pad

0-11140 Cure 2500KV Generator Pad

0-11200 Relocate & Set 2500KV Generator

0-11205 Relocate 1250KV Generator to Temp Pad

0-11210 Electrical Connections at 2500KV Generator

Project Start 09/10/18 Page 3 of 18 Edwards Lifescience
Project Finish 07/23/20 TASK filter: All Activities Proposal Schedule with Buil
Data Date 09/01/18
Run Date 10/05/18 Snyder L

2019 2020

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Submittal/Review/Fabricate Steel (Bldg C)

DIVISION 07 - THERMAL & MOISTURE PROTECTION

Bid & Award Aluminum Panels

Submittal/Review/Procure Material to Shop Aluminum Panels (Bldg B)

Submittal/Review/Procure Material to Shop Aluminum Panels (Bldg A)

Submittal/Review/Procure Material to Shop Aluminum Panels (Bldg C)

DIVISION 08 - OPENINGS

d & Award Glass/Glazing

Submittal/Review/Fabricate Curtainwall/Glazing (Bldg B)

Submittal/Review/Fabricate Curtainwall/Glazing (Bldg A)

Submittal/Review/Fabricate Curtainwall/Glazing (Bldg C)

DIVISION 14 - ELEVATORS

Bid & Award Elevators

Prepare Shop Drawings Elevators

Review/Approve Shop Drawings Elevators

Fabricate Elevators

CONSTRUCTION - PHASE 0 - ELECTRICAL IMPROVEMENTS

ELECTRICAL / GENERATOR WORK

nstruction
ation
Underground Dig Alert
corative Fence at Redhill Ave & Alton Pkwy
nstruct Access Road from Alton
cess Road from Alton Available

oordination Meeting
Relocate (E) Motorized Gate at MLE
(N) Motorized Gate at Access Road
Phase 0 Construction Fencing

Electrical Safe-off
Sawcut/Demo Asphalt
Demo Electrical Conduit/Infrastructure
Layout New Service Yard

Underground Electrical Ductbank to New Service Yard
Pull Box & Underground Electrical Ductbank to Future Lab Bldg
Slurry & Backfill Electrical Trench

Repair A/C Paving & Remove Trench Plates
Fine Grade 2500KV Generator Pad

Form/Rebar 2500KV Generator Pad
Inspect 2500KV Generator Pad
Pour 2500KV Generator Pad
Pour 1250KV Generator Pad

Cure 2500KV Generator Pad
Relocate & Set 2500KV Generator
Relocate 1250KV Generator to Temp Pad
Electrical Connections at 2500KV Generator

es Campus Expansion Remaining Level of Effort
lding B Concrete - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work

Activity ID Activity Name Dur Current Start Current Finish
Aug Sep Oct Nov Dec
0-11220 Fuel, Start-up & Test 2500KV Generator
5 01/22/19 01/28/19
0-11510 2500KV Generator Online 0 01/28/19
67 01/03/19 04/05/19
CONSTRUCTION - PHASE 1 - UTILITY RELOCATIONS

UNDERGROUND UTILITY RELOCATIONS 67 01/03/19 04/05/19

1A-09100 Relocate MLE Electrical 40 01/03/19 02/27/19
5 02/28/19 03/06/19
1A-09110 Patch Existing Areas of Temporary Construction Access 0 03/06/19
04/05/19
1A-09120 Access Road from Redhill Available 22 03/07/19 04/05/19
22 03/07/19 07/07/20
1A-09130 Reroute Storm Drain 363 02/01/19

1A-09140 Reroute Fire Water & Other Utilities between HVC & Museum Deck

CONSTRUCTION - PHASE 1 - BLDG B (OFFICE/LAB/SITE)

EARTHWORK 26 02/01/19 03/08/19

1B-10000 Start Construction 0 02/01/19 02/01/19
1 02/01/19 03/01/19
1B-10010 Survey 20 02/04/19 03/08/19
5 03/04/19 12/02/19
1B-10020 Earthwork 185 03/11/19 05/24/19
06/10/19
1B-10030 Certify Pad 55 03/11/19 06/10/19
55 03/25/19 06/10/19
FOUNDATIONS / STRUCTURE 55 03/25/19 06/24/19
55 03/25/19 06/24/19
1B-15000 Drill/Rebar/Pour Piles (522) 55 04/08/19 07/01/19
55 04/08/19 07/09/19
1B-15100 Form/Rebar/Pour Pilecaps 40 05/06/19 07/23/19
40 05/13/19 08/06/19
1B-15200 Excavate/Form/Pour Elevator Pits 40 05/28/19 08/20/19
40 06/11/19 09/18/19
1B-15300 Form/Rebar/Pour Gradebeams 40 06/25/19 10/02/19
40 07/24/19 10/30/19
1B-15400 Prep/Pour Vertical (1st to 2nd Floor) 40 08/07/19 12/02/19
40 09/05/19 05/13/20
1B-18000 Underslab Plumbing Rough-in 20 10/31/19 12/02/19
145 10/17/19 12/02/19
1B-18100 Fine Grade for SOG 12/16/19
30 10/17/19 12/16/19
1B-18110 Sand/Vapor Barrier for SOG 30 10/17/19 12/23/19
30 10/31/19 03/25/20
1B-18120 Form/Rebar/Pour SOG 30 10/31/19 03/11/20
30 11/07/19 04/08/20
1B-18200 Prep/Pour Concrete Deck (2nd Floor) 80 12/03/19 04/22/20
30 01/30/20 02/12/20
1B-18210 Prep/Pour Vertical (2nd to 3rd Floor) 30 02/27/20 12/09/19
10 04/09/20 01/22/20
1B-18220 Prep/Pour Concrete Deck (3rd Floor) 40 12/17/19
15 11/15/19
1B-18230 Prep/Pour Vertical (3rd to Main Roof) 40 11/22/19

1B-18240 Prep/Pour Concrete Deck (Main Roof)

1B-19000 Precast Stairs

EXTERIOR SKIN

1B-30000 Exterior Framing

1B-30010 Exterior MEP Rough-in

1B-30020 Exterior Sheathing

1B-30100 Precast Panels

1B-30150 GFRC Panels

1B-30300 Curtainwall

1B-30350 Storefront Framing

1B-30360 Storefront Glazing

1B-30370 Storefront Doors

1B-30400 Steel & Glass Guardrails

1B-30500 Weatherproofing for Aluminum Panels

1B-30510 Field Measure & Fab Aluminum Panels

Project Start 09/10/18 Page 4 of 18 Edwards Lifescience
Project Finish 07/23/20 TASK filter: All Activities Proposal Schedule with Buil
Data Date 09/01/18
Run Date 10/05/18 Snyder L

2019 2020

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Fuel, Start-up & Test 2500KV Generator

2500KV Generator Online

CONSTRUCTION - PHASE 1 - UTILITY RELOCATIONS

UNDERGROUND UTILITY RELOCATIONS

Relocate MLE Electrical
Patch Existing Areas of Temporary Construction Access
Access Road from Redhill Available
Reroute Storm Drain
Reroute Fire Water & Other Utilities between HVC & Museum Deck

CONSTRUCTION - PHASE 1 - BLDG B (OFFICE/LAB

EARTHWORK

Start Construction
Survey

Earthwork
Certify Pad
FOUNDATIONS / STRUCTURE

Drill/Rebar/Pour Piles (522)
Form/Rebar/Pour Pilecaps
Excavate/Form/Pour Elevator Pits
Form/Rebar/Pour Gradebeams
Prep/Pour Vertical (1st to 2nd Floor)
Underslab Plumbing Rough-in
Fine Grade for SOG
Sand/Vapor Barrier for SOG
Form/Rebar/Pour SOG
Prep/Pour Concrete Deck (2nd Floor)
Prep/Pour Vertical (2nd to 3rd Floor)
Prep/Pour Concrete Deck (3rd Floor)
Prep/Pour Vertical (3rd to Main Roof)
Prep/Pour Concrete Deck (Main Roof)
Precast Stairs
EXTERIOR SKIN

Exterior Framing
Exterior MEP Rough-in

Exterior Sheathing
Precast Panels

GFRC Panels
Curtainwall

Storefront Framing
Storefront Glazing
Storefront Doors

Steel & Glass Guardrails
Weatherproofing for Aluminum Panels

Field Measure & Fab Aluminum Panels

es Campus Expansion Remaining Level of Effort
lding B Concrete - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work

Activity ID Activity Name Dur Current Start Current Finish
Aug Sep Oct Nov Dec
1B-30520 Install Aluminum Panels
60 12/24/19 03/18/20
1B-30600 MEP Trim 10 04/23/20 05/06/20

1B-30900 Cleanup & Prepunch 5 05/07/20 05/13/20
165 09/19/19 05/13/20
ROOF
165 09/19/19 05/13/20
ROOF DECKS 10 09/19/19 10/02/19
10 10/03/19 10/16/19
1B-40000 MEP Penetrations & Roof Drains 10 03/19/20 04/01/20
10 03/26/20 04/08/20
1B-40030 Sheetmetal Flashing 20 04/09/20 05/06/20
5 05/07/20 05/13/20
1B-40100 Waterproofing 95 10/31/19 03/18/20
20 10/31/19 12/02/19
1B-40110 Topping Slabs 20 10/31/19 12/02/19
20 11/07/19 12/09/19
1B-40300 Roof Deck Pavers & Finishes 30 11/15/19 12/31/19
10 12/24/19 01/08/20
1B-40900 Cleanup & Prepunch Roof Decks 30 01/02/20 02/12/20
20 01/02/20 01/29/20
MAIN ROOFS 20 02/13/20 03/11/20
5 03/12/20 03/18/20
1B-41000 MEP Penetrations & Roof Drains
106 10/31/19 04/02/20
1B-41010 Mechanical Curbs
86 10/31/19 03/05/20
1B-41030 Sheetmetal Flashing 15 10/31/19 11/21/19
15 11/07/19 12/02/19
1B-41100 Roofing 15 11/07/19 12/02/19
15 11/07/19 12/02/19
1B-41200 Set Mechanical Equipment 15 11/07/19 12/02/19
15 11/15/19 12/09/19
1B-41210 Hookup Mechanical Equipment 15 11/15/19 12/09/19
15 11/15/19 12/09/19
1B-41300 Roof Screen Panels
5 12/05/19 12/11/19
1B-41400 Sheetmetal Trim & Finish 5 12/09/19 12/13/19
10 12/11/19 12/24/19
1B-41900 Cleanup & Prepunch Roof 10 11/22/19 12/09/19
10 12/03/19 12/16/19
INTERIOR 10 12/03/19 12/16/19
10 12/03/19 12/16/19
1ST FLOOR CORE 5 12/12/19 12/18/19
10 12/18/19 01/02/20
1B-50000 Overhead Mechanical Rough-in 10 01/03/20 01/16/20
10 01/10/20 01/23/20
1B-50010 Overhead Plumbing Rough-in 20 01/17/20 02/13/20
5 01/17/20 01/23/20
1B-50020 Overhead Fire Sprinkler Rough-in 10 01/17/20 01/30/20

1B-50030 Overhead Electrical Rough-in Edwards Lifescience
Proposal Schedule with Buil
1B-50100 Wall Framing & Furring
Snyder L
1B-50110 Wall Plumbing Rough-in

1B-50120 Wall Electrical Rough-in

1B-50130 Wall Low Voltage Rough-in

1B-50140 Wall MEP & Framing Inspections

1B-50150 Wall Insulation (dry-in)

1B-50160 Drywall Walls

1B-50200 Hard Ceiling Framing

1B-50210 Hard Ceiling Mechanical Rough-in

1B-50220 Hard Ceiling Fire Sprinkler Rough-in

1B-50230 Hard Ceiling Electrical Rough-in

1B-50240 Hard Ceiling MEP Inspections

1B-50250 Drywall Ceilings

1B-50260 Tape Drywall Walls & Ceilings

1B-50300 Prime & Paint

1B-50310 Electrical Panels & Pull Wire

1B-50320 Door Frames

1B-50460 Suspended & Surface Mounted Fixtures

Project Start 09/10/18 Page 5 of 18
Project Finish 07/23/20 TASK filter: All Activities
Data Date 09/01/18
Run Date 10/05/18

2019 2020

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Install Aluminum Panels

MEP Trim

Cleanup & Prepunch

ROOF

ROOF DECKS

MEP Penetrations & Roof Drains

Sheetmetal Flashing

Waterproofing

Topping Slabs

Roof Deck Pavers & Finishes

Cleanup & Prepunch Roof Decks

MAIN ROOFS

MEP Penetrations & Roof Drains

Mechanical Curbs

Sheetmetal Flashing

Roofing

Set Mechanical Equipment

Hookup Mechanical Equipment

Roof Screen Panels

Sheetmetal Trim & Finish

Cleanup & Prepunch Roof

INTERIOR

1ST FLOOR CORE

Overhead Mechanical Rough-in

Overhead Plumbing Rough-in

Overhead Fire Sprinkler Rough-in

Overhead Electrical Rough-in

Wall Framing & Furring

Wall Plumbing Rough-in

Wall Electrical Rough-in

Wall Low Voltage Rough-in

Wall MEP & Framing Inspections

Wall Insulation (dry-in)

Drywall Walls

Hard Ceiling Framing

Hard Ceiling Mechanical Rough-in

Hard Ceiling Fire Sprinkler Rough-in

Hard Ceiling Electrical Rough-in

Hard Ceiling MEP Inspections

Drywall Ceilings

Tape Drywall Walls & Ceilings

Prime & Paint

Electrical Panels & Pull Wire

Door Frames

Suspended & Surface Mounted Fixtures

es Campus Expansion Remaining Level of Effort
lding B Concrete - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work

Activity ID Activity Name Dur Current Start Current Finish
Aug Sep Oct Nov Dec
1B-50600 Flooring
10 01/24/20 02/06/20
1B-50610 Base 2 02/07/20 02/10/20
5 02/07/20 02/13/20
1B-50620 Hang Doors 5 02/14/20 02/20/20
5 02/21/20 02/27/20
1B-50630 Finish Paint 5 02/21/20 02/27/20
5 02/21/20 02/27/20
1B-50640 Door Hardware 5 02/21/20 02/27/20
5 02/21/20 02/27/20
1B-50650 Mechanical Trim
20 01/17/20 02/13/20
1B-50660 Fire Sprinkler Trim 10 02/07/20 02/20/20
10 02/14/20 02/27/20
1B-50670 Electrical Trim
5 02/28/20 03/05/20
1B-50680 Low Voltage Trim 86 11/15/19 03/19/20
15 11/15/19 12/09/19
1B-50800 Tile (Restrooms) 15 11/22/19 12/16/19
15 11/22/19 12/16/19
1B-50820 Plumbing Fixtures (Restrooms) 15 11/22/19 12/16/19
15 11/22/19 12/16/19
1B-50840 Toilet Accessories (Restrooms) 15 12/03/19 12/23/19
15 12/03/19 12/23/19
1B-50900 Cleanup & Prepunch Interior 15 12/03/19 12/23/19

2ND FLOOR CORE 5 12/19/19 12/26/19
5 12/23/19 12/30/19
1B-55000 Overhead Mechanical Rough-in 10 12/26/19 01/09/20
10 12/10/19 12/23/19
1B-55010 Overhead Plumbing Rough-in 10 12/17/19 12/31/19
10 12/17/19 12/31/19
1B-55020 Overhead Fire Sprinkler Rough-in 10 12/17/19 12/31/19
5 12/27/19 01/03/20
1B-55030 Overhead Electrical Rough-in 10 01/03/20 01/16/20
10 01/17/20 01/30/20
1B-55100 Wall Framing & Furring 10 01/24/20 02/06/20
20 01/31/20 02/27/20
1B-55110 Wall Plumbing Rough-in 5 01/31/20 02/06/20
10 01/31/20 02/13/20
1B-55120 Wall Electrical Rough-in 10 02/07/20 02/20/20
2 02/21/20 02/24/20
1B-55130 Wall Low Voltage Rough-in 5 02/21/20 02/27/20
5 02/28/20 03/05/20
1B-55140 Wall MEP & Framing Inspections 5 03/06/20 03/12/20
5 03/06/20 03/12/20
1B-55150 Wall Insulation (dry-in) 5 03/06/20 03/12/20
5 03/06/20 03/12/20
1B-55160 Drywall Walls 5 03/06/20 03/12/20
20 01/31/20 02/27/20
1B-55200 Hard Ceiling Framing
Edwards Lifescience
1B-55210 Hard Ceiling Mechanical Rough-in Proposal Schedule with Buil

1B-55220 Hard Ceiling Fire Sprinkler Rough-in Snyder L

1B-55230 Hard Ceiling Electrical Rough-in

1B-55240 Hard Ceiling MEP Inspections

1B-55250 Drywall Ceilings

1B-55260 Tape Drywall Walls & Ceilings

1B-55300 Prime & Paint

1B-55310 Electrical Panels & Pull Wire

1B-55320 Door Frames

1B-55460 Suspended & Surface Mounted Fixtures

1B-55600 Flooring

1B-55610 Base

1B-55620 Hang Doors

1B-55630 Finish Paint

1B-55640 Door Hardware

1B-55650 Mechanical Trim

1B-55660 Fire Sprinkler Trim

1B-55670 Electrical Trim

1B-55680 Low Voltage Trim

1B-55800 Tile (Restrooms)

Project Start 09/10/18 Page 6 of 18
Project Finish 07/23/20 TASK filter: All Activities
Data Date 09/01/18
Run Date 10/05/18

2019 2020

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Flooring

Base

Hang Doors

Finish Paint

Door Hardware

Mechanical Trim

Fire Sprinkler Trim

Electrical Trim

Low Voltage Trim

Tile (Restrooms)

Plumbing Fixtures (Restrooms)

Toilet Accessories (Restrooms)

Cleanup & Prepunch Interior

2ND FLOOR CORE

Overhead Mechanical Rough-in

Overhead Plumbing Rough-in

Overhead Fire Sprinkler Rough-in

Overhead Electrical Rough-in

Wall Framing & Furring

Wall Plumbing Rough-in

Wall Electrical Rough-in

Wall Low Voltage Rough-in

Wall MEP & Framing Inspections

Wall Insulation (dry-in)

Drywall Walls

Hard Ceiling Framing

Hard Ceiling Mechanical Rough-in

Hard Ceiling Fire Sprinkler Rough-in

Hard Ceiling Electrical Rough-in

Hard Ceiling MEP Inspections

Drywall Ceilings

Tape Drywall Walls & Ceilings

Prime & Paint

Electrical Panels & Pull Wire

Door Frames

Suspended & Surface Mounted Fixtures

Flooring

Base

Hang Doors

Finish Paint

Door Hardware

Mechanical Trim

Fire Sprinkler Trim

Electrical Trim

Low Voltage Trim

Tile (Restrooms)

es Campus Expansion Remaining Level of Effort
lding B Concrete - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work

Activity ID Activity Name Dur Current Start Current Finish
Aug Sep Oct Nov Dec
1B-55820 Plumbing Fixtures (Restrooms)
10 02/21/20 03/05/20
1B-55840 Toilet Accessories (Restrooms) 10 02/28/20 03/12/20

1B-55900 Cleanup & Prepunch Interior 5 03/13/20 03/19/20
86 12/03/19 04/02/20
3RD FLOOR CORE 15 12/03/19 12/23/19
15 12/10/19 12/31/19
1B-60000 Overhead Mechanical Rough-in 15 12/10/19 12/31/19
15 12/10/19 12/31/19
1B-60010 Overhead Plumbing Rough-in 15 12/10/19 12/31/19
15 12/17/19 01/08/20
1B-60020 Overhead Fire Sprinkler Rough-in 15 12/17/19 01/08/20
15 12/17/19 01/08/20
1B-60030 Overhead Electrical Rough-in
5 01/06/20 01/10/20
1B-60100 Wall Framing & Furring 5 01/08/20 01/14/20
10 01/10/20 01/23/20
1B-60110 Wall Plumbing Rough-in 10 12/24/19 01/08/20
10 01/02/20 01/15/20
1B-60120 Wall Electrical Rough-in 10 01/02/20 01/15/20
10 01/02/20 01/15/20
1B-60130 Wall Low Voltage Rough-in 5 01/13/20 01/17/20
10 01/17/20 01/30/20
1B-60140 Wall MEP & Framing Inspections 10 01/31/20 02/13/20
10 02/07/20 02/20/20
1B-60150 Wall Insulation (dry-in) 20 02/14/20 03/12/20
5 02/14/20 02/20/20
1B-60160 Drywall Walls 10 02/14/20 02/27/20
10 02/21/20 03/05/20
1B-60200 Hard Ceiling Framing 2 03/06/20 03/09/20
5 03/06/20 03/12/20
1B-60210 Hard Ceiling Mechanical Rough-in 5 03/13/20 03/19/20
5 03/20/20 03/26/20
1B-60220 Hard Ceiling Fire Sprinkler Rough-in 5 03/20/20 03/26/20
5 03/20/20 03/26/20
1B-60230 Hard Ceiling Electrical Rough-in 5 03/20/20 03/26/20
5 03/20/20 03/26/20
1B-60240 Hard Ceiling MEP Inspections 20 02/14/20 03/12/20
10 03/06/20 03/19/20
1B-60250 Drywall Ceilings 10 03/13/20 03/26/20
5 03/27/20 04/02/20
1B-60260 Tape Drywall Walls & Ceilings 50 01/24/20 04/02/20

1B-60300 Prime & Paint 30 01/24/20 03/05/20
20 02/14/20 03/12/20
1B-60310 Electrical Panels & Pull Wire 20 02/21/20 03/19/20
20 02/28/20 03/26/20
1B-60320 Door Frames 20 03/06/20 04/02/20

1B-60460 Suspended & Surface Mounted Fixtures Edwards Lifescience
Proposal Schedule with Buil
1B-60600 Flooring
Snyder L
1B-60610 Base

1B-60620 Hang Doors

1B-60630 Finish Paint

1B-60640 Door Hardware

1B-60650 Mechanical Trim

1B-60660 Fire Sprinkler Trim

1B-60670 Electrical Trim

1B-60680 Low Voltage Trim

1B-60800 Tile (Restrooms)

1B-60820 Plumbing Fixtures (Restrooms)

1B-60840 Toilet Accessories (Restrooms)

1B-60900 Cleanup & Prepunch Interior

INTERIOR STAIRS

1B-70000 Drywall & Tape Stairs

1B-70010 Handrails

1B-70020 Prime & Paint

1B-70030 Flooring

1B-70040 MEP Trim

Project Start 09/10/18 Page 7 of 18
Project Finish 07/23/20 TASK filter: All Activities
Data Date 09/01/18
Run Date 10/05/18

2019 2020

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Plumbing Fixtures (Restrooms)

Toilet Accessories (Restrooms)

Cleanup & Prepunch Interior

3RD FLOOR CORE

Overhead Mechanical Rough-in

Overhead Plumbing Rough-in

Overhead Fire Sprinkler Rough-in

Overhead Electrical Rough-in

Wall Framing & Furring

Wall Plumbing Rough-in

Wall Electrical Rough-in

Wall Low Voltage Rough-in

Wall MEP & Framing Inspections

Wall Insulation (dry-in)

Drywall Walls

Hard Ceiling Framing

Hard Ceiling Mechanical Rough-in

Hard Ceiling Fire Sprinkler Rough-in

Hard Ceiling Electrical Rough-in

Hard Ceiling MEP Inspections

Drywall Ceilings

Tape Drywall Walls & Ceilings

Prime & Paint

Electrical Panels & Pull Wire

Door Frames

Suspended & Surface Mounted Fixtures

Flooring

Base

Hang Doors

Finish Paint

Door Hardware

Mechanical Trim

Fire Sprinkler Trim

Electrical Trim

Low Voltage Trim

Tile (Restrooms)

Plumbing Fixtures (Restrooms)

Toilet Accessories (Restrooms)

Cleanup & Prepunch Interior

INTERIOR STAIRS

Drywall & Tape Stairs

Handrails

Prime & Paint

Flooring

MEP Trim

es Campus Expansion Remaining Level of Effort
lding B Concrete - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work

Activity ID Activity Name Dur Current Start Current Finish
Aug Sep Oct Nov Dec
ELEVATORS
56 02/14/20 05/01/20
1B-71000 Elevator Pre-Check List & Corrections
10 02/14/20 02/27/20
1B-71010 Elevator Rails (#1) 5 02/28/20 03/05/20
5 03/06/20 03/12/20
1B-71020 Elevator Equipment (#1) 3 03/13/20 03/17/20
3 03/18/20 03/20/20
1B-71030 Elevator Temp Platform (#1) 5 03/23/20 03/27/20
5 04/10/20 04/16/20
1B-71040 Elevator Door Frames (#1) 5 03/13/20 03/19/20
5 03/20/20 03/26/20
1B-71050 Elevator Cab & Finishes (#1) 3 03/27/20 03/31/20
3 04/01/20 04/03/20
1B-71060 Elevator Test & Adjust (#1) 5 04/06/20 04/10/20
5 04/17/20 04/23/20
1B-72010 Elevator Rails (#2) 5 03/27/20 04/02/20
5 04/03/20 04/09/20
1B-72020 Elevator Equipment (#2) 3 04/10/20 04/14/20
3 04/15/20 04/17/20
1B-72030 Elevator Temp Platform (#2) 5 04/20/20 04/24/20
5 04/27/20 05/01/20
1B-72040 Elevator Door Frames (#2)
322 03/04/19 06/08/20
1B-72050 Elevator Cab & Finishes (#2)
20 03/04/19 03/29/19
1B-72060 Elevator Test & Adjust (#2) 20 04/01/19 04/26/19
20 10/31/19 12/02/19
1B-73010 Elevator Rails (#3) 20 12/03/19 12/31/19
120 11/15/19 05/06/20
1B-73020 Elevator Equipment (#3) 40 04/13/20 06/08/20
81 03/13/20 07/07/20
1B-73030 Elevator Temp Platform (#3)
20 03/13/20 04/09/20
1B-73040 Elevator Door Frames (#3) 20 05/26/20 06/22/20
40 04/27/20 06/22/20
1B-73050 Elevator Cab & Finishes (#3) 10 06/23/20 07/07/20

1B-73060 Elevator Test & Adjust (#3) 0 07/07/20
2 06/05/20 06/08/20
SITEWORK 20 06/09/20 07/07/20
0 07/07/20
1B-80000 Site Wet Utilities 295 04/01/19 05/28/20

1B-80100 Site Dry Utilities

1B-80200 Hardscape (Parking Aisle)

1B-80210 Landscape/Irrigation (Parking Aisle)

1B-80400 Hardscape (Main Courtyard)

1B-80410 Landscape (Main Courtyard)

INSPECTIONS / PUNCHLIST

1B-89000 Permanent Power

1B-90000 Final Inspections

1B-90005 Commissioning/LEED Approval

1B-90010 Inclement Weather Allowance

1B-90020 Substantial Completion

1B-90100 Prepare Punchlist

1B-90110 Punchlist Corrections

1B-90120 Final Completion

CONSTRUCTION - PHASE 1 - BLDG A (PAVILION/MUSEUM)

EARTHWORK 16 04/08/19 04/29/19

1A-10000 Start Construction 0 04/08/19 04/08/19
1 04/08/19 04/15/19
1A-10010 Survey 5 04/09/19 04/09/19
1 04/09/19 04/22/19
1A-10020 Demo 5 04/16/19 04/29/19
5 04/23/19 12/09/19
1A-10050 Pre-Grade Meeting with City 154 04/30/19

1A-10100 Earthwork

1A-10110 Certify Pad

FOUNDATIONS / STRUCTURE

Project Start 09/10/18 Page 8 of 18 Edwards Lifescience
Project Finish 07/23/20 TASK filter: All Activities Proposal Schedule with Buil
Data Date 09/01/18
Run Date 10/05/18 Snyder L

2019 2020

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

ELEVATORS

Elevator Pre-Check List & Corrections

Elevator Rails (#1)

Elevator Equipment (#1)

Elevator Temp Platform (#1)

Elevator Door Frames (#1)

Elevator Cab & Finishes (#1)

Elevator Test & Adjust (#1)

Elevator Rails (#2)

Elevator Equipment (#2)

Elevator Temp Platform (#2)

Elevator Door Frames (#2)

Elevator Cab & Finishes (#2)

Elevator Test & Adjust (#2)

Elevator Rails (#3)

Elevator Equipment (#3)

Elevator Temp Platform (#3)

Elevator Door Frames (#3)

Elevator Cab & Finishes (#3)

Elevator Test & Adjust (#3)

SITEWORK

Site Wet Utilities

Site Dry Utilities

Hardscape (Parking Aisle)

Landscape/Irrigation (Parking Aisle)

Hardscape (Main Courtyard)

Landscape (Main Courtyard)

INSPECTIONS / PUNCHLIST

Permanent Power

Final Inspections

Commissioning/LEED Approval

Inclement Weather Allowance

Substantial Completion

Prepare Punchlist

Punchlist Corrections

Final Completion

CONSTRUCTION - PHASE 1 - BLDG A (PAVILION/MUSEUM)

EARTHWORK

Start Construction
Survey

Demo
Pre-Grade Meeting with City

Earthwork
Certify Pad

FOUNDATIONS / STRUCTURE

es Campus Expansion Remaining Level of Effort
lding B Concrete - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work

Activity ID Activity Name Dur Current Start Current Finish
Aug Sep Oct Nov Dec
1A-15000 Drill/Rebar/Pour Piles (144)
15 04/30/19 05/20/19
1A-15100 Form/Rebar/Pour Pilecaps 10 05/21/19 06/04/19
10 05/21/19 06/04/19
1A-15200 Excavate/Form/Pour Elevator Pit 10 06/05/19 06/18/19
20 06/19/19 07/17/19
1A-15300 Form/Rebar/Pour Gradebeams 20 07/18/19 08/14/19
20 08/15/19 09/12/19
1A-16000 Form/Rebar/Pour/Strip CIP Walls (Pour 1) 10 09/13/19 09/26/19
15 09/27/19 10/17/19
1A-16100 Form/Rebar/Pour/Strip CIP Walls (Pour 2)
5 10/18/19 10/24/19
1A-16110 Form/Rebar/Pour/Strip CIP Walls (Pour 3) 5 10/25/19 10/31/19
5 11/01/19 11/07/19
1A-17000 Erect Structural Steel 5 11/01/19 11/07/19
2 11/08/19 11/12/19
1A-17010 Weld Structural Steel 2 11/13/19 11/14/19
5 11/15/19 11/21/19
1A-17100 Metal Deck/Edge Metal/Shear Studs (2nd Floor) 5 11/01/19 11/07/19
5 11/08/19 11/15/19
1A-17110 Metal Deck/Edge Metal/Shear Studs (Low Roof) 5 11/22/19 12/02/19
5 12/03/19 12/09/19
1A-17120 Metal Deck (High Roof) 20 10/25/19 11/22/19
90 12/10/19 04/15/20
1A-18000 Underslab Plumbing Rough-in
15 12/10/19 12/31/19
1A-18100 Fine Grade for SOG 5 12/24/19 12/31/19

1A-18110 Sand/Vapor Barrier for SOG 10 01/02/20 01/15/20
15 12/10/19 12/31/19
1A-18120 Form/Rebar/Pour SOG
5 01/16/20 01/22/20
1A-18200 MEP/Rebar/Pour Concrete on Metal Deck (2nd Floor) 20 01/23/20 02/19/20
40 01/02/20 02/26/20
1A-18300 MEP/Rebar/Pour Concrete on Metal Deck (Low Roof) 10 01/30/20 02/12/20
10 02/27/20 03/11/20
1A-18400 Fireproofing 1st Floor
5 03/12/20 03/18/20
1A-18410 Fireproofing 2nd Floor 20 01/16/20 02/12/20

1A-19000 Prep/Pour Ramp & Precast Stairs 5 01/16/20 01/22/20
20 01/23/20 02/19/20
EXTERIOR SKIN 30 02/20/20 04/01/20
10 03/19/20 04/01/20
1A-30000 Exterior Framing
5 04/02/20 04/08/20
1A-30010 Exterior MEP Rough-in 5 04/09/20 04/15/20
41 11/01/19 01/03/20
1A-30020 Exterior Sheathing
41 11/01/19 01/03/20
1A-30050 Intumescent & High Performance Paint at Exposed Steel 3 11/01/19 11/05/19
3 11/01/19 11/05/19
1A-30200 Waterproofing for Wood Panel System 3 11/01/19 11/05/19
3 11/06/19 11/08/19
1A-30210 Wood Panel System
Edwards Lifescience
1A-30300 Curtainwall Proposal Schedule with Buil

1A-30350 Storefront Framing Snyder L

1A-30360 Storefront Glazing

1A-30370 Storefront Doors

1A-30400 Steel & Glass Guardrails

1A-30500 Weatherproofing for Aluminum Panels

1A-30510 Field Measure & Fab Aluminum Panels

1A-30520 Install Aluminum Panels

1A-30550 Composite LED Screen

1A-30600 MEP Trim

1A-30900 Cleanup & Prepunch

ROOF

LOW ROOF

1A-40000 MEP Penetrations & Roof Drains

1A-40010 Mechanical Curbs

1A-40020 Roof Hatch

1A-40030 Sheetmetal Flashing

Project Start 09/10/18 Page 9 of 18
Project Finish 07/23/20 TASK filter: All Activities
Data Date 09/01/18
Run Date 10/05/18

2019 2020

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Drill/Rebar/Pour Piles (144)

Form/Rebar/Pour Pilecaps

Excavate/Form/Pour Elevator Pit

Form/Rebar/Pour Gradebeams

Form/Rebar/Pour/Strip CIP Walls (Pour 1)

Form/Rebar/Pour/Strip CIP Walls (Pour 2)

Form/Rebar/Pour/Strip CIP Walls (Pour 3)

Erect Structural Steel

Weld Structural Steel

Metal Deck/Edge Metal/Shear Studs (2nd Floor)

Metal Deck/Edge Metal/Shear Studs (Low Roof)

Metal Deck (High Roof)

Underslab Plumbing Rough-in

Fine Grade for SOG

Sand/Vapor Barrier for SOG

Form/Rebar/Pour SOG

MEP/Rebar/Pour Concrete on Metal Deck (2nd Floor)

MEP/Rebar/Pour Concrete on Metal Deck (Low Roof)

Fireproofing 1st Floor

Fireproofing 2nd Floor

Prep/Pour Ramp & Precast Stairs

EXTERIOR SKIN

Exterior Framing

Exterior MEP Rough-in

Exterior Sheathing

Intumescent & High Performance Paint at Exposed Steel

Waterproofing for Wood Panel System

Wood Panel System

Curtainwall

Storefront Framing

Storefront Glazing

Storefront Doors

Steel & Glass Guardrails

Weatherproofing for Aluminum Panels

Field Measure & Fab Aluminum Panels

Install Aluminum Panels

Composite LED Screen

MEP Trim

Cleanup & Prepunch

ROOF

LOW ROOF

MEP Penetrations & Roof Drains

Mechanical Curbs

Roof Hatch

Sheetmetal Flashing

es Campus Expansion Remaining Level of Effort
lding B Concrete - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work

Activity ID Activity Name Dur Current Start Current Finish
Aug Sep Oct Nov Dec
1A-40100 Roofing
1A-40200 Set Mechanical Equipment 5 11/12/19 11/18/19
1A-40210 Hookup Mechanical Equipment 2 11/19/19 11/20/19
1A-40300 Operable Skylight 10 11/21/19 12/06/19
1A-40400 Sheetmetal Trim & Finish 20 11/19/19 12/18/19
1A-40900 Cleanup & Prepunch Roof 5 12/19/19 12/26/19
5 12/27/19 01/03/20
INTERIOR Overhead Mechanical Rough-in 105 12/03/19 04/29/20
Overhead Plumbing Rough-in
1ST FLOOR Overhead Fire Sprinkler Rough-in 100 12/03/19 04/22/20
1A-50000 Overhead Electrical Rough-in 5 12/03/19 12/09/19
1A-50010 Wall Framing & Furring 5 12/10/19 12/16/19
1A-50020 Wall Plumbing Rough-in 5 12/10/19 12/16/19
1A-50030 Wall Electrical Rough-in 5 12/10/19 12/16/19
1A-50100 Wall Low Voltage Rough-in 5 12/10/19 12/16/19
1A-50110 Wall MEP & Framing Inspections 5 12/17/19 12/23/19
1A-50120 Wall Insulation (dry-in) 5 12/17/19 12/23/19
1A-50130 Drywall Walls 5 12/17/19 12/23/19
1A-50140 Hard Ceiling Framing 2 12/24/19 12/26/19
1A-50150 Hard Ceiling Mechanical Rough-in 2 01/16/20 01/17/20
1A-50160 Hard Ceiling Fire Sprinkler Rough-in 5 01/20/20 01/24/20
1A-50200 Hard Ceiling Electrical Rough-in 3 12/17/19 12/19/19
1A-50210 Hard Ceiling MEP Inspections 3 12/20/19 12/24/19
1A-50220 Drywall Ceilings 3 12/20/19 12/24/19
1A-50230 Tape Drywall Walls & Ceilings 3 12/20/19 12/24/19
1A-50240 Prime & Paint 2 12/26/19 12/27/19
1A-50250 Electrical Panels & Pull Wire 3 01/27/20 01/29/20
1A-50260 Door Frames
1A-50300 Ceiling Grid 10 01/30/20 02/12/20
1A-50310 Mechanical Fixtures in Grid 5 02/13/20 02/19/20
1A-50320 Fire Sprinkler Drops in Grid
1A-50400 Electrical Fixtures in Grid 10 02/20/20 03/04/20
1A-50410 Ceiling Grid & MEP Inspections 3 02/20/20 02/24/20
1A-50420 Ceiling Tile 5 02/20/20 02/26/20
1A-50430 Suspended & Surface Mounted Fixtures 5 02/27/20 03/04/20
1A-50440 Millwork/Cabinetry/Wall Finishes 5 02/27/20 03/04/20
1A-50450 Countertops 5 02/27/20 03/04/20
1A-50460 Flooring 2 03/05/20 03/06/20
1A-50500 Base 5 03/09/20 03/13/20
1A-50510 Hang Doors 5 03/16/20 03/20/20
1A-50600 Finish Paint
1A-50610 Door Hardware 10 02/27/20 03/11/20
1A-50620 Mechanical Trim 3 03/12/20 03/16/20
1A-50630 Fire Sprinkler Trim 5 03/23/20 03/27/20
1A-50640 2 03/30/20 03/31/20
1A-50650 3 03/30/20 04/01/20
1A-50660 5 04/02/20 04/08/20
3 04/09/20 04/13/20
Project Start 09/10/18 Page 10 of 18 5 04/09/20 04/15/20
Project Finish 07/23/20 TASK filter: All Activities 5 04/09/20 04/15/20
Data Date 09/01/18
Run Date 10/05/18 Edwards Lifescience
Proposal Schedule with Buil

Snyder L

2019 2020

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Roofing

Set Mechanical Equipment

Hookup Mechanical Equipment

Operable Skylight

Sheetmetal Trim & Finish

Cleanup & Prepunch Roof

INTERIOR

1ST FLOOR

Overhead Mechanical Rough-in

Overhead Plumbing Rough-in

Overhead Fire Sprinkler Rough-in

Overhead Electrical Rough-in

Wall Framing & Furring

Wall Plumbing Rough-in

Wall Electrical Rough-in

Wall Low Voltage Rough-in

Wall MEP & Framing Inspections

Wall Insulation (dry-in)

Drywall Walls

Hard Ceiling Framing

Hard Ceiling Mechanical Rough-in

Hard Ceiling Fire Sprinkler Rough-in

Hard Ceiling Electrical Rough-in

Hard Ceiling MEP Inspections

Drywall Ceilings

Tape Drywall Walls & Ceilings

Prime & Paint

Electrical Panels & Pull Wire

Door Frames

Ceiling Grid

Mechanical Fixtures in Grid

Fire Sprinkler Drops in Grid

Electrical Fixtures in Grid

Ceiling Grid & MEP Inspections

Ceiling Tile

Suspended & Surface Mounted Fixtures

Millwork/Cabinetry/Wall Finishes

Countertops

Flooring

Base

Hang Doors

Finish Paint

Door Hardware

Mechanical Trim

Fire Sprinkler Trim

es Campus Expansion Remaining Level of Effort
lding B Concrete - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work

Activity ID Activity Name Dur Current Start Current Finish
Aug Sep Oct Nov Dec
1A-50670 Electrical Trim
1A-50680 Low Voltage Trim 5 04/09/20 04/15/20
1A-50800 Tile (Restrooms) 5 04/09/20 04/15/20
1A-50820 Plumbing Fixtures (Restrooms) 5 02/20/20 02/26/20
1A-50840 Toilet Accessories (Restrooms) 3 02/27/20 03/02/20
1A-50900 Cleanup & Prepunch Interior 3 03/03/20 03/05/20
2ND FLOOR 5 04/16/20 04/22/20
1A-55000 Overhead Mechanical Rough-in Page 11 of 18 100 12/10/19 04/29/20
1A-55010 Overhead Plumbing Rough-in TASK filter: All Activities 5 12/10/19 12/16/19
1A-55020 Overhead Fire Sprinkler Rough-in 5 12/17/19 12/23/19
1A-55030 Overhead Electrical Rough-in 5 12/17/19 12/23/19
1A-55100 Wall Framing & Furring 5 12/17/19 12/23/19
1A-55110 Wall Plumbing Rough-in 5 12/17/19 12/23/19
1A-55120 Wall Electrical Rough-in 5 12/24/19 12/31/19
1A-55130 Wall Low Voltage Rough-in 5 12/24/19 12/31/19
1A-55140 Wall MEP & Framing Inspections 5 12/24/19 12/31/19
1A-55150 Wall Insulation 2 01/02/20 01/03/20
1A-55160 Drywall Walls 2 01/20/20 01/21/20
1A-55200 Hard Ceiling Framing 5 01/27/20 01/31/20
1A-55210 Hard Ceiling Mechanical Rough-in 3 12/24/19 12/27/19
1A-55220 Hard Ceiling Fire Sprinkler Rough-in 3 12/30/19 01/02/20
1A-55230 Hard Ceiling Electrical Rough-in 3 12/30/19 01/02/20
1A-55240 Hard Ceiling MEP Inspections 3 12/30/19 01/02/20
1A-55250 Drywall Ceilings 2 01/03/20 01/06/20
1A-55260 Tape Drywall Walls & Ceilings 3 02/03/20 02/05/20
1A-55300 Prime & Paint 10 02/06/20 02/19/20
1A-55310 Electrical Panels & Pull Wire 5 02/20/20 02/26/20
1A-55320 Door Frames 10 02/27/20 03/11/20
1A-55400 Ceiling Grid 3 02/27/20 03/02/20
1A-55410 Mechanical Fixtures in Grid 5 02/27/20 03/04/20
1A-55420 Fire Sprinkler Drops in Grid 5 03/05/20 03/11/20
1A-55430 Electrical Fixtures in Grid 5 03/05/20 03/11/20
1A-55440 Ceiling Grid & MEP Inspections 5 03/05/20 03/11/20
1A-55450 Ceiling Tile 2 03/12/20 03/13/20
1A-55460 Suspended & Surface Mounted Fixtures 5 03/16/20 03/20/20
1A-55500 Millwork/Cabinetry/Wall Finishes 5 03/23/20 03/27/20
1A-55510 Countertops 10 03/05/20 03/18/20
1A-55600 Flooring 3 03/19/20 03/23/20
1A-55605 Walkway Pedestal Pavers 5 03/30/20 04/03/20
1A-55610 Base 10 02/27/20 03/11/20
1A-55620 Hang Doors 2 04/06/20 04/07/20
1A-55630 Finish Paint 3 04/06/20 04/08/20
1A-55640 Door Hardware 5 04/09/20 04/15/20
1A-55650 Mechanical Trim 3 04/16/20 04/20/20
1A-55660 Fire Sprinkler Trim 5 04/16/20 04/22/20
1A-55670 Electrical Trim 5 04/16/20 04/22/20
5 04/16/20 04/22/20
Project Start 09/10/18
Edwards Lifescience
Project Finish 07/23/20 Proposal Schedule with Buil

Data Date 09/01/18 Snyder L

Run Date 10/05/18

2019 2020

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Electrical Trim

Low Voltage Trim

Tile (Restrooms)

Plumbing Fixtures (Restrooms)

Toilet Accessories (Restrooms)

Cleanup & Prepunch Interior

2ND FLOOR

Overhead Mechanical Rough-in

Overhead Plumbing Rough-in

Overhead Fire Sprinkler Rough-in

Overhead Electrical Rough-in

Wall Framing & Furring

Wall Plumbing Rough-in

Wall Electrical Rough-in

Wall Low Voltage Rough-in

Wall MEP & Framing Inspections

Wall Insulation

Drywall Walls

Hard Ceiling Framing

Hard Ceiling Mechanical Rough-in

Hard Ceiling Fire Sprinkler Rough-in

Hard Ceiling Electrical Rough-in

Hard Ceiling MEP Inspections

Drywall Ceilings

Tape Drywall Walls & Ceilings

Prime & Paint

Electrical Panels & Pull Wire

Door Frames

Ceiling Grid

Mechanical Fixtures in Grid

Fire Sprinkler Drops in Grid

Electrical Fixtures in Grid

Ceiling Grid & MEP Inspections

Ceiling Tile

Suspended & Surface Mounted Fixtures

Millwork/Cabinetry/Wall Finishes

Countertops

Flooring

Walkway Pedestal Pavers

Base

Hang Doors

Finish Paint

Door Hardware

Mechanical Trim

Fire Sprinkler Trim

Electrical Trim

es Campus Expansion Remaining Level of Effort
lding B Concrete - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work

Activity ID Activity Name Dur Current Start Current Finish
Aug Sep Oct Nov Dec
1A-55680 Low Voltage Trim
5 04/16/20 04/22/20
1A-55900 Cleanup & Prepunch Interior 5 04/23/20 04/29/20
35 02/03/20 03/20/20
INTERIOR STAIRS
10 02/03/20 02/14/20
1A-70000 Drywall & Tape Stairs 10 02/17/20 02/28/20

1A-70010 Handrails 5 03/02/20 03/06/20
5 03/09/20 03/13/20
1A-70020 Prime & Paint 5 03/16/20 03/20/20
36 02/20/20 04/09/20
1A-70030 Flooring
10 02/20/20 03/04/20
1A-70040 MEP Trim 5 03/05/20 03/11/20
5 03/12/20 03/18/20
ELEVATOR 3 03/19/20 03/23/20
3 03/24/20 03/26/20
1A-71000 Elevator Pre-Check List & Corrections 5 03/27/20 04/02/20
5 04/03/20 04/09/20
1A-71010 Elevator Rails
280 04/01/19 05/06/20
1A-71020 Elevator Equipment
20 04/01/19 04/26/19
1A-71030 Elevator Temp Platform 20 04/29/19 05/24/19
60 01/16/20 04/08/20
1A-71040 Elevator Door Frames 20 04/09/20 05/06/20
55 03/12/20 05/28/20
1A-71050 Elevator Cab & Finishes
15 03/12/20 04/01/20
1A-71060 Elevator Test & Adjust 10 04/30/20 05/13/20
40 03/19/20 05/13/20
SITEWORK 10 05/14/20 05/28/20

1A-80000 Site Wet Utilities 0 05/28/20
2 04/28/20 04/29/20
1A-80100 Site Dry Utilities 20 04/30/20 05/28/20
0 05/28/20
1A-80400 Hardscape (Entry/Museum) 313 04/29/19 07/22/20

1A-80410 Landscape (Entry/Museum)

INSPECTIONS / PUNCHLIST

1A-89000 Permanent Power

1A-90000 Final Inspections

1A-90005 Commissioning/LEED Approval

1A-90010 Inclement Weather Allowance

1A-90020 Substantial Completion

1A-90100 Prepare Punchlist

1A-90110 Punchlist Corrections

1A-90120 Final Completion

CONSTRUCTION - PHASE 1 - BLDG C (CAFE/CONFERENCE)

EARTHWORK 21 06/25/19 07/24/19

1C-10000 Start Construction 0 06/25/19 06/25/19
1 06/25/19 07/17/19
1C-10010 Survey 15 06/26/19 07/24/19
5 07/18/19 12/19/19
1C-10020 Earthwork 102 07/25/19 08/28/19
09/12/19
1C-10030 Certify Pad 25 07/25/19 09/12/19
15 08/22/19 09/26/19
FOUNDATIONS / STRUCTURE 10 08/29/19 10/10/19
15 09/06/19 10/24/19
1C-15000 Drill/Rebar/Pour Piles (246) 10 09/27/19 10/31/19
15 10/04/19 10/31/19
1C-15100 Form/Rebar/Pour Pilecaps 10 10/18/19
10 10/18/19
1C-15200 Excavate/Form/Pour Elevator Pit

1C-15300 Form/Rebar/Pour Gradebeams

1C-17000 Erect Structural Steel

1C-17010 Weld Structural Steel

1C-17020 Erect BRB's

1C-17100 Metal Deck/Edge Metal/Shear Studs (2nd Floor)

Project Start 09/10/18 Page 12 of 18 Edwards Lifescience
Project Finish 07/23/20 TASK filter: All Activities Proposal Schedule with Buil
Data Date 09/01/18
Run Date 10/05/18 Snyder L

2019 2020

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Low Voltage Trim

Cleanup & Prepunch Interior

INTERIOR STAIRS

Drywall & Tape Stairs

Handrails

Prime & Paint

Flooring

MEP Trim

ELEVATOR

Elevator Pre-Check List & Corrections

Elevator Rails

Elevator Equipment

Elevator Temp Platform

Elevator Door Frames

Elevator Cab & Finishes

Elevator Test & Adjust

SITEWORK

Site Wet Utilities

Site Dry Utilities

Hardscape (Entry/Museum)

Landscape (Entry/Museum)

INSPECTIONS / PUNCHLIST

Permanent Power

Final Inspections

Commissioning/LEED Approval

Inclement Weather Allowance

Substantial Completion

Prepare Punchlist

Punchlist Corrections

Final Completion

CONSTRUCTION - PHASE 1 - BLDG C (CAFE/CO

EARTHWORK

Start Construction
Survey

Earthwork
Certify Pad
FOUNDATIONS / STRUCTURE

Drill/Rebar/Pour Piles (246)
Form/Rebar/Pour Pilecaps
Excavate/Form/Pour Elevator Pit
Form/Rebar/Pour Gradebeams
Erect Structural Steel
Weld Structural Steel
Erect BRB's
Metal Deck/Edge Metal/Shear Studs (2nd Floor)

es Campus Expansion Remaining Level of Effort
lding B Concrete - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work

Activity ID Activity Name Dur Current Start Current Finish
Aug Sep Oct Nov Dec
1C-17110 Metal Deck/Edge Metal (Roof)
10 11/01/19 11/15/19
1C-18000 Underslab Plumbing Rough-in 10 11/08/19 11/22/19
10 11/08/19 11/22/19
1C-18050 Complete Rebar/Pour Gradebeams at Moment Frames
2 11/25/19 11/26/19
1C-18100 Fine Grade for SOG 5 11/27/19 12/05/19
10 12/06/19 12/19/19
1C-18110 Sand/Vapor Barrier for SOG 15 11/08/19 12/03/19
95 12/13/19 04/27/20
1C-18120 Form/Rebar/Pour SOG
15 12/13/19 01/06/20
1C-18200 MEP/Rebar/Pour Concrete on Metal Deck (2nd Floor) 10 12/20/19 01/06/20
10 12/30/19 01/13/20
EXTERIOR SKIN
5 01/14/20 01/20/20
1C-30000 Exterior Framing 20 01/21/20 02/17/20
60 01/07/20 03/30/20
1C-30010 Exterior MEP Rough-in 10 03/03/20 03/16/20
10 03/17/20 03/30/20
1C-30020 Exterior Sheathing
5 03/31/20 04/06/20
1C-30200 Waterproofing for Wood Rain Screen 20 01/14/20 02/10/20
10 01/14/20 01/27/20
1C-30210 Wood Rain Screen 30 01/21/20 03/02/20
40 02/18/20 04/13/20
1C-30300 Curtainwall
5 04/14/20 04/20/20
1C-30350 Storefront Framing 5 04/21/20 04/27/20
132 11/18/19 05/26/20
1C-30360 Storefront Glazing
122 12/04/19 05/26/20
1C-30370 Storefront Doors 5 12/04/19 12/10/19
5 12/11/19 12/17/19
1C-30400 Steel & Glass Guardrails
10 03/31/20 04/13/20
1C-30500 Weatherproofing for Aluminum Panels 10 04/07/20 04/20/20
20 04/21/20 05/18/20
1C-30510 Field Measure & Fab Aluminum Panels
5 05/19/20 05/26/20
1C-30520 Install Aluminum Panels 60 11/18/19 02/13/20

1C-30600 MEP Trim 5 11/18/19 11/22/19
5 11/18/19 11/22/19
1C-30900 Cleanup & Prepunch 5 11/25/19 12/03/19
10 12/04/19 12/17/19
ROOF 5 12/18/19 12/24/19
20 12/26/19 01/23/20
ROOF DECK 20 12/18/19 01/16/20
10 01/24/20 02/06/20
1C-40000 MEP Penetrations & Roof Drains 5 02/07/20 02/13/20
122 12/13/19 06/04/20
1C-40030 Sheetmetal Flashing
109 12/13/19 05/15/20
1C-40100 Waterproofing 10 12/13/19 12/27/19
10 12/20/19 01/06/20
1C-40110 Topping Slabs
Edwards Lifescience
1C-40300 Roof Deck Pavers & Finishes Proposal Schedule with Buil

1C-40900 Cleanup & Prepunch Roof Decks Snyder L

MAIN ROOF

1C-41000 MEP Penetrations & Roof Drains

1C-41010 Mechanical Curbs

1C-41030 Sheetmetal Flashing

1C-41100 Roofing

1C-41200 Set Mechanical Equipment

1C-41210 Hookup Mechanical Equipment

1C-41300 Roof Screen Panels

1C-41400 Sheetmetal Trim & Finish

1C-41900 Cleanup & Prepunch Roof

INTERIOR

1ST FLOOR CORE

1C-50000 Overhead Mechanical Rough-in

1C-50010 Overhead Plumbing Rough-in

Project Start 09/10/18 Page 13 of 18
Project Finish 07/23/20 TASK filter: All Activities
Data Date 09/01/18
Run Date 10/05/18

2019 2020

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Metal Deck/Edge Metal (Roof)

Underslab Plumbing Rough-in

Complete Rebar/Pour Gradebeams at Moment Frames

Fine Grade for SOG

Sand/Vapor Barrier for SOG

Form/Rebar/Pour SOG

MEP/Rebar/Pour Concrete on Metal Deck (2nd Floor)

EXTERIOR SKIN

Exterior Framing

Exterior MEP Rough-in

Exterior Sheathing

Waterproofing for Wood Rain Screen

Wood Rain Screen

Curtainwall

Storefront Framing

Storefront Glazing

Storefront Doors

Steel & Glass Guardrails

Weatherproofing for Aluminum Panels

Field Measure & Fab Aluminum Panels

Install Aluminum Panels

MEP Trim

Cleanup & Prepunch

ROOF

ROOF DECK

MEP Penetrations & Roof Drains

Sheetmetal Flashing

Waterproofing

Topping Slabs

Roof Deck Pavers & Finishes

Cleanup & Prepunch Roof Decks

MAIN ROOF

MEP Penetrations & Roof Drains

Mechanical Curbs

Sheetmetal Flashing

Roofing

Set Mechanical Equipment

Hookup Mechanical Equipment

Roof Screen Panels

Sheetmetal Trim & Finish

Cleanup & Prepunch Roof

INTERIOR

1ST FLOOR CORE

Overhead Mechanical Rough-in

Overhead Plumbing Rough-in

es Campus Expansion Remaining Level of Effort
lding B Concrete - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work

Activity ID Activity Name Dur Current Start Current Finish
Aug Sep Oct Nov Dec
1C-50020 Overhead Fire Sprinkler Rough-in
10 12/20/19 01/06/20
1C-50030 Overhead Electrical Rough-in 10 12/20/19 01/06/20
10 12/20/19 01/06/20
1C-50100 Wall Framing & Furring 10 12/30/19 01/13/20
10 12/30/19 01/13/20
1C-50110 Wall Plumbing Rough-in 10 12/30/19 01/13/20

1C-50120 Wall Electrical Rough-in 5 01/09/20 01/15/20
5 01/13/20 01/17/20
1C-50130 Wall Low Voltage Rough-in 10 01/15/20 01/28/20
10 01/07/20 01/20/20
1C-50140 Wall MEP & Framing Inspections 10 01/14/20 01/27/20
10 01/14/20 01/27/20
1C-50150 Wall Insulation (dry-in) 10 01/14/20 01/27/20
5 01/23/20 01/29/20
1C-50160 Drywall Walls 10 01/27/20 02/07/20
10 02/10/20 02/21/20
1C-50200 Hard Ceiling Framing 10 02/17/20 02/28/20
20 02/24/20 03/20/20
1C-50210 Hard Ceiling Mechanical Rough-in 5 02/24/20 02/28/20
20 03/02/20 03/27/20
1C-50220 Hard Ceiling Fire Sprinkler Rough-in 10 03/30/20 04/10/20
10 04/06/20 04/17/20
1C-50230 Hard Ceiling Electrical Rough-in 2 04/20/20 04/21/20
5 04/20/20 04/24/20
1C-50240 Hard Ceiling MEP Inspections 5 04/27/20 05/01/20
5 05/04/20 05/08/20
1C-50250 Drywall Ceilings 5 05/04/20 05/08/20
5 05/04/20 05/08/20
1C-50260 Tape Drywall Walls & Ceilings 5 05/04/20 05/08/20
5 05/04/20 05/08/20
1C-50300 Prime & Paint 15 02/24/20 03/13/20
5 03/09/20 03/13/20
1C-50310 Electrical Panels & Pull Wire 5 03/16/20 03/20/20
5 05/11/20 05/15/20
1C-50320 Door Frames 112 12/30/19 06/04/20
15 12/30/19 01/20/20
1C-50400 Ceiling Finishes 15 01/07/20 01/27/20
15 01/07/20 01/27/20
1C-50460 Suspended & Surface Mounted Fixtures 15 01/07/20 01/27/20
15 01/07/20 01/27/20
1C-50600 Flooring 15 01/14/20 02/03/20
15 01/14/20 02/03/20
1C-50610 Base 15 01/14/20 02/03/20
5 01/30/20 02/05/20
1C-50620 Hang Doors 5 02/03/20 02/07/20
10 02/05/20 02/18/20
1C-50630 Finish Paint
Edwards Lifescience
1C-50640 Door Hardware Proposal Schedule with Buil

1C-50650 Mechanical Trim Snyder L

1C-50660 Fire Sprinkler Trim

1C-50670 Electrical Trim

1C-50680 Low Voltage Trim

1C-50800 Tile (Restrooms)

1C-50820 Plumbing Fixtures (Restrooms)

1C-50840 Toilet Accessories (Restrooms)

1C-50900 Cleanup & Prepunch Interior

2ND FLOOR CORE

1C-55000 Overhead Mechanical Rough-in

1C-55010 Overhead Plumbing Rough-in

1C-55020 Overhead Fire Sprinkler Rough-in

1C-55030 Overhead Electrical Rough-in

1C-55100 Wall Framing & Furring

1C-55110 Wall Plumbing Rough-in

1C-55120 Wall Electrical Rough-in

1C-55130 Wall Low Voltage Rough-in

1C-55140 Wall MEP & Framing Inspections

1C-55150 Wall Insulation (dry-in)

1C-55160 Drywall Walls

Project Start 09/10/18 Page 14 of 18
Project Finish 07/23/20 TASK filter: All Activities
Data Date 09/01/18
Run Date 10/05/18

2019 2020

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Overhead Fire Sprinkler Rough-in

Overhead Electrical Rough-in

Wall Framing & Furring

Wall Plumbing Rough-in

Wall Electrical Rough-in

Wall Low Voltage Rough-in

Wall MEP & Framing Inspections

Wall Insulation (dry-in)

Drywall Walls

Hard Ceiling Framing

Hard Ceiling Mechanical Rough-in

Hard Ceiling Fire Sprinkler Rough-in

Hard Ceiling Electrical Rough-in

Hard Ceiling MEP Inspections

Drywall Ceilings

Tape Drywall Walls & Ceilings

Prime & Paint

Electrical Panels & Pull Wire

Door Frames

Ceiling Finishes

Suspended & Surface Mounted Fixtures

Flooring

Base

Hang Doors

Finish Paint

Door Hardware

Mechanical Trim

Fire Sprinkler Trim

Electrical Trim

Low Voltage Trim

Tile (Restrooms)

Plumbing Fixtures (Restrooms)

Toilet Accessories (Restrooms)

Cleanup & Prepunch Interior

2ND FLOOR CORE

Overhead Mechanical Rough-in

Overhead Plumbing Rough-in

Overhead Fire Sprinkler Rough-in

Overhead Electrical Rough-in

Wall Framing & Furring

Wall Plumbing Rough-in

Wall Electrical Rough-in

Wall Low Voltage Rough-in

Wall MEP & Framing Inspections

Wall Insulation (dry-in)

Drywall Walls

es Campus Expansion Remaining Level of Effort
lding B Concrete - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work

Activity ID Activity Name Dur Current Start Current Finish
Aug Sep Oct Nov Dec
1C-55200 Hard Ceiling Framing
10 01/21/20 02/03/20
1C-55210 Hard Ceiling Mechanical Rough-in 10 01/28/20 02/10/20
10 01/28/20 02/10/20
1C-55220 Hard Ceiling Fire Sprinkler Rough-in 10 01/28/20 02/10/20
10 01/28/20 02/10/20
1C-55230 Hard Ceiling Electrical Rough-in
5 02/11/20 02/17/20
1C-55235 Operable Wall Tracks 10 02/13/20 02/26/20
10 02/27/20 03/11/20
1C-55240 Hard Ceiling MEP Inspections 10 03/05/20 03/18/20
20 03/12/20 04/08/20
1C-55250 Drywall Ceilings
5 03/12/20 03/18/20
1C-55260 Tape Drywall Walls & Ceilings 20 03/19/20 04/15/20
10 04/16/20 04/29/20
1C-55300 Prime & Paint 10 04/23/20 05/06/20

1C-55310 Electrical Panels & Pull Wire 2 05/07/20 05/08/20
5 05/07/20 05/13/20
1C-55320 Door Frames 5 05/14/20 05/20/20
5 05/21/20 05/28/20
1C-55400 Ceiling Finishes 5 05/21/20 05/28/20
5 05/21/20 05/28/20
1C-55460 Suspended & Surface Mounted Fixtures 5 05/21/20 05/28/20
5 05/21/20 05/28/20
1C-55600 Flooring 5 05/21/20 05/28/20
20 03/12/20 04/08/20
1C-55610 Base 10 04/02/20 04/15/20
10 04/09/20 04/22/20
1C-55620 Hang Doors 5 05/29/20 06/04/20
35 03/12/20 04/29/20
1C-55630 Finish Paint
15 03/12/20 04/01/20
1C-55640 Door Hardware 10 03/26/20 04/08/20
10 04/02/20 04/15/20
1C-55650 Mechanical Trim 10 04/09/20 04/22/20
10 04/16/20 04/29/20
1C-55660 Fire Sprinkler Trim 40 03/12/20 05/06/20

1C-55670 Electrical Trim 10 03/12/20 03/25/20
5 03/26/20 04/01/20
1C-55680 Low Voltage Trim 5 04/02/20 04/08/20
3 04/09/20 04/13/20
1C-55690 Operable Wall Panels 3 04/14/20 04/16/20
5 04/17/20 04/23/20
1C-55800 Tile (Restrooms) 5 04/30/20 05/06/20

1C-55820 Plumbing Fixtures (Restrooms) 293 04/29/19 06/23/20

1C-55840 Toilet Accessories (Restrooms) 20 04/29/19 05/24/19
20 05/28/19 06/24/19
1C-55900 Cleanup & Prepunch Interior 100 01/07/20 05/26/20

INTERIOR STAIRS Edwards Lifescience
Proposal Schedule with Buil
1C-70000 Drywall & Tape Stairs
Snyder L
1C-70010 Handrails

1C-70020 Prime & Paint

1C-70030 Flooring

1C-70040 MEP Trim

ELEVATORS

1C-71000 Elevator Pre-Check List & Corrections

1C-71010 Elevator Rails

1C-71020 Elevator Equipment

1C-71030 Elevator Temp Platform

1C-71040 Elevator Door Frames

1C-71050 Elevator Cab & Finishes

1C-71060 Elevator Test & Adjust

SITEWORK

1C-80000 Site Wet Utilities

1C-80100 Site Dry Utilities

1C-80400 Hardscape (Cafe/Conference)

Project Start 09/10/18 Page 15 of 18
Project Finish 07/23/20 TASK filter: All Activities
Data Date 09/01/18
Run Date 10/05/18

2019 2020

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Hard Ceiling Framing

Hard Ceiling Mechanical Rough-in

Hard Ceiling Fire Sprinkler Rough-in

Hard Ceiling Electrical Rough-in

Operable Wall Tracks

Hard Ceiling MEP Inspections

Drywall Ceilings

Tape Drywall Walls & Ceilings

Prime & Paint

Electrical Panels & Pull Wire

Door Frames

Ceiling Finishes

Suspended & Surface Mounted Fixtures

Flooring

Base

Hang Doors

Finish Paint

Door Hardware

Mechanical Trim

Fire Sprinkler Trim

Electrical Trim

Low Voltage Trim

Operable Wall Panels

Tile (Restrooms)

Plumbing Fixtures (Restrooms)

Toilet Accessories (Restrooms)

Cleanup & Prepunch Interior

INTERIOR STAIRS

Drywall & Tape Stairs

Handrails

Prime & Paint

Flooring

MEP Trim

ELEVATORS

Elevator Pre-Check List & Corrections

Elevator Rails

Elevator Equipment

Elevator Temp Platform

Elevator Door Frames

Elevator Cab & Finishes

Elevator Test & Adjust

SITEWORK

Site Wet Utilities

Site Dry Utilities

Hardscape (Cafe/Conference)

es Campus Expansion Remaining Level of Effort
lding B Concrete - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work

Activity ID Activity Name Dur Current Start Current Finish
Aug Sep Oct Nov Dec

1C-80410 Landscape (Cafe/Conference) 40 04/28/20 06/23/20

INSPECTIONS / PUNCHLIST 73 04/09/20 07/22/20

1C-89000 Permanent Power 15 04/09/20 04/29/20

1C-90000 Final Inspections 10 06/24/20 07/08/20

1C-90005 Commissioning/LEED Approval 40 05/12/20 07/08/20

1C-90010 Inclement Weather Allowance 10 07/09/20 07/22/20

1C-90020 Substantial Completion 0 07/22/20

1C-90100 Prepare Punchlist 2 06/22/20 06/23/20

1C-90110 Punchlist Corrections 20 06/24/20 07/22/20

1C-90120 Final Completion 0 07/22/20

CONSTRUCTION - PHASE 1 - OFFSITE 278 01/03/19 02/06/20

REDHILL DECELERATION LANE, LEFT TURN LANE, MEDIAN, U/G UTILITIES 278 01/03/19 02/06/20

1S-11900 Submit/Approve Traffic Control Plans 60 01/03/19 03/27/19

1S-12000 Post Advanced Construction Notification & Street Signage 10 03/28/19 04/10/19

1S-12010 Contact Underground Dig Alert & Record Permit Number 1 04/11/19 04/11/19

1S-12020 Verify, Document & Submit Existing Conditions Prior to Start 5 04/12/19 04/18/19

1S-12030 Survey Demo Limits Prior to Start & Confirm with Contract Documents 5 04/19/19 04/25/19

1S-12040 Preconstruction Conference with City of Irvine as Required 5 04/26/19 05/02/19

1S-12100 Setup Temporary Traffic Control Measures 3 05/03/19 05/07/19

1S-12110 Setup Temporary BMP's 5 05/08/19 05/14/19

1S-12112 Construct (N) 16 in ACP Water Main 15 05/15/19 06/05/19

1S-12114 Construct (N) Fire, Domestic & Irrigation D.I. Laterals 15 05/15/19 06/05/19

1S-12116 R&R Fire Hydrant & Remove Lateral 15 05/15/19 06/05/19

1S-12118 Survey & Layout Raised Islands 1 06/06/19 06/06/19

1S-12120 Sawcut & Demo Hardscapes for Raised Islands 3 06/07/19 06/11/19

1S-12122 Grade & Compact Subgrades for Raised Islands 3 06/12/19 06/14/19

1S-12124 Form Raised Islands & Certify Formwork 2 06/17/19 06/18/19

1S-12126 Pour & Strip Curb Islands 2 06/19/19 06/20/19

1S-12128 Backfill & Compact Curb Islands 5 06/21/19 06/27/19

1S-12130 Patch A/C Paving at Curb Islands 5 06/28/19 07/05/19

1S-12132 Grind & Overlay A/C Paving at Curb Islands 5 07/08/19 07/12/19

1S-12134 Temporary Striping 1 07/15/19 07/15/19

1S-12136 Remove & Relocate Construction Fencing 2 06/06/19 06/07/19

1S-12138 Safe-off & Re-Route Irrigation 2 06/10/19 06/11/19

1S-12140 Remove & Salvage Signage as Applicable 2 06/12/19 06/13/19

1S-12150 Remove & Relocate Existing Low Volt Pull Box & Assoc. Cabling 5 06/14/19 06/20/19

1S-12160 Remove & Protect Existing Bus Bench, Trash Can & Associated Signage 5 06/21/19 06/27/19

1S-12200 Demo (E) Hardscapes & Landscapes 3 06/28/19 07/02/19

1S-12210 Survey (N) Curb & Gutter 1 07/03/19 07/03/19

1S-12220 Prepare Subgrade for (N) Deceleration Lane, Curb & Gutter 5 07/05/19 07/11/19

1S-12230 Test Subgrade for Compaction 2 07/12/19 07/15/19

1S-12240 Install (N) Below Grade Signal Conduit & Associated Pull Boxes 10 07/16/19 07/29/19

1S-12242 Relocate Pedestrian Light Pole 5 07/30/19 08/05/19

1S-12250 Form (N) Curb & Gutter & EntranceApron 5 07/30/19 08/05/19

1S-12260 Survey & Record (N) Curb & Gutter Formwork - Prepour 1 08/06/19 08/06/19

Project Start 09/10/18 Page 16 of 18 Edwards Lifescience
Project Finish 07/23/20 TASK filter: All Activities Proposal Schedule with Buil
Data Date 09/01/18
Run Date 10/05/18 Snyder L

2019 2020

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Landscape (Cafe/Conference)

INSPECTIONS / PUNCHLIST

Permanent Power

Final Inspections

Commissioning/LEED Approval

Inclement Weather Allowance

Substantial Completion

Prepare Punchlist

Punchlist Corrections

Final Completion

CONSTRUCTION - PHASE 1 - OFFSITE

REDHILL DECELERATION LANE, LEFT TURN LANE, MEDIAN, U/G UTILITIES

Submit/Approve Traffic Control Plans
Post Advanced Construction Notification & Street Signage
Contact Underground Dig Alert & Record Permit Number
Verify, Document & Submit Existing Conditions Prior to Start
Survey Demo Limits Prior to Start & Confirm with Contract Documents
Preconstruction Conference with City of Irvine as Required
Setup Temporary Traffic Control Measures
Setup Temporary BMP's
Construct (N) 16 in ACP Water Main
Construct (N) Fire, Domestic & Irrigation D.I. Laterals
R&R Fire Hydrant & Remove Lateral
Survey & Layout Raised Islands
Sawcut & Demo Hardscapes for Raised Islands
Grade & Compact Subgrades for Raised Islands
Form Raised Islands & Certify Formwork
Pour & Strip Curb Islands
Backfill & Compact Curb Islands
Patch A/C Paving at Curb Islands
Grind & Overlay A/C Paving at Curb Islands
Temporary Striping
Remove & Relocate Construction Fencing
Safe-off & Re-Route Irrigation
Remove & Salvage Signage as Applicable
Remove & Relocate Existing Low Volt Pull Box & Assoc. Cabling
Remove & Protect Existing Bus Bench, Trash Can & Associated Signage
Demo (E) Hardscapes & Landscapes
Survey (N) Curb & Gutter
Prepare Subgrade for (N) Deceleration Lane, Curb & Gutter
Test Subgrade for Compaction
Install (N) Below Grade Signal Conduit & Associated Pull Boxes
Relocate Pedestrian Light Pole
Form (N) Curb & Gutter & EntranceApron
Survey & Record (N) Curb & Gutter Formwork - Prepour

es Campus Expansion Remaining Level of Effort
lding B Concrete - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work

Activity ID Activity Name Dur Current Start Current Finish
Aug Sep Oct Nov Dec
1S-12270 Pour (N) Curb & Gutter, Entrance Apron, Strip & Cure
5 08/07/19 08/13/19
1S-12280 Backfill & Compact Behind Curb & Gutter, Entrance Apron 3 08/14/19 08/16/19
1 08/19/19 08/19/19
1S-12290 Survey Subgrade for Sidewalks at EntranceApron 1 08/20/19 08/20/19
5 08/21/19 08/27/19
1S-12300 Install (N) Posts & Signage as Applicable 1 08/28/19 08/28/19
3 08/29/19 09/03/19
1S-12310 Form Sidewalks 2 09/04/19 09/05/19
3 09/06/19 09/10/19
1S-12320 Survey & Record (N) Sidewalk Formwork 1 09/11/19 09/11/19
2 09/12/19 09/13/19
1S-12330 Pour Sidewalks, Strip & Cure 10 01/02/20* 01/15/20
5 01/16/20 01/22/20
1S-12340 Install Relocated Bus Stop Bench, Trash Can & Associated Signage 10 01/23/20 02/05/20
1 02/06/20 02/06/20
1S-12350 Prepare Roadway Subgrade with .65' Aggregate Base & Compact 110 08/01/19 01/09/20

1S-12360 Test Compaction of A.B. 10 08/01/19* 08/14/19
1 08/15/19 08/15/19
1S-12370 A/C Paving 5 08/16/19 08/22/19
5 08/23/19 08/29/19
1S-12372 Grind & Overlay A/C Paving 5 08/30/19 09/06/19
3 09/09/19 09/11/19
1S-12374 Slurry Seal A/C Paving 5 09/12/19 09/18/19

1S-12376 Striping 1st Pass, Cure & Final Stripe 15 09/19/19 10/09/19
10 09/19/19 10/02/19
1S-12380 Final Clean
2 09/19/19 09/20/19
ALTON PKWY STREET WIDENING & U/G UTILITIES 2 09/23/19 09/24/19
2 09/25/19 09/26/19
1S-20000 Post Advanced Construction Notification & Street Signage 5 09/27/19 10/03/19
5 10/04/19 10/10/19
1S-20010 Contact Underground Dig Alert & Record Permit Number 5 10/11/19 10/17/19
1 10/18/19 10/18/19
1S-20020 Verify, Document & Submit Existing Conditions Prior to Start 2 10/21/19 10/22/19
1 10/23/19 10/23/19
1S-20030 Survey Demo Limits Prior to Start & Confirm with Contract Documents 10 10/24/19 11/06/19
2 11/07/19 11/08/19
1S-20040 Preconstruction Conference with City of Irvine as Required 1 11/12/19 11/12/19
2 11/13/19 11/14/19
1S-20050 Setup Temporary Traffic Control Measures 1 11/15/19 11/15/19
1 11/18/19 11/18/19
1S-20060 Setup Temporary BMP's 1 11/19/19 11/19/19
1 11/20/19 11/20/19
1S-20070 Sanitary Sewer Improvements 1 11/21/19 11/21/19
2 11/22/19 11/25/19
1S-20080 Relocate Fire Hydrants 2 11/26/19 11/27/19

1S-20090 Remove & Relocate Construction Fencing Edwards Lifescience
Proposal Schedule with Buil
1S-20100 Safe-off & Re-Route Irrigation
Snyder L
1S-20110 Remove & Salvage Signage as Applicable

1S-20120 Remove & Relocate Existing Low Volt Pull Box & Assoc. Cabling

1S-20130 Remove & Protect Existing Bus Bench, Trash Can & Associated Signage

1S-20140 Demo (E) Hardscapes & Landscapes

1S-20150 Survey (N) Curb & Gutter

1S-20160 Prepare Subgrade for (N) Street Widening, Curb & Gutter

1S-20170 Test Subgrade for Compaction

1S-20180 Install (N) Below Grade Signal Conduit & Associated Pull Boxes

1S-20190 Form (N) Curb & Gutter & EntranceApron

1S-20200 Survey & Record (N) Curb & Gutter Formwork - Prepour

1S-20210 Pour (N) Curb & Gutter, Entrance Apron, Strip & Cure

1S-20220 Backfill & Compact Behind Curb & Gutter, Entrance Apron

1S-20230 Survey Subgrade for Sidewalks

1S-20240 Install (N) Posts & Signage as Applicable

1S-20250 Form Sidewalks

1S-20260 Pour Sidewalks, Strip & Cure

1S-20270 Install Relocated Signage

1S-20280 Prepare Roadway Subgrade with .65' Aggregate Base & Compact

Project Start 09/10/18 Page 17 of 18
Project Finish 07/23/20 TASK filter: All Activities
Data Date 09/01/18
Run Date 10/05/18

2019 2020

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Pour (N) Curb & Gutter, Entrance Apron, Strip & Cure

Backfill & Compact Behind Curb & Gutter, Entrance Apron

Survey Subgrade for Sidewalks at EntranceApron

Install (N) Posts & Signage as Applicable

Form Sidewalks

Survey & Record (N) Sidewalk Formwork

Pour Sidewalks, Strip & Cure

Install Relocated Bus Stop Bench, Trash Can & Associated Signage

Prepare Roadway Subgrade with .65' Aggregate Base & Compact

Test Compaction of A.B.

A/C Paving

Grind & Overlay A/C Paving

Slurry Seal A/C Paving

Striping 1st Pass, Cure & Final Stripe

Final Clean

ALTON PKWY STREET WIDENING & U/G UTILITIES

Post Advanced Construction Notification & Street Signage

Contact Underground Dig Alert & Record Permit Number

Verify, Document & Submit Existing Conditions Prior to Start

Survey Demo Limits Prior to Start & Confirm with Contract Documents

Preconstruction Conference with City of Irvine as Required

Setup Temporary Traffic Control Measures

Setup Temporary BMP's

Sanitary Sewer Improvements

Relocate Fire Hydrants

Remove & Relocate Construction Fencing

Safe-off & Re-Route Irrigation

Remove & Salvage Signage as Applicable

Remove & Relocate Existing Low Volt Pull Box & Assoc. Cabling

Remove & Protect Existing Bus Bench, Trash Can & Associated Signage

Demo (E) Hardscapes & Landscapes

Survey (N) Curb & Gutter

Prepare Subgrade for (N) Street Widening, Curb & Gutter

Test Subgrade for Compaction

Install (N) Below Grade Signal Conduit & Associated Pull Boxes

Form (N) Curb & Gutter & EntranceApron

Survey & Record (N) Curb & Gutter Formwork - Prepour

Pour (N) Curb & Gutter, Entrance Apron, Strip & Cure

Backfill & Compact Behind Curb & Gutter, Entrance Apron

Survey Subgrade for Sidewalks

Install (N) Posts & Signage as Applicable

Form Sidewalks

Pour Sidewalks, Strip & Cure

Install Relocated Signage

Prepare Roadway Subgrade with .65' Aggregate Base & Compact

es Campus Expansion Remaining Level of Effort
lding B Concrete - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work

Activity ID Activity Name Dur Current Start Current Finish
Aug Sep Oct Nov Dec
1S-20290 Test Compaction of A.B.
1S-20300 A/C Paving 1 12/02/19 12/02/19
1S-20310 Grind & Overlay A/C Paving 2 12/03/19 12/04/19
1S-20320 Slurry Seal A/C Paving 2 12/05/19 12/06/19
1S-20330 Striping 1st Pass, Cure & Final Stripe 2 12/09/19 12/10/19
1S-20340 Final Inspections 10 12/11/19 12/24/19
10 12/26/19 01/09/20

Project Start 09/10/18 Page 18 of 18 Edwards Lifescience
Project Finish 07/23/20 TASK filter: All Activities Proposal Schedule with Buil
Data Date 09/01/18
Run Date 10/05/18 Snyder L

2019 2020

c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Test Compaction of A.B.

A/C Paving

Grind & Overlay A/C Paving

Slurry Seal A/C Paving

Striping 1st Pass, Cure & Final Stripe

Final Inspections

es Campus Expansion Remaining Level of Effort
lding B Concrete - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work