Activity ID Activity Name Dur Current Start Current
Finish
Aug Sep Oct Nov Dec
1C-10020 Earthwork 15 06/26/19 07/17/19
5 07/18/19 07/24/19
1C-10030 Certify Pad 12/19/19
102 07/25/19
FOUNDATIONS / STRUCTURE
1C-15000 Drill/Rebar/Pour Piles (246) 25 07/25/19 08/28/19
15 08/22/19 09/12/19
1C-15100 Form/Rebar/Pour Pilecaps 10 08/29/19 09/12/19
15 09/06/19 09/26/19
1C-15200 Excavate/Form/Pour Elevator Pit 10 09/27/19 10/10/19
15 10/04/19 10/24/19
1C-15300 Form/Rebar/Pour Gradebeams 10 10/18/19 10/31/19
10 10/18/19 10/31/19
1C-17000 Erect Structural Steel 10 11/01/19 11/15/19
10 11/08/19 11/22/19
1C-17010 Weld Structural Steel 10 11/08/19 11/22/19
11/26/19
1C-17020 Erect BRB's 2 11/25/19 12/05/19
5 11/27/19 12/19/19
1C-17100 Metal Deck/Edge Metal/Shear Studs (2nd Floor) 10 12/06/19 12/03/19
15 11/08/19 04/27/20
1C-17110 Metal Deck/Edge Metal (Roof) 95 12/13/19
1C-18000 Underslab Plumbing Rough-in
1C-18050 Complete Rebar/Pour Gradebeams at Moment Frames
1C-18100 Fine Grade for SOG
1C-18110 Sand/Vapor Barrier for SOG
1C-18120 Form/Rebar/Pour SOG
1C-18200 MEP/Rebar/Pour Concrete on Metal Deck (2nd Floor)
EXTERIOR SKIN
1C-30000 Exterior Framing 15 12/13/19 01/06/20
10 12/20/19 01/06/20
1C-30010 Exterior MEP Rough-in 10 12/30/19 01/13/20
01/20/20
1C-30020 Exterior Sheathing 5 01/14/20 02/17/20
20 01/21/20 03/30/20
1C-30200 Waterproofing for Wood Rain Screen 60 01/07/20 03/16/20
10 03/03/20 03/30/20
1C-30210 Wood Rain Screen 10 03/17/20 04/06/20
02/10/20
1C-30300 Curtainwall 5 03/31/20 01/27/20
20 01/14/20 03/02/20
1C-30350 Storefront Framing 10 01/14/20 04/13/20
30 01/21/20 04/20/20
1C-30360 Storefront Glazing 40 02/18/20 04/27/20
05/26/20
1C-30370 Storefront Doors 5 04/14/20
5 04/21/20
1C-30400 Steel & Glass Guardrails 132 11/18/19
1C-30500 Weatherproofing for Aluminum Panels
1C-30510 Field Measure & Fab Aluminum Panels
1C-30520 Install Aluminum Panels
1C-30600 MEP Trim
1C-30900 Cleanup & Prepunch
ROOF
ROOF DECK 122 12/04/19 05/26/20
5 12/04/19 12/10/19
1C-40000 MEP Penetrations & Roof Drains 5 12/11/19 12/17/19
04/13/20
1C-40030 Sheetmetal Flashing 10 03/31/20 04/20/20
10 04/07/20 05/18/20
1C-40100 Waterproofing 20 04/21/20 05/26/20
02/13/20
1C-40110 Topping Slabs 5 05/19/20 11/22/19
60 11/18/19 11/22/19
1C-40300 Roof Deck Pavers & Finishes
5 11/18/19
1C-40900 Cleanup & Prepunch Roof Decks 5 11/18/19
MAIN ROOF
1C-41000 MEP Penetrations & Roof Drains
1C-41010 Mechanical Curbs
Project Start 09/10/18 Page 13 of 18 Edwards Lifescience
Project Finish 07/23/20 TASK filter: All Activities Proposal Schedule with C
Data Date 09/01/18
Run Date 10/05/18 Snyder L
2019 2020
c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Earthwork
Certify Pad
FOUNDATIONS / STRUCTURE
Drill/Rebar/Pour Piles (246)
Form/Rebar/Pour Pilecaps
Excavate/Form/Pour Elevator Pit
Form/Rebar/Pour Gradebeams
Erect Structural Steel
Weld Structural Steel
Erect BRB's
Metal Deck/Edge Metal/Shear Studs (2nd Floor)
Metal Deck/Edge Metal (Roof)
Underslab Plumbing Rough-in
Complete Rebar/Pour Gradebeams at Moment Frames
Fine Grade for SOG
Sand/Vapor Barrier for SOG
Form/Rebar/Pour SOG
MEP/Rebar/Pour Concrete on Metal Deck (2nd Floor)
EXTERIOR SKIN
Exterior Framing
Exterior MEP Rough-in
Exterior Sheathing
Waterproofing for Wood Rain Screen
Wood Rain Screen
Curtainwall
Storefront Framing
Storefront Glazing
Storefront Doors
Steel & Glass Guardrails
Weatherproofing for Aluminum Panels
Field Measure & Fab Aluminum Panels
Install Aluminum Panels
MEP Trim
Cleanup & Prepunch
ROOF
ROOF DECK
MEP Penetrations & Roof Drains
Sheetmetal Flashing
Waterproofing
Topping Slabs
Roof Deck Pavers & Finishes
Cleanup & Prepunch Roof Decks
MAIN ROOF
MEP Penetrations & Roof Drains
Mechanical Curbs
es Campus Expansion Remaining Level of Effort
ConXtech Steel - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work
Activity ID Activity Name Dur Current Start Current
Finish
Aug Sep Oct Nov Dec
1C-41030 Sheetmetal Flashing 5 11/25/19 12/03/19
10 12/04/19 12/17/19
1C-41100 Roofing 12/24/19
5 12/18/19 01/23/20
1C-41200 Set Mechanical Equipment 20 12/26/19 01/16/20
20 12/18/19 02/06/20
1C-41210 Hookup Mechanical Equipment 10 01/24/20 02/13/20
06/04/20
1C-41300 Roof Screen Panels 5 02/07/20
122 12/13/19
1C-41400 Sheetmetal Trim & Finish
1C-41900 Cleanup & Prepunch Roof
INTERIOR
1ST FLOOR CORE 109 12/13/19 05/15/20
10 12/13/19 12/27/19
1C-50000 Overhead Mechanical Rough-in 10 12/20/19 01/06/20
10 12/20/19 01/06/20
1C-50010 Overhead Plumbing Rough-in 10 12/20/19 01/06/20
10 12/20/19 01/06/20
1C-50020 Overhead Fire Sprinkler Rough-in 10 12/30/19 01/13/20
10 12/30/19 01/13/20
1C-50030 Overhead Electrical Rough-in 10 12/30/19 01/13/20
5 01/09/20 01/15/20
1C-50100 Wall Framing & Furring 5 01/13/20 01/17/20
10 01/15/20 01/28/20
1C-50110 Wall Plumbing Rough-in 10 01/07/20 01/20/20
10 01/14/20 01/27/20
1C-50120 Wall Electrical Rough-in 10 01/14/20 01/27/20
10 01/14/20 01/27/20
1C-50130 Wall Low Voltage Rough-in 5 01/23/20 01/29/20
10 01/27/20 02/07/20
1C-50140 Wall MEP & Framing Inspections 10 02/10/20 02/21/20
10 02/17/20 02/28/20
1C-50150 Wall Insulation (dry-in) 20 02/24/20 03/20/20
5 02/24/20 02/28/20
1C-50160 Drywall Walls 20 03/02/20 03/27/20
10 03/30/20 04/10/20
1C-50200 Hard Ceiling Framing 10 04/06/20 04/17/20
2 04/20/20 04/21/20
1C-50210 Hard Ceiling Mechanical Rough-in 5 04/20/20 04/24/20
5 04/27/20 05/01/20
1C-50220 Hard Ceiling Fire Sprinkler Rough-in 5 05/04/20 05/08/20
5 05/04/20 05/08/20
1C-50230 Hard Ceiling Electrical Rough-in 5 05/04/20 05/08/20
5 05/04/20 05/08/20
1C-50240 Hard Ceiling MEP Inspections 5 05/04/20 05/08/20
15 02/24/20 03/13/20
1C-50250 Drywall Ceilings 5 03/09/20 03/13/20
5 03/16/20 03/20/20
1C-50260 Tape Drywall Walls & Ceilings 5 05/11/20 05/15/20
1C-50300 Prime & Paint
1C-50310 Electrical Panels & Pull Wire
1C-50320 Door Frames
1C-50400 Ceiling Finishes
1C-50460 Suspended & Surface Mounted Fixtures
1C-50600 Flooring
1C-50610 Base
1C-50620 Hang Doors
1C-50630 Finish Paint
1C-50640 Door Hardware
1C-50650 Mechanical Trim
1C-50660 Fire Sprinkler Trim
1C-50670 Electrical Trim
1C-50680 Low Voltage Trim
1C-50800 Tile (Restrooms)
1C-50820 Plumbing Fixtures (Restrooms)
1C-50840 Toilet Accessories (Restrooms)
1C-50900 Cleanup & Prepunch Interior
Project Start 09/10/18 Page 14 of 18 Edwards Lifescience
Project Finish 07/23/20 TASK filter: All Activities Proposal Schedule with C
Data Date 09/01/18
Run Date 10/05/18 Snyder L
2019 2020
c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Sheetmetal Flashing
Roofing
Set Mechanical Equipment
Hookup Mechanical Equipment
Roof Screen Panels
Sheetmetal Trim & Finish
Cleanup & Prepunch Roof
INTERIOR
1ST FLOOR CORE
Overhead Mechanical Rough-in
Overhead Plumbing Rough-in
Overhead Fire Sprinkler Rough-in
Overhead Electrical Rough-in
Wall Framing & Furring
Wall Plumbing Rough-in
Wall Electrical Rough-in
Wall Low Voltage Rough-in
Wall MEP & Framing Inspections
Wall Insulation (dry-in)
Drywall Walls
Hard Ceiling Framing
Hard Ceiling Mechanical Rough-in
Hard Ceiling Fire Sprinkler Rough-in
Hard Ceiling Electrical Rough-in
Hard Ceiling MEP Inspections
Drywall Ceilings
Tape Drywall Walls & Ceilings
Prime & Paint
Electrical Panels & Pull Wire
Door Frames
Ceiling Finishes
Suspended & Surface Mounted Fixtures
Flooring
Base
Hang Doors
Finish Paint
Door Hardware
Mechanical Trim
Fire Sprinkler Trim
Electrical Trim
Low Voltage Trim
Tile (Restrooms)
Plumbing Fixtures (Restrooms)
Toilet Accessories (Restrooms)
Cleanup & Prepunch Interior
es Campus Expansion Remaining Level of Effort
ConXtech Steel - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work
Activity ID Activity Name Dur Current Start Current
Finish
Aug Sep Oct Nov Dec
2ND FLOOR CORE 112 12/30/19 06/04/20
15 12/30/19 01/20/20
1C-55000 Overhead Mechanical Rough-in 15 01/07/20 01/27/20
15 01/07/20 01/27/20
1C-55010 Overhead Plumbing Rough-in 15 01/07/20 01/27/20
15 01/07/20 01/27/20
1C-55020 Overhead Fire Sprinkler Rough-in 15 01/14/20 02/03/20
15 01/14/20 02/03/20
1C-55030 Overhead Electrical Rough-in 15 01/14/20 02/03/20
02/05/20
1C-55100 Wall Framing & Furring 5 01/30/20 02/07/20
5 02/03/20 02/18/20
1C-55110 Wall Plumbing Rough-in 10 02/05/20 02/03/20
10 01/21/20 02/10/20
1C-55120 Wall Electrical Rough-in 10 01/28/20 02/10/20
10 01/28/20 02/10/20
1C-55130 Wall Low Voltage Rough-in 10 01/28/20 02/10/20
10 01/28/20 02/17/20
1C-55140 Wall MEP & Framing Inspections 5 02/11/20 02/26/20
10 02/13/20 03/11/20
1C-55150 Wall Insulation (dry-in) 10 02/27/20 03/18/20
10 03/05/20 04/08/20
1C-55160 Drywall Walls 20 03/12/20 03/18/20
5 03/12/20 04/15/20
1C-55200 Hard Ceiling Framing 20 03/19/20 04/29/20
10 04/16/20 05/06/20
1C-55210 Hard Ceiling Mechanical Rough-in 10 04/23/20 05/08/20
2 05/07/20 05/13/20
1C-55220 Hard Ceiling Fire Sprinkler Rough-in 5 05/07/20 05/20/20
5 05/14/20 05/28/20
1C-55230 Hard Ceiling Electrical Rough-in 5 05/21/20 05/28/20
5 05/21/20 05/28/20
1C-55235 Operable Wall Tracks 5 05/21/20 05/28/20
5 05/21/20 05/28/20
1C-55240 Hard Ceiling MEP Inspections 5 05/21/20 05/28/20
5 05/21/20 04/08/20
1C-55250 Drywall Ceilings 20 03/12/20 04/15/20
10 04/02/20 04/22/20
1C-55260 Tape Drywall Walls & Ceilings 10 04/09/20 06/04/20
5 05/29/20 04/29/20
1C-55300 Prime & Paint 35 03/12/20
04/01/20
1C-55310 Electrical Panels & Pull Wire 15 03/12/20 04/08/20
10 03/26/20 04/15/20
1C-55320 Door Frames 10 04/02/20 04/22/20
10 04/09/20 04/29/20
1C-55400 Ceiling Finishes 10 04/16/20
1C-55460 Suspended & Surface Mounted Fixtures
1C-55600 Flooring
1C-55610 Base
1C-55620 Hang Doors
1C-55630 Finish Paint
1C-55640 Door Hardware
1C-55650 Mechanical Trim
1C-55660 Fire Sprinkler Trim
1C-55670 Electrical Trim
1C-55680 Low Voltage Trim
1C-55690 Operable Wall Panels
1C-55800 Tile (Restrooms)
1C-55820 Plumbing Fixtures (Restrooms)
1C-55840 Toilet Accessories (Restrooms)
1C-55900 Cleanup & Prepunch Interior
INTERIOR STAIRS
1C-70000 Drywall & Tape Stairs
1C-70010 Handrails
1C-70020 Prime & Paint
1C-70030 Flooring
1C-70040 MEP Trim
Project Start 09/10/18 Page 15 of 18 Edwards Lifescience
Project Finish 07/23/20 TASK filter: All Activities Proposal Schedule with C
Data Date 09/01/18
Run Date 10/05/18 Snyder L
2019 2020
c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
2ND FLOOR CORE
Overhead Mechanical Rough-in
Overhead Plumbing Rough-in
Overhead Fire Sprinkler Rough-in
Overhead Electrical Rough-in
Wall Framing & Furring
Wall Plumbing Rough-in
Wall Electrical Rough-in
Wall Low Voltage Rough-in
Wall MEP & Framing Inspections
Wall Insulation (dry-in)
Drywall Walls
Hard Ceiling Framing
Hard Ceiling Mechanical Rough-in
Hard Ceiling Fire Sprinkler Rough-in
Hard Ceiling Electrical Rough-in
Operable Wall Tracks
Hard Ceiling MEP Inspections
Drywall Ceilings
Tape Drywall Walls & Ceilings
Prime & Paint
Electrical Panels & Pull Wire
Door Frames
Ceiling Finishes
Suspended & Surface Mounted Fixtures
Flooring
Base
Hang Doors
Finish Paint
Door Hardware
Mechanical Trim
Fire Sprinkler Trim
Electrical Trim
Low Voltage Trim
Operable Wall Panels
Tile (Restrooms)
Plumbing Fixtures (Restrooms)
Toilet Accessories (Restrooms)
Cleanup & Prepunch Interior
INTERIOR STAIRS
Drywall & Tape Stairs
Handrails
Prime & Paint
Flooring
MEP Trim
es Campus Expansion Remaining Level of Effort
ConXtech Steel - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work
Activity ID Activity Name Dur Current Start Current
Finish
Aug Sep Oct Nov Dec
ELEVATORS 40 03/12/20 05/06/20
1C-71000 Elevator Pre-Check List & Corrections 10 03/12/20 03/25/20
5 03/26/20 04/01/20
1C-71010 Elevator Rails 5 04/02/20 04/08/20
3 04/09/20 04/13/20
1C-71020 Elevator Equipment 3 04/14/20 04/16/20
5 04/17/20 04/23/20
1C-71030 Elevator Temp Platform 5 04/30/20 05/06/20
06/23/20
1C-71040 Elevator Door Frames 293 04/29/19
05/24/19
1C-71050 Elevator Cab & Finishes 20 04/29/19 06/24/19
20 05/28/19 05/26/20
1C-71060 Elevator Test & Adjust 100 01/07/20 06/23/20
40 04/28/20 07/22/20
SITEWORK 73 04/09/20
04/29/20
1C-80000 Site Wet Utilities 15 04/09/20 07/08/20
10 06/24/20 07/08/20
1C-80100 Site Dry Utilities 40 05/12/20 07/22/20
10 07/09/20 07/22/20
1C-80400 Hardscape (Cafe/Conference) 06/23/20
0 07/22/20
1C-80410 Landscape (Cafe/Conference) 2 06/22/20 07/22/20
20 06/24/20 02/06/20
INSPECTIONS / PUNCHLIST 0
278 01/03/19
1C-89000 Permanent Power
1C-90000 Final Inspections
1C-90005 Commissioning/LEED Approval
1C-90010 Inclement Weather Allowance
1C-90020 Substantial Completion
1C-90100 Prepare Punchlist
1C-90110 Punchlist Corrections
1C-90120 Final Completion
CONSTRUCTION - PHASE 1 - OFFSITE
REDHILL DECELERATION LANE, LEFT TURN LANE, MEDIAN, U/G UTILITIES 278 01/03/19 02/06/20
1S-11900 Submit/Approve Traffic Control Plans 60 01/03/19 03/27/19
10 03/28/19 04/10/19
1S-12000 Post Advanced Construction Notification & Street Signage 04/11/19
1 04/11/19 04/18/19
1S-12010 Contact Underground Dig Alert & Record Permit Number 5 04/12/19 04/25/19
5 04/19/19 05/02/19
1S-12020 Verify, Document & Submit Existing Conditions Prior to Start 5 04/26/19 05/07/19
3 05/03/19 05/14/19
1S-12030 Survey Demo Limits Prior to Start & Confirm with Contract Documents 5 05/08/19 06/05/19
15 05/15/19 06/05/19
1S-12040 Preconstruction Conference with City of Irvine as Required 15 05/15/19 06/05/19
15 05/15/19 06/06/19
1S-12100 Setup Temporary Traffic Control Measures 1 06/06/19 06/11/19
3 06/07/19 06/14/19
1S-12110 Setup Temporary BMP's 3 06/12/19 06/18/19
2 06/17/19 06/20/19
1S-12112 Construct (N) 16 in ACP Water Main 2 06/19/19 06/27/19
5 06/21/19 07/05/19
1S-12114 Construct (N) Fire, Domestic & Irrigation D.I. Laterals 5 06/28/19 07/12/19
5 07/08/19 07/15/19
1S-12116 R&R Fire Hydrant & Remove Lateral 1 07/15/19 06/07/19
2 06/06/19
1S-12118 Survey & Layout Raised Islands
1S-12120 Sawcut & Demo Hardscapes for Raised Islands
1S-12122 Grade & Compact Subgrades for Raised Islands
1S-12124 Form Raised Islands & Certify Formwork
1S-12126 Pour & Strip Curb Islands
1S-12128 Backfill & Compact Curb Islands
1S-12130 Patch A/C Paving at Curb Islands
1S-12132 Grind & Overlay A/C Paving at Curb Islands
1S-12134 Temporary Striping
1S-12136 Remove & Relocate Construction Fencing
Project Start 09/10/18 Page 16 of 18 Edwards Lifescience
Project Finish 07/23/20 TASK filter: All Activities Proposal Schedule with C
Data Date 09/01/18
Run Date 10/05/18 Snyder L
2019 2020
c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
ELEVATORS
Elevator Pre-Check List & Corrections
Elevator Rails
Elevator Equipment
Elevator Temp Platform
Elevator Door Frames
Elevator Cab & Finishes
Elevator Test & Adjust
SITEWORK
Site Wet Utilities
Site Dry Utilities
Hardscape (Cafe/Conference)
Landscape (Cafe/Conference)
INSPECTIONS / PUNCHLIST
Permanent Power
Final Inspections
Commissioning/LEED Approval
Inclement Weather Allowance
Substantial Completion
Prepare Punchlist
Punchlist Corrections
Final Completion
CONSTRUCTION - PHASE 1 - OFFSITE
REDHILL DECELERATION LANE, LEFT TURN LANE, MEDIAN, U/G UTILITIES
Submit/Approve Traffic Control Plans
Post Advanced Construction Notification & Street Signage
Contact Underground Dig Alert & Record Permit Number
Verify, Document & Submit Existing Conditions Prior to Start
Survey Demo Limits Prior to Start & Confirm with Contract Documents
Preconstruction Conference with City of Irvine as Required
Setup Temporary Traffic Control Measures
Setup Temporary BMP's
Construct (N) 16 in ACP Water Main
Construct (N) Fire, Domestic & Irrigation D.I. Laterals
R&R Fire Hydrant & Remove Lateral
Survey & Layout Raised Islands
Sawcut & Demo Hardscapes for Raised Islands
Grade & Compact Subgrades for Raised Islands
Form Raised Islands & Certify Formwork
Pour & Strip Curb Islands
Backfill & Compact Curb Islands
Patch A/C Paving at Curb Islands
Grind & Overlay A/C Paving at Curb Islands
Temporary Striping
Remove & Relocate Construction Fencing
es Campus Expansion Remaining Level of Effort
ConXtech Steel - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work
Activity ID Activity Name Dur Current Start Current
Finish
Aug Sep Oct Nov Dec
1S-12138 Safe-off & Re-Route Irrigation 2 06/10/19 06/11/19
2 06/12/19 06/13/19
1S-12140 Remove & Salvage Signage as Applicable 5 06/14/19 06/20/19
5 06/21/19 06/27/19
1S-12150 Remove & Relocate Existing Low Volt Pull Box & Assoc. Cabling 3 06/28/19 07/02/19
1 07/03/19 07/03/19
1S-12160 Remove & Protect Existing Bus Bench, Trash Can & Associated Signage 5 07/05/19 07/11/19
2 07/12/19 07/15/19
1S-12200 Demo (E) Hardscapes & Landscapes 10 07/16/19 07/29/19
5 07/30/19 08/05/19
1S-12210 Survey (N) Curb & Gutter 5 07/30/19 08/05/19
1 08/06/19 08/06/19
1S-12220 Prepare Subgrade for (N) Deceleration Lane, Curb & Gutter 5 08/07/19 08/13/19
3 08/14/19 08/16/19
1S-12230 Test Subgrade for Compaction 1 08/19/19 08/19/19
1 08/20/19 08/20/19
1S-12240 Install (N) Below Grade Signal Conduit & Associated Pull Boxes 5 08/21/19 08/27/19
1 08/28/19 08/28/19
1S-12242 Relocate Pedestrian Light Pole 3 08/29/19 09/03/19
2 09/04/19 09/05/19
1S-12250 Form (N) Curb & Gutter & EntranceApron 3 09/06/19 09/10/19
1 09/11/19 09/11/19
1S-12260 Survey & Record (N) Curb & Gutter Formwork - Prepour 2 09/12/19 09/13/19
10 01/02/20* 01/15/20
1S-12270 Pour (N) Curb & Gutter, Entrance Apron, Strip & Cure 5 01/16/20 01/22/20
10 01/23/20 02/05/20
1S-12280 Backfill & Compact Behind Curb & Gutter, Entrance Apron 1 02/06/20 02/06/20
110 08/01/19 01/09/20
1S-12290 Survey Subgrade for Sidewalks at EntranceApron
1S-12300 Install (N) Posts & Signage as Applicable
1S-12310 Form Sidewalks
1S-12320 Survey & Record (N) Sidewalk Formwork
1S-12330 Pour Sidewalks, Strip & Cure
1S-12340 Install Relocated Bus Stop Bench, Trash Can & Associated Signage
1S-12350 Prepare Roadway Subgrade with .65' Aggregate Base & Compact
1S-12360 Test Compaction of A.B.
1S-12370 A/C Paving
1S-12372 Grind & Overlay A/C Paving
1S-12374 Slurry Seal A/C Paving
1S-12376 Striping 1st Pass, Cure & Final Stripe
1S-12380 Final Clean
ALTON PKWY STREET WIDENING & U/G UTILITIES
1S-20000 Post Advanced Construction Notification & Street Signage 10 08/01/19* 08/14/19
1 08/15/19 08/15/19
1S-20010 Contact Underground Dig Alert & Record Permit Number 5 08/16/19 08/22/19
5 08/23/19 08/29/19
1S-20020 Verify, Document & Submit Existing Conditions Prior to Start 5 08/30/19 09/06/19
3 09/09/19 09/11/19
1S-20030 Survey Demo Limits Prior to Start & Confirm with Contract Documents 5 09/12/19 09/18/19
10/09/19
1S-20040 Preconstruction Conference with City of Irvine as Required 15 09/19/19 10/02/19
10 09/19/19 09/20/19
1S-20050 Setup Temporary Traffic Control Measures 09/24/19
2 09/19/19 09/26/19
1S-20060 Setup Temporary BMP's 2 09/23/19 10/03/19
2 09/25/19 10/10/19
1S-20070 Sanitary Sewer Improvements 5 09/27/19 10/17/19
5 10/04/19 10/18/19
1S-20080 Relocate Fire Hydrants 5 10/11/19 10/22/19
1 10/18/19
1S-20090 Remove & Relocate Construction Fencing 2 10/21/19
1S-20100 Safe-off & Re-Route Irrigation
1S-20110 Remove & Salvage Signage as Applicable
1S-20120 Remove & Relocate Existing Low Volt Pull Box & Assoc. Cabling
1S-20130 Remove & Protect Existing Bus Bench, Trash Can & Associated Signage
1S-20140 Demo (E) Hardscapes & Landscapes
1S-20150 Survey (N) Curb & Gutter
1S-20160 Prepare Subgrade for (N) Street Widening, Curb & Gutter
Project Start 09/10/18 Page 17 of 18 Edwards Lifescience
Project Finish 07/23/20 TASK filter: All Activities Proposal Schedule with C
Data Date 09/01/18
Run Date 10/05/18 Snyder L
2019 2020
c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Safe-off & Re-Route Irrigation
Remove & Salvage Signage as Applicable
Remove & Relocate Existing Low Volt Pull Box & Assoc. Cabling
Remove & Protect Existing Bus Bench, Trash Can & Associated Signage
Demo (E) Hardscapes & Landscapes
Survey (N) Curb & Gutter
Prepare Subgrade for (N) Deceleration Lane, Curb & Gutter
Test Subgrade for Compaction
Install (N) Below Grade Signal Conduit & Associated Pull Boxes
Relocate Pedestrian Light Pole
Form (N) Curb & Gutter & EntranceApron
Survey & Record (N) Curb & Gutter Formwork - Prepour
Pour (N) Curb & Gutter, Entrance Apron, Strip & Cure
Backfill & Compact Behind Curb & Gutter, Entrance Apron
Survey Subgrade for Sidewalks at EntranceApron
Install (N) Posts & Signage as Applicable
Form Sidewalks
Survey & Record (N) Sidewalk Formwork
Pour Sidewalks, Strip & Cure
Install Relocated Bus Stop Bench, Trash Can & Associated Signage
Prepare Roadway Subgrade with .65' Aggregate Base & Compact
Test Compaction of A.B.
A/C Paving
Grind & Overlay A/C Paving
Slurry Seal A/C Paving
Striping 1st Pass, Cure & Final Stripe
Final Clean
ALTON PKWY STREET WIDENING & U/G UTILITIES
Post Advanced Construction Notification & Street Signage
Contact Underground Dig Alert & Record Permit Number
Verify, Document & Submit Existing Conditions Prior to Start
Survey Demo Limits Prior to Start & Confirm with Contract Documents
Preconstruction Conference with City of Irvine as Required
Setup Temporary Traffic Control Measures
Setup Temporary BMP's
Sanitary Sewer Improvements
Relocate Fire Hydrants
Remove & Relocate Construction Fencing
Safe-off & Re-Route Irrigation
Remove & Salvage Signage as Applicable
Remove & Relocate Existing Low Volt Pull Box & Assoc. Cabling
Remove & Protect Existing Bus Bench, Trash Can & Associated Signage
Demo (E) Hardscapes & Landscapes
Survey (N) Curb & Gutter
Prepare Subgrade for (N) Street Widening, Curb & Gutter
es Campus Expansion Remaining Level of Effort
ConXtech Steel - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work
Activity ID Activity Name Dur Current Start Current Aug Sep Oct Nov Dec
Finish
1S-20170 Test Subgrade for Compaction
1S-20180 Install (N) Below Grade Signal Conduit & Associated Pull Boxes 1 10/23/19 10/23/19
1S-20190 Form (N) Curb & Gutter & EntranceApron 10 10/24/19 11/06/19
1S-20200 Survey & Record (N) Curb & Gutter Formwork - Prepour 11/08/19
1S-20210 Pour (N) Curb & Gutter, Entrance Apron, Strip & Cure 2 11/07/19 11/12/19
1S-20220 Backfill & Compact Behind Curb & Gutter, Entrance Apron 1 11/12/19 11/14/19
1S-20230 Survey Subgrade for Sidewalks 2 11/13/19 11/15/19
1S-20240 Install (N) Posts & Signage as Applicable 1 11/15/19 11/18/19
1S-20250 Form Sidewalks 1 11/18/19 11/19/19
1S-20260 Pour Sidewalks, Strip & Cure 1 11/19/19 11/20/19
1S-20270 Install Relocated Signage 1 11/20/19 11/21/19
1S-20280 Prepare Roadway Subgrade with .65' Aggregate Base & Compact 1 11/21/19 11/25/19
1S-20290 Test Compaction of A.B. 2 11/22/19 11/27/19
1S-20300 A/C Paving 2 11/26/19 12/02/19
1S-20310 Grind & Overlay A/C Paving 1 12/02/19 12/04/19
1S-20320 Slurry Seal A/C Paving 2 12/03/19 12/06/19
1S-20330 Striping 1st Pass, Cure & Final Stripe 2 12/05/19 12/10/19
1S-20340 Final Inspections 2 12/09/19 12/24/19
10 12/11/19 01/09/20
10 12/26/19
Project Start 09/10/18 Page 18 of 18 Edwards Lifescience
Project Finish 07/23/20 TASK filter: All Activities Proposal Schedule with C
Data Date 09/01/18
Run Date 10/05/18 Snyder L
2019 2020
c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Test Subgrade for Compaction
Install (N) Below Grade Signal Conduit & Associated Pull Boxes
Form (N) Curb & Gutter & EntranceApron
Survey & Record (N) Curb & Gutter Formwork - Prepour
Pour (N) Curb & Gutter, Entrance Apron, Strip & Cure
Backfill & Compact Behind Curb & Gutter, Entrance Apron
Survey Subgrade for Sidewalks
Install (N) Posts & Signage as Applicable
Form Sidewalks
Pour Sidewalks, Strip & Cure
Install Relocated Signage
Prepare Roadway Subgrade with .65' Aggregate Base & Compact
Test Compaction of A.B.
A/C Paving
Grind & Overlay A/C Paving
Slurry Seal A/C Paving
Striping 1st Pass, Cure & Final Stripe
Final Inspections
es Campus Expansion Remaining Level of Effort
ConXtech Steel - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work
concrete schedule
Activity ID Activity Name Dur Current Start Current Finish
Aug Sep Oct Nov Dec
Edwards ELS Expansion (10/05/18 proposal w/Concrete B)
471 09/10/18 07/23/20
SUMMARY & MILESTONES
431 11/05/18 07/23/20
OVERALL 431 11/05/18 07/22/20
S1000 Start Construction 0 11/05/18* 07/22/20 Start Con
431 11/05/18 07/22/20 Phase 0 S
S1010 Overall Construction (SUMMARY) 07/22/20
0 07/22/20
S1090 Substantial Completion 60 04/28/20 07/23/20
01/28/19
S1100 Punchlist & Closeout (SUMMARY) 0
431 11/05/18 01/28/19
S1110 Final Completion 01/28/19
54 11/05/18 07/08/20
DETAIL 0 11/05/18 04/05/19
PHASE 0 54 11/05/18 07/07/20
0 10/30/19
S2000 Phase 0 Start Construction
384 01/03/19 07/07/20
S2010 Phase 0 Construction Duration (SUMMARY) 67 01/03/19
0 02/01/19* 07/07/20
S2050 Phase 0 Complete Construction 07/07/20*
363 02/01/19 05/29/20
PHASE 1 (BUILDING B) 0
0 10/31/19 05/28/20
S2190 Utility Relocations (SUMMARY) 0 09/26/19
0 07/08/20
S2200 Phase 1 Start Construction (Building B) 05/28/20
22 06/05/20
S2210 Phase 1 Construction Duration (Building B) (SUMMARY) 0 05/28/20
05/28/20
S2215 Phase 1 Concrete Roof Deck Complete (Building B) 290 04/08/19 07/23/20
0 04/08/19
S2220 Ready for Tenant Improvements (Building B) (by SL) 07/22/20
290 04/08/19 10/10/19
S2250 Phase 1 Substantial Completion (Building B) 0
0 12/03/19 07/22/20
S2255 Ready for Tenant Improvements (Building B) (by Others) 0
0 05/29/20 07/22/20
S2260 Phase 1 Punchlist & Corrections (Building B) (SUMMARY) 07/22/20
22 04/28/20 02/06/20
S2270 Phase 1 Final Completion (Building B) 0
02/06/20
PHASE 1 (BUILDING A) 273 06/25/19 02/06/20
0 06/25/19*
S2100 Phase 1 Start Construction (Building A)
273 06/25/19
S2110 Phase 1 Construction Duration (Building A) (SUMMARY) 0
0 12/13/19
S2115 Phase 1 Steel Erection Complete (Building A) 0
0 07/23/20
S2120 Ready for Tenant Improvements (Building A) (by SL)
22 06/22/20
S2150 Phase 1 Substantial Completion (Building A) 0
S2155 Ready for Tenant Improvements (Building A) (by Others) 218 03/28/19
0 03/28/19
S2160 Phase 1 Punchlist & Corrections (Building A) (SUMMARY)
218 03/28/19
S2170 Phase 1 Final Completion (Building A) 0
PHASE 1 (BUILDING C)
S2300 Phase 1 Start Construction (Building C)
S2310 Phase 1 Construction Duration (Building C) (SUMMARY)
S2315 Phase 1 Steel Erection Complete (Building C)
S2320 Ready for Tenant Improvements (Building C) (by SL)
S2350 Phase 1 Substantial Completion (Building C)
S2355 Ready for Tenant Improvements (Building C) (by Others)
S2360 Phase 1 Punchilst & Corrections (Building C) (SUMMARY)
S2370 Phase 1 Final Completion (Building C)
PHASE 1 (OFFSITE - ALTON PKWY & REDHILL AVE)
S2400 Phase 1 Start Construction (Offsite)
S2410 Phase 1 Construction Duration (Offsite) (SUMMARY)
S2420 Phase 1 Complete Construction (Offsite)
Project Start 09/10/18 Page 1 of 18 Edwards Lifescience
Project Finish 07/23/20 TASK filter: All Activities Proposal Schedule with Buil
Data Date 09/01/18
Run Date 10/05/18 Snyder L
2019 2020
c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Edwards ELS Expansion (10/05/18 proposal w/Conc
SUMMARY & MILESTONES
OVERALL
nstruction
Overall Construction (SUMMARY)
Substantial Completion
Punchlist & Closeout (SUMMARY)
Final Completion
DETAIL
PHASE 0
Start Construction
Phase 0 Construction Duration (SUMMARY)
Phase 0 Complete Construction
PHASE 1 (BUILDING B)
Utility Relocations (SUMMARY)
Phase 1 Start Construction (Building B)
Phase 1 Construction Duration (Building B) (SUMMARY
Phase 1 Concrete Roof Deck Complete (Building B)
Ready for Tenant Improvements (Building B) (by SL)
Phase 1 Substantial Completion (Building B)
Ready for Tenant Improvements (Building B) (by Others)
Phase 1 Punchlist & Corrections (Building B) (SUMMAR
Phase 1 Final Completion (Building B)
PHASE 1 (BUILDING A)
Phase 1 Start Construction (Building A)
Phase 1 Construction Duration (Building A) (SUMMARY)
Phase 1 Steel Erection Complete (Building A)
Ready for Tenant Improvements (Building A) (by SL)
Phase 1 Substantial Completion (Building A)
Ready for Tenant Improvements (Building A) (by Others)
Phase 1 Punchlist & Corrections (Building A) (SUMMARY)
Phase 1 Final Completion (Building A)
PHASE 1 (BUILDING C)
Phase 1 Start Construction (Building C)
Phase 1 Construction Duration (Building C) (SUMMA
Phase 1 Steel Erection Complete (Building C)
Ready for Tenant Improvements (Building C) (by SL)
Phase 1 Substantial Completion (Building C)
Ready for Tenant Improvements (Building C) (by Oth
Phase 1 Punchilst & Corrections (Building C) (SUMM
Phase 1 Final Completion (Building C)
PHASE 1 (OFFSITE - ALTON PKWY & REDHILL AVE)
Phase 1 Start Construction (Offsite)
Phase 1 Construction Duration (Offsite) (SUMMARY)
Phase 1 Complete Construction (Offsite)
es Campus Expansion Remaining Level of Effort
lding B Concrete - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work
Activity ID Activity Name Dur Current Start Current Finish
Aug Sep Oct Nov Dec
CONTRACT AWARD 30 09/10/18 10/19/18 CONTRACT
D1000 Prepare Proposal 20 09/10/18* 10/05/18 Prepare Proposal
0 10/05/18 Submit Proposal
D1010 Submit Proposal 5 10/08/18 10/12/18
0 10/12/18 Owner Review
D1020 Owner Review Proposal / Interview 5 10/15/18 10/19/18 Owner Award C
09/12/19
D1030 Owner Award Contract 218 10/29/18 Execute Cont
D1040 Execute Contract
CRITICAL PERMIT MILESTONES
. 113 10/29/18 04/15/19
D2000 Phase 0 Building Permit 0 10/29/18* Phase 0 Bu
0 12/17/18*
D2005 Precise Grading Permit for Building A, B & C 0 01/15/19*
0 02/15/19*
D2010 1st Plan Check Comments from City for Building A & B 0 02/15/19*
0 03/15/19*
D2020 1st Plan Check Comments from City for Building C 0 04/15/19*
0 01/02/19 01/02/19
D2030 Foundation Only Permit (if not bldg) for Building A, B & C
0 01/02/19*
D2040 Full Building Permit for Building A & B 0 01/02/19*
0 01/02/19*
D2050 Full Building Permit for Building C 0 01/02/19*
0 01/02/19*
ONSITE/OFFSITE PERMITS 0 01/02/19*
0 01/02/19*
D2100 Site Electrical Permit 200 11/28/18 09/12/19
D2110 SCE Permit 30 11/28/18 01/14/19
30 08/01/19 09/12/19
D2120 OCFA Permit 298 10/22/18 12/31/19
D2130 Yard Permit
D2140 Civil Permit
D2150 MCE Offsite Encroachment Permit
D2160 IRWD Permit
FAA PERMITS
D2200 Obtain FAA Crane Permit (Generator Relocation)
D2210 Obtain FAA Crane Permit (Steel Erection)
CRITICAL SUBMITTALS & PROCUREMENT
DIVISION 02 - SITE 45 10/22/18 12/28/18
P023000.10 Bid & Award Piles 15 10/22/18 11/09/18 Bid & Aw
10 11/13/18 11/28/18 Prep
P023000.20 Prepare Shop Drawings for Piles 20 11/29/18 12/28/18
10 11/29/18 12/12/18 T
P023000.21 City Review Shop Drawings for Piles 12/19/18
5 12/13/18 12/28/18
P023000.30 Test Piles 5 12/20/18 09/27/19
180 01/16/19
P023000.31 Document Test Piles 02/12/19
20 01/16/19 05/07/19
P023000.32 City Review Test Piles 60 02/13/19 06/05/19
20 05/08/19 09/27/19
DIVISION 03 - CONCRETE 80 06/06/19 08/07/19
167 12/10/18
P034000.10 Bid & Award Precast 01/15/19
23 12/10/18* 01/25/19
P034000.20 Prepare Shop Drawings Precast 8 01/16/19 01/28/19
1 01/28/19 07/24/19
P034000.21 Review/Approve Shop Drawings Precast
125 01/29/19
P034000.29 Fabricate Precast Panels
DIVISION 05 - METALS
P051000.05 Bid Structural Steel
P051000.06 Steel Bidders Review 1st Plan Check & Update Bids (Bldg A & B)
P051000.10 Award Structural Steel
P051000.30 Submittal/Review/Fabricate Steel (Bldg A)
Project Start 09/10/18 Page 2 of 18 Edwards Lifescience
Project Finish 07/23/20 TASK filter: All Activities Proposal Schedule with Buil
Data Date 09/01/18
Run Date 10/05/18 Snyder L
2019 2020
c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
T AWARD
al
l
Proposal / Interview
Contract
tract
CRITICAL PERMIT MILESTONES
.
uilding Permit
Precise Grading Permit for Building A, B & C
1st Plan Check Comments from City for Building A & B
1st Plan Check Comments from City for Building C
Foundation Only Permit (if not bldg) for Building A, B & C
Full Building Permit for Building A & B
Full Building Permit for Building C
ONSITE/OFFSITE PERMITS
Site Electrical Permit
SCE Permit
OCFA Permit
Yard Permit
Civil Permit
MCE Offsite Encroachment Permit
IRWD Permit
FAA PERMITS
Obtain FAA Crane Permit (Generator Relocation)
Obtain FAA Crane Permit (Steel Erection)
CRITICAL SUBMITTALS & PROCUREMENT
DIVISION 02 - SITE
ward Piles
pare Shop Drawings for Piles
City Review Shop Drawings for Piles
Test Piles
Document Test Piles
City Review Test Piles
DIVISION 03 - CONCRETE
Bid & Award Precast
Prepare Shop Drawings Precast
Review/Approve Shop Drawings Precast
Fabricate Precast Panels
DIVISION 05 - METALS
Bid Structural Steel
Steel Bidders Review 1st Plan Check & Update Bids (Bldg A & B)
Award Structural Steel
Submittal/Review/Fabricate Steel (Bldg A)
es Campus Expansion Remaining Level of Effort
lding B Concrete - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work
Activity ID Activity Name Dur Current Start Current Finish
Aug Sep Oct Nov Dec
P051000.40 Submittal/Review/Fabricate Steel (Bldg C) 125 02/12/19 08/07/19
DIVISION 07 - THERMAL & MOISTURE PROTECTION 165 01/16/19 09/06/19
P074243.10 Bid & Award Aluminum Panels 20 01/16/19 02/12/19
P074243.20 Submittal/Review/Procure Material to Shop Aluminum Panels (Bldg B) 125 02/13/19 08/08/19
P074243.21 Submittal/Review/Procure Material to Shop Aluminum Panels (Bldg A) 125 02/27/19 08/22/19
P074243.29 Submittal/Review/Procure Material to Shop Aluminum Panels (Bldg C) 125 03/13/19 09/06/19
DIVISION 08 - OPENINGS 290 11/01/18 12/31/19
P084000.10 Bid & Award Glass/Glazing 20 11/01/18* 12/03/18 Bid
P084000.20 Submittal/Review/Fabricate Curtainwall/Glazing (Bldg B) 250 12/04/18 12/02/19
P084000.30 Submittal/Review/Fabricate Curtainwall/Glazing (Bldg A) 250 12/18/18 12/16/19
P084000.40 Submittal/Review/Fabricate Curtainwall/Glazing (Bldg C) 250 01/07/19 12/31/19
DIVISION 14 - ELEVATORS 220 01/16/19 11/25/19
P142000.10 Bid & Award Elevators 20 01/16/19 02/12/19
P142000.20 Prepare Shop Drawings Elevators 60 02/13/19 05/07/19
P142000.21 Review/Approve Shop Drawings Elevators 20 05/08/19 06/05/19
P142000.29 Fabricate Elevators 120 06/06/19 11/25/19
CONSTRUCTION - PHASE 0 - ELECTRICAL IMPROVEMENTS 54 11/05/18 01/28/19
ELECTRICAL / GENERATOR WORK 54 11/05/18 01/28/19
0-10000 Start Construction 0 11/05/18 11/09/18 Start Con
5 11/05/18 11/14/18 Mobilizat
0-10010 Mobilization 2 11/13/18 11/30/18 Notify U
10 11/15/18 11/30/18
0-10020 Notify Underground Dig Alert 10 11/15/18 11/30/18 Dec
0 12/07/18 Con
0-10030 Decorative Fence at Redhill Ave & Alton Pkwy 5 12/03/18 01/03/19 Acc
15 12/10/18 01/03/19
0-10035 Construct Access Road from Alton 15 12/10/18 01/10/19 Co
5 01/04/19 12/11/18
0-10036 Access Road from Alton Available 2 12/10/18 12/13/18 E
2 12/12/18 12/18/18 S
0-10040 Coordination Meeting 3 12/14/18 12/10/18
1 12/10/18 12/26/18 L
0-10050 Relocate (E) Motorized Gate at MLE 10 12/11/18 12/26/18
10 12/11/18 12/28/18
0-10060 (N) Motorized Gate at Access Road 2 12/27/18 01/02/19
1 01/02/19 12/27/18
0-10070 Phase 0 Construction Fencing 1 12/27/18 01/03/19
3 12/28/18 01/04/19
0-10100 Electrical Safe-off 1 01/04/19 01/07/19
1 01/07/19 01/07/19
0-10300 Sawcut/Demo Asphalt 1 01/07/19 01/14/19
5 01/08/19 01/16/19
0-10310 Demo Electrical Conduit/Infrastructure 2 01/15/19 01/16/19
2 01/15/19 01/21/19
0-11000 Layout New Service Yard 3 01/17/19
0-11010 Underground Electrical Ductbank to New Service Yard
0-11020 Pull Box & Underground Electrical Ductbank to Future Lab Bldg
0-11030 Slurry & Backfill Electrical Trench
0-11040 Repair A/C Paving & Remove Trench Plates
0-11100 Fine Grade 2500KV Generator Pad
0-11110 Form/Rebar 2500KV Generator Pad
0-11120 Inspect 2500KV Generator Pad
0-11130 Pour 2500KV Generator Pad
0-11135 Pour 1250KV Generator Pad
0-11140 Cure 2500KV Generator Pad
0-11200 Relocate & Set 2500KV Generator
0-11205 Relocate 1250KV Generator to Temp Pad
0-11210 Electrical Connections at 2500KV Generator
Project Start 09/10/18 Page 3 of 18 Edwards Lifescience
Project Finish 07/23/20 TASK filter: All Activities Proposal Schedule with Buil
Data Date 09/01/18
Run Date 10/05/18 Snyder L
2019 2020
c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Submittal/Review/Fabricate Steel (Bldg C)
DIVISION 07 - THERMAL & MOISTURE PROTECTION
Bid & Award Aluminum Panels
Submittal/Review/Procure Material to Shop Aluminum Panels (Bldg B)
Submittal/Review/Procure Material to Shop Aluminum Panels (Bldg A)
Submittal/Review/Procure Material to Shop Aluminum Panels (Bldg C)
DIVISION 08 - OPENINGS
d & Award Glass/Glazing
Submittal/Review/Fabricate Curtainwall/Glazing (Bldg B)
Submittal/Review/Fabricate Curtainwall/Glazing (Bldg A)
Submittal/Review/Fabricate Curtainwall/Glazing (Bldg C)
DIVISION 14 - ELEVATORS
Bid & Award Elevators
Prepare Shop Drawings Elevators
Review/Approve Shop Drawings Elevators
Fabricate Elevators
CONSTRUCTION - PHASE 0 - ELECTRICAL IMPROVEMENTS
ELECTRICAL / GENERATOR WORK
nstruction
ation
Underground Dig Alert
corative Fence at Redhill Ave & Alton Pkwy
nstruct Access Road from Alton
cess Road from Alton Available
oordination Meeting
Relocate (E) Motorized Gate at MLE
(N) Motorized Gate at Access Road
Phase 0 Construction Fencing
Electrical Safe-off
Sawcut/Demo Asphalt
Demo Electrical Conduit/Infrastructure
Layout New Service Yard
Underground Electrical Ductbank to New Service Yard
Pull Box & Underground Electrical Ductbank to Future Lab Bldg
Slurry & Backfill Electrical Trench
Repair A/C Paving & Remove Trench Plates
Fine Grade 2500KV Generator Pad
Form/Rebar 2500KV Generator Pad
Inspect 2500KV Generator Pad
Pour 2500KV Generator Pad
Pour 1250KV Generator Pad
Cure 2500KV Generator Pad
Relocate & Set 2500KV Generator
Relocate 1250KV Generator to Temp Pad
Electrical Connections at 2500KV Generator
es Campus Expansion Remaining Level of Effort
lding B Concrete - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work
Activity ID Activity Name Dur Current Start Current Finish
Aug Sep Oct Nov Dec
0-11220 Fuel, Start-up & Test 2500KV Generator
5 01/22/19 01/28/19
0-11510 2500KV Generator Online 0 01/28/19
67 01/03/19 04/05/19
CONSTRUCTION - PHASE 1 - UTILITY RELOCATIONS
UNDERGROUND UTILITY RELOCATIONS 67 01/03/19 04/05/19
1A-09100 Relocate MLE Electrical 40 01/03/19 02/27/19
5 02/28/19 03/06/19
1A-09110 Patch Existing Areas of Temporary Construction Access 0 03/06/19
04/05/19
1A-09120 Access Road from Redhill Available 22 03/07/19 04/05/19
22 03/07/19 07/07/20
1A-09130 Reroute Storm Drain 363 02/01/19
1A-09140 Reroute Fire Water & Other Utilities between HVC & Museum Deck
CONSTRUCTION - PHASE 1 - BLDG B (OFFICE/LAB/SITE)
EARTHWORK 26 02/01/19 03/08/19
1B-10000 Start Construction 0 02/01/19 02/01/19
1 02/01/19 03/01/19
1B-10010 Survey 20 02/04/19 03/08/19
5 03/04/19 12/02/19
1B-10020 Earthwork 185 03/11/19 05/24/19
06/10/19
1B-10030 Certify Pad 55 03/11/19 06/10/19
55 03/25/19 06/10/19
FOUNDATIONS / STRUCTURE 55 03/25/19 06/24/19
55 03/25/19 06/24/19
1B-15000 Drill/Rebar/Pour Piles (522) 55 04/08/19 07/01/19
55 04/08/19 07/09/19
1B-15100 Form/Rebar/Pour Pilecaps 40 05/06/19 07/23/19
40 05/13/19 08/06/19
1B-15200 Excavate/Form/Pour Elevator Pits 40 05/28/19 08/20/19
40 06/11/19 09/18/19
1B-15300 Form/Rebar/Pour Gradebeams 40 06/25/19 10/02/19
40 07/24/19 10/30/19
1B-15400 Prep/Pour Vertical (1st to 2nd Floor) 40 08/07/19 12/02/19
40 09/05/19 05/13/20
1B-18000 Underslab Plumbing Rough-in 20 10/31/19 12/02/19
145 10/17/19 12/02/19
1B-18100 Fine Grade for SOG 12/16/19
30 10/17/19 12/16/19
1B-18110 Sand/Vapor Barrier for SOG 30 10/17/19 12/23/19
30 10/31/19 03/25/20
1B-18120 Form/Rebar/Pour SOG 30 10/31/19 03/11/20
30 11/07/19 04/08/20
1B-18200 Prep/Pour Concrete Deck (2nd Floor) 80 12/03/19 04/22/20
30 01/30/20 02/12/20
1B-18210 Prep/Pour Vertical (2nd to 3rd Floor) 30 02/27/20 12/09/19
10 04/09/20 01/22/20
1B-18220 Prep/Pour Concrete Deck (3rd Floor) 40 12/17/19
15 11/15/19
1B-18230 Prep/Pour Vertical (3rd to Main Roof) 40 11/22/19
1B-18240 Prep/Pour Concrete Deck (Main Roof)
1B-19000 Precast Stairs
EXTERIOR SKIN
1B-30000 Exterior Framing
1B-30010 Exterior MEP Rough-in
1B-30020 Exterior Sheathing
1B-30100 Precast Panels
1B-30150 GFRC Panels
1B-30300 Curtainwall
1B-30350 Storefront Framing
1B-30360 Storefront Glazing
1B-30370 Storefront Doors
1B-30400 Steel & Glass Guardrails
1B-30500 Weatherproofing for Aluminum Panels
1B-30510 Field Measure & Fab Aluminum Panels
Project Start 09/10/18 Page 4 of 18 Edwards Lifescience
Project Finish 07/23/20 TASK filter: All Activities Proposal Schedule with Buil
Data Date 09/01/18
Run Date 10/05/18 Snyder L
2019 2020
c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Fuel, Start-up & Test 2500KV Generator
2500KV Generator Online
CONSTRUCTION - PHASE 1 - UTILITY RELOCATIONS
UNDERGROUND UTILITY RELOCATIONS
Relocate MLE Electrical
Patch Existing Areas of Temporary Construction Access
Access Road from Redhill Available
Reroute Storm Drain
Reroute Fire Water & Other Utilities between HVC & Museum Deck
CONSTRUCTION - PHASE 1 - BLDG B (OFFICE/LAB
EARTHWORK
Start Construction
Survey
Earthwork
Certify Pad
FOUNDATIONS / STRUCTURE
Drill/Rebar/Pour Piles (522)
Form/Rebar/Pour Pilecaps
Excavate/Form/Pour Elevator Pits
Form/Rebar/Pour Gradebeams
Prep/Pour Vertical (1st to 2nd Floor)
Underslab Plumbing Rough-in
Fine Grade for SOG
Sand/Vapor Barrier for SOG
Form/Rebar/Pour SOG
Prep/Pour Concrete Deck (2nd Floor)
Prep/Pour Vertical (2nd to 3rd Floor)
Prep/Pour Concrete Deck (3rd Floor)
Prep/Pour Vertical (3rd to Main Roof)
Prep/Pour Concrete Deck (Main Roof)
Precast Stairs
EXTERIOR SKIN
Exterior Framing
Exterior MEP Rough-in
Exterior Sheathing
Precast Panels
GFRC Panels
Curtainwall
Storefront Framing
Storefront Glazing
Storefront Doors
Steel & Glass Guardrails
Weatherproofing for Aluminum Panels
Field Measure & Fab Aluminum Panels
es Campus Expansion Remaining Level of Effort
lding B Concrete - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work
Activity ID Activity Name Dur Current Start Current Finish
Aug Sep Oct Nov Dec
1B-30520 Install Aluminum Panels
60 12/24/19 03/18/20
1B-30600 MEP Trim 10 04/23/20 05/06/20
1B-30900 Cleanup & Prepunch 5 05/07/20 05/13/20
165 09/19/19 05/13/20
ROOF
165 09/19/19 05/13/20
ROOF DECKS 10 09/19/19 10/02/19
10 10/03/19 10/16/19
1B-40000 MEP Penetrations & Roof Drains 10 03/19/20 04/01/20
10 03/26/20 04/08/20
1B-40030 Sheetmetal Flashing 20 04/09/20 05/06/20
5 05/07/20 05/13/20
1B-40100 Waterproofing 95 10/31/19 03/18/20
20 10/31/19 12/02/19
1B-40110 Topping Slabs 20 10/31/19 12/02/19
20 11/07/19 12/09/19
1B-40300 Roof Deck Pavers & Finishes 30 11/15/19 12/31/19
10 12/24/19 01/08/20
1B-40900 Cleanup & Prepunch Roof Decks 30 01/02/20 02/12/20
20 01/02/20 01/29/20
MAIN ROOFS 20 02/13/20 03/11/20
5 03/12/20 03/18/20
1B-41000 MEP Penetrations & Roof Drains
106 10/31/19 04/02/20
1B-41010 Mechanical Curbs
86 10/31/19 03/05/20
1B-41030 Sheetmetal Flashing 15 10/31/19 11/21/19
15 11/07/19 12/02/19
1B-41100 Roofing 15 11/07/19 12/02/19
15 11/07/19 12/02/19
1B-41200 Set Mechanical Equipment 15 11/07/19 12/02/19
15 11/15/19 12/09/19
1B-41210 Hookup Mechanical Equipment 15 11/15/19 12/09/19
15 11/15/19 12/09/19
1B-41300 Roof Screen Panels
5 12/05/19 12/11/19
1B-41400 Sheetmetal Trim & Finish 5 12/09/19 12/13/19
10 12/11/19 12/24/19
1B-41900 Cleanup & Prepunch Roof 10 11/22/19 12/09/19
10 12/03/19 12/16/19
INTERIOR 10 12/03/19 12/16/19
10 12/03/19 12/16/19
1ST FLOOR CORE 5 12/12/19 12/18/19
10 12/18/19 01/02/20
1B-50000 Overhead Mechanical Rough-in 10 01/03/20 01/16/20
10 01/10/20 01/23/20
1B-50010 Overhead Plumbing Rough-in 20 01/17/20 02/13/20
5 01/17/20 01/23/20
1B-50020 Overhead Fire Sprinkler Rough-in 10 01/17/20 01/30/20
1B-50030 Overhead Electrical Rough-in Edwards Lifescience
Proposal Schedule with Buil
1B-50100 Wall Framing & Furring
Snyder L
1B-50110 Wall Plumbing Rough-in
1B-50120 Wall Electrical Rough-in
1B-50130 Wall Low Voltage Rough-in
1B-50140 Wall MEP & Framing Inspections
1B-50150 Wall Insulation (dry-in)
1B-50160 Drywall Walls
1B-50200 Hard Ceiling Framing
1B-50210 Hard Ceiling Mechanical Rough-in
1B-50220 Hard Ceiling Fire Sprinkler Rough-in
1B-50230 Hard Ceiling Electrical Rough-in
1B-50240 Hard Ceiling MEP Inspections
1B-50250 Drywall Ceilings
1B-50260 Tape Drywall Walls & Ceilings
1B-50300 Prime & Paint
1B-50310 Electrical Panels & Pull Wire
1B-50320 Door Frames
1B-50460 Suspended & Surface Mounted Fixtures
Project Start 09/10/18 Page 5 of 18
Project Finish 07/23/20 TASK filter: All Activities
Data Date 09/01/18
Run Date 10/05/18
2019 2020
c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Install Aluminum Panels
MEP Trim
Cleanup & Prepunch
ROOF
ROOF DECKS
MEP Penetrations & Roof Drains
Sheetmetal Flashing
Waterproofing
Topping Slabs
Roof Deck Pavers & Finishes
Cleanup & Prepunch Roof Decks
MAIN ROOFS
MEP Penetrations & Roof Drains
Mechanical Curbs
Sheetmetal Flashing
Roofing
Set Mechanical Equipment
Hookup Mechanical Equipment
Roof Screen Panels
Sheetmetal Trim & Finish
Cleanup & Prepunch Roof
INTERIOR
1ST FLOOR CORE
Overhead Mechanical Rough-in
Overhead Plumbing Rough-in
Overhead Fire Sprinkler Rough-in
Overhead Electrical Rough-in
Wall Framing & Furring
Wall Plumbing Rough-in
Wall Electrical Rough-in
Wall Low Voltage Rough-in
Wall MEP & Framing Inspections
Wall Insulation (dry-in)
Drywall Walls
Hard Ceiling Framing
Hard Ceiling Mechanical Rough-in
Hard Ceiling Fire Sprinkler Rough-in
Hard Ceiling Electrical Rough-in
Hard Ceiling MEP Inspections
Drywall Ceilings
Tape Drywall Walls & Ceilings
Prime & Paint
Electrical Panels & Pull Wire
Door Frames
Suspended & Surface Mounted Fixtures
es Campus Expansion Remaining Level of Effort
lding B Concrete - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work
Activity ID Activity Name Dur Current Start Current Finish
Aug Sep Oct Nov Dec
1B-50600 Flooring
10 01/24/20 02/06/20
1B-50610 Base 2 02/07/20 02/10/20
5 02/07/20 02/13/20
1B-50620 Hang Doors 5 02/14/20 02/20/20
5 02/21/20 02/27/20
1B-50630 Finish Paint 5 02/21/20 02/27/20
5 02/21/20 02/27/20
1B-50640 Door Hardware 5 02/21/20 02/27/20
5 02/21/20 02/27/20
1B-50650 Mechanical Trim
20 01/17/20 02/13/20
1B-50660 Fire Sprinkler Trim 10 02/07/20 02/20/20
10 02/14/20 02/27/20
1B-50670 Electrical Trim
5 02/28/20 03/05/20
1B-50680 Low Voltage Trim 86 11/15/19 03/19/20
15 11/15/19 12/09/19
1B-50800 Tile (Restrooms) 15 11/22/19 12/16/19
15 11/22/19 12/16/19
1B-50820 Plumbing Fixtures (Restrooms) 15 11/22/19 12/16/19
15 11/22/19 12/16/19
1B-50840 Toilet Accessories (Restrooms) 15 12/03/19 12/23/19
15 12/03/19 12/23/19
1B-50900 Cleanup & Prepunch Interior 15 12/03/19 12/23/19
2ND FLOOR CORE 5 12/19/19 12/26/19
5 12/23/19 12/30/19
1B-55000 Overhead Mechanical Rough-in 10 12/26/19 01/09/20
10 12/10/19 12/23/19
1B-55010 Overhead Plumbing Rough-in 10 12/17/19 12/31/19
10 12/17/19 12/31/19
1B-55020 Overhead Fire Sprinkler Rough-in 10 12/17/19 12/31/19
5 12/27/19 01/03/20
1B-55030 Overhead Electrical Rough-in 10 01/03/20 01/16/20
10 01/17/20 01/30/20
1B-55100 Wall Framing & Furring 10 01/24/20 02/06/20
20 01/31/20 02/27/20
1B-55110 Wall Plumbing Rough-in 5 01/31/20 02/06/20
10 01/31/20 02/13/20
1B-55120 Wall Electrical Rough-in 10 02/07/20 02/20/20
2 02/21/20 02/24/20
1B-55130 Wall Low Voltage Rough-in 5 02/21/20 02/27/20
5 02/28/20 03/05/20
1B-55140 Wall MEP & Framing Inspections 5 03/06/20 03/12/20
5 03/06/20 03/12/20
1B-55150 Wall Insulation (dry-in) 5 03/06/20 03/12/20
5 03/06/20 03/12/20
1B-55160 Drywall Walls 5 03/06/20 03/12/20
20 01/31/20 02/27/20
1B-55200 Hard Ceiling Framing
Edwards Lifescience
1B-55210 Hard Ceiling Mechanical Rough-in Proposal Schedule with Buil
1B-55220 Hard Ceiling Fire Sprinkler Rough-in Snyder L
1B-55230 Hard Ceiling Electrical Rough-in
1B-55240 Hard Ceiling MEP Inspections
1B-55250 Drywall Ceilings
1B-55260 Tape Drywall Walls & Ceilings
1B-55300 Prime & Paint
1B-55310 Electrical Panels & Pull Wire
1B-55320 Door Frames
1B-55460 Suspended & Surface Mounted Fixtures
1B-55600 Flooring
1B-55610 Base
1B-55620 Hang Doors
1B-55630 Finish Paint
1B-55640 Door Hardware
1B-55650 Mechanical Trim
1B-55660 Fire Sprinkler Trim
1B-55670 Electrical Trim
1B-55680 Low Voltage Trim
1B-55800 Tile (Restrooms)
Project Start 09/10/18 Page 6 of 18
Project Finish 07/23/20 TASK filter: All Activities
Data Date 09/01/18
Run Date 10/05/18
2019 2020
c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Flooring
Base
Hang Doors
Finish Paint
Door Hardware
Mechanical Trim
Fire Sprinkler Trim
Electrical Trim
Low Voltage Trim
Tile (Restrooms)
Plumbing Fixtures (Restrooms)
Toilet Accessories (Restrooms)
Cleanup & Prepunch Interior
2ND FLOOR CORE
Overhead Mechanical Rough-in
Overhead Plumbing Rough-in
Overhead Fire Sprinkler Rough-in
Overhead Electrical Rough-in
Wall Framing & Furring
Wall Plumbing Rough-in
Wall Electrical Rough-in
Wall Low Voltage Rough-in
Wall MEP & Framing Inspections
Wall Insulation (dry-in)
Drywall Walls
Hard Ceiling Framing
Hard Ceiling Mechanical Rough-in
Hard Ceiling Fire Sprinkler Rough-in
Hard Ceiling Electrical Rough-in
Hard Ceiling MEP Inspections
Drywall Ceilings
Tape Drywall Walls & Ceilings
Prime & Paint
Electrical Panels & Pull Wire
Door Frames
Suspended & Surface Mounted Fixtures
Flooring
Base
Hang Doors
Finish Paint
Door Hardware
Mechanical Trim
Fire Sprinkler Trim
Electrical Trim
Low Voltage Trim
Tile (Restrooms)
es Campus Expansion Remaining Level of Effort
lding B Concrete - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work
Activity ID Activity Name Dur Current Start Current Finish
Aug Sep Oct Nov Dec
1B-55820 Plumbing Fixtures (Restrooms)
10 02/21/20 03/05/20
1B-55840 Toilet Accessories (Restrooms) 10 02/28/20 03/12/20
1B-55900 Cleanup & Prepunch Interior 5 03/13/20 03/19/20
86 12/03/19 04/02/20
3RD FLOOR CORE 15 12/03/19 12/23/19
15 12/10/19 12/31/19
1B-60000 Overhead Mechanical Rough-in 15 12/10/19 12/31/19
15 12/10/19 12/31/19
1B-60010 Overhead Plumbing Rough-in 15 12/10/19 12/31/19
15 12/17/19 01/08/20
1B-60020 Overhead Fire Sprinkler Rough-in 15 12/17/19 01/08/20
15 12/17/19 01/08/20
1B-60030 Overhead Electrical Rough-in
5 01/06/20 01/10/20
1B-60100 Wall Framing & Furring 5 01/08/20 01/14/20
10 01/10/20 01/23/20
1B-60110 Wall Plumbing Rough-in 10 12/24/19 01/08/20
10 01/02/20 01/15/20
1B-60120 Wall Electrical Rough-in 10 01/02/20 01/15/20
10 01/02/20 01/15/20
1B-60130 Wall Low Voltage Rough-in 5 01/13/20 01/17/20
10 01/17/20 01/30/20
1B-60140 Wall MEP & Framing Inspections 10 01/31/20 02/13/20
10 02/07/20 02/20/20
1B-60150 Wall Insulation (dry-in) 20 02/14/20 03/12/20
5 02/14/20 02/20/20
1B-60160 Drywall Walls 10 02/14/20 02/27/20
10 02/21/20 03/05/20
1B-60200 Hard Ceiling Framing 2 03/06/20 03/09/20
5 03/06/20 03/12/20
1B-60210 Hard Ceiling Mechanical Rough-in 5 03/13/20 03/19/20
5 03/20/20 03/26/20
1B-60220 Hard Ceiling Fire Sprinkler Rough-in 5 03/20/20 03/26/20
5 03/20/20 03/26/20
1B-60230 Hard Ceiling Electrical Rough-in 5 03/20/20 03/26/20
5 03/20/20 03/26/20
1B-60240 Hard Ceiling MEP Inspections 20 02/14/20 03/12/20
10 03/06/20 03/19/20
1B-60250 Drywall Ceilings 10 03/13/20 03/26/20
5 03/27/20 04/02/20
1B-60260 Tape Drywall Walls & Ceilings 50 01/24/20 04/02/20
1B-60300 Prime & Paint 30 01/24/20 03/05/20
20 02/14/20 03/12/20
1B-60310 Electrical Panels & Pull Wire 20 02/21/20 03/19/20
20 02/28/20 03/26/20
1B-60320 Door Frames 20 03/06/20 04/02/20
1B-60460 Suspended & Surface Mounted Fixtures Edwards Lifescience
Proposal Schedule with Buil
1B-60600 Flooring
Snyder L
1B-60610 Base
1B-60620 Hang Doors
1B-60630 Finish Paint
1B-60640 Door Hardware
1B-60650 Mechanical Trim
1B-60660 Fire Sprinkler Trim
1B-60670 Electrical Trim
1B-60680 Low Voltage Trim
1B-60800 Tile (Restrooms)
1B-60820 Plumbing Fixtures (Restrooms)
1B-60840 Toilet Accessories (Restrooms)
1B-60900 Cleanup & Prepunch Interior
INTERIOR STAIRS
1B-70000 Drywall & Tape Stairs
1B-70010 Handrails
1B-70020 Prime & Paint
1B-70030 Flooring
1B-70040 MEP Trim
Project Start 09/10/18 Page 7 of 18
Project Finish 07/23/20 TASK filter: All Activities
Data Date 09/01/18
Run Date 10/05/18
2019 2020
c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Plumbing Fixtures (Restrooms)
Toilet Accessories (Restrooms)
Cleanup & Prepunch Interior
3RD FLOOR CORE
Overhead Mechanical Rough-in
Overhead Plumbing Rough-in
Overhead Fire Sprinkler Rough-in
Overhead Electrical Rough-in
Wall Framing & Furring
Wall Plumbing Rough-in
Wall Electrical Rough-in
Wall Low Voltage Rough-in
Wall MEP & Framing Inspections
Wall Insulation (dry-in)
Drywall Walls
Hard Ceiling Framing
Hard Ceiling Mechanical Rough-in
Hard Ceiling Fire Sprinkler Rough-in
Hard Ceiling Electrical Rough-in
Hard Ceiling MEP Inspections
Drywall Ceilings
Tape Drywall Walls & Ceilings
Prime & Paint
Electrical Panels & Pull Wire
Door Frames
Suspended & Surface Mounted Fixtures
Flooring
Base
Hang Doors
Finish Paint
Door Hardware
Mechanical Trim
Fire Sprinkler Trim
Electrical Trim
Low Voltage Trim
Tile (Restrooms)
Plumbing Fixtures (Restrooms)
Toilet Accessories (Restrooms)
Cleanup & Prepunch Interior
INTERIOR STAIRS
Drywall & Tape Stairs
Handrails
Prime & Paint
Flooring
MEP Trim
es Campus Expansion Remaining Level of Effort
lding B Concrete - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work
Activity ID Activity Name Dur Current Start Current Finish
Aug Sep Oct Nov Dec
ELEVATORS
56 02/14/20 05/01/20
1B-71000 Elevator Pre-Check List & Corrections
10 02/14/20 02/27/20
1B-71010 Elevator Rails (#1) 5 02/28/20 03/05/20
5 03/06/20 03/12/20
1B-71020 Elevator Equipment (#1) 3 03/13/20 03/17/20
3 03/18/20 03/20/20
1B-71030 Elevator Temp Platform (#1) 5 03/23/20 03/27/20
5 04/10/20 04/16/20
1B-71040 Elevator Door Frames (#1) 5 03/13/20 03/19/20
5 03/20/20 03/26/20
1B-71050 Elevator Cab & Finishes (#1) 3 03/27/20 03/31/20
3 04/01/20 04/03/20
1B-71060 Elevator Test & Adjust (#1) 5 04/06/20 04/10/20
5 04/17/20 04/23/20
1B-72010 Elevator Rails (#2) 5 03/27/20 04/02/20
5 04/03/20 04/09/20
1B-72020 Elevator Equipment (#2) 3 04/10/20 04/14/20
3 04/15/20 04/17/20
1B-72030 Elevator Temp Platform (#2) 5 04/20/20 04/24/20
5 04/27/20 05/01/20
1B-72040 Elevator Door Frames (#2)
322 03/04/19 06/08/20
1B-72050 Elevator Cab & Finishes (#2)
20 03/04/19 03/29/19
1B-72060 Elevator Test & Adjust (#2) 20 04/01/19 04/26/19
20 10/31/19 12/02/19
1B-73010 Elevator Rails (#3) 20 12/03/19 12/31/19
120 11/15/19 05/06/20
1B-73020 Elevator Equipment (#3) 40 04/13/20 06/08/20
81 03/13/20 07/07/20
1B-73030 Elevator Temp Platform (#3)
20 03/13/20 04/09/20
1B-73040 Elevator Door Frames (#3) 20 05/26/20 06/22/20
40 04/27/20 06/22/20
1B-73050 Elevator Cab & Finishes (#3) 10 06/23/20 07/07/20
1B-73060 Elevator Test & Adjust (#3) 0 07/07/20
2 06/05/20 06/08/20
SITEWORK 20 06/09/20 07/07/20
0 07/07/20
1B-80000 Site Wet Utilities 295 04/01/19 05/28/20
1B-80100 Site Dry Utilities
1B-80200 Hardscape (Parking Aisle)
1B-80210 Landscape/Irrigation (Parking Aisle)
1B-80400 Hardscape (Main Courtyard)
1B-80410 Landscape (Main Courtyard)
INSPECTIONS / PUNCHLIST
1B-89000 Permanent Power
1B-90000 Final Inspections
1B-90005 Commissioning/LEED Approval
1B-90010 Inclement Weather Allowance
1B-90020 Substantial Completion
1B-90100 Prepare Punchlist
1B-90110 Punchlist Corrections
1B-90120 Final Completion
CONSTRUCTION - PHASE 1 - BLDG A (PAVILION/MUSEUM)
EARTHWORK 16 04/08/19 04/29/19
1A-10000 Start Construction 0 04/08/19 04/08/19
1 04/08/19 04/15/19
1A-10010 Survey 5 04/09/19 04/09/19
1 04/09/19 04/22/19
1A-10020 Demo 5 04/16/19 04/29/19
5 04/23/19 12/09/19
1A-10050 Pre-Grade Meeting with City 154 04/30/19
1A-10100 Earthwork
1A-10110 Certify Pad
FOUNDATIONS / STRUCTURE
Project Start 09/10/18 Page 8 of 18 Edwards Lifescience
Project Finish 07/23/20 TASK filter: All Activities Proposal Schedule with Buil
Data Date 09/01/18
Run Date 10/05/18 Snyder L
2019 2020
c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
ELEVATORS
Elevator Pre-Check List & Corrections
Elevator Rails (#1)
Elevator Equipment (#1)
Elevator Temp Platform (#1)
Elevator Door Frames (#1)
Elevator Cab & Finishes (#1)
Elevator Test & Adjust (#1)
Elevator Rails (#2)
Elevator Equipment (#2)
Elevator Temp Platform (#2)
Elevator Door Frames (#2)
Elevator Cab & Finishes (#2)
Elevator Test & Adjust (#2)
Elevator Rails (#3)
Elevator Equipment (#3)
Elevator Temp Platform (#3)
Elevator Door Frames (#3)
Elevator Cab & Finishes (#3)
Elevator Test & Adjust (#3)
SITEWORK
Site Wet Utilities
Site Dry Utilities
Hardscape (Parking Aisle)
Landscape/Irrigation (Parking Aisle)
Hardscape (Main Courtyard)
Landscape (Main Courtyard)
INSPECTIONS / PUNCHLIST
Permanent Power
Final Inspections
Commissioning/LEED Approval
Inclement Weather Allowance
Substantial Completion
Prepare Punchlist
Punchlist Corrections
Final Completion
CONSTRUCTION - PHASE 1 - BLDG A (PAVILION/MUSEUM)
EARTHWORK
Start Construction
Survey
Demo
Pre-Grade Meeting with City
Earthwork
Certify Pad
FOUNDATIONS / STRUCTURE
es Campus Expansion Remaining Level of Effort
lding B Concrete - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work
Activity ID Activity Name Dur Current Start Current Finish
Aug Sep Oct Nov Dec
1A-15000 Drill/Rebar/Pour Piles (144)
15 04/30/19 05/20/19
1A-15100 Form/Rebar/Pour Pilecaps 10 05/21/19 06/04/19
10 05/21/19 06/04/19
1A-15200 Excavate/Form/Pour Elevator Pit 10 06/05/19 06/18/19
20 06/19/19 07/17/19
1A-15300 Form/Rebar/Pour Gradebeams 20 07/18/19 08/14/19
20 08/15/19 09/12/19
1A-16000 Form/Rebar/Pour/Strip CIP Walls (Pour 1) 10 09/13/19 09/26/19
15 09/27/19 10/17/19
1A-16100 Form/Rebar/Pour/Strip CIP Walls (Pour 2)
5 10/18/19 10/24/19
1A-16110 Form/Rebar/Pour/Strip CIP Walls (Pour 3) 5 10/25/19 10/31/19
5 11/01/19 11/07/19
1A-17000 Erect Structural Steel 5 11/01/19 11/07/19
2 11/08/19 11/12/19
1A-17010 Weld Structural Steel 2 11/13/19 11/14/19
5 11/15/19 11/21/19
1A-17100 Metal Deck/Edge Metal/Shear Studs (2nd Floor) 5 11/01/19 11/07/19
5 11/08/19 11/15/19
1A-17110 Metal Deck/Edge Metal/Shear Studs (Low Roof) 5 11/22/19 12/02/19
5 12/03/19 12/09/19
1A-17120 Metal Deck (High Roof) 20 10/25/19 11/22/19
90 12/10/19 04/15/20
1A-18000 Underslab Plumbing Rough-in
15 12/10/19 12/31/19
1A-18100 Fine Grade for SOG 5 12/24/19 12/31/19
1A-18110 Sand/Vapor Barrier for SOG 10 01/02/20 01/15/20
15 12/10/19 12/31/19
1A-18120 Form/Rebar/Pour SOG
5 01/16/20 01/22/20
1A-18200 MEP/Rebar/Pour Concrete on Metal Deck (2nd Floor) 20 01/23/20 02/19/20
40 01/02/20 02/26/20
1A-18300 MEP/Rebar/Pour Concrete on Metal Deck (Low Roof) 10 01/30/20 02/12/20
10 02/27/20 03/11/20
1A-18400 Fireproofing 1st Floor
5 03/12/20 03/18/20
1A-18410 Fireproofing 2nd Floor 20 01/16/20 02/12/20
1A-19000 Prep/Pour Ramp & Precast Stairs 5 01/16/20 01/22/20
20 01/23/20 02/19/20
EXTERIOR SKIN 30 02/20/20 04/01/20
10 03/19/20 04/01/20
1A-30000 Exterior Framing
5 04/02/20 04/08/20
1A-30010 Exterior MEP Rough-in 5 04/09/20 04/15/20
41 11/01/19 01/03/20
1A-30020 Exterior Sheathing
41 11/01/19 01/03/20
1A-30050 Intumescent & High Performance Paint at Exposed Steel 3 11/01/19 11/05/19
3 11/01/19 11/05/19
1A-30200 Waterproofing for Wood Panel System 3 11/01/19 11/05/19
3 11/06/19 11/08/19
1A-30210 Wood Panel System
Edwards Lifescience
1A-30300 Curtainwall Proposal Schedule with Buil
1A-30350 Storefront Framing Snyder L
1A-30360 Storefront Glazing
1A-30370 Storefront Doors
1A-30400 Steel & Glass Guardrails
1A-30500 Weatherproofing for Aluminum Panels
1A-30510 Field Measure & Fab Aluminum Panels
1A-30520 Install Aluminum Panels
1A-30550 Composite LED Screen
1A-30600 MEP Trim
1A-30900 Cleanup & Prepunch
ROOF
LOW ROOF
1A-40000 MEP Penetrations & Roof Drains
1A-40010 Mechanical Curbs
1A-40020 Roof Hatch
1A-40030 Sheetmetal Flashing
Project Start 09/10/18 Page 9 of 18
Project Finish 07/23/20 TASK filter: All Activities
Data Date 09/01/18
Run Date 10/05/18
2019 2020
c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Drill/Rebar/Pour Piles (144)
Form/Rebar/Pour Pilecaps
Excavate/Form/Pour Elevator Pit
Form/Rebar/Pour Gradebeams
Form/Rebar/Pour/Strip CIP Walls (Pour 1)
Form/Rebar/Pour/Strip CIP Walls (Pour 2)
Form/Rebar/Pour/Strip CIP Walls (Pour 3)
Erect Structural Steel
Weld Structural Steel
Metal Deck/Edge Metal/Shear Studs (2nd Floor)
Metal Deck/Edge Metal/Shear Studs (Low Roof)
Metal Deck (High Roof)
Underslab Plumbing Rough-in
Fine Grade for SOG
Sand/Vapor Barrier for SOG
Form/Rebar/Pour SOG
MEP/Rebar/Pour Concrete on Metal Deck (2nd Floor)
MEP/Rebar/Pour Concrete on Metal Deck (Low Roof)
Fireproofing 1st Floor
Fireproofing 2nd Floor
Prep/Pour Ramp & Precast Stairs
EXTERIOR SKIN
Exterior Framing
Exterior MEP Rough-in
Exterior Sheathing
Intumescent & High Performance Paint at Exposed Steel
Waterproofing for Wood Panel System
Wood Panel System
Curtainwall
Storefront Framing
Storefront Glazing
Storefront Doors
Steel & Glass Guardrails
Weatherproofing for Aluminum Panels
Field Measure & Fab Aluminum Panels
Install Aluminum Panels
Composite LED Screen
MEP Trim
Cleanup & Prepunch
ROOF
LOW ROOF
MEP Penetrations & Roof Drains
Mechanical Curbs
Roof Hatch
Sheetmetal Flashing
es Campus Expansion Remaining Level of Effort
lding B Concrete - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work
Activity ID Activity Name Dur Current Start Current Finish
Aug Sep Oct Nov Dec
1A-40100 Roofing
1A-40200 Set Mechanical Equipment 5 11/12/19 11/18/19
1A-40210 Hookup Mechanical Equipment 2 11/19/19 11/20/19
1A-40300 Operable Skylight 10 11/21/19 12/06/19
1A-40400 Sheetmetal Trim & Finish 20 11/19/19 12/18/19
1A-40900 Cleanup & Prepunch Roof 5 12/19/19 12/26/19
5 12/27/19 01/03/20
INTERIOR Overhead Mechanical Rough-in 105 12/03/19 04/29/20
Overhead Plumbing Rough-in
1ST FLOOR Overhead Fire Sprinkler Rough-in 100 12/03/19 04/22/20
1A-50000 Overhead Electrical Rough-in 5 12/03/19 12/09/19
1A-50010 Wall Framing & Furring 5 12/10/19 12/16/19
1A-50020 Wall Plumbing Rough-in 5 12/10/19 12/16/19
1A-50030 Wall Electrical Rough-in 5 12/10/19 12/16/19
1A-50100 Wall Low Voltage Rough-in 5 12/10/19 12/16/19
1A-50110 Wall MEP & Framing Inspections 5 12/17/19 12/23/19
1A-50120 Wall Insulation (dry-in) 5 12/17/19 12/23/19
1A-50130 Drywall Walls 5 12/17/19 12/23/19
1A-50140 Hard Ceiling Framing 2 12/24/19 12/26/19
1A-50150 Hard Ceiling Mechanical Rough-in 2 01/16/20 01/17/20
1A-50160 Hard Ceiling Fire Sprinkler Rough-in 5 01/20/20 01/24/20
1A-50200 Hard Ceiling Electrical Rough-in 3 12/17/19 12/19/19
1A-50210 Hard Ceiling MEP Inspections 3 12/20/19 12/24/19
1A-50220 Drywall Ceilings 3 12/20/19 12/24/19
1A-50230 Tape Drywall Walls & Ceilings 3 12/20/19 12/24/19
1A-50240 Prime & Paint 2 12/26/19 12/27/19
1A-50250 Electrical Panels & Pull Wire 3 01/27/20 01/29/20
1A-50260 Door Frames
1A-50300 Ceiling Grid 10 01/30/20 02/12/20
1A-50310 Mechanical Fixtures in Grid 5 02/13/20 02/19/20
1A-50320 Fire Sprinkler Drops in Grid
1A-50400 Electrical Fixtures in Grid 10 02/20/20 03/04/20
1A-50410 Ceiling Grid & MEP Inspections 3 02/20/20 02/24/20
1A-50420 Ceiling Tile 5 02/20/20 02/26/20
1A-50430 Suspended & Surface Mounted Fixtures 5 02/27/20 03/04/20
1A-50440 Millwork/Cabinetry/Wall Finishes 5 02/27/20 03/04/20
1A-50450 Countertops 5 02/27/20 03/04/20
1A-50460 Flooring 2 03/05/20 03/06/20
1A-50500 Base 5 03/09/20 03/13/20
1A-50510 Hang Doors 5 03/16/20 03/20/20
1A-50600 Finish Paint
1A-50610 Door Hardware 10 02/27/20 03/11/20
1A-50620 Mechanical Trim 3 03/12/20 03/16/20
1A-50630 Fire Sprinkler Trim 5 03/23/20 03/27/20
1A-50640 2 03/30/20 03/31/20
1A-50650 3 03/30/20 04/01/20
1A-50660 5 04/02/20 04/08/20
3 04/09/20 04/13/20
Project Start 09/10/18 Page 10 of 18 5 04/09/20 04/15/20
Project Finish 07/23/20 TASK filter: All Activities 5 04/09/20 04/15/20
Data Date 09/01/18
Run Date 10/05/18 Edwards Lifescience
Proposal Schedule with Buil
Snyder L
2019 2020
c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Roofing
Set Mechanical Equipment
Hookup Mechanical Equipment
Operable Skylight
Sheetmetal Trim & Finish
Cleanup & Prepunch Roof
INTERIOR
1ST FLOOR
Overhead Mechanical Rough-in
Overhead Plumbing Rough-in
Overhead Fire Sprinkler Rough-in
Overhead Electrical Rough-in
Wall Framing & Furring
Wall Plumbing Rough-in
Wall Electrical Rough-in
Wall Low Voltage Rough-in
Wall MEP & Framing Inspections
Wall Insulation (dry-in)
Drywall Walls
Hard Ceiling Framing
Hard Ceiling Mechanical Rough-in
Hard Ceiling Fire Sprinkler Rough-in
Hard Ceiling Electrical Rough-in
Hard Ceiling MEP Inspections
Drywall Ceilings
Tape Drywall Walls & Ceilings
Prime & Paint
Electrical Panels & Pull Wire
Door Frames
Ceiling Grid
Mechanical Fixtures in Grid
Fire Sprinkler Drops in Grid
Electrical Fixtures in Grid
Ceiling Grid & MEP Inspections
Ceiling Tile
Suspended & Surface Mounted Fixtures
Millwork/Cabinetry/Wall Finishes
Countertops
Flooring
Base
Hang Doors
Finish Paint
Door Hardware
Mechanical Trim
Fire Sprinkler Trim
es Campus Expansion Remaining Level of Effort
lding B Concrete - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work
Activity ID Activity Name Dur Current Start Current Finish
Aug Sep Oct Nov Dec
1A-50670 Electrical Trim
1A-50680 Low Voltage Trim 5 04/09/20 04/15/20
1A-50800 Tile (Restrooms) 5 04/09/20 04/15/20
1A-50820 Plumbing Fixtures (Restrooms) 5 02/20/20 02/26/20
1A-50840 Toilet Accessories (Restrooms) 3 02/27/20 03/02/20
1A-50900 Cleanup & Prepunch Interior 3 03/03/20 03/05/20
2ND FLOOR 5 04/16/20 04/22/20
1A-55000 Overhead Mechanical Rough-in Page 11 of 18 100 12/10/19 04/29/20
1A-55010 Overhead Plumbing Rough-in TASK filter: All Activities 5 12/10/19 12/16/19
1A-55020 Overhead Fire Sprinkler Rough-in 5 12/17/19 12/23/19
1A-55030 Overhead Electrical Rough-in 5 12/17/19 12/23/19
1A-55100 Wall Framing & Furring 5 12/17/19 12/23/19
1A-55110 Wall Plumbing Rough-in 5 12/17/19 12/23/19
1A-55120 Wall Electrical Rough-in 5 12/24/19 12/31/19
1A-55130 Wall Low Voltage Rough-in 5 12/24/19 12/31/19
1A-55140 Wall MEP & Framing Inspections 5 12/24/19 12/31/19
1A-55150 Wall Insulation 2 01/02/20 01/03/20
1A-55160 Drywall Walls 2 01/20/20 01/21/20
1A-55200 Hard Ceiling Framing 5 01/27/20 01/31/20
1A-55210 Hard Ceiling Mechanical Rough-in 3 12/24/19 12/27/19
1A-55220 Hard Ceiling Fire Sprinkler Rough-in 3 12/30/19 01/02/20
1A-55230 Hard Ceiling Electrical Rough-in 3 12/30/19 01/02/20
1A-55240 Hard Ceiling MEP Inspections 3 12/30/19 01/02/20
1A-55250 Drywall Ceilings 2 01/03/20 01/06/20
1A-55260 Tape Drywall Walls & Ceilings 3 02/03/20 02/05/20
1A-55300 Prime & Paint 10 02/06/20 02/19/20
1A-55310 Electrical Panels & Pull Wire 5 02/20/20 02/26/20
1A-55320 Door Frames 10 02/27/20 03/11/20
1A-55400 Ceiling Grid 3 02/27/20 03/02/20
1A-55410 Mechanical Fixtures in Grid 5 02/27/20 03/04/20
1A-55420 Fire Sprinkler Drops in Grid 5 03/05/20 03/11/20
1A-55430 Electrical Fixtures in Grid 5 03/05/20 03/11/20
1A-55440 Ceiling Grid & MEP Inspections 5 03/05/20 03/11/20
1A-55450 Ceiling Tile 2 03/12/20 03/13/20
1A-55460 Suspended & Surface Mounted Fixtures 5 03/16/20 03/20/20
1A-55500 Millwork/Cabinetry/Wall Finishes 5 03/23/20 03/27/20
1A-55510 Countertops 10 03/05/20 03/18/20
1A-55600 Flooring 3 03/19/20 03/23/20
1A-55605 Walkway Pedestal Pavers 5 03/30/20 04/03/20
1A-55610 Base 10 02/27/20 03/11/20
1A-55620 Hang Doors 2 04/06/20 04/07/20
1A-55630 Finish Paint 3 04/06/20 04/08/20
1A-55640 Door Hardware 5 04/09/20 04/15/20
1A-55650 Mechanical Trim 3 04/16/20 04/20/20
1A-55660 Fire Sprinkler Trim 5 04/16/20 04/22/20
1A-55670 Electrical Trim 5 04/16/20 04/22/20
5 04/16/20 04/22/20
Project Start 09/10/18
Edwards Lifescience
Project Finish 07/23/20 Proposal Schedule with Buil
Data Date 09/01/18 Snyder L
Run Date 10/05/18
2019 2020
c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Electrical Trim
Low Voltage Trim
Tile (Restrooms)
Plumbing Fixtures (Restrooms)
Toilet Accessories (Restrooms)
Cleanup & Prepunch Interior
2ND FLOOR
Overhead Mechanical Rough-in
Overhead Plumbing Rough-in
Overhead Fire Sprinkler Rough-in
Overhead Electrical Rough-in
Wall Framing & Furring
Wall Plumbing Rough-in
Wall Electrical Rough-in
Wall Low Voltage Rough-in
Wall MEP & Framing Inspections
Wall Insulation
Drywall Walls
Hard Ceiling Framing
Hard Ceiling Mechanical Rough-in
Hard Ceiling Fire Sprinkler Rough-in
Hard Ceiling Electrical Rough-in
Hard Ceiling MEP Inspections
Drywall Ceilings
Tape Drywall Walls & Ceilings
Prime & Paint
Electrical Panels & Pull Wire
Door Frames
Ceiling Grid
Mechanical Fixtures in Grid
Fire Sprinkler Drops in Grid
Electrical Fixtures in Grid
Ceiling Grid & MEP Inspections
Ceiling Tile
Suspended & Surface Mounted Fixtures
Millwork/Cabinetry/Wall Finishes
Countertops
Flooring
Walkway Pedestal Pavers
Base
Hang Doors
Finish Paint
Door Hardware
Mechanical Trim
Fire Sprinkler Trim
Electrical Trim
es Campus Expansion Remaining Level of Effort
lding B Concrete - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work
Activity ID Activity Name Dur Current Start Current Finish
Aug Sep Oct Nov Dec
1A-55680 Low Voltage Trim
5 04/16/20 04/22/20
1A-55900 Cleanup & Prepunch Interior 5 04/23/20 04/29/20
35 02/03/20 03/20/20
INTERIOR STAIRS
10 02/03/20 02/14/20
1A-70000 Drywall & Tape Stairs 10 02/17/20 02/28/20
1A-70010 Handrails 5 03/02/20 03/06/20
5 03/09/20 03/13/20
1A-70020 Prime & Paint 5 03/16/20 03/20/20
36 02/20/20 04/09/20
1A-70030 Flooring
10 02/20/20 03/04/20
1A-70040 MEP Trim 5 03/05/20 03/11/20
5 03/12/20 03/18/20
ELEVATOR 3 03/19/20 03/23/20
3 03/24/20 03/26/20
1A-71000 Elevator Pre-Check List & Corrections 5 03/27/20 04/02/20
5 04/03/20 04/09/20
1A-71010 Elevator Rails
280 04/01/19 05/06/20
1A-71020 Elevator Equipment
20 04/01/19 04/26/19
1A-71030 Elevator Temp Platform 20 04/29/19 05/24/19
60 01/16/20 04/08/20
1A-71040 Elevator Door Frames 20 04/09/20 05/06/20
55 03/12/20 05/28/20
1A-71050 Elevator Cab & Finishes
15 03/12/20 04/01/20
1A-71060 Elevator Test & Adjust 10 04/30/20 05/13/20
40 03/19/20 05/13/20
SITEWORK 10 05/14/20 05/28/20
1A-80000 Site Wet Utilities 0 05/28/20
2 04/28/20 04/29/20
1A-80100 Site Dry Utilities 20 04/30/20 05/28/20
0 05/28/20
1A-80400 Hardscape (Entry/Museum) 313 04/29/19 07/22/20
1A-80410 Landscape (Entry/Museum)
INSPECTIONS / PUNCHLIST
1A-89000 Permanent Power
1A-90000 Final Inspections
1A-90005 Commissioning/LEED Approval
1A-90010 Inclement Weather Allowance
1A-90020 Substantial Completion
1A-90100 Prepare Punchlist
1A-90110 Punchlist Corrections
1A-90120 Final Completion
CONSTRUCTION - PHASE 1 - BLDG C (CAFE/CONFERENCE)
EARTHWORK 21 06/25/19 07/24/19
1C-10000 Start Construction 0 06/25/19 06/25/19
1 06/25/19 07/17/19
1C-10010 Survey 15 06/26/19 07/24/19
5 07/18/19 12/19/19
1C-10020 Earthwork 102 07/25/19 08/28/19
09/12/19
1C-10030 Certify Pad 25 07/25/19 09/12/19
15 08/22/19 09/26/19
FOUNDATIONS / STRUCTURE 10 08/29/19 10/10/19
15 09/06/19 10/24/19
1C-15000 Drill/Rebar/Pour Piles (246) 10 09/27/19 10/31/19
15 10/04/19 10/31/19
1C-15100 Form/Rebar/Pour Pilecaps 10 10/18/19
10 10/18/19
1C-15200 Excavate/Form/Pour Elevator Pit
1C-15300 Form/Rebar/Pour Gradebeams
1C-17000 Erect Structural Steel
1C-17010 Weld Structural Steel
1C-17020 Erect BRB's
1C-17100 Metal Deck/Edge Metal/Shear Studs (2nd Floor)
Project Start 09/10/18 Page 12 of 18 Edwards Lifescience
Project Finish 07/23/20 TASK filter: All Activities Proposal Schedule with Buil
Data Date 09/01/18
Run Date 10/05/18 Snyder L
2019 2020
c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Low Voltage Trim
Cleanup & Prepunch Interior
INTERIOR STAIRS
Drywall & Tape Stairs
Handrails
Prime & Paint
Flooring
MEP Trim
ELEVATOR
Elevator Pre-Check List & Corrections
Elevator Rails
Elevator Equipment
Elevator Temp Platform
Elevator Door Frames
Elevator Cab & Finishes
Elevator Test & Adjust
SITEWORK
Site Wet Utilities
Site Dry Utilities
Hardscape (Entry/Museum)
Landscape (Entry/Museum)
INSPECTIONS / PUNCHLIST
Permanent Power
Final Inspections
Commissioning/LEED Approval
Inclement Weather Allowance
Substantial Completion
Prepare Punchlist
Punchlist Corrections
Final Completion
CONSTRUCTION - PHASE 1 - BLDG C (CAFE/CO
EARTHWORK
Start Construction
Survey
Earthwork
Certify Pad
FOUNDATIONS / STRUCTURE
Drill/Rebar/Pour Piles (246)
Form/Rebar/Pour Pilecaps
Excavate/Form/Pour Elevator Pit
Form/Rebar/Pour Gradebeams
Erect Structural Steel
Weld Structural Steel
Erect BRB's
Metal Deck/Edge Metal/Shear Studs (2nd Floor)
es Campus Expansion Remaining Level of Effort
lding B Concrete - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work
Activity ID Activity Name Dur Current Start Current Finish
Aug Sep Oct Nov Dec
1C-17110 Metal Deck/Edge Metal (Roof)
10 11/01/19 11/15/19
1C-18000 Underslab Plumbing Rough-in 10 11/08/19 11/22/19
10 11/08/19 11/22/19
1C-18050 Complete Rebar/Pour Gradebeams at Moment Frames
2 11/25/19 11/26/19
1C-18100 Fine Grade for SOG 5 11/27/19 12/05/19
10 12/06/19 12/19/19
1C-18110 Sand/Vapor Barrier for SOG 15 11/08/19 12/03/19
95 12/13/19 04/27/20
1C-18120 Form/Rebar/Pour SOG
15 12/13/19 01/06/20
1C-18200 MEP/Rebar/Pour Concrete on Metal Deck (2nd Floor) 10 12/20/19 01/06/20
10 12/30/19 01/13/20
EXTERIOR SKIN
5 01/14/20 01/20/20
1C-30000 Exterior Framing 20 01/21/20 02/17/20
60 01/07/20 03/30/20
1C-30010 Exterior MEP Rough-in 10 03/03/20 03/16/20
10 03/17/20 03/30/20
1C-30020 Exterior Sheathing
5 03/31/20 04/06/20
1C-30200 Waterproofing for Wood Rain Screen 20 01/14/20 02/10/20
10 01/14/20 01/27/20
1C-30210 Wood Rain Screen 30 01/21/20 03/02/20
40 02/18/20 04/13/20
1C-30300 Curtainwall
5 04/14/20 04/20/20
1C-30350 Storefront Framing 5 04/21/20 04/27/20
132 11/18/19 05/26/20
1C-30360 Storefront Glazing
122 12/04/19 05/26/20
1C-30370 Storefront Doors 5 12/04/19 12/10/19
5 12/11/19 12/17/19
1C-30400 Steel & Glass Guardrails
10 03/31/20 04/13/20
1C-30500 Weatherproofing for Aluminum Panels 10 04/07/20 04/20/20
20 04/21/20 05/18/20
1C-30510 Field Measure & Fab Aluminum Panels
5 05/19/20 05/26/20
1C-30520 Install Aluminum Panels 60 11/18/19 02/13/20
1C-30600 MEP Trim 5 11/18/19 11/22/19
5 11/18/19 11/22/19
1C-30900 Cleanup & Prepunch 5 11/25/19 12/03/19
10 12/04/19 12/17/19
ROOF 5 12/18/19 12/24/19
20 12/26/19 01/23/20
ROOF DECK 20 12/18/19 01/16/20
10 01/24/20 02/06/20
1C-40000 MEP Penetrations & Roof Drains 5 02/07/20 02/13/20
122 12/13/19 06/04/20
1C-40030 Sheetmetal Flashing
109 12/13/19 05/15/20
1C-40100 Waterproofing 10 12/13/19 12/27/19
10 12/20/19 01/06/20
1C-40110 Topping Slabs
Edwards Lifescience
1C-40300 Roof Deck Pavers & Finishes Proposal Schedule with Buil
1C-40900 Cleanup & Prepunch Roof Decks Snyder L
MAIN ROOF
1C-41000 MEP Penetrations & Roof Drains
1C-41010 Mechanical Curbs
1C-41030 Sheetmetal Flashing
1C-41100 Roofing
1C-41200 Set Mechanical Equipment
1C-41210 Hookup Mechanical Equipment
1C-41300 Roof Screen Panels
1C-41400 Sheetmetal Trim & Finish
1C-41900 Cleanup & Prepunch Roof
INTERIOR
1ST FLOOR CORE
1C-50000 Overhead Mechanical Rough-in
1C-50010 Overhead Plumbing Rough-in
Project Start 09/10/18 Page 13 of 18
Project Finish 07/23/20 TASK filter: All Activities
Data Date 09/01/18
Run Date 10/05/18
2019 2020
c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Metal Deck/Edge Metal (Roof)
Underslab Plumbing Rough-in
Complete Rebar/Pour Gradebeams at Moment Frames
Fine Grade for SOG
Sand/Vapor Barrier for SOG
Form/Rebar/Pour SOG
MEP/Rebar/Pour Concrete on Metal Deck (2nd Floor)
EXTERIOR SKIN
Exterior Framing
Exterior MEP Rough-in
Exterior Sheathing
Waterproofing for Wood Rain Screen
Wood Rain Screen
Curtainwall
Storefront Framing
Storefront Glazing
Storefront Doors
Steel & Glass Guardrails
Weatherproofing for Aluminum Panels
Field Measure & Fab Aluminum Panels
Install Aluminum Panels
MEP Trim
Cleanup & Prepunch
ROOF
ROOF DECK
MEP Penetrations & Roof Drains
Sheetmetal Flashing
Waterproofing
Topping Slabs
Roof Deck Pavers & Finishes
Cleanup & Prepunch Roof Decks
MAIN ROOF
MEP Penetrations & Roof Drains
Mechanical Curbs
Sheetmetal Flashing
Roofing
Set Mechanical Equipment
Hookup Mechanical Equipment
Roof Screen Panels
Sheetmetal Trim & Finish
Cleanup & Prepunch Roof
INTERIOR
1ST FLOOR CORE
Overhead Mechanical Rough-in
Overhead Plumbing Rough-in
es Campus Expansion Remaining Level of Effort
lding B Concrete - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work
Activity ID Activity Name Dur Current Start Current Finish
Aug Sep Oct Nov Dec
1C-50020 Overhead Fire Sprinkler Rough-in
10 12/20/19 01/06/20
1C-50030 Overhead Electrical Rough-in 10 12/20/19 01/06/20
10 12/20/19 01/06/20
1C-50100 Wall Framing & Furring 10 12/30/19 01/13/20
10 12/30/19 01/13/20
1C-50110 Wall Plumbing Rough-in 10 12/30/19 01/13/20
1C-50120 Wall Electrical Rough-in 5 01/09/20 01/15/20
5 01/13/20 01/17/20
1C-50130 Wall Low Voltage Rough-in 10 01/15/20 01/28/20
10 01/07/20 01/20/20
1C-50140 Wall MEP & Framing Inspections 10 01/14/20 01/27/20
10 01/14/20 01/27/20
1C-50150 Wall Insulation (dry-in) 10 01/14/20 01/27/20
5 01/23/20 01/29/20
1C-50160 Drywall Walls 10 01/27/20 02/07/20
10 02/10/20 02/21/20
1C-50200 Hard Ceiling Framing 10 02/17/20 02/28/20
20 02/24/20 03/20/20
1C-50210 Hard Ceiling Mechanical Rough-in 5 02/24/20 02/28/20
20 03/02/20 03/27/20
1C-50220 Hard Ceiling Fire Sprinkler Rough-in 10 03/30/20 04/10/20
10 04/06/20 04/17/20
1C-50230 Hard Ceiling Electrical Rough-in 2 04/20/20 04/21/20
5 04/20/20 04/24/20
1C-50240 Hard Ceiling MEP Inspections 5 04/27/20 05/01/20
5 05/04/20 05/08/20
1C-50250 Drywall Ceilings 5 05/04/20 05/08/20
5 05/04/20 05/08/20
1C-50260 Tape Drywall Walls & Ceilings 5 05/04/20 05/08/20
5 05/04/20 05/08/20
1C-50300 Prime & Paint 15 02/24/20 03/13/20
5 03/09/20 03/13/20
1C-50310 Electrical Panels & Pull Wire 5 03/16/20 03/20/20
5 05/11/20 05/15/20
1C-50320 Door Frames 112 12/30/19 06/04/20
15 12/30/19 01/20/20
1C-50400 Ceiling Finishes 15 01/07/20 01/27/20
15 01/07/20 01/27/20
1C-50460 Suspended & Surface Mounted Fixtures 15 01/07/20 01/27/20
15 01/07/20 01/27/20
1C-50600 Flooring 15 01/14/20 02/03/20
15 01/14/20 02/03/20
1C-50610 Base 15 01/14/20 02/03/20
5 01/30/20 02/05/20
1C-50620 Hang Doors 5 02/03/20 02/07/20
10 02/05/20 02/18/20
1C-50630 Finish Paint
Edwards Lifescience
1C-50640 Door Hardware Proposal Schedule with Buil
1C-50650 Mechanical Trim Snyder L
1C-50660 Fire Sprinkler Trim
1C-50670 Electrical Trim
1C-50680 Low Voltage Trim
1C-50800 Tile (Restrooms)
1C-50820 Plumbing Fixtures (Restrooms)
1C-50840 Toilet Accessories (Restrooms)
1C-50900 Cleanup & Prepunch Interior
2ND FLOOR CORE
1C-55000 Overhead Mechanical Rough-in
1C-55010 Overhead Plumbing Rough-in
1C-55020 Overhead Fire Sprinkler Rough-in
1C-55030 Overhead Electrical Rough-in
1C-55100 Wall Framing & Furring
1C-55110 Wall Plumbing Rough-in
1C-55120 Wall Electrical Rough-in
1C-55130 Wall Low Voltage Rough-in
1C-55140 Wall MEP & Framing Inspections
1C-55150 Wall Insulation (dry-in)
1C-55160 Drywall Walls
Project Start 09/10/18 Page 14 of 18
Project Finish 07/23/20 TASK filter: All Activities
Data Date 09/01/18
Run Date 10/05/18
2019 2020
c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Overhead Fire Sprinkler Rough-in
Overhead Electrical Rough-in
Wall Framing & Furring
Wall Plumbing Rough-in
Wall Electrical Rough-in
Wall Low Voltage Rough-in
Wall MEP & Framing Inspections
Wall Insulation (dry-in)
Drywall Walls
Hard Ceiling Framing
Hard Ceiling Mechanical Rough-in
Hard Ceiling Fire Sprinkler Rough-in
Hard Ceiling Electrical Rough-in
Hard Ceiling MEP Inspections
Drywall Ceilings
Tape Drywall Walls & Ceilings
Prime & Paint
Electrical Panels & Pull Wire
Door Frames
Ceiling Finishes
Suspended & Surface Mounted Fixtures
Flooring
Base
Hang Doors
Finish Paint
Door Hardware
Mechanical Trim
Fire Sprinkler Trim
Electrical Trim
Low Voltage Trim
Tile (Restrooms)
Plumbing Fixtures (Restrooms)
Toilet Accessories (Restrooms)
Cleanup & Prepunch Interior
2ND FLOOR CORE
Overhead Mechanical Rough-in
Overhead Plumbing Rough-in
Overhead Fire Sprinkler Rough-in
Overhead Electrical Rough-in
Wall Framing & Furring
Wall Plumbing Rough-in
Wall Electrical Rough-in
Wall Low Voltage Rough-in
Wall MEP & Framing Inspections
Wall Insulation (dry-in)
Drywall Walls
es Campus Expansion Remaining Level of Effort
lding B Concrete - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work
Activity ID Activity Name Dur Current Start Current Finish
Aug Sep Oct Nov Dec
1C-55200 Hard Ceiling Framing
10 01/21/20 02/03/20
1C-55210 Hard Ceiling Mechanical Rough-in 10 01/28/20 02/10/20
10 01/28/20 02/10/20
1C-55220 Hard Ceiling Fire Sprinkler Rough-in 10 01/28/20 02/10/20
10 01/28/20 02/10/20
1C-55230 Hard Ceiling Electrical Rough-in
5 02/11/20 02/17/20
1C-55235 Operable Wall Tracks 10 02/13/20 02/26/20
10 02/27/20 03/11/20
1C-55240 Hard Ceiling MEP Inspections 10 03/05/20 03/18/20
20 03/12/20 04/08/20
1C-55250 Drywall Ceilings
5 03/12/20 03/18/20
1C-55260 Tape Drywall Walls & Ceilings 20 03/19/20 04/15/20
10 04/16/20 04/29/20
1C-55300 Prime & Paint 10 04/23/20 05/06/20
1C-55310 Electrical Panels & Pull Wire 2 05/07/20 05/08/20
5 05/07/20 05/13/20
1C-55320 Door Frames 5 05/14/20 05/20/20
5 05/21/20 05/28/20
1C-55400 Ceiling Finishes 5 05/21/20 05/28/20
5 05/21/20 05/28/20
1C-55460 Suspended & Surface Mounted Fixtures 5 05/21/20 05/28/20
5 05/21/20 05/28/20
1C-55600 Flooring 5 05/21/20 05/28/20
20 03/12/20 04/08/20
1C-55610 Base 10 04/02/20 04/15/20
10 04/09/20 04/22/20
1C-55620 Hang Doors 5 05/29/20 06/04/20
35 03/12/20 04/29/20
1C-55630 Finish Paint
15 03/12/20 04/01/20
1C-55640 Door Hardware 10 03/26/20 04/08/20
10 04/02/20 04/15/20
1C-55650 Mechanical Trim 10 04/09/20 04/22/20
10 04/16/20 04/29/20
1C-55660 Fire Sprinkler Trim 40 03/12/20 05/06/20
1C-55670 Electrical Trim 10 03/12/20 03/25/20
5 03/26/20 04/01/20
1C-55680 Low Voltage Trim 5 04/02/20 04/08/20
3 04/09/20 04/13/20
1C-55690 Operable Wall Panels 3 04/14/20 04/16/20
5 04/17/20 04/23/20
1C-55800 Tile (Restrooms) 5 04/30/20 05/06/20
1C-55820 Plumbing Fixtures (Restrooms) 293 04/29/19 06/23/20
1C-55840 Toilet Accessories (Restrooms) 20 04/29/19 05/24/19
20 05/28/19 06/24/19
1C-55900 Cleanup & Prepunch Interior 100 01/07/20 05/26/20
INTERIOR STAIRS Edwards Lifescience
Proposal Schedule with Buil
1C-70000 Drywall & Tape Stairs
Snyder L
1C-70010 Handrails
1C-70020 Prime & Paint
1C-70030 Flooring
1C-70040 MEP Trim
ELEVATORS
1C-71000 Elevator Pre-Check List & Corrections
1C-71010 Elevator Rails
1C-71020 Elevator Equipment
1C-71030 Elevator Temp Platform
1C-71040 Elevator Door Frames
1C-71050 Elevator Cab & Finishes
1C-71060 Elevator Test & Adjust
SITEWORK
1C-80000 Site Wet Utilities
1C-80100 Site Dry Utilities
1C-80400 Hardscape (Cafe/Conference)
Project Start 09/10/18 Page 15 of 18
Project Finish 07/23/20 TASK filter: All Activities
Data Date 09/01/18
Run Date 10/05/18
2019 2020
c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Hard Ceiling Framing
Hard Ceiling Mechanical Rough-in
Hard Ceiling Fire Sprinkler Rough-in
Hard Ceiling Electrical Rough-in
Operable Wall Tracks
Hard Ceiling MEP Inspections
Drywall Ceilings
Tape Drywall Walls & Ceilings
Prime & Paint
Electrical Panels & Pull Wire
Door Frames
Ceiling Finishes
Suspended & Surface Mounted Fixtures
Flooring
Base
Hang Doors
Finish Paint
Door Hardware
Mechanical Trim
Fire Sprinkler Trim
Electrical Trim
Low Voltage Trim
Operable Wall Panels
Tile (Restrooms)
Plumbing Fixtures (Restrooms)
Toilet Accessories (Restrooms)
Cleanup & Prepunch Interior
INTERIOR STAIRS
Drywall & Tape Stairs
Handrails
Prime & Paint
Flooring
MEP Trim
ELEVATORS
Elevator Pre-Check List & Corrections
Elevator Rails
Elevator Equipment
Elevator Temp Platform
Elevator Door Frames
Elevator Cab & Finishes
Elevator Test & Adjust
SITEWORK
Site Wet Utilities
Site Dry Utilities
Hardscape (Cafe/Conference)
es Campus Expansion Remaining Level of Effort
lding B Concrete - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work
Activity ID Activity Name Dur Current Start Current Finish
Aug Sep Oct Nov Dec
1C-80410 Landscape (Cafe/Conference) 40 04/28/20 06/23/20
INSPECTIONS / PUNCHLIST 73 04/09/20 07/22/20
1C-89000 Permanent Power 15 04/09/20 04/29/20
1C-90000 Final Inspections 10 06/24/20 07/08/20
1C-90005 Commissioning/LEED Approval 40 05/12/20 07/08/20
1C-90010 Inclement Weather Allowance 10 07/09/20 07/22/20
1C-90020 Substantial Completion 0 07/22/20
1C-90100 Prepare Punchlist 2 06/22/20 06/23/20
1C-90110 Punchlist Corrections 20 06/24/20 07/22/20
1C-90120 Final Completion 0 07/22/20
CONSTRUCTION - PHASE 1 - OFFSITE 278 01/03/19 02/06/20
REDHILL DECELERATION LANE, LEFT TURN LANE, MEDIAN, U/G UTILITIES 278 01/03/19 02/06/20
1S-11900 Submit/Approve Traffic Control Plans 60 01/03/19 03/27/19
1S-12000 Post Advanced Construction Notification & Street Signage 10 03/28/19 04/10/19
1S-12010 Contact Underground Dig Alert & Record Permit Number 1 04/11/19 04/11/19
1S-12020 Verify, Document & Submit Existing Conditions Prior to Start 5 04/12/19 04/18/19
1S-12030 Survey Demo Limits Prior to Start & Confirm with Contract Documents 5 04/19/19 04/25/19
1S-12040 Preconstruction Conference with City of Irvine as Required 5 04/26/19 05/02/19
1S-12100 Setup Temporary Traffic Control Measures 3 05/03/19 05/07/19
1S-12110 Setup Temporary BMP's 5 05/08/19 05/14/19
1S-12112 Construct (N) 16 in ACP Water Main 15 05/15/19 06/05/19
1S-12114 Construct (N) Fire, Domestic & Irrigation D.I. Laterals 15 05/15/19 06/05/19
1S-12116 R&R Fire Hydrant & Remove Lateral 15 05/15/19 06/05/19
1S-12118 Survey & Layout Raised Islands 1 06/06/19 06/06/19
1S-12120 Sawcut & Demo Hardscapes for Raised Islands 3 06/07/19 06/11/19
1S-12122 Grade & Compact Subgrades for Raised Islands 3 06/12/19 06/14/19
1S-12124 Form Raised Islands & Certify Formwork 2 06/17/19 06/18/19
1S-12126 Pour & Strip Curb Islands 2 06/19/19 06/20/19
1S-12128 Backfill & Compact Curb Islands 5 06/21/19 06/27/19
1S-12130 Patch A/C Paving at Curb Islands 5 06/28/19 07/05/19
1S-12132 Grind & Overlay A/C Paving at Curb Islands 5 07/08/19 07/12/19
1S-12134 Temporary Striping 1 07/15/19 07/15/19
1S-12136 Remove & Relocate Construction Fencing 2 06/06/19 06/07/19
1S-12138 Safe-off & Re-Route Irrigation 2 06/10/19 06/11/19
1S-12140 Remove & Salvage Signage as Applicable 2 06/12/19 06/13/19
1S-12150 Remove & Relocate Existing Low Volt Pull Box & Assoc. Cabling 5 06/14/19 06/20/19
1S-12160 Remove & Protect Existing Bus Bench, Trash Can & Associated Signage 5 06/21/19 06/27/19
1S-12200 Demo (E) Hardscapes & Landscapes 3 06/28/19 07/02/19
1S-12210 Survey (N) Curb & Gutter 1 07/03/19 07/03/19
1S-12220 Prepare Subgrade for (N) Deceleration Lane, Curb & Gutter 5 07/05/19 07/11/19
1S-12230 Test Subgrade for Compaction 2 07/12/19 07/15/19
1S-12240 Install (N) Below Grade Signal Conduit & Associated Pull Boxes 10 07/16/19 07/29/19
1S-12242 Relocate Pedestrian Light Pole 5 07/30/19 08/05/19
1S-12250 Form (N) Curb & Gutter & EntranceApron 5 07/30/19 08/05/19
1S-12260 Survey & Record (N) Curb & Gutter Formwork - Prepour 1 08/06/19 08/06/19
Project Start 09/10/18 Page 16 of 18 Edwards Lifescience
Project Finish 07/23/20 TASK filter: All Activities Proposal Schedule with Buil
Data Date 09/01/18
Run Date 10/05/18 Snyder L
2019 2020
c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Landscape (Cafe/Conference)
INSPECTIONS / PUNCHLIST
Permanent Power
Final Inspections
Commissioning/LEED Approval
Inclement Weather Allowance
Substantial Completion
Prepare Punchlist
Punchlist Corrections
Final Completion
CONSTRUCTION - PHASE 1 - OFFSITE
REDHILL DECELERATION LANE, LEFT TURN LANE, MEDIAN, U/G UTILITIES
Submit/Approve Traffic Control Plans
Post Advanced Construction Notification & Street Signage
Contact Underground Dig Alert & Record Permit Number
Verify, Document & Submit Existing Conditions Prior to Start
Survey Demo Limits Prior to Start & Confirm with Contract Documents
Preconstruction Conference with City of Irvine as Required
Setup Temporary Traffic Control Measures
Setup Temporary BMP's
Construct (N) 16 in ACP Water Main
Construct (N) Fire, Domestic & Irrigation D.I. Laterals
R&R Fire Hydrant & Remove Lateral
Survey & Layout Raised Islands
Sawcut & Demo Hardscapes for Raised Islands
Grade & Compact Subgrades for Raised Islands
Form Raised Islands & Certify Formwork
Pour & Strip Curb Islands
Backfill & Compact Curb Islands
Patch A/C Paving at Curb Islands
Grind & Overlay A/C Paving at Curb Islands
Temporary Striping
Remove & Relocate Construction Fencing
Safe-off & Re-Route Irrigation
Remove & Salvage Signage as Applicable
Remove & Relocate Existing Low Volt Pull Box & Assoc. Cabling
Remove & Protect Existing Bus Bench, Trash Can & Associated Signage
Demo (E) Hardscapes & Landscapes
Survey (N) Curb & Gutter
Prepare Subgrade for (N) Deceleration Lane, Curb & Gutter
Test Subgrade for Compaction
Install (N) Below Grade Signal Conduit & Associated Pull Boxes
Relocate Pedestrian Light Pole
Form (N) Curb & Gutter & EntranceApron
Survey & Record (N) Curb & Gutter Formwork - Prepour
es Campus Expansion Remaining Level of Effort
lding B Concrete - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work
Activity ID Activity Name Dur Current Start Current Finish
Aug Sep Oct Nov Dec
1S-12270 Pour (N) Curb & Gutter, Entrance Apron, Strip & Cure
5 08/07/19 08/13/19
1S-12280 Backfill & Compact Behind Curb & Gutter, Entrance Apron 3 08/14/19 08/16/19
1 08/19/19 08/19/19
1S-12290 Survey Subgrade for Sidewalks at EntranceApron 1 08/20/19 08/20/19
5 08/21/19 08/27/19
1S-12300 Install (N) Posts & Signage as Applicable 1 08/28/19 08/28/19
3 08/29/19 09/03/19
1S-12310 Form Sidewalks 2 09/04/19 09/05/19
3 09/06/19 09/10/19
1S-12320 Survey & Record (N) Sidewalk Formwork 1 09/11/19 09/11/19
2 09/12/19 09/13/19
1S-12330 Pour Sidewalks, Strip & Cure 10 01/02/20* 01/15/20
5 01/16/20 01/22/20
1S-12340 Install Relocated Bus Stop Bench, Trash Can & Associated Signage 10 01/23/20 02/05/20
1 02/06/20 02/06/20
1S-12350 Prepare Roadway Subgrade with .65' Aggregate Base & Compact 110 08/01/19 01/09/20
1S-12360 Test Compaction of A.B. 10 08/01/19* 08/14/19
1 08/15/19 08/15/19
1S-12370 A/C Paving 5 08/16/19 08/22/19
5 08/23/19 08/29/19
1S-12372 Grind & Overlay A/C Paving 5 08/30/19 09/06/19
3 09/09/19 09/11/19
1S-12374 Slurry Seal A/C Paving 5 09/12/19 09/18/19
1S-12376 Striping 1st Pass, Cure & Final Stripe 15 09/19/19 10/09/19
10 09/19/19 10/02/19
1S-12380 Final Clean
2 09/19/19 09/20/19
ALTON PKWY STREET WIDENING & U/G UTILITIES 2 09/23/19 09/24/19
2 09/25/19 09/26/19
1S-20000 Post Advanced Construction Notification & Street Signage 5 09/27/19 10/03/19
5 10/04/19 10/10/19
1S-20010 Contact Underground Dig Alert & Record Permit Number 5 10/11/19 10/17/19
1 10/18/19 10/18/19
1S-20020 Verify, Document & Submit Existing Conditions Prior to Start 2 10/21/19 10/22/19
1 10/23/19 10/23/19
1S-20030 Survey Demo Limits Prior to Start & Confirm with Contract Documents 10 10/24/19 11/06/19
2 11/07/19 11/08/19
1S-20040 Preconstruction Conference with City of Irvine as Required 1 11/12/19 11/12/19
2 11/13/19 11/14/19
1S-20050 Setup Temporary Traffic Control Measures 1 11/15/19 11/15/19
1 11/18/19 11/18/19
1S-20060 Setup Temporary BMP's 1 11/19/19 11/19/19
1 11/20/19 11/20/19
1S-20070 Sanitary Sewer Improvements 1 11/21/19 11/21/19
2 11/22/19 11/25/19
1S-20080 Relocate Fire Hydrants 2 11/26/19 11/27/19
1S-20090 Remove & Relocate Construction Fencing Edwards Lifescience
Proposal Schedule with Buil
1S-20100 Safe-off & Re-Route Irrigation
Snyder L
1S-20110 Remove & Salvage Signage as Applicable
1S-20120 Remove & Relocate Existing Low Volt Pull Box & Assoc. Cabling
1S-20130 Remove & Protect Existing Bus Bench, Trash Can & Associated Signage
1S-20140 Demo (E) Hardscapes & Landscapes
1S-20150 Survey (N) Curb & Gutter
1S-20160 Prepare Subgrade for (N) Street Widening, Curb & Gutter
1S-20170 Test Subgrade for Compaction
1S-20180 Install (N) Below Grade Signal Conduit & Associated Pull Boxes
1S-20190 Form (N) Curb & Gutter & EntranceApron
1S-20200 Survey & Record (N) Curb & Gutter Formwork - Prepour
1S-20210 Pour (N) Curb & Gutter, Entrance Apron, Strip & Cure
1S-20220 Backfill & Compact Behind Curb & Gutter, Entrance Apron
1S-20230 Survey Subgrade for Sidewalks
1S-20240 Install (N) Posts & Signage as Applicable
1S-20250 Form Sidewalks
1S-20260 Pour Sidewalks, Strip & Cure
1S-20270 Install Relocated Signage
1S-20280 Prepare Roadway Subgrade with .65' Aggregate Base & Compact
Project Start 09/10/18 Page 17 of 18
Project Finish 07/23/20 TASK filter: All Activities
Data Date 09/01/18
Run Date 10/05/18
2019 2020
c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Pour (N) Curb & Gutter, Entrance Apron, Strip & Cure
Backfill & Compact Behind Curb & Gutter, Entrance Apron
Survey Subgrade for Sidewalks at EntranceApron
Install (N) Posts & Signage as Applicable
Form Sidewalks
Survey & Record (N) Sidewalk Formwork
Pour Sidewalks, Strip & Cure
Install Relocated Bus Stop Bench, Trash Can & Associated Signage
Prepare Roadway Subgrade with .65' Aggregate Base & Compact
Test Compaction of A.B.
A/C Paving
Grind & Overlay A/C Paving
Slurry Seal A/C Paving
Striping 1st Pass, Cure & Final Stripe
Final Clean
ALTON PKWY STREET WIDENING & U/G UTILITIES
Post Advanced Construction Notification & Street Signage
Contact Underground Dig Alert & Record Permit Number
Verify, Document & Submit Existing Conditions Prior to Start
Survey Demo Limits Prior to Start & Confirm with Contract Documents
Preconstruction Conference with City of Irvine as Required
Setup Temporary Traffic Control Measures
Setup Temporary BMP's
Sanitary Sewer Improvements
Relocate Fire Hydrants
Remove & Relocate Construction Fencing
Safe-off & Re-Route Irrigation
Remove & Salvage Signage as Applicable
Remove & Relocate Existing Low Volt Pull Box & Assoc. Cabling
Remove & Protect Existing Bus Bench, Trash Can & Associated Signage
Demo (E) Hardscapes & Landscapes
Survey (N) Curb & Gutter
Prepare Subgrade for (N) Street Widening, Curb & Gutter
Test Subgrade for Compaction
Install (N) Below Grade Signal Conduit & Associated Pull Boxes
Form (N) Curb & Gutter & EntranceApron
Survey & Record (N) Curb & Gutter Formwork - Prepour
Pour (N) Curb & Gutter, Entrance Apron, Strip & Cure
Backfill & Compact Behind Curb & Gutter, Entrance Apron
Survey Subgrade for Sidewalks
Install (N) Posts & Signage as Applicable
Form Sidewalks
Pour Sidewalks, Strip & Cure
Install Relocated Signage
Prepare Roadway Subgrade with .65' Aggregate Base & Compact
es Campus Expansion Remaining Level of Effort
lding B Concrete - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work
Activity ID Activity Name Dur Current Start Current Finish
Aug Sep Oct Nov Dec
1S-20290 Test Compaction of A.B.
1S-20300 A/C Paving 1 12/02/19 12/02/19
1S-20310 Grind & Overlay A/C Paving 2 12/03/19 12/04/19
1S-20320 Slurry Seal A/C Paving 2 12/05/19 12/06/19
1S-20330 Striping 1st Pass, Cure & Final Stripe 2 12/09/19 12/10/19
1S-20340 Final Inspections 10 12/11/19 12/24/19
10 12/26/19 01/09/20
Project Start 09/10/18 Page 18 of 18 Edwards Lifescience
Project Finish 07/23/20 TASK filter: All Activities Proposal Schedule with Buil
Data Date 09/01/18
Run Date 10/05/18 Snyder L
2019 2020
c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Test Compaction of A.B.
A/C Paving
Grind & Overlay A/C Paving
Slurry Seal A/C Paving
Striping 1st Pass, Cure & Final Stripe
Final Inspections
es Campus Expansion Remaining Level of Effort
lding B Concrete - 10/05/2018 Actual Level of Effort
Langston Remaining Work
Critical Remaining Work