MECHANICAL UNIT
Progress Report

July 2022

Pasukan Projek Khas 2, JKR Malaysia

Ir. JASMI BIN WAHAB
PENGARAH PEMBINAAN, JUSA C

Ir. ABDULDAN BIN ADTONG
Jurutera Mekanikal Penguasa Kanan, J54

SABAH SARAWAK

EDITH G KULINTIN MOHD HERMAN BIN ABU BAKAR
Jurutera Mekanikal, J41 Jurutera Mekanikal Kanan, J48

ANTHONY TIMBAH MARITHA DEMI ANAK JOHN
Penolong Jurutera Mekanikal Kanan, JA38 Jurutera Mekanikal, J41

MASINAH @ HELEN BINTI LATIP JOSHUA ANAK AJONG
Penolong Jurutera Mekanikal Kanan. JA36 Penolong Jurutera Mekanikal Kanan,JA36

DAVID BIN JAMES HAIRI BIN JOBLI
Penolong Jurutera Mekanikal, JA29 Penolong Jurutera Mekanikal, JA29

FRANKY DICKSON
Penolong Jurutera Mekanikal, JA29

JOMOT @ LIMBAKOD BIN LIMPOT
Penolong Jurutera Mekanikal, JA29

LAZIMIHI BIN DIHING
Penolong Jurutera Mekanikal, JA29

TABURAN PROJEK SABAH

Tajuk Projek :

KERJA-KERJA PEMBAIKAN STRUKTUR DAN
PENYENGGARAAN BANGUNAN SERTA LAIN-LAIN KERJA
BERKAITAN DI SK PEKAN TUARAN, SABAH

KONTRAKTOR : PEMBORONG BINA BERSAMA
NO KONTRAK
TARIKH MILIK TAPAK : JKR/IP/PPK2/06/2021
TARIKH SIAP ASAL
: 25.10.2021

: 5.6.2022
EOT No.1 (26.9.2022)

TARIKH SIAP BAHARU : -
HARGA KONTRAK ASAL :
KEMAJUAN KERJA –JUL 2022 : RM 1,323,000.00
NSC MEKANIKAL :
SKOP KERJA MEKANIKAL 74% (Jadual) / 81 - +Days (Sebenar)
AIR CONDITIONING SYSTEM, :
TEMPOH SIAP : PAKEJ
KAEDAH PERLAKSANAAN :
P. PENGUASA : % Jadual % Sebenar
PELANGGAN :
PERUNDING MEKANIKAL : 80% 82%
HODT :
WPP(M) : 32 MINGGU
KOS KONTRAK MEKANIKAL :
STATUS PROJEK TERKINI: KONVENSIONAL DALAMAN

IR MOHD ZAINAZIM BIN ZAINI

KEM. PENDIDIKAN MALAYSIA

-

CAWANGAN FASILITI SENGGARAAN BANGUNAN

IR. ABDULDAN BIN ADTONG

RM 42,740.00

1. Tarikh Siap EOT No.1 – 26.9.2022

Gambar Projek Terkini
(PIC:PJ Anthony)

Tajuk Projek :

KERJA-KERJA PEMBAIKAN STRUKTUR DAN
PENYENGGARAAN BANGUNAN SERTA LAIN-LAIN KERJA
BERKAITAN DI SMK MAT SALLEH RANAU, SABAH

KONTRAKTOR : SURE REACH ENTERPRISE
NO KONTRAK : JKR/IP/CFSB/12/2020
TARIKH MILIK TAPAK : 14.5.2021
TARIKH SIAP ASAL : 23.12.2021
EOT (No.1) : 21.2.2022
TARIKH SIAP BAHARU : EOT (No.2) : 11.4.2022 % Sebenar
HARGA KONTRAK ASAL : EOT (No.3) : 16.5.2022 100%
KEMAJUAN KERJA –JUL 2022 : 23.12.2021
NSC MEKANIKAL : RM 1,326,750.00 100%
SKOP KERJA MEKANIKAL 100%, CPC 15.7.2022 100%
INTERNAL COLD-WATER : -
SYSTEM
INTERNAL SANITARY SYSTEM : % Jadual
AIR CONDITIONING SYSTEM, : 100%
TEMPOH SIAP :
KAEDAH PERLAKSANAAN : 100%
P. PENGUASA : 100%
PELANGGAN : 32 MINGGU
PERUNDING MEKANIKAL : KONVENSIONAL DALAMAN
HODT : IR. PATRICK WOON
WPP(M) : KEM. PENDIDIKAN MALAYSIA
KOS KONTRAK MEKANIKAL : -
STATUS PROJEK TERKINI: -
IR. ABDULDAN BIN ADTONG
RM 177,826.00

1. CPC telah dikeluarkan pada 15 Julai 2022.
2. Majlis Penyerahan Projek Siap telah dibuat pada 21 Julai 2022.
3. LAD telah dikenakan kepada kontraktor sebanyak RM 87.72/Hari.

Gambar Projek Terkini
(PIC:PJ Anthony)

Tajuk Projek :

KERJA-KERJA PEMBAIKAN STRUKTUR DAN
PENYENGGARAAN BANGUNAN SERTA LAIN-LAIN KERJA
BERKAITAN DI SMK TENGHILAN, TUARAN, SABAH

KONTRAKTOR : EG ENGINEERING SERVICES
NO KONTRAK
TARIKH MILIK TAPAK : JKR/IP/CFSB/300/ 2021
TARIKH SIAP ASAL
: 25.10.2021

: 22.5.2022
EOT No.1 (14.8.2022)

TARIKH SIAP BAHARU : ----
HARGA KONTRAK ASAL :
KEMAJUAN KERJA – JUL 2022 : RM 1,296,210.00
NSC MEKANIKAL :
SKOP KERJA MEKANIKAL 100% (Jadual) / 100% - Days (Sebenar)
INTERNAL COLD-WATER :
SYSTEM PAKEJ
TEMPOH SIAP :
KAEDAH PERLAKSANAAN : 100% Jadual 100% Sebenar
P. PENGUASA :
PELANGGAN : 100% 100%
PERUNDING MEKANIKAL :
HODT : 30 MINGGU
WPP(M) : KONVENSIONAL DALAMAN
KOS KONTRAK MEKANIKAL : JUVINIA AUGUSTINE ZUJIP
STATUS PROJEK TERKINI: KEM. PENDIDIKAN MALAYSIA
-
CAWANGAN FASILITI SENGGARAAN BANGUNAN
IR. ABDULDAN BIN ADTONG
RM 41,040.00

1. Kerja-Kerja Pembaikan Sistem Paip Air Dalaman telah disiapkan 100%

Gambar Projek Terkini
(PIC:PJ Anthony)

Tajuk Projek :

PEMBINAAN KOMPLEKS PEJABAT SURUHANJAYA
PENCEGAHAN RASUAH MALAYSIA (SPRM) SABAH

KONTRAKTOR : WIJAYA DAYA SDN BHD
NO KONTRAK :
TARIKH MILIK TAPAK : JKR/IP/CKUB/126/2021
TARIKH SIAP ASAL :
14 JULAI 2021

9 JANUARI 2024
130 Minggu
Tempoh Tanggungan Kecacatan:
12bln + 3bln + 14hari

TARIKH SIAP BAHARU : -
HARGA KONTRAK ASAL :
KEMAJUAN KERJA - JUN 2022 : RM 44,990,000.00
NSC MEKANIKAL :
SKOP KERJA MEKANIKAL 9% (Jadual) / 12 % -49 Days (Sebenar)
INTERNAL COLD-WATER :
SYSTEM JANGKAAN SST KELUAR AWAL JANUARI 2022
INTERNAL SANITARY SYSTEM :
FIRE PROTECTION SYSTEM : ATDA
AIR CONDITIONING SYSTEM, :
LIFT SYSTEM : RM 688,520.00 0%
TEMPOH SIAP :
KAEDAH PERLAKSANAAN : 0%
P. PENGUASA :
PELANGGAN : RM 1,155,000.00 0%
PERUNDING MEKANIKAL :
HOPT : RM 3,990,000.00 0%
WPP(M) :
KOS KONTRAK MEKANIKAL : RM 1,260.000.00 0%
STATUS PROJEK TERKINI:
N/A 130 MINGGU

KONVENSIONAL PERUNDING

Ir. JASMI BIN WAHAB

SPRM

Perwira Al-Shura Consulting Engineer Sdn Bhd

Cawangan Kerja Bangunan Am 1 (CKBA 1)

IR. ABDULDAN BIN ADTONG

RM 7,487,500.00

Gambar Projek Terkini
(PIC:PJ Anthony)

Tajuk Projek :

PENGURUSAN FASILITI DAN PENYENGGARAAN (FMM) DI
PERUMAHAN KASTAM SEPANGGAR, SABAH

KONTRAKTOR : KEJURUTERAAN PENYEJUKAN LEADING SDN
BHD

NO KONTRAK : JKR/IP/CFSB/10/2020

TARIKH MILIK TAPAK : 1 APRIL 2021

TARIKH SIAP ASAL : 30 APRIL 2024

TARIKH SIAP BAHARU : -
HARGA KONTRAK ASAL : RM 4,112,800.00
KEMAJUAN KERJA – JUN 2022 : 44% (Jadual) / 44% (Sebenar)

NSC MEKANIKAL :-

SKOP KERJA MEKANIKAL % Jadual % Sebenar

INTERNAL COLD WATER : PPM
SYSTEM

INTERNAL SANITARY SYSTEM : PPM

FIRE PROTECTION SYSTEM : PPM

AIR CONDITIONING SYSTEM, : PPM

LIFT SYSTEM : PPM

TEMPOH SIAP : 3.08 TAHUN

KAEDAH PERLAKSANAAN : KONTRAK FASILITI (FMM)

P. PENGUASA : IR. JASMI BIN WAHAB

PELANGGAN : KASTAM DIRAJA MALAYSIA

PERUNDING MEKANIKAL :-

HODT : CAWANGAN FASILITI SENGGARAAN BANGUNAN

WPP(M) : IR. ABDULDAN BIN ADTONG

KOS KONTRAK MEKANIKAL : RM 746,700.00

STATUS PROJEK : PEMBINAAN

VO. MEKANIKAL / OMISSION / RASIONALISASI:-
1. Cadangan pemasangan ACSU di Lift Motor Room
2. Penggantian ARD bagi keseluruhan lif ABID 2, 3 dan 4.
3. Pembaikan menyeluruh sistem STP termasuk pam. Panel dan tangka.
4. Penukaran Sistem Pemantauan Kebakaran Automatik Berpusat (CMS)
5. Pembaikan MFAP termasuk penggera dan pengesan kebakaran.
6. Cadangan pembaikan sistem perpaipan Hose Reel – kebocoran paip bawah tanah.

STATUS PROJEK TERKINI:
N/A

Gambar Projek Terkini
(PIC:PJ Anthony)

Tajuk Projek :

NAIKTARAF SISTEM PENYAMAN UDARA JENIS BERASINGAN
SERTA LAIN-LAIN KERJA BERKAITAN BAGI BILIK PENGINAPAN
BLOK ASRAMA KINABALU, ASRAMA MESILAU DAN ASRAMA
DANUM DI KAMPUS TADBIRAN AWAM NEGARA (INTAN) SABAH

KONTRAKTOR : PALMA VOLTAGE SDN BHD % Sebenar
NO KONTRAK : JKR/PPK2/5/2022(M) 16%
TARIKH MILIK TAPAK : 9 JUN 2022
TARIKH SIAP ASAL : 8 SEPTEMBER 2022
TARIKH SIAP BAHARU :-
HARGA KONTRAK ASAL : RM 396,180.00
KEMAJUAN KERJA : 18% (Jadual) / 16% - (Sebenar)
NSC MEKANIKAL :-
SKOP KERJA MEKANIKAL
% Jadual
Air Cooled Split Unit System : 18%
TEMPOH SIAP : 12 MINGGU
KAEDAH PERLAKSANAAN : SEBUTHARGA
P. PENGUASA : Ir. ABDULDAN BIN ADTONG
PELANGGAN : INTAN SABAH
HODT :
WPP(M) :
KOS KONTRAK MEKANIKAL : N/A
STATUS PROJEK TERKINI:

1. Kerja-Kerja Pemasangan telah dimulakan di Blok Asrama Mesilau dan Asrama Kinabalu.

Gambar Projek Terkini
(PIC:PJ Anthony)

Tajuk Projek :

NAIKTARAF SISTEM PENCEGAH KEBAKARAN DI
KAMPUS INTAN SABAH

KONTRAKTOR : TECHNOHASIL ENGINEERING SDN. BHD.
NO KONTRAK/SEBUTHARGA :
TARIKH MILIK TAPAK : JKR/PPK2/6/2022(M)
TARIKH SIAP ASAL :
TARIKH SIAP BAHARU : 22 JUN 2022
HARGA KONTRAK ASAL :
KEMAJUAN KERJA – Jun 2022 : 21 SEPTEMBER 2022
NO INDEN KERJA :
SKOP KERJA MEKANIKAL -
TEMPOH SIAP :
KAEDAH PERLAKSANAAN : RM 272,180.00
P. PENGUASA :
PELANGGAN : 25 % (Jadual) /26.64 % - (Sebenar)
HODT / PENGURUS PROGRAM :
PENYELARAS PROGRAM : JKR/PPK2/6/2022(M)
STATUS PROJEK TERKINI:
33 % Jadual 26.64 % Sebenar

12 MINGGU

SEBUTHARGA

Ir. ABDULDAN BIN ADTONG

INTAN SABAH

BFBA2, CFSB

WAN ISNIZAR BINTI WAN AHMAD

1. Kerja-kerja sedang dalam pembinaan di Blok Pentadbiran, Dewan dan Asrama Mesilau.

Gambar Projek Terkini
(PIC:PJ Anthony)

Tajuk Projek :

KERJA-KERJA PEMBAIKAN STRUKTUR DAN
PENYENGGARAAN BANGUNAN SERTA LAIN-LAIN KERJA
BERKAITAN DI SMK TUN FUAD STEPHENS, SABAH

KONTRAKTOR : LMEND INDUSTRIES SDN. BHD.
NO KONTRAK
TARIKH MILIK TAPAK : JKR/IP/CFSB/13/2020
TARIKH SIAP ASAL
: 9.3.2021

: 7.11.2021
EOT No.1

TARIKH SIAP BAHARU : 6.1.2022

HARGA KONTRAK ASAL : RM 1,326,750.00

KEMAJUAN KERJA : 100%, CPC pada 11.2.2022

NSC MEKANIKAL :-

SKOP KERJA MEKANIKAL 100% Jadual 100% Sebenar

INTERNAL COLD-WATER : 100% 100%
SYSTEM

TEMPOH SIAP : 32 MINGGU

KAEDAH PERLAKSANAAN : KONVENSIONAL DALAMAN

P. PENGUASA : IR. PATRICK WOON

PELANGGAN : KEM. PENDIDIKAN MALAYSIA

PERUNDING MEKANIKAL :-

HODT :-

WPP(M) : IR. ABDULDAN BIN ADTONG

KOS KONTRAK MEKANIKAL : RM 10,590.00

VO. MEKANIKAL / OMISSION / RASIONALISASI:-
1. Telah proses penyerahan kerja siap
2. Di bawah DLP - defect liability period

STATUS PROJEK TERKINI:
1. Projek dalam tempoh DLP.

Gambar Projek Terkini
(PIC:PJ Anthony)

Tajuk Projek :

KERJA-KERJA PENYELENGGARAAN DAN

BAIKPULIH SERTA LAIN-LAIN KERJA BERKAITAN DI

KOMPLEKS PERUMAHAN POLIS TAMAN NELLY,

KOTA KINABALU, SABAH (FASA2)

KONTRAKTOR : VH GENERAL CONSTRUCTION
NO KONTRAK :
TARIKH MILIK TAPAK : JKR/IP/PPK2/04/2021
TARIKH SIAP ASAL :
TARIKH SIAP BAHARU : 18 OKTOBER 2021
HARGA KONTRAK ASAL :
KEMAJUAN KERJA : 29 MEI 2022
NSC MEKANIKAL :
SKOP KERJA MEKANIKAL N/A
INTERNAL COLD WATER SYSTEM :
RM 1,749,000.00

99 % (Jadual) / 59 % (Sebenar)

-

54 % Jadual 48 % Sebenar

42 % 31 %

INTERNAL SANITARY SYSTEM : 66 % 65 %

TEMPOH SIAP : 32 MINGGU

KAEDAH PERLAKSANAAN : TENDER

P. PENGUASA : PN. JAETTY GHANIE

PELANGGAN : KEM. PENDIDIKAN MALAYSIA

PERUNDING MEKANIKAL : N/A

HODT : N/A

WPP(M) : IR. ABDULDAN BIN ADTONG

KOS KONTRAK MEKANIKAL : RM 210,850.00

STATUS PROJEK TERKINI:
• Kelewatan pada cold water system disebabkan kelewatan pemasangan scaffolding
• EOT No1 : 9/8/2022

Gambar Projek Terkini
(PIC:PJ Helen)

Tajuk Projek :

PENGURUSAN FASILITI DI KOMPLEKS MAHKAMAH
BARU KOTA KINABALU, SABAH.

KONTRAKTOR : STRIVE EXCELLENCE SDEN. BHD.

NO KONTRAK : JKR/IP/CFSB/08/2019
TARIKH MILIK TAPAK
TARIKH SIAP ASAL : 15 SEPTEMBER 2019
HARGA KONTRAK
KEMAJUAN KERJA : 14 SEPTEMBER 2022
NSC MEKANIKAL
SKOP KERJA MEKANIKAL : RM 7,612,608.36

: 80 % (Jadual) / 79.2 % (Sebenar)

:-

100% Jadual 100% Sebenar

ACMV :
FIRE PROTECTION SYSTEM :

LIFT SYSTEM : 100 % 100 %
:
LPG, HAND DRAYER, ROLLER
SHUTTER :

MOTORISED SYSTEM, KITCHEN
HOOD, MEC. ABOVE CEILING

TEMPOH SIAP : 3 TAHUN
KAEDAH PERLAKSANAAN : TENDER

P. PENGUASA : PENGARAH PEMBINAAN, PPK2
PELANGGAN : MAHKAMAH PERSEKUTUAN MALAYSIA,

BAHAGIAN PENGURUSAN ISTANA KEHAKIMAN

HODT : N/A
WPP(M) : IR. ABDULDAN BIN ADTONG
KOS KONTRAK MEKANIKAL : RM 1,792,800.00

STATUS PROJEK TERKINI:
• Kontrak Tamat pada September 2022

Gambar Projek Terkini
(PIC:PJ Helen)

Tajuk Projek :

CADANGAN MEMBINA SATU BLOK BANGUNAN PENTADBIRAN,
DEWAN SERBAGUNA DAN AUDITORIUM DI INSTITUT PENDIDIKAN
GURU KAMPUS GAYA (FASA 2) KOTA KINABALU, SABAH.

KONTRAKTOR : ZBN GROUP HOLDINGS SDN. BHD.
NO KONTRAK :
TARIKH MILIK TAPAK : KPM/BP/2019/3
TARIKH SIAP ASAL :
10 JUN 2019

15 MAC 2021
EOT 1 – 51 HARI (Force majeure-PKP)
EOT 2 – 63 HARI (PKP)
EOT 3 – 142 HARI (PKP 2.0)
Eot 4 – 60 HARI (PKP 3.0)

TARIKH SIAP BAHARU : 25 JANUARI 2022
HARGA KONTRAK ASAL :
KEMAJUAN KERJA – JUN 2021 : RM 58,812,736.33
NSC MEKANIKAL :
SKOP KERJA MEKANIKAL 100% (Jadual) / 100 % (Sebenar)
INTERNAL COLD WATER SYSTEM :
-

% Jadual % Sebenar

INTERNAL SANITARY SYSTEM : 100% 100%
FIRE PROTECTION SYSTEM :
AIR CONDITIONING SYSTEM : 21 BULAN
LIFT SYSTEM : KONVENSIONAL PERUNDING
TEMPOH SIAP : PENGARAH PEMBINAAN, PPK2
KAEDAH PERLAKSANAAN : KEM. PENDIDIKAN MALAYSIA
PEM CONSULT (EN. JORDAN 012-8283092)
P. PENGUASA : En. AHMAD JAMIL BIN JAAFAR
IR. ABDULDAN BIN ADTONG
PELANGGAN : RM 6,580,249.00

PERUNDING MEKANIKAL :

HODT :

WPP(M) :

KOS KONTRAK MEKANIKAL :

STATUS PROJEK TERKINI:
• Dalam tempoh DLP
• Dalam proses penyediaan SOFA

Gambar Projek Terkini
(PIC:PJ Helen)

Malis/Perasmian serah Projek Siap

Sesi tunjuk ajar sistem
Fire Fighting di IPG

Tajuk Projek :

PEMBINAAN RKAT TAMBAHAN PELBAGAI KELAS
KEM LOK KAWI, SABAH (REKA & BINA)

KONTRAKTOR : JAWALA CORPORATION SDN BHD
NO KONTRAK :
TARIKH MILIK TAPAK : 20 September 2021
TARIKH SIAP ASAL : 08 MAC 2022

TARIKH SIAP BAHARU : 04 OGOS 2025

HARGA KONTRAK ASAL : RM 188,171,891.00

KEMAJUAN KERJA : 3% (Jadual) / 1.8 % (Sebenar)

NSC MEKANIKAL :-

SKOP KERJA MEKANIKAL % Jadual % Sebenar

INTERNAL COLD WATER : 0% 0%
SYSTEM

INTERNAL SANITARY SYSTEM : 0% 0%

AIR CONDITIONING SYSTEM, : 0% 0%

TEMPOH SIAP : 178 MINGGU

KAEDAH PERLAKSANAAN : SEBUTHARGA

P. PENGUASA : Ir. PATRICK BASUN

PELANGGAN : KEMENTERIAAN PERTAHANAN MALAYSIA

HODT : N/A

WPP(M) : IR. ABDULDAN BIN ADTONG

KOS KONTRAK MEKANIKAL : RM-

STATUS PROJEK TERKINI:
• Menunggu kelulusan Lukisan Arkitek daripada HODT (A) untuk membolehkan lukisan Mekanikal

dibuat perubahan dan akan dihantar ke HODT(M) untuk kelulusan.

Gambar Projek Terkini
(PIC:PJ Helen)

Tajuk Projek :

PENGGANTIAN PENUH SEKOLAH MENENGAH SAINS SABAH, DI
BUKIT PADANG, KOTA KINABALU, SABAH (REKA DAN BINA)

KONTRAKTOR : BANGKIT ENERGY & PRO LOGISTIC
(EM) SDN. BHD.
NO KONTRAK
TARIKH MILIK TAPAK : JKR/IP/CKUB/162/2021
TARIKH SIAP ASAL
TARIKH SIAP BAHARU : 1 JULAI 2021
HARGA KONTRAK ASAL
KEMAJUAN KERJA – JUN 2022 : 26 JULAI 2024
NSC MEKANIKAL
SKOP KERJA MEKANIKAL : 26 JULAI 2026
ACMV
FIRE FIGHTING & PROTECTION SYST. : RM 74,789,899.00
INTERNAL COLD WATER & SANITARY
PLUMBING SYSTEM : 5% (Jadual) / 8% + 26 DAYS (Sebenar)
KITCHEN EQUIPMENT
EMERGENCY SHOWER & EYE WASHLIFT : N/A
SYSTEM
FUME CUPBORD % Jadual % Sebenar
MAINTENANCE DURING DLP
TEMPOH SIAP : 0% 0%
KAEDAH PERLAKSANAAN
P. PENGUASA : 0% 0%
PELANGGAN
: 0% 0%

: 0% 0%
: 0% 0%

: 0% 0%

: 0% 0%

: 21 BULAN

: REKA DAN BINA/TENDER TERBUKA

: PENGARAH PEMBINAAN, PPK2

: KEM. PENDIDIKAN MALAYSIA

PERUNDING MEKANIKAL : PETAREKA PERUNDING
Ir. DANNY WONG-0198811187
HODT Cik AZIRA MISMAN-016-8025334

WPP(M) : Ir. ISFANIZAM BIN ISMAIL
KOS KONTRAK MEKANIKAL 019-302 7070
STATUS PROJEK TERKINI:
• Pejabat tapak telah disiapkan : IR. ABDULDAN BIN ADTONG
• Kerja-kerja tanah (piling , MLT)
: RM 2,130,130.00

Gambar Projek Terkini
(PIC:PJ Helen)

Perspective view of SMSS

Laluan Sewerage

Tajuk Projek :

PENGURUSAN FASILITI DAN PENYELENGGARAAN (FMM) DI

PEJABAT BAHARU MENARA KASTAM SABAH, JALAN UMS, KOTA

KINABALU, SABAH.

.

KONTRAKTOR : FINCHO SDN. BHD

NO KONTRAK : JKR/IP/CFSB/48/2021

TARIKH MILIK TAPAK : 1 APRIL 2021
TARIKH SIAP ASAL : 30 APRIL 2024
HARGA KONTRAK : RM 4,049,200.00
KEMAJUAN KERJA : 37.84% (Jadual) / 37.84 % (Sebenar)
NSC MEKANIKAL :-

SKOP KERJA MEKANIKAL % Jadual % Sebenar

ACMV :

MECHANICAL ABOVE CEILING :

BMS, HAND DRAYER, ROLLER SHUTTER :

FIRE FIGHTING : 36 % 36 %
LIFT SYSTEM :

RAINWATER HARVESTING :

SEWERAGE TREATMENT AND PUMPING :
STATION

COLD WATER AND BOOSTER PUMP :

TEMPOH SIAP : 3.08 TAHUN / 37 BULAN

KAEDAH PERLAKSANAAN : TENDER

P. PENGUASA : PENGARAH PEMBINAAN, PPK2

PELANGGAN : JABATAN KASTAM DIRAJA MALAYSIA
ZON SABAH

HODT : N/A

WPP(M) : IR. ABDULDAN BIN ADTONG

KOS KONTRAK MEKANIKAL : RM 914,310.00

STATUS PROJEK TERKINI:
• 13 FCA Mekanikal telah diluluskan dan telah dimaklumkam secara rasmi kepada kontraktor fm.

Gambar Projek Terkini
(PIC:PJ Helen)

Tajuk Projek :

KERJA-KERJA NAIKTARAF BANGLO NO.2 SERTA LAIN-LAIN KERJA
BERKAITAN DI PANGKALAN TLDM SEPANGGAR KOTA KINABALU,
SABAH.

KONTRAKTOR : LINDUNG ENTERPRISE
NO KONTRAK :
TARIKH MILIK TAPAK : 20 September 2021
TARIKH SIAP ASAL : 21 Februari 2022

TARIKH SIAP BAHARU : 21 FEBRUARI 2022

HARGA KONTRAK ASAL : RM 424,210.00

KEMAJUAN KERJA : 40 % (Jadual) / 40 % (Sebenar)

NSC MEKANIKAL : KONTRAKTOR PAKAR MEKANIKAL BELUM
DILANTIK

SKOP KERJA MEKANIKAL % Jadual % Sebenar

INTERNAL COLD WATER : 35% 35%
SYSTEM

INTERNAL SANITARY SYSTEM : 35% 35%

AIR CONDITIONING SYSTEM, : 1% 1%

TEMPOH SIAP : 22 MINGGU

KAEDAH PERLAKSANAAN : SEBUTHARGA

P. PENGUASA : Ir. PATRICK BASUN

PELANGGAN : PANGKALAN TLDM KOTA KINABALU

PERUNDING MEKANIKAL : N/A

HODT : N/A

WPP(M) : IR. ABDULDAN BIN ADTONG

KOS KONTRAK MEKANIKAL : RM 30, 130.00

STATUS PROJEK TERKINI:
• EOT No.1: 19/7/2022

Gambar Projek Terkini
(PIC:PJ Helen)

Perspective view of TLDM Banglo No,.2

Tajuk Projek :

CADANGAN PEMBINAAN OPERASI HADAPAN (FOB)
DI PULAU MABUL, SEMPORNA, SABAH

KONTRAKTOR : HARTAMAS BORNEO SDN. BHD.
NO KONTRAK : JKR/IP/CKUB/221/2020
TARIKH MILIK TAPAK : 04 JANUARI 2021
TARIKH SIAP ASAL : 13 JANUARI 2024

TARIKH SIAP BAHARU :-

HARGA KONTRAK ASAL : RM 41,550,200.00

KEMAJUAN KERJA -JUN 2022 : 25.00% (Jadual) / 23.8% (Sebenar)

NSC MEKANIKAL : SUASA CHEM SDN (KITCHEN & LPG)

KOS KONTRAK MEKANIKAL : RM 360,000.00

NSC MEKANIKAL : MKAP BINA SDN. BHD (SISTEM PENYAMAN UDARA,
SISTEM PENCEGAH KEBAKARAN & SISTEM BEKALAN
MINYAK (BFI))

KOS KONTRAK MEKANIKAL : RM4,087,680.00

SKOP KERJA MEKANIKAL % Jadual % Sebenar

INTERNAL COLD WATER SYSTEM : 0.1

INTERNAL SANITARY SYSTEM : 15

FIRE PROTECTION SYSTEM :

AIR CONDITIONING SYSTEM, :

BULK FUEL :

KITCHEN & LPG :

TEMPOH SIAP : 36 BULAN

KAEDAH PERLAKSANAAN : KONVENSIONAL PERUNDING

P. PENGUASA : IR. JASMI BIN WAHAB

PELANGGAN : KEMENTERIAN DALAM NEGERI

PERUNDING MEKANIKAL : CAW. KEJURUTERAAN MEKANIKAL JKR

HODT :-

WPP(M) : IR. ABDULDAN BIN ADTONG

VO. MEKANIKAL / OMISSION / RASIONALISASI:-

1. Perubahan Sistem Penyaman udara di Bilik Pusat Komunikasi. Kelulusan Perubahan Kerja (KPK) No.
1 telah dimajukan kepada ukurbahan pada 4 Mac 2022 berjumlah RM7,200.00.

2. QS Consultant mohon agar lukisan perubahan rekabentuk penyaman udara dikemukan untuk tujuan
KPK.

Gambar Projek Terkini
(PIC:PJ David)

ISU DI TAPAK:
1. Shop drawing untuk sistem perpaipan dalaman belum diterima (Bangunan utama).
2. Shop drawing untuk sistem perpaipan sanitary diterima (Bangunan Utama) dengan komen.
3. Shop drawing dari NSC mekanikal belum diterima.
4. Pindaan Reka bentuk Sistem Penyaman Udara.
5. Bilangan tangki air simpanan di Blok Kediaman dan Blok Pentadbiran bercanggah BQ dan lukisan.
6. Kelulusan system pencegah kebakaran daripda pihak BOMBA.
7. ATI untuk system dapur belum diterima.
8. Pemasangan paip sistem sanitari di Blok Penempatan di bawah beam menyebabkan kedalaman

pemasangan gully trap melebihi daripada spesifikasi di dalam lukisan.

STATUS PROJEK TERKINI:
1. Dibincangkan dalam mesyuarat tapak dan teknikal dan surat telah dikeluarkan.
2. Surat telah dikeluarkan pada 18 Mac 2022 (Lukisan ditolak)
3. Dokumen masih dalam semakan CKM.
4. Lukisan pindaan rekabentuk sistem penyaman udara telah diterima. KPK telah dihantar ke QS

PPK2.
5. Telah dibincangkan dalam mesyuarat teknikal bil.1/2022. Kapasiti tangki merujuk berdasarkan

kapasiti dalam lukisan pembinaan.
6. Menunggu shop drawing yang telah diluluskan utk dikemukakan kepada BOMBA untuk kelulusan.
7. Menunggu shop drawing yang telah diluluskan utk dikemukaka untuk kelulusan ATI.
8. NCP telah dikeluarkan.

Text

Tajuk Projek :

TAWARAN SEMULA KERJA-KERJA PENGUBAHSUAIAN
BANGUNAN UNTUK DIJADIKAN ONE STOP FAMILY CENTER
LPPKN NEGERI SABAH

KONTRAKTOR : HB WAJA SDN. BHD.

NO KONTRAK : JKR/IP/CKUB/74/2017

TARIKH MILIK TAPAK : 18 OKTOBER 2021

TARIKH SIAP ASAL : 16 OKTOBER 2022

TARIKH SIAP BAHARU :-

HARGA KONTRAK ASAL : RM 2,221,738.10

KEMAJUAN KERJA : 73% (Jadual) / 57% (Sebenar)

NSC MEKANIKAL : Kerja Pakej

SKOP KERJA MEKANIKAL 15% Jadual 0% Sebenar

INTERNAL COLD WATER SYSTEM :
- Water Pump
- Water Tank 80% 50%

INTERNAL SANITARY SYSTEM : 80% 50%

FIRE PROTECTION SYSTEM :
- Fire Alarm System
- Fire Extinguiaher 50% 10%

AIR CONDITIONING SYSTEM :
- VRV System
- Exhaust Fan 20% 0%

TEMPOH SIAP : 12 BULAN

KAEDAH PERLAKSANAAN : KONVENSIONAL

P. PENGUASA : IR. JASMI BIN WAHAB

PELANGGAN : LEMBAGA PENDUDUK DAN PEMBANGUNAN

PERUNDING MEKANIKAL : IN HOUSE

HODT : PASUKAN PROJEK KHAS 2

WPP(M) : IR. ABDULDAN BIN ADTONG

KOS KONTRAK MEKANIKAL : RM542,164.00

ISU DI TAPAK:
1. Lukisan kerja (shop drawing)
2. Borang kelulusan bahan.
3. Pemasangan sanitary pipe di ground floor.
4. Tidak ada dalam BQ untuk pasangan Plinth penyaman udara.

TINDAKAN /STATUS:
1. Shop drawing Internal cold water & Sanitary dalam (diterima kedua kali pada (8/4/2022).
2. Rujuk jadual kelulusan bahan.
3. Mesyuarat koordinasi, kontraktor perlu kemukakan method statement pemasangan.
4. Telah dibincangkan, dipasang dengan remeasurement harga pada tapak yang telah dibuat.

Gambar Projek Terkini
(PIC:PJ David)

Tajuk Projek :

PEMBINAAN MAKMAL KOMPUTER SABAH (MENYIAPKAN BAKI
KERJA BAGI 37 MAKMAL KOMPUTER) ZON 2 :
SK SUMANDI SEMPORNA, SK BALIMBANG SEMPORNA, SK
GELAM-GELAM SEMPORNA, SK SISIPAN SEMPORNA, SK
EGANG-EGANG SEMPORNA, SK SULABAYAN SEMPORNA, SK
HAMPALAN SEMPORNA, SK TANGKALLOH SEMPORNA, SK
TERUSAN BARU SEMPORNA DAN SK TERUSAN TENGAH
SEMPORNA.

KONTRAKTOR : SYARIKAT GVC INDAH SDN. BHD.
NO KONTRAK : JKR/IP/CKUB/98/2020
TARIKH MILIK TAPAK : 16 JUN 2020
TARIKH SIAP ASAL : 13 JUN 2022

TARIKH SIAP BAHARU : 13 JUN 2022

HARGA KONTRAK ASAL : RM 23,688,338.00

HARGA KONTRAK SEMASA : RM 24,098,896.16

KEMAJUAN KERJA - OKTOBER : 100% (Jadual) / 100% (Sebenar)
2021

NSC MEKANIKAL :-

SKOP KERJA MEKANIKAL % Jadual % Sebenar

FIRE PROTECTION SYSTEM : 100 100

AIR CONDITIONING SYSTEM, : 100 100

TEMPOH SIAP : 104 MINGGU

KAEDAH PERLAKSANAAN : KONVENSIONAL

P. PENGUASA : IR. JASMI BIN WAHAB

PELANGGAN : KEMENTERIAN PENDIDIKAN MALAYSIA

PERUNDING MEKANIKAL : CAW. KEJURUTERAAN MEKANIKAL JKR

HODT :

WPP(M) : IR. ABDULDAN BIN ADTONG

KOS KONTRAK MEKANIKAL : RM 434,482.00

VO. MEKANIKAL / OMISSION / RASIONALISASI:-
1. RM7,280.00 ~ Perubahan rekabentuk sistem penghawa dingin disebabkan oleh bekalan elektrik
2. Pelarasan harga kontrak No. 1 telah dikemukakan pada QS berjumlah RM171,250.00 pada 4 Julai

2022.

STATUS PROJEK TERKINI:
Dalam tempoh kecacatan.

Gambar Projek Terkini
(PIC:PJ David)

Tajuk Projek :

MENYIAPKAN BAKI KERJA-KERJA PEMBAIKAN KECACATAN
UNTUK PROJEK CADANGAN PEMBINAAN SEKOLAH
PEDALAMAN (ZON SABAH) (REKA DAN BINA)-ZON1

KONTRAKTOR : MILURE SOLUTION
NO KONTRAK : JKR/IP/CKP/1/2021
TARIKH MILIK TAPAK : 17 SEPTEMBER 2021
TARIKH SIAP ASAL : 16 MAC 2022

TARIKH SIAP BAHARU :-
HARGA KONTRAK ASAL
HARGA KONTRAK SEMASA : RM 1,633,789.00
KEMAJUAN KERJA
NSC MEKANIKAL : RM -
SKOP KERJA MEKANIKAL
SISTEM PERPAIPAN AIR : Jadual : 100% Sebenar: 100%
DALAMAN DAN SANITARI
TEMPOH SIAP :-

% Jadual % Sebenar

: 100 98%

: 6 BULAN

KAEDAH PERLAKSANAAN : IN-HOUSE

P. PENGUASA :

PELANGGAN : KEMENTERIAN PELAJARAN MALAYSIA

PERUNDING MEKANIKAL : UNIT MEKANIKAL PPK2

HODT :-

WPP(M) : IR. ABDULDAN BIN ADTONG

ISU DI TAPAK:
1. SK Malubang ~ Sebuah rumah yang tidak dilakukan pembaikan disebabkan kerosakan pada

struktur bangunan.
2. SK Mangkapon ~ Pam tandas sekolah tidak dipasang disebabkan tidak ada pemasangan rain

harvesting.

STATUS PROJEK TERKINI:
1. Pelarasan harga kontrak.

Gambar Projek Terkini
(PIC:PJ David)

Tajuk Projek :

CADANGAN PEMBINAAN PANGKALAN MARITIM AGENSI
PENGUATKUASAAN MARITIM MALAYSIA (APMM)
SEMPORNA, SABAH

KONTROKTOR : PRINSIP HASIL SDN BHD

NO. KONTRAK : JKR/IP/CKBU/18/2020

TARIKH MILIK TAPAK : 30hb. JAN, 2020

TARIKH SIAP ASAL : 29hb. JAN, 2022

EXTENSION OF TIME (EOT) : (1). 21. 03. 2022 (2). 23. 05. 2022
(3). 22. 08. 2022 (4). 21. 10. 2022

TARIKH SIAP BAHARU : 25hb Jan, 2022

HARGA KONTRAK ASAL : RM65,282,936.00

KEMAJUAN : JADUAL = 50.00 % SEBENAR = 34.00 % (-74 Hari)

TEMPOH SIAP : 24 BULAN

KAEDAH PELAKSANAAN : KONVENTIONAL PERUNDING

PEGAWAI PENGUASA : Ir. JASMI BIN WAHAB

PELANGGAN : ESSCOM / KEM. DALAM NEGERI

PERUNDING MEKANIKAL : JURUTERA PERUNDING INTELEK SDN BHD

HODT : Ir. AZIZAH BINTI KASSIM

WPP(M) : Ir, ABDULDAN BIN ADTONG

KOS KONTRAK MEKANIKAL : RM3,186.100.00

BIL. SKOP MEKANIKAL ( %)

1. COLD WATER & SANITARY PLUMBING SYSTEM
- PRINSIP HASIL SDN BHD (RM580.000.00)

2. FIRE PROTECTION SYSTEM
- ARIF NIAGA RESOURCES SDN BHD (RM949,300.00)

3. AIR CONDITIONING SYSTEM
- KHINAS RESOURCES SDN BHD (RM1,289,800.00)

4. LIFT SYSTEM
- SWORD ELEVATOR SDN BHD (RM367,000.00)

5. BULK FUEL INSTALLATION SYSTEM
- ZM GLOBAL TRADING (RM2,003,000.00)

Gambar Projek Terkini
(PIC:PJ Franky)

ISU DITAPAK:
(1). Dokumen V.O Transfer pump – Telah diluluskan

(2). V.O struktur plinth tangka hydren dan hose reel. Perlu semakan semula, terdapat dalam bq

mekanikal.

STATUS PROJEK TERKINI:

- Konvensional Perunding (Perunding JPI) (Tarikh Siap 21 Okt. 2022)

- NSC Mekanikal telah dilantik.

(i). FIRE PROTECTION SYSTEM (Arif Niaga Resources S/B) - Dalam proses kelulusan

bahan dan lukisan pembinaaan.

(ii). AIR CONDITIONING SYSTEM (Khinas Resources S/B) - Dalam proses kelulusan bahan dan

lukisan pembinaaan.

(iii). LIFT SYSTEM (Sword Elevator Sdn Bhd) Kelulusan bahan dan lukisan pembinaaan telah

selesai.

BULK FUEL INSTALLATION SYSTEM (ZM Global Trading) - Dalam proses kelulusan bahan dan

lukisan pembinaaan.

Tajuk Projek :

KERJA-KERJA PENYELENGGARAAN DAN BAIKPULIH
BANGUNAN SERTA LAIN-LAIN KERJA BERKAITAN DI
PERUMAHAN BATALION 16 PGA KUDAT, SABAH

KONTROKTOR : PEMBORONG IKHLAS
NO. KONTRAK : JKR/PPK2/02/2020
TARIKH MILIK TAPAK : 18hb. OKT, 2021
TARIKH SIAP ASAL : 29hb. MEI, 2022
EXTENSION OF TIME (EOT) : - E.O.T No. 1 = 11/08/2022

TARIKH SIAP BAHARU : 11hb. OGO, 2022
HARGA KONTRAK ASAL : RM1,862,915.00
KEMAJUAN (28. 05. 2022) : JADUAL = 90.00 % SEBENAR = 90.00 %

SKOP MEKANIKAL ( %)
1. INTERNAL COLD WATER PLUMBING SYSTEM
2. INTERNAL SANITARY PLUMBING SYSTEM
3. BOOSTER PUMP SYSTEM

Sub Kontraktor Pakar (M) : Success Enterprise (RM288.800.00)

TEMPOH SIAP : 32 MINGGU

KAEDAH PELAKSANAAN : KONVENTIONAL

PEGAWAI PENGUASA : JAK (J48)

PELANGGAN : KEM. DALAM NEGERI

PERUNDING MEKANIKAL : UNIT MEKANIKAL PPK2

HODT : UNIT MEKANIKAL PPK2

WPP(M) : Ir, ABDULDAN BIN ADTONG

KOS KONTRAK MEKANIKAL : RM288.800.00

V.O / RASIONALISASI MEKANIKAL:
(1). Rasionalisasi Harga Kontrak Skop Kerja Mekanikal pada Mac, 2022
(2). Cadangan kerja tambahan untuk perkara berikut:

(a). Paip bekalan air dari pum ke tangka simpanan atas ( 1 lot).
(b). Tangki kapasiti 100gallon di rumah teres (5 unit)

Gambar Projek Terkini
(PIC:PJ Franky)

ISU DITAPAK:
(1). Pihak kontraktor bercadang untuk menukar booster pump system dari kawalan electrod ke
VSD. Surat rasmi belum dikemukakan.
(2). Pelanggan memohon tambahan kerja: manifold/ header di semua blok apartment (36 unit).
Menganti perpaipan sanitari di 22 unit 1st floor. Mengganti ball float valve c/w copper ball di suction
tank sedia ada.

STATUS PROJEK TERKINI:
(1). (a). Memo ke unit awam telah dikeluarkan supaya kerja dapat di laksanakan sebagai kerja
tambahan sekiranya skop tiada dalam skop awam.
(1). (b). Surat permohonan tambahan tangki di rumah teres telah dikeluarkan oleh pihak
pelanggan.

Tajuk Projek :

PEMBINAAN GANTIAN 12 BD DAN LAIN-LAIN
KEMUDAHAN DI SMK WALLACE BAY, TAWAU, SABAH

KONTRAKTOR : KK SUCCESS VISION SDN BHD
NO. KONTRAK : JKR/PPK2/02/2020
TARIKH MILIK TAPAK : 21hb. DIS, 2021
TARIKH SIAP ASAL : 18hb. DIS, 2023
EXTENSION OF TIME (EOT) : E.O.T No.

TARIKH SIAP BAHARU : 18hb DIS, 2023

HARGA KONTRAK ASAL : RM18,191,076.80

KEMAJUAN (25. 03. 2022) : JADUAL = 10% SEBENAR = 4%

SKOP MEKANIKAL ( %)
1. SISTEM BEKALAN AIR DAN SANITARI DALAMAN
Sub Kontraktor Pakar (M) :

2. SISTEM PENYAMAN UDARA DAN PENGUDARANN MEKANIKAL
Sub Kontraktor Pakar (M) :

- KEMAJUAN : J=00.00%, S=00.00%, STATUS -/+ 00 HARI

3. SISTEM PENCEGAH KEBAKARAN DAN PAM
Sub Kontraktor Pakar (M) :

TEMPOH SIAP : 104 MINGGU

KAEDAH PELAKSANAAN : KONVENTIONAL PERUNDING

PEGAWAI PENGUASA : PENGARAH PEMBINAAN PPK 2

PELANGGAN : KEM. PENDIDIKAN MALAYSIA

PERUNDING MEKANIKAL : JURUPERUNDING M&E NTM (S) SDN BHD

HODT : Ir.

WPP(M) : Ir, ABDULDAN BIN ADTONG

KOS KONTRAK MEKANIKAL : RM XXX,XXX.00

ISU DITAPAK:

(1). Kontraktor NSC bagi Sistem Penyaman Udara telah dilantik.

(2). Keputusan J/K Sebut harga NSC Sistem Pencegah Kebakaran telah dihantarn ke HODT
Mekanikal untuk tindakan lanjut – Tawaran Semula

Gambar Projek Terkini
(PIC:PJ Franky)

STATUS PROJEK TERKINI:

- Konvensional Perunding

- Peringkat Penyediaan S/ Harga

NCS oleh Jurutera Perunding M&E NTM (S) S/B

(1). Fire fighting Fighting - (HR + Water transfer pumping system)

(2). Air Conditioning - (Split Unit)

- Perpaipan air dalaman dan sanitari dalaman dilaksanakan oleh kontraktor utama.

Tajuk Projek :

NAIKTARAF HOSPITAL TAWAU, TAWAU SABAH
(REKA & BINA)

KONTROKTOR : SRI ESBINA SDN BHD
NO. KONTRAK
TARIKH MILIK TAPAK : JKR/IP/CKBU/74/2017
TARIKH SIAP ASAL
EXTENSION OF TIME (EOT) : 30hb. MEI, 2017

TARIKH SIAP BAHARU : 25hb. MEI, 2020
HARGA KONTRAK ASAL
KEMAJUAN (8hb. April, 2022) : (1). 25. 12. 2020 (2). 11. 02. 2021
Bil (A). Mechanical Works = 47% (3). 15. 04. 2021 (4). 13. 05. 2021
(5). 24. 09. 2021 (6). 08. 04. 2022
(7). 08. 04. 2022 (8). 00. 12. 2022

: 31hb Dec, 2022

: RM210,988,00.00

: JADUAL = 74 % SEBENAR = 73 %

1. Air Conditioning and Mechanical Ventilation System (RM16,800,000.00)

2. Internal Cold Water Plumbing (RM1,488,500.00)

3. Heat Pumps, Boilers etc. / Hot Water Reticulation System (RM2,000.000.00)

4. Internal Sanitary and Waste Water System (RM593,000.00)

5. Fire Protection Systems (RM 3,662,561.00)

6. Building Supervisory System (RM1,236,800.00)

7. Lifts and Dumbwaiters System (RM4,730,000.00)

Bil (B). Medical Equipment Related To Mechanical = 36%
1. Sterilizers and Associated Equipment (RM 4,085,748.00)
2. Dental Unit & Associated Equipment (RM1,988,766.00)
3. Laboratory Equipment (RM347,600.00)
4. Reverse Osmosis Water System (RM1,848754.00)
5. Burns and Patient Handling Equipment (RM891,600.00)
6. Domestic Electricals (RM32,000.00)
7. Water Purification System (Stand Alone System) (RM104,581.00)
8. Medical Gases Pipeline Systems (RM5,979,400.00)

Gambar Projek Terkini
(PIC:PJ Franky)

VO MEKANIKAL / RASIONALISASI:
Kontraktor menuntut v.o kerja pemasangan sebuah lif.
-Mesyuarat GFA (HODT/ HOPT/ WPP) dan berkaitan pada 6/7/2022.

ISU DITAPAK:
Peralatan ACMV : Chiller & Cooling tower lewat hantar ke tapak.

STATUS PROJEK TERKINI:
(1). FAT secara online telah dilaksanakan pada 22/03/2022
(2). DOA akan dikemukakan pada 13/12/2022
-Nota: Belum Dilaksanakan
(1). FAT secara online telah dilaksanakan pada 22/03/2022
(2). DOA akan dikemukakan pada 13/12/2022
-Nota: Belum Dilaksanakan

Text

Text

Tajuk Projek :

PEMBINAAN KOMPLEKS PERUMAHAN DAN BANGUNAN
PENTADBIRAN BATALION 20, PGA BELURAN

KONTROKTOR : HAWA TEKNIK SDN BHD

NO. KONTRAK : JKR/IP/CKUB/2021

TARIKH MILIK TAPAK : 3hb. FEB, 2021

TARIKH SIAP ASAL : 10hb. DIS, 2024

EXTENSION OF TIME (EOT) : (1).
(2).
(3).

TARIKH SIAP BAHARU : 10hb DIS, 2024

HARGA KONTRAK ASAL : RM343,111,111.00

KEMAJUAN (14hb. April, 2022) : JADUAL = 4.84 % SEBENAR = 6.93 %

Bil Mechanical Works = %

1. Air Conditioning Ventilation And Exhaust Systems (RM5,740,000.00)

2. Fire Protection Systems (RM840,500.00)

3. Internal Cold Water & Sanitary Plumbing (RM4,020.000.00)

4. Kitchen Equipment & LPG Systems(RM1,240,000.00)

5. Outdoor Shooting Range Target System (5,300,000.00

6. Fuel Dispensing System (1,150.000.00)

7. Workshop Equipment System RM1,500.00.00)

ISU DITAPAK:
1. Tambahan Blok Kuarters 5-6 Blok.
2. Workshop Equipment : Overhead Crane ditukar ke Jin Crane.

STATUS PROJEK TERKINI:
1. Belum dimuktamadkan
2. Perunding HODT belum memberikan kata putus.