Gambar Projek Terkini
(PIC:JMK Herman)
KONTRAKTOR : ALAMGHIR SDN. BHD.
NO KONTRAK
TARIKH MILIK TAPAK : JKR/IP/CKUB/76/2022
TARIKH SIAP ASAL
TARIKH SIAP BAHARU : 07/4/2022
HARGA KONTRAK ASAL
KEMAJUAN KERJA - SEPT 2021 : 31/7/2024
NSC MEKANIKAL
SKOP KERJA MEKANIKAL : 31/7/2024
INTERNAL COLD WATER SYSTEM
INTERNAL SANITARY SYSTEM : RM 30,975,775.00
FIRE PROTECTION SYSTEM
AIR CONDITIONING SYSTEM : 0% (Jadual) / 0% +0 DAYS (Sebenar)
LIQUIDIFIED PETROLEUM GASES (LPG)
SYSTEM : N/A
KITCHEN EQUIPMENT
BOOSTER PUMP % Jadual % Sebenar
PORTABLE AIR COMPRESSOR & WATER JET
: 0% 0%
: 0% 0%
: 0% 0%
: 0% 0%
: 0% 0%
: 0% 0%
: 0% 0%
: 0% 0%
WASHER EXTRACTOR & TUMBLE DRYER : 0% 0%
TEMPOH SIAP : 28 BULAN
KAEDAH PERLAKSANAAN : KONVENSIONAL PERUNDING/TENDER
TERBUKA
P. PENGUASA : PENGARAH PEMBINAAN, PPK2
PELANGGAN :
KEM. PERTAHANAN (MINDEF)
PERUNDING MEKANIKAL : CH Engineering
Ir. Robert Tan Wei – 0128082338
Mustaqim – 0138085859
HODT : Ir. AZIZAH KASIM & Ir. Naguib
012-6694799
WPP(M) : Ir. Abduldan bin Adtong
KOS KONTRAK MEKANIKAL : Belum lantik NSC (Anggaran
RM500,000.00)
Tajuk Projek :
PROJEK PEMBINAAN RKAT TAMBAHAN PELBAGAI
KELAS KEM BATU 10 SIBU, SARAWAK (TENDER
SEMULA)
Gambar Projek Terkini
(PIC:JMK Herman)
STATUS PROJEK TERKINI:
N/A
KONTRAKTOR : ALAMGHIR SDN. BHD.
NO KONTRAK
TARIKH MILIK TAPAK : JKR/IP/CKUB/60/2022
TARIKH SIAP ASAL
TARIKH SIAP BAHARU : 17/3/2022
HARGA KONTRAK ASAL
KEMAJUAN KERJA - SEPT 2021 : 15/5/2024
NSC MEKANIKAL
SKOP KERJA MEKANIKAL : 15/5/2024
INTERNAL COLD WATER SYSTEM
INTERNAL SANITARY SYSTEM : RM 28,731,119.90
FIRE PROTECTION SYSTEM
AIR CONDITIONING SYSTEM : 0% (Jadual) / 0% +0 DAYS (Sebenar)
LIQUIDIFIED PETROLEUM GASES (LPG)
SYSTEM : N/A
KITCHEN EQUIPMENT
BOOSTER PUMP % Jadual % Sebenar
PORTABLE AIR COMPRESSOR & WATER JET
: 0% 0%
: 0% 0%
: 0% 0%
: 0% 0%
: 0% 0%
: 0% 0%
: 0% 0%
: 0% 0%
WASHER EXTRACTOR & TUMBLE DRYER : 0% 0%
26 BULAN
TEMPOH SIAP :
KAEDAH PERLAKSANAAN : KONVENSIONAL PERUNDING/TENDER
TERBUKA
P. PENGUASA : PENGARAH PEMBINAAN, PPK2
PELANGGAN :
KEM. PENDIDIKAN MALAYSIA
PERUNDING MEKANIKAL : Perunding CHL Sdn Bhd
Ir. Mohd Dzulasri bin Hipeny
HODT
WPP(M) : Ir. ZAINI & Pn. Ernawati
KOS KONTRAK MEKANIKAL
: Ir. Abduldan bin Adtong
STATUS PROJEK TERKINI:
N/A : Belum lantik NSC (Anggaran
RM1,530,000.00)
Tajuk Projek :
PEMBINAAN GANTIAN 12BD, LIMA (5) UNIT RUMAH
GURU DAN LAIN-LAIN KEMUDAHAN DI SMK SRI
SADONG, SIMUNJAN, SARAWAK
Gambar Projek Terkini
(PIC:JMK Herman)
KONTRAKTOR : BLACKFOX ENGINEERING SDN. BHD.
NO KONTRAK : JKR/IP/CKUB/231/2020
TARIKH MILIK TAPAK : 11 JANUARI 2021
TARIKH SIAP ASAL : 07 JANUARI 2024
EOT 1 – 07 MAC 2024
TARIKH SIAP BAHARU : 07 MAC 2024
HARGA KONTRAK ASAL : RM410,300,000.00
KEMAJUAN KERJA - SEPT 2021 : 8.17% (Jadual) / % 9.82 +15 Days (Sebenar)
NSC MEKANIKAL :-
SKOP KERJA MEKANIKAL % Jadual % Sebenar
ACMV : 10.43%
Lifts & Escalators : 0%
Medical Gases Pipeline : 0%
Fire Protection Systems : 2.25%
LPG : 0%
Building Supervisory System : 0%
Hot Water Reticulation System : 5%
Pneumatic Tube System 0%
Kitchen Equipment & Central Plating 0%
Cold Room & Associated Equipment : 0%
Internal Cold Water ; 5.53%
Internal Sanitary & Wastewater System : 14.8%
Hydrotherapy Pool System :
0%
Reverse Osmosis (RO) Water System : 0%
Medical Equipment : 0%
Audiiometry Room (ENT) : 0%
Operation and Maintenance Manuals 0%
TEMPOH SIAP
KAEDAH PERLAKSANAAN : 164 MINGGU
P. PENGUASA : REKA DAN BINA
: PENGARAH PEMBINAAN, PPK2
PELANGGAN : KEM. KESIHATAN MALAYSIA
PERUNDING MEKANIKAL : DPI KONSULT (EN. IZAIDY – 017 582 4054)
HODT : Ir. YATIM SELAMAT BIN LATIB
WPP(M) : Ir. ABDULDAN BIN ADTONG
KOS KONTRAK MEKANIKAL : RM 96,689,728.00
Tajuk Projek :
MENYIAPKAN BAKI KERJA TERBENGKALAI BAGI CADANGAN
PEMBINAAN HOSPITAL PETRAJAYA (300 KATIL) PETRAJAYA,
KUCHING, SARAWAK (REKA DAN BINA) - TENDER SEMULA
Gambar Projek Terkini
(PIC:JM Maritha)
VO. MEKANIKAL / OMISSION / RASIONALISASI:-
Belum ada perubahan kerja bagi skop mekanikal setakat ini
ISU DI TAPAK:
1) NCP M001 : Pemasangan paip sanitari di wad awam & wad VIP (Aras 7) tanpa Lukisan
Pembinaan yang diluluskan
2) NCP M002 : Pemasangan ducting ACMV di wad awam & wad VIP (Aras 7) tanpa Lukisan
Pembinaan yang diluluskan
STATUS PROJEK TERKINI:
1) Kontraktor telah dapat surat Tiada Halangan bagi Lukisan Pembinaan Paip Sanitari tetapi
belum ada edaran Lukisan pembinaan yang telah diluluskan diedarkan ke Pejabat Tapak. NCP
M001belum dapat ditutup.
2) NCP M002: Masih dalam tindakan kontraktor.
KONTRAKTOR : DASACON SDN. BHD.
NO KONTRAK : JKR/IP/CKM/88/2022
TARIKH MILIK TAPAK : 4 APRIL 2022
TARIKH SIAP ASAL : 3 APRIL 2023
TARIKH SIAP SEMASA : 3 APRIL 2023
HARGA KONTRAK ASAL : RM 2,788,420.00
KEMAJUAN KERJA - JUN 2022 : 15% (Jadual) / 12 % (Sebenar) (LEWAT 25 HARI)
NSC MEKANIKAL : TIDAK BERKENAAN
TEMPOH SIAP
KAEDAH PERLAKSANAAN : 52 MINGGU
P. PENGUASA : JKR IN-HOUSE
PELANGGAN : JURUTERA MEKANIKAL PENGUASA KANAN
PERUNDING MEKANIKAL : KEMENTERIAN KESIHATAN MALAYSIA
HODT : TIDAK BERKENAAN
WPP(UTAMA) : Ir. ZALINA BINTI MOHD YUSUF
KOS KONTRAK MEKANIKAL : MOHD HERMAN BIN ABU BAKAR
STATUS PROJEK TERKINI: : RM 2,788,420.00
N/A
Tajuk Projek :
KERJA PENGGANTIAN LIF DI HOSPITAL UMUM
SARAWAK, SARAWAK
Gambar Projek Terkini
(PIC:JM Maritha)
KONTRAKTOR : HBS ENGINEERING SDN. BHD.
NO KONTRAK : JKR/IP/CKM/226/2019
TARIKH MILIK TAPAK : 18 DISEMBER 2019
TARIKH SIAP ASAL : 21 APRIL 2021
TARIKH SIAP BAHARU : 11 JANUARI 2023
HARGA KONTRAK ASAL : RM 1,328,920.00
RM 4,553,920.00 (SEMASA)
KEMAJUAN KERJA - JUN 2022 : FASA 1 - 100% (Jadual) / 98 % (Sebenar)
FASA 2 – 87 % (Jadual) / 84 % (Sebenar) (LEWAT 24
HARI)
NSC MEKANIKAL : TIDAK BERKENAAN
TEMPOH SIAP : 36 BULAN 25 HARI
KAEDAH PERLAKSANAAN : JKR IN-HOUSE
P. PENGUASA : PENGARAH PEMBINAAN, PPK2
PELANGGAN : KEM. DALAM NEGERI MALAYSIA
PERUNDING MEKANIKAL : TIDAK BERKENAAN
HODT : BURQANUDIN HUSSAIN
WPP(M) : MOHD HERMAN BIN ABU BAKAR
KOS KONTRAK MEKANIKAL : RM 4,553,920.00
VO. MEKANIKAL / OMISSION / RASIONALISASI:-
KONTRAK ASAL
• Penggantian dua (2) unit lif di Cawangan Khas IPK Kuching berkapasiti 750KG dan berkelajuan
1.5m/s dan kerja berkaitan.
• Kerja-kerja membaiki struktur di Lift Motor Room dan kerja berkaitan.
• Kerja-kerja penggantian Genset berkapasiti 150kVA dan kerja berkaitan.
PERJANJIAN TAMBAHAN
• Penggantian lima (5) unit lif di Kuarters IPK Kuching berkapasiti min 800KG dan berkelajuan min
1.0m/s dan kerja berkaitan.
ISU DI TAPAK:
1) Fasa 1: T&c Genset
2) Fasa 1: Kerja-kerja Waterproofing Di Lift Motor Room
STATUS PROJEK TERKINI:
1)Dijadualkan pada 20 julai 2022
2) Belum dilaksanakan
Tajuk Projek :
KERJA PENGGANTIAN DUA (2) UNIT LIF DAN LAIN-
LAIN KERJA DI CAWANGAN KHAS IP POLIS
KONTINJEN SARAWAK
Gambar Projek Terkini
(PIC:JM Maritha)
KONTRAKTOR : SAMADO SDN. BHD.
NO KONTRAK
TARIKH MILIK TAPAK : KPM/BP/2019/5
TARIKH SIAP ASAL
: 27 JUN 2019
TARIKH SIAP BAHARU
HARGA KONTRAK ASAL : 26 JUN 2021
KEMAJUAN KERJA – JUN 2022 EOT 1 – 56 HARI (PKP)
NSC MEKANIKAL EOT 2 – 58 HARI (PKPB)
SKOP KERJA MEKANIKAL EOT 3 – 23 HARI (KELEWATAN MENERIMA
PLUMBING & SANITARY WORKS
FIRE PROTECTION WORKS LUKISAN PEMBINAAN PROJEK)
AIR CONDITIONING AND Eot 4 – 60 HARI (PKP 3.0)
MECHANICAL VENTILATION Eot 5 – 107 HARI (KELEWATAN MENERIMA
WORKS
KITCHEN EQUIPMENT WORKS LUKISAN PEMBINAAN ELEKTRIK PINDAAN 02 &
EXTERNAL WORKS
TEMPOH SIAP KERJA BERKAITAN KELULUSAN DARIPADA SEB)
KAEDAH PERLAKSANAAN Eot 6 – 84 HARI (ATAS ALASAN KERJA WANG
P. PENGUASA
PELANGGAN PERUNTUKAN SEMENTARA BUILT IN FURNITURE
& LAB FURNITURE)
: 19 JULAI 2022
: RM 41,775,209.71
: 98.00% (Jadual) / 97.00 % (Sebenar) -21HARI
:-
% Jadual % Sebenar
: 100% 97%
: 98.5% 88%
: 98.5% 95%
: 98% 35%
: 100% 98%
: 24 BULAN
: KONVENSIONAL PERUNDING
: PENGARAH PEMBINAAN, PPK2
: KEM. PENDIDIKAN MALAYSIA
PERUNDING MEKANIKAL : PERUNDING KAZ SDN BHD
HODT : IR. HJH AISHAH HAZLINA BINTI MD DEAN
WPP(M) : IR. ABG ASRI BIN ARIFFIN
KOS KONTRAK MEKANIKAL : RM 2,162,549.20
Tajuk Projek :
PEMBINAAN SEKOLAH BAHARU 24 BILIK DARJAH, (200)
PELAJAR ASRAMA, (24 UNIT) RUMAH GURU DAN LAIN-
LAIN KEMUDAHAN DI SEKOLAH KEBANGSAAN SAMALAJU,
BINTULU, SARAWAK
Gambar Projek Terkini
(PIC: PJ Hairi)
VO. MEKANIKAL / OMISSION / RASIONALISASI:-
1. VO – Sistem Penyaman Udara dan Pengudaraan Mekanikal untuk Bilk Mesyuarat Utama di
Komplek Sekolah (tiada perrtambahan kos dan masa)
ISU DI TAPAK:
Ketiadaan sumber bekalan air di tapak menyukarkan kerja pengujian hosereel dan riser paip di
Kompleks Sekolah & Rumah Kuarters dan ketiadaan bekalan elektrik untuk membuat pengujian
hosereel pump & water pump serta system pencegahan kebakaran automatik
STATUS PROJEK TERKINI:
Isu bekalan air & elektrik masih di dalam proses pihak berkuasa
KONTRAKTOR : PERSADA SAUJANA (M) SDN. BHD.
NO KONTRAK
TARIKH MILIK TAPAK : KPM/BP/2020/11
TARIKH SIAP ASAL
: 15 OKTOBER 2020
: 14 OKTOBER 2022
EOT 1 – 60 HARI (Force majeure-PKP)
TARIKH SIAP BAHARU : 13 DISEMBER 2022
HARGA KONTRAK ASAL : RM 12,704,344.00
KEMAJUAN KERJA - SEPT 2021 : -% (Jadual) / -% (Sebenar) % Sebenar
NSC MEKANIKAL : -
SKOP KERJA MEKANIKAL
INTERNAL COLD WATER : % Jadual
SYSTEM
INTERNAL SANITARY SYSTEM : Pindaan Jadual Perancangan
FIRE FIGHTING SYSTEM : dan Pelaksanaan masih belum
AIR CONDITIONING SYSTEM :
KITCHEN EXHAUST SYSTEM & : diluluskan kerana masih ada
LPG ulasan yang perlu dikemaskini
FUME EXTRACTION SYSTEM :
GAS MANIFOLD SYSTEM : oleh pihak kontraktor
4 POST LIFT :
COMPRESSED AIR PIPING :
TEMPOH SIAP
KAEDAH PERLAKSANAAN : 24 BULAN
P. PENGUASA : KONVENSIONAL PERUNDING
PELANGGAN : PENGARAH PEMBINAAN, PPK2
: KEM. PENDIDIKAN MALAYSIA
PERUNDING MEKANIKAL
HODT : PERUNDING MME SDN BHD
WPP(M) : Ir. Hjh. Aishah Hazlina binti Md Dean
: Ir. Abg. Mohd. Moasili b. Hj. Abg. Mohd. Nailie
KOS KONTRAK MEKANIKAL
STATUS PROJEK TERKINI: : RM599,520.00
Tajuk Projek :
MENAIKTARAF SEKOLAH MENENGAH VOKASIONAL
BINTULU KEPADA KOLEJ VOKASIONAL, BINTULU
Gambar Projek Terkini
(PIC:PJ Joshua)
SARAWAK
ACTIVITIES 2021
INTEREST 2022
EVENTS
MICS
ETC
I.E.
Lawatan kerja
Pengarah Rekabentuk CKM
Nama: Hospital Tawau, Tawau Sabah Pembinaan Bangunan Tambahan
(Reka & Bina),28 – 30/3/2022 Hospital Miri, Sarawak (Reka Dan Bina)-
Tender Semula,13/5/2022
Lawatan ke Hospital Papar bersama Pengarah Rekabentuk CKM
Lawatan Tapak Kementerian Kerja Raya ke tapak
Projek Menyiapkan Baki Kerja Terbengkalai Bagi
Cadangan Pembinaan Hospital Petrajaya (300
Katil) Petrajaya, Kuching, Sarawak (Reka & Bina) -
Tender Semula ,14 Julai 2022
Projek Hospital Petrajaya
Penyelarasan TSA bersama kontraktor dan WPP
Mekanikal di Pejabat Tapak HPJ pada 24 Jun 2022
Kerja-kerja Penggantian Lif Di Hospital Umum Sarawak
Lawatan Tapak oleh Pegawai Penguasa dan Mesyuarat
Tapak No. 2 pada 22-23 Jun 2022
Hospital Tawau, Tawau Sabah (Reka & Bina)
Lawatan KSN, KP ICU dan TKP bangunan ke Hospital Tawau
Mesyuarat Kordinasi Fasiliti Kesihatan Di Negeri Sarawak Untuk Kerja
– Kerja Mekanikal
Menyiapkan Baki Kerja Terbengkalai Bagi Cadangan Pembinaan Hospital
Petrajaya (300 Katil) Petrajaya, Kuching, Sarawak (Reka Dan Bina) -
Tender Semula (LEFT)
Projek Pembinaan Dan Penyiapan Hospital Pengajar Dan Pusak
Kesihatan Prima (Pkp) Universiti Malaysia Sarawak (Unimas), Kota
Samarahan, Sarawak (Reka Dan Bina) (RIGHT)
Tarikh: 10.1.2022
Penyerahan Fire Certificate bagi projek FM
Mahkamah KK bersama pihak BOMBA &
Mahkamah
Serahan SST kepada Projek di Intan Sabah
• Naiktaraf Sistem Penyaman Udara Jenis Berasingan Serta Lain-
lain Kerja Berkaitan Bagi Bilik Penginapan Blok Asrama Kinabalu,
Asrama Mesilau Dan Asrama Danum Di Kampus Tadbiran Awam
Negara (Intan) Sabah
• Naiktaraf Sistem Pencegah Kebakaran Di Kampus Intan Sabah
Hello!
Lawatan Pemeriksaan Premis Bagi Tujun Penguatkuasaan Akta Perkhidmatan
Bomba 1988 (Akta 341) oleh Jabatan Bomba dan Penyelamat Malaysia
(JBPM) ke Bangunan Hangar PGU, PDRM Terminal 2 Kota Kinabalu
International Airport, Sabah
Lawatan koordinasi
dengan pihak
Bomba Sabah
membincangkan
akan isu-isu
berkaitan bagi
Projek di Sabah
Penyerahan Projek Makmal Komputer Zon 1
Majlis Penyerahan Kerja-kerja Penggantian Lif PGA Sarawak
Malis Penyerahan Projek Siap bagi kerja – kerja
pembaikan struktur dan penyelenggaraan
bangunan serta lain – lain kerja berkaitan di SMK
Likas Kota Kinabalu, Sabah.
Majlis Tamat Kontrak:
Menyiapkan baki kerja bagi pengurusan fasiliti dan
penyelenggaraan (FMM) berkonsepkan comprehensive
maintaenance bagi Rumah Keluara Angkatan Tentera (RKAT)
di Pangkalan TLDM, Kota Kinabalu, Sabah
Majlis Penyerahan Projek Siap SMK Mat Salleh Ranau
Majlis Penyerahan Hospital Sri Aman II ,15 Julai 2022
Disempurnakan oleh Yg. Brs. En. Mohd Rashidi Bin Yahaya,
Timbalan Setiausaha Bahagian (TSUB) Kanan,
Kementerian Kesihatan Malaysia
KURSUS PENGENALAN
SISTEM LIF, ESCALATOR
DAN DUMBWAITER
Kursus Tertutup Sistem Mekanikal anjuran Lawatan praktikal sistem lif ke tapak bina
CREaTE JKR di JKR WP Labuan (26/7 – Projek Pembinaan Kuarters Pusat
2/8/2022) melibatkan kakitangan JKR Koreksional Labuan
Negeri/Kader/Pasukan Projek di Borneo
Testing & Commissioning
Genset bagi Kerja-kerja JPKK, Pembinaan tambahan
bangunan akademik dan fasiliti
Penggantian Lif Di Ibu Pejabat luar bagi kampus Kolej Komuniti
Tambunan, Sabah (Reka &Bina) –
Polis, Kuching ,Sarawak bersama-
Bengkel Pendaftaran &
sama Unit Elektrik PPK2 Sarawak
Pelabelan Aset
MAJLIS PECAH TANAH
Sarawak – Sabah Link Road
CREDITS: This presentation template was created by Slidesgo, including icons by
Flaticon and infographics & images by Freepik
Persahabatan Labuan VS PPK2
SELAMAT DATANG
kepada semua peserta
ROADSHOW DAN TAKLIMAT PENGGUNAAN SISTEM
APLIKASIPENGURUSAN KENDERAAN ATAS TALIAN JKR (SPaKAT)
&
LAWATAN KERJA PENGARAH REKABENTUK CAWANGAN KERJA
MEKANIKAL (CKM) JKR MALAYSIA KE PASUKAN PROJEK KHAS 2
TARIKH : 1/8/22 – 2/8/22
MASA : 8.30 PAGI – 5.00 PETANG
TEMPAT : BILIK MESYUARAT A PPK2