PPK2 Mekanikal Unit - Feb 2023

Mekanikal Unit - Progress Ebook (FEB 2023)

MECHANICAL UNIT Progress Report Sept 2022 Pasukan Projek Khas 2, JKR Malaysia


Ir. JASMI BIN WAHAB PENGARAH PEMBINAAN, JUSA C Ir. ABDULDAN BIN ADTONG Jurutera Mekanikal Penguasa Kanan, J54 SABAH Ts. EDITH G KULINTIN Jurutera Mekanikal, J41 ANTHONY TIMBAH Penolong Jurutera Mekanikal Kanan, JA38 MASINAH @ HELEN BINTI LATIP Penolong Jurutera Mekanikal Kanan. JA36 DAVID BIN JAMES Penolong Jurutera Mekanikal, JA29 FRANKY DICKSON Penolong Jurutera Mekanikal, JA29 JOMOT @ LIMBAKOD BIN LIMPOT Penolong Jurutera Mekanikal, JA29 LAZIMIHI BIN DIHING Penolong Jurutera Mekanikal FARISH BIN ADDIN Pembantu Kemahiran H19 SARAWAK MOHD HERMAN BIN ABU BAKAR Jurutera Mekanikal Kanan, J48 MARITHA DEMI ANAK JOHN Jurutera Mekanikal, J41 JOSHUA ANAK AJONG Penolong Jurutera Mekanikal Kanan,JA36 HAIRI BIN JOBLI Penolong Jurutera Mekanikal, JA29


TABURAN PROJEK SABAH


PEMBINAAN GANTIAN PENUH PEJABAT PENDIDIKAN DAERAH SIPITANG DAN LAINLAIN KEMUDAHAN MENGIKUT PIAWAI (REKA & BINA) Tajuk Projek : KONTRAKTOR : JURUBINA UTAMA SDN. BHD NO KONTRAK : JKR/IP/CKUB/195/2022 TARIKH MILIK TAPAK : 8 OGOS 2022 TARIKH SIAP ASAL : 11 OGOS 2024 TARIKH SIAP BAHARU : N/A HARGA KONTRAK ASAL : RM 10,114,496.00 KEMAJUAN KERJA : 9% (Jadual) / 10% (Sebenar) NSC MEKANIKAL : - SKOP KERJA MEKANIKAL 0% Jadual 0% Sebenar INTERNAL COLD WATER SYSTEM : 0% 0% INTERNAL SANITARY SYSTEM : 0% 0% AIR CONDITIONING SYSTEM, : 0% 0% VENTILATION FAN : 0% 0% TEMPOH SIAP : 105 MINGGU KAEDAH PERLAKSANAAN : TENDER P. PENGUASA : EN. NORRIS BIN LEONAROUS PELANGGAN : KEM. PENDIDIKAN MALAYSIA PERUNDING MEKANIKAL : PERUNDING JAYAREKA SDN. BHD. HODT : - WPP(M) : IR. ABDULDAN BIN ADTONG KOS KONTRAK MEKANIKAL : RM 0.00


Gambar Projek Terkini (PIC:JM Edith) ISU DI TAPAK: JM PPK2 memohon kemukakan calon RE/IOW Mekanikal mengikut keperluan. STATUS PROJEK TERKINI: Bengkel RDI akan diadakan pada 16-17 Feb 2023 di CKP, KL


CADANGAN PEMBINAAN HOSPITAL LAWAS (76 KATIL) LAWAS, SARAWAK (REKA DAN BINA) FASA 2B : KERJA BANGUNAN DAN KERJA-KERJA BERKAITAN - TENDER SEMULA Tajuk Projek : KONTRAKTOR : MCS MANAGEMENT SDN BHD NO KONTRAK : JKR/IP/CFSB/08/2019 TARIKH MILIK TAPAK : 30 JUN 2020 TARIKH SIAP ASAL : 26 DISEMBER 2023 TARIKH SIAP BAHARU : 24 FEBRUARI 2024 HARGA KONTRAK ASAL : RM 165,000,000.00 KEMAJUAN KERJA : 24.41 % (Jadual) / 25.21 % (Sebenar) NSC MEKANIKAL : J.ROGER PRESTON (MALAYSIA) SDN BHD SKOP KERJA MEKANIKAL 0 % Jadual 0 % Sebenar ACMV : 0% 0% FIRE PROTECTION SYSTEM : 0% 0% LIFT SYSTEM : 0% 0% INTERNAL HOT/COLD WATER SYSTEM : 0% 0% INTERNAL SANITARY SYSTEM : 0% 0% TEMPOH SIAP : 232.1 MINGGU KAEDAH PERLAKSANAAN : TENDER SEMULA P. PENGUASA : PENGARAH PEMBINAAN, PPK2 PELANGGAN : HOSPITAL LAWAS, SARAWAK PERUNDING MEKANIKAL : - HODT : JKR CKK WPP(M) : IR. ABDULDAN BIN ADTONG KOS KONTRAK MEKANIKAL : RM 1,792,800.00


Gambar Projek Terkini (PIC:JM Edith) ISU DI TAPAK: Kemukakan Shop Drawing yang telah disahkan kepada Konsultan, Cold & hot water: received softcopy on 25 Jan, Fire:received softcopy on 29 Jan. STATUS PROJEK TERKINI: 1. Surat Peringatan Pertama - Pengemukaan NCP Mekanikal 001(25/11/2022) 2. Perlantikan RE dan IOW Mekanikal (30/11/2022) 3. TSA Mortuary (29/11/2022) 4. Mesyuarat Koordinasi Mekanikal Bil.1


PEMBINAAN GANTIAN PENUH 36 BILIK DARJAH, 4 UNIT RUMAH GURU DI SMK LAWAS, SARAWAK Tajuk Projek : KONTRAKTOR : MCS MANAGEMENT SDN BHD NO KONTRAK : JKR/IP/CFSB/08/2019 TARIKH MILIK TAPAK : 11 MAC 2022 TARIKH SIAP ASAL : 26 DISEMBER 2023 TARIKH SIAP BAHARU : 24 FEBRUARI 2024 HARGA KONTRAK ASAL : RM 165,000,000.00 KEMAJUAN KERJA : 4.97 % (Jadual) / 5.11 % (Sebenar) NSC MEKANIKAL : MUSE ENTERPRISE (SB116845) SKOP KERJA MEKANIKAL 0 % Jadual 0 % Sebenar ACMV : 0% 0% FIRE PROTECTION SYSTEM : 0% 0% LIFT SYSTEM : 0% 0% INTERNAL HOT/COLD WATER SYSTEM : 0% 0% INTERNAL SANITARY SYSTEM : 0% 0% TEMPOH SIAP : 232.1 MINGGU KAEDAH PERLAKSANAAN : TENDER P. PENGUASA : PENGARAH PEMBINAAN, PPK2 PELANGGAN : PPD LAWAS, SARAWAK PERUNDING MEKANIKAL : - HODT : JKR CKK WPP(M) : IR. ABDULDAN BIN ADTONG KOS KONTRAK MEKANIKAL : RM 0


Gambar Projek Terkini (PIC:JM Edith) ISU DI TAPAK: STATUS PROJEK TERKINI: Kelulusan bahan 31/1/2023 kpd WPPU


DAIF SABAH (2021)- PEMBINAAN BANGUNAN GANTIAN PENUH 12 BILIK DARJAH, PENTADBIRAN DAN LAIN-LAIN KEMUDAHAN MENGIKUT PIAWAI DI SK PEKAN KIMANIS, PAPAR, SABAH (REKA DAN BINA) Tajuk Projek : KONTRAKTOR : JT CEMERLANG SDN BHD NO KONTRAK : JKR/IP/CKUB/314/2022 TARIKH MILIK TAPAK : 23 DISEMBER 2022 TARIKH SIAP ASAL : 28 NOVEMBER 2024 TARIKH SIAP BAHARU : N/A HARGA KONTRAK ASAL : RM 16,880,500.00 KEMAJUAN KERJA : 0 % (Jadual) / 0 % (Sebenar) NSC MEKANIKAL : - SKOP KERJA MEKANIKAL 0 % Jadual 0 % Sebenar ACMV : 0% 0% FIRE PROTECTION SYSTEM : 0% 0% LIFT SYSTEM : 0% 0% INTERNAL HOT/COLD WATER SYSTEM : 0% 0% INTERNAL SANITARY SYSTEM : 0% 0% TEMPOH SIAP : 101 MINGGU KAEDAH PERLAKSANAAN : TENDER P. PENGUASA : PENGARAH PEMBINAAN, PPK2 PELANGGAN : PPD PAPAR, SABAH PERUNDING MEKANIKAL : ZLS ENGINEERING MANAGEMENT SDN. BHD HODT : JKR CKK WPP(M) : IR. ABDULDAN BIN ADTONG KOS KONTRAK MEKANIKAL : RM 0


Gambar Projek Terkini (PIC:JM Edith) ISU DI TAPAK: 1. Mesyuarat Pra-Pembinaan no.1 2. Lawatan tapak HODT BPP1 bersama Audit Negara ke bangunan yang akan dirobohkan. STATUS PROJEK TERKINI: 1. Bengkel CPM diadakan pada 6-8 Feb 2023 di RAIA Hotel, KK


KERJA-KERJA PEMBAIKAN STRUKTUR DAN PENYENGGARAAN BANGUNAN SERTA LAIN-LAIN KERJA BERKAITAN DI SK PEKAN TUARAN, SABAH Tajuk Projek : KONTRAKTOR : PEMBORONG BINA BERSAMA NO KONTRAK : JKR/IP/PPK2/06/2021 TARIKH MILIK TAPAK : 25.10.2021 TARIKH SIAP ASAL : 5.6.2022 TARIKH SIAP BAHARU : 5.10.2022 HARGA KONTRAK ASAL : RM 1,323,000.00 KEMAJUAN KERJA : 100% (Jadual) / - +Days (Sebenar) NSC MEKANIKAL : PAKEJ SKOP KERJA MEKANIKAL % Jadual % Sebenar AIR CONDITIONING SYSTEM, : 100% 100% TEMPOH SIAP : 32 MINGGU (50 MINGGU) KAEDAH PERLAKSANAAN : KONVENSIONAL DALAMAN P. PENGUASA : JAETTY GHANIE PELANGGAN : KEM. PENDIDIKAN MALAYSIA PERUNDING MEKANIKAL : - HODT : CAWANGAN FASILITI SENGGARAAN BANGUNAN WPP(M) : Ir. ABDULDAN BIN ADTONG KOS KONTRAK MEKANIKAL : RM 42,740.00 STATUS PROJEK TERKINI: 1. PROJEK TELAH SIAP SEPENUHNYA. PENYERAHAN PROJEK TELAH DIBUAT PADA 5.10.2022. 2. DLP pada 4.10.2023


Gambar Projek Terkini (PIC:PJ Anthony)


KERJA-KERJA PEMBAIKAN STRUKTUR DAN PENYENGGARAAN BANGUNAN SERTA LAIN-LAIN KERJA BERKAITAN DI SMK MAT SALLEH RANAU, SABAH Tajuk Projek : KONTRAKTOR : SURE REACH ENTERPRISE NO KONTRAK : JKR/IP/CFSB/12/2020 TARIKH MILIK TAPAK : 14.5.2021 TARIKH SIAP ASAL : 23.12.2021 EOT (No.1) : 21.2.2022 EOT (No.2) : 11.4.2022 EOT (No.3) : 16.5.2022 TARIKH SIAP BAHARU : 15.7.2022 HARGA KONTRAK ASAL : RM 1,326,750.00 KEMAJUAN KERJA : 100%, CPC 15.7.2022 NSC MEKANIKAL : - SKOP KERJA MEKANIKAL % Jadual % Sebenar INTERNAL COLD-WATER SYSTEM : 100% 100% INTERNAL SANITARY SYSTEM : 100% 100% AIR CONDITIONING SYSTEM, : 100% 100% TEMPOH SIAP : 32 MINGGU KAEDAH PERLAKSANAAN : KONVENSIONAL DALAMAN P. PENGUASA : Ir. PATRICK WOON PELANGGAN : KEM. PENDIDIKAN MALAYSIA PERUNDING MEKANIKAL : - HODT : - WPP(M) : IR. ABDULDAN BIN ADTONG KOS KONTRAK MEKANIKAL : RM 177,826.00 STATUS PROJEK TERKINI: 1. PROJEK TELAH SIAP SEPENUHNYA. PENYERAHAN PROJEK TELAH DIBUAT PADA 21 JULAI 2022. 2. DLP pada 14.7.2023


Gambar Projek Terkini (PIC:PJ Anthony)


KERJA-KERJA PEMBAIKAN STRUKTUR DAN PENYENGGARAAN BANGUNAN SERTA LAIN-LAIN KERJA BERKAITAN DI SMK TENGHILAN, TUARAN, SABAH Tajuk Projek : KONTRAKTOR : EG ENGINEERING SERVICES NO KONTRAK : JKR/IP/CFSB/300/ 2021 TARIKH MILIK TAPAK : 25.10.2021 TARIKH SIAP ASAL : 22.5.2022 EOT No.1 (14.8.2022) TARIKH SIAP BAHARU : 14.8.2022 HARGA KONTRAK ASAL : RM 1,296,210.00 KEMAJUAN KERJA : 100% (Jadual) / 100% - Days (Sebenar) NSC MEKANIKAL : PAKEJ SKOP KERJA MEKANIKAL 100% Jadual 100% Sebenar INTERNAL COLD-WATER SYSTEM : 100% 100% TEMPOH SIAP : 30 MINGGU KAEDAH PERLAKSANAAN : KONVENSIONAL DALAMAN P. PENGUASA : JUVINIA AUGUSTINE ZUJIP PELANGGAN : KEM. PENDIDIKAN MALAYSIA PERUNDING MEKANIKAL : - HODT : CAWANGAN FASILITI SENGGARAAN BANGUNAN WPP(M) : IR. ABDULDAN BIN ADTONG KOS KONTRAK MEKANIKAL : RM 41,040.00 STATUS PROJEK TERKINI: 1. PROJEK TELAH SIAP SEPENUHNYA. PENYERAHAN PROJEK TELAH DIBUAT PADA 7 SEPTEMBER 2022. 2. DLP pada 13.8.2023


Gambar Projek Terkini (PIC:PJ Anthony)


PEMBINAAN KOMPLEKS PEJABAT SURUHANJAYA PENCEGAHAN RASUAH MALAYSIA (SPRM) SABAH Tajuk Projek : KONTRAKTOR : WIJAYA DAYA SDN BHD NO KONTRAK : JKR/IP/CKUB/126/2021 TARIKH MILIK TAPAK : 14 JULAI 2021 TARIKH SIAP ASAL : 9 JANUARI 2024 130 Minggu Tempoh Tanggungan Kecacatan: 12bln + 3bln + 14hari TARIKH SIAP BAHARU : - HARGA KONTRAK ASAL : RM 44,990,000.00 KEMAJUAN KERJA : 17.08% (Jadual) / 20.04% +2.96 Days (Sebenar) NSC MEKANIKAL : JANGKAAN SST KELUAR AWAL JANUARI 2022 SKOP KERJA MEKANIKAL ATDA INTERNAL COLD-WATER SYSTEM : RM 688,520.00 11 % INTERNAL SANITARY SYSTEM : 11 % FIRE PROTECTION SYSTEM : RM 1,155,000.00 2 % AIR CONDITIONING SYSTEM, : RM 3,990,000.00 0 % LIFT SYSTEM : RM 1,260.000.00 12 % TEMPOH SIAP : 130 MINGGU KAEDAH PERLAKSANAAN : KONVENSIONAL PERUNDING P. PENGUASA : Ir. JASMI BIN WAHAB PELANGGAN : SPRM PERUNDING MEKANIKAL : Perwira Al-Shura Consulting Engineer Sdn Bhd HOPT : Cawangan Kerja Bangunan Am 1 (CKBA 1) WPP(M) : Ir. ABDULDAN BIN ADTONG KOS KONTRAK MEKANIKAL : RM 7,487,500.00 STATUS PROJEK TERKINI: 1. Pelantikan NSC Sistem Penyaman Udara masih belum dibuat.


Gambar Projek Terkini (PIC:PJ Anthony)


PENGURUSAN FASILITI DAN PENYENGGARAAN (FMM) DI PERUMAHAN KASTAM SEPANGGAR, SABAH Tajuk Projek : KONTRAKTOR : KEJURUTERAAN PENYEJUKAN LEADING SDN BHD NO KONTRAK : JKR/IP/CFSB/10/2020 TARIKH MILIK TAPAK : 1 APRIL 2021 TARIKH SIAP ASAL : 30 APRIL 2024 TARIKH SIAP BAHARU : - HARGA KONTRAK ASAL : RM 4,112,800.00 KEMAJUAN KERJA : 54% (Jadual) / 52% (Sebenar) NSC MEKANIKAL : - SKOP KERJA MEKANIKAL 42% Jadual 42% Sebenar INTERNAL COLD WATER SYSTEM : PPM INTERNAL SANITARY SYSTEM : PPM FIRE PROTECTION SYSTEM : PPM AIR CONDITIONING SYSTEM, : PPM LIFT SYSTEM : PPM TEMPOH SIAP : 3.08 TAHUN KAEDAH PERLAKSANAAN : KONTRAK FASILITI (FMM) P. PENGUASA : IR. JASMI BIN WAHAB PELANGGAN : KASTAM DIRAJA MALAYSIA PERUNDING MEKANIKAL : - HODT : CAWANGAN FASILITI SENGGARAAN BANGUNAN WPP(M) : Ir. ABDULDAN BIN ADTONG KOS KONTRAK MEKANIKAL : RM 746,700.00 STATUS PROJEK : PEMBINAAN STATUS PROJEK TERKINI: 1. Kerja-Kerja PPM sedang berjalan seperti dijadualkan.


Gambar Projek Terkini (PIC:PJ Anthony)


NAIKTARAF SISTEM PENYAMAN UDARA JENIS BERASINGAN SERTA LAIN-LAIN KERJA BERKAITAN BAGI BILIK PENGINAPAN BLOK ASRAMA KINABALU, ASRAMA MESILAU DAN ASRAMA DANUM DI KAMPUS TADBIRAN AWAM NEGARA (INTAN) SABAH Tajuk Projek : KONTRAKTOR : PALMA VOLTAGE SDN BHD NO KONTRAK : JKR/PPK2/5/2022(M) TARIKH MILIK TAPAK : 9 JUN 2022 TARIKH SIAP ASAL : 8 SEPTEMBER 2022 TARIKH SIAP BAHARU : 13 OKTOBER 2022 HARGA KONTRAK ASAL : RM 396,180.00 KEMAJUAN KERJA : 100% (Jadual) / 100% - (Sebenar) NSC MEKANIKAL : - SKOP KERJA MEKANIKAL % Jadual % Sebenar Air Cooled Split Unit System : 100% 100% TEMPOH SIAP : 12 MINGGU KAEDAH PERLAKSANAAN : SEBUTHARGA P. PENGUASA : Ir. ABDULDAN BIN ADTONG PELANGGAN : INTAN SABAH HODT : - WPP(M) : - KOS KONTRAK MEKANIKAL : N/A STATUS PROJEK TERKINI: 1. PROJEK TELAH SIAP SEPENUHNYA. PENYERAHAN PROJEK TELAH DIBUAT PADA 31 SEPTEMBER 2022. 2. DLP pada 12.10.2023


Gambar Projek Terkini (PIC:PJ Anthony)


NAIKTARAF SISTEM PENCEGAH KEBAKARAN DI KAMPUS INTAN SABAH Tajuk Projek : KONTRAKTOR : TECHNOHASIL ENGINEERING SDN. BHD. NO KONTRAK/SEBUTHARGA : JKR/PPK2/6/2022(M) TARIKH MILIK TAPAK : 22 JUN 2022 TARIKH SIAP ASAL : 21 SEPTEMBER 2022 TARIKH SIAP BAHARU : 23 NOVEMBER 2022 (Lanjutan masa no.1) HARGA KONTRAK ASAL : RM 272,180.00 HARGA KONTRAK SEMASA : RM 298,667.00 (APK No.1) KEMAJUAN KERJA : 100 % (Jadual) / 100 % - (Sebenar) NO INDEN KERJA : JKR/PPK2/6/2022(M) SKOP KERJA MEKANIKAL 100% Jadual 100 % Sebenar TEMPOH SIAP : 12 MINGGU KAEDAH PERLAKSANAAN : SEBUTHARGA P. PENGUASA : Ir. ABDULDAN BIN ADTONG PELANGGAN : INTAN SABAH HODT / PENGURUS PROGRAM : BFBA2, CFSB PENYELARAS PROGRAM : WAN ISNIZAR BINTI WAN AHMAD STATUS PROJEK TERKINI: 1. PROJEK TELAH SIAP SEPENUHNYA. PENYERAHAN PROJEK TELAH DIBUAT PADA 13 Oktober 2022. 2. DLP pada 12.10.2023


Gambar Projek Terkini (PIC:PJ Anthony)


KERJA-KERJA PEMBAIKAN STRUKTUR DAN PENYENGGARAAN BANGUNAN SERTA LAIN-LAIN KERJA BERKAITAN DI SMK TUN FUAD STEPHENS, SABAH Tajuk Projek : KONTRAKTOR : LMEND INDUSTRIES SDN. BHD. NO KONTRAK : JKR/IP/CFSB/13/2020 TARIKH MILIK TAPAK : 9.3.2021 TARIKH SIAP ASAL : 7.11.2021 EOT No.1 TARIKH SIAP BAHARU : 6.1.2022 HARGA KONTRAK ASAL : RM 1,326,750.00 KEMAJUAN KERJA : 100%, CPC pada 11.2.2022 NSC MEKANIKAL : - SKOP KERJA MEKANIKAL 100% Jadual 100% Sebenar INTERNAL COLD-WATER SYSTEM : 100% 100% TEMPOH SIAP : 32 MINGGU KAEDAH PERLAKSANAAN : KONVENSIONAL DALAMAN P. PENGUASA : IR. PATRICK WOON PELANGGAN : KEM. PENDIDIKAN MALAYSIA PERUNDING MEKANIKAL : - HODT : - WPP(M) : IR. ABDULDAN BIN ADTONG KOS KONTRAK MEKANIKAL : RM 10,590.00 VO. MEKANIKAL / OMISSION / RASIONALISASI:- 1. Telah proses penyerahan kerja siap 2. Di bawah DLP - defect liability period STATUS PROJEK TERKINI: 1. Projek dalam tempoh DLP.


Gambar Projek Terkini (PIC:PJ Anthony)


DAIF SABAH (2021) - PEMBINAAN BANGUNAN GANTIAN DI SK KUALA ABAI, KOTA BELUD, SABAH (REKA DAN BINA) Tajuk Projek : KONTRAKTOR : JT CEMERLANG SDN. BHD. NO KONTRAK : JKR/IP/CKUB/275/2022 TARIKH MILIK TAPAK : 16.11.2022 TARIKH SIAP ASAL : 12.11.2024 TARIKH SIAP BAHARU : - HARGA KONTRAK ASAL : RM 20,163,000.00 KEMAJUAN KERJA : Jadual - 0.11% / Sebenar 0.11% NSC MEKANIKAL : - SKOP KERJA MEKANIKAL 0% Jadual 0% Sebenar INTERNAL CWS SYSTEM : 0% 0% ACMV SYSTEM : 0% 0% FIRE FIGHTING SYSTEM : 0% 0% LIFT SYSTEM : 0% 0% INTERNAL SANITARY SYSTEM : 0% 0% TEMPOH SIAP : 104 MINGGU KAEDAH PERLAKSANAAN : REKA & BINA PENGARAH PROJEK : PENGARAH PEMBINAAN PELANGGAN : KEM. PENDIDIKAN MALAYSIA PERUNDING MEKANIKAL : ZLS ENGINEERING SDN BHD HODT : CAWANGAN KERJA PENDIDIKAN WPP(M) : IR. ABDULDAN BIN ADTONG KOS KONTRAK MEKANIKAL : - VO. MEKANIKAL / OMISSION / RASIONALISASI:- STATUS PROJEK TERKINI: 1. Isu sempadan tapak tanah.


Gambar Projek Terkini (PIC:PJ Anthony)


DAIF SABAH (2020) – PEMBINAAN GANTIAN PENUH 12 BILIK DARJAH DAN LAIN-LAIN KEMUDAHAN DI SEKOLAH KEBANGSAAN NANAMUN, KOTA BELUD, SABAH (REKA & BINA) Tajuk Projek : KONTRAKTOR : SYARIKAT TENOM QUARRY NO KONTRAK : JKR/CKUB/21519/2022 TARIKH MILIK TAPAK : 14HB JULAI 2022 TARIKH SIAP ASAL : 29HB MEI 2024 TARIKH SIAP BAHARU : - HARGA KONTRAK ASAL : RM 17,300,000.00 KEMAJUAN KERJA : Jadual : 5.03%, Sebenar : 4.44% +/- 3 hari NSC MEKANIKAL : - SKOP KERJA MEKANIKAL 0% Jadual 0% Sebenar INTERNAL CWS SYSTEM : 0% 0% ACMV SYSTEM : 0% 0% FIRE FIGHTING SYSTEM : 0% 0% INTERNAL SANITARY SYSTEM : 0 % 0 % TEMPOH SIAP : 98 MINGGU KAEDAH PERLAKSANAAN : REKA & BINA PENGARAH PROJEK : PENGARAH PEMBINAAN PELANGGAN : KEM. PENDIDIKAN MALAYSIA PERUNDING MEKANIKAL : PERUNDING JAYAREKA S/B HODT : CAWANGAN KERJA PENDIDIKAN WPP(M) : IR. ABDULDAN BIN ADTONG KOS KONTRAK MEKANIKAL : - VO. MEKANIKAL / OMISSION / RASIONALISASI:- STATUS PROJEK TERKINI: 1. Isu Penyuraian murid. 2. Terdapat pindaan pelan pembangunan.


Gambar Projek Terkini (PIC:PJ Anthony)


PEMBINAAN BANGUNAN TAMBAHAN FASA 2 DI SEKOLAH SUKAN MALAYSIA SABAH, KOTA KINABALU, SABAH (REKA DAN BINA) Tajuk Projek : KONTRAKTOR : ZAINAL & DIN CONSTRUCTION SDN BHD NO KONTRAK : JKR/CKUB/22227/2022 TARIKH MILIK TAPAK : 05-09-2022 TARIKH SIAP ASAL : 07-09-2025 TARIKH SIAP BAHARU : - HARGA KONTRAK ASAL : RM 76,990,000.00 KEMAJUAN KERJA : 5 % Jadual / 5 % Sebenar +/- 0 hari NSC MEKANIKAL : - SKOP KERJA MEKANIKAL 0% Jadual 0% Sebenar INTERNAL CWS SYSTEM : 0% 0% ACMV SYSTEM 0% 0% FIRE FIGHTING SYSTEM 0% 0% OTHER MECH. SYSTEM 0% 0% BUILDING INFORMATION MODELLING 0% 0% TEMPOH SIAP : 157 MINGGU KAEDAH PERLAKSANAAN : REKA & BINA PENGARAH PROJEK : PENGARAH PEMBINAAN PELANGGAN : KEM. PENDIDIKAN MALAYSIA PERUNDING MEKANIKAL : NHK ULTIMATE CONSULT S/B HODT : CAWANGAN KERJA PENDIDIKAN WPP(M) : IR. ABDULDAN BIN ADTONG KOS KONTRAK MEKANIKAL : RM 3,600,000.00 (ANGGARAN) VO. MEKANIKAL / OMISSION / RASIONALISASI:- - STATUS PROJEK TERKINI:


Gambar Projek Terkini (PIC:PJ Anthony)


KERJA-KERJA PENYELENGGARAAN DAN BAIKPULIH SERTA LAIN-LAIN KERJA BERKAITAN DI KOMPLEKS PERUMAHAN POLIS TAMAN NELLY, KOTA KINABALU, SABAH (FASA2) KONTRAKTOR : VH GENERAL CONSTRUCTION NO KONTRAK : JKR/IP/PPK2/04/2021 TARIKH MILIK TAPAK : 18 OKTOBER 2021 TARIKH SIAP ASAL : 29 MEI 2022 TARIKH SIAP BAHARU : N/A HARGA KONTRAK ASAL : RM 1,749,000.00 KEMAJUAN KERJA : 100 % (Jadual) / 100 % (Sebenar) NSC MEKANIKAL : - SKOP KERJA MEKANIKAL 100 % Jadual 100 % Sebenar INTERNAL COLD WATER SYSTEM : 100 % 100 % INTERNAL SANITARY SYSTEM : 100 % 100 % TEMPOH SIAP : 32 MINGGU KAEDAH PERLAKSANAAN : TENDER P. PENGUASA : Ir ZAINAZIM PELANGGAN : KEM. PENDIDIKAN MALAYSIA PERUNDING MEKANIKAL : N/A HODT : N/A WPP(M) : IR. ABDULDAN BIN ADTONG KOS KONTRAK MEKANIKAL : RM 210,850.00 STATUS PROJEK TERKINI: • Lawatan pemeriksaan kerja siap telah dibuat pada 13.9.2022 EOT No1 : 9.8.2022 EOT No. 2: 15.9.2022 • Penyerahan dibuat pada 7 Oktober 2022 • Dalam tempoh DLP Tajuk Projek :


Gambar Projek Terkini (PIC:PJ Helen)


PENGURUSAN FASILITI DI KOMPLEKS MAHKAMAH BARU KOTA KINABALU, SABAH. Tajuk Projek : KONTRAKTOR : JBS ENGINEERING SDN. BHD NO KONTRAK : JKR/IP/CSFB/154/2022 TARIKH MILIK TAPAK : 15 Ogos 2022 TARIKH SIAP ASAL : 14 SEPTEMBER 2025 HARGA KONTRAK : RM 8,200,935.92 KEMAJUAN KERJA : 8 % (Jadual) / 8 % (Sebenar) NSC MEKANIKAL : - SKOP KERJA MEKANIKAL 9 % Jadual 9 % Sebenar ACMV : 9% 9% FIRE PROTECTION SYSTEM : LIFT SYSTEM : LPG, HAND DRAYER, ROLLER SHUTTER : MOTORISED SYSTEM, KITCHEN HOOD, MEC. ABOVE CEILING : TEMPOH SIAP : 3 TAHUN KAEDAH PERLAKSANAAN : TENDER P. PENGUASA : PENGARAH PEMBINAAN, PPK2 PELANGGAN : MAHKAMAH PERSEKUTUAN MALAYSIA, BAHAGIAN PENGURUSAN ISTANA KEHAKIMAN HODT : N/A WPP(M) : IR. ABDULDAN BIN ADTONG KOS KONTRAK MEKANIKAL : RM 1,484,177.00 STATUS PROJEK TERKINI: • Isu kondensasi pada bilik pejabat Yang Arif di aras 4 • Cubaan pecah masuk di rumah pam • Sijil pembaharuan FC telah diperolehi daripada Bomba • Sijil pembaharuan lift telah diperolehi daripada JKKP


Gambar Projek Terkini (PIC:PJ Helen)


CADANGAN MEMBINA SATU BLOK BANGUNAN PENTADBIRAN, DEWAN SERBAGUNA DAN AUDITORIUM DI INSTITUT PENDIDIKAN GURU KAMPUS GAYA (FASA 2) KOTA KINABALU, SABAH. Tajuk Projek : KONTRAKTOR : ZBN GROUP HOLDINGS SDN. BHD. NO KONTRAK : KPM/BP/2019/3 TARIKH MILIK TAPAK : 10 JUN 2019 TARIKH SIAP ASAL : 15 MAC 2021 EOT 1 – 51 HARI (Force majeure-PKP) EOT 2 – 63 HARI (PKP) EOT 3 – 142 HARI (PKP 2.0) Eot 4 – 60 HARI (PKP 3.0) TARIKH SIAP BAHARU : 25 JANUARI 2022 HARGA KONTRAK ASAL : RM 58,812,736.33 KEMAJUAN KERJA – JUN 2021 : 100% (Jadual) / 100 % (Sebenar) NSC MEKANIKAL : - SKOP KERJA MEKANIKAL % Jadual % Sebenar INTERNAL COLD WATER SYSTEM : 100% 100% INTERNAL SANITARY SYSTEM : FIRE PROTECTION SYSTEM : AIR CONDITIONING SYSTEM : LIFT SYSTEM : TEMPOH SIAP : 21 BULAN KAEDAH PERLAKSANAAN : KONVENSIONAL PERUNDING P. PENGUASA : PENGARAH PEMBINAAN, PPK2 PELANGGAN : KEM. PENDIDIKAN MALAYSIA PERUNDING MEKANIKAL : PEM CONSULT (EN. JORDAN 012-8283092) HODT : En. AHMAD JAMIL BIN JAAFAR WPP(M) : IR. ABDULDAN BIN ADTONG KOS KONTRAK MEKANIKAL : RM 6,580,249.00 STATUS PROJEK TERKINI: • Aduan pada sistem penyaman udara yang bising • Permohonan pemasangan penyaman udara bagi bilik yang tidak ada aircond • DLP berakhir pada 31 Mac 2023 • Dalam proses penyediaan final account


Gambar Projek Terkini (PIC:PJ Helen)


PEMBINAAN RKAT TAMBAHAN PELBAGAI KELAS KEM LOK KAWI, SABAH (REKA & BINA) Tajuk Projek : KONTRAKTOR : JAWALA CORPORATION SDN BHD NO KONTRAK : JKR/IP/CKUB/49/2022 TARIKH MILIK TAPAK : 20 September 2021 TARIKH SIAP ASAL : 08 MAC 2022 TARIKH SIAP BAHARU : 04 OGOS 2025 HARGA KONTRAK ASAL : RM 188,171,891.00 KEMAJUAN KERJA : 2.40 % (Jadual) / 2.14% (Sebenar) -0.26 / lewat 13 hari NSC MEKANIKAL : - SKOP KERJA MEKANIKAL % Jadual % Sebenar INTERNAL COLD WATER SYSTEM : 0% 0% INTERNAL SANITARY SYSTEM : 0% 0% AIR CONDITIONING SYSTEM, : 0% 0% TEMPOH SIAP : 178 MINGGU KAEDAH PERLAKSANAAN : REKA DAN BINA P. PENGUASA : PENGARAH PEMBINAAN PPK2 PELANGGAN : KEMENTERIAAN PERTAHANAN MALAYSIA HODT : N/A WPP(M) : IR. ABDULDAN BIN ADTONG KOS KONTRAK MEKANIKAL : RMSTATUS PROJEK TERKINI: • Lukisan Arkitek telah diluluskan oleh HODT A pada 23.9.2022 • Lukisan mekanikal telah dikemukakan kepada HODTM pada 28.10.2022 • 27.12.2022 Serah lukisan pembinaan mekanikal untuk kelulusan • 4.1.2023 Tiada halanggan berkenaan lukisan kerja kontraktor perlu kemukakan maklumbalas perkara 4 & 5 bagi ulasan terdahulu.


Gambar Projek Terkini (PIC:PJ Helen)


PENGGANTIAN PENUH SEKOLAH MENENGAH SAINS SABAH, DI BUKIT PADANG, KOTA KINABALU, SABAH (REKA DAN BINA) Tajuk Projek : KONTRAKTOR : BANGKIT ENERGY & PRO LOGISTIC (EM) SDN. BHD. NO KONTRAK : JKR/IP/CKUB/162/2021 TARIKH MILIK TAPAK : 1 JULAI 2021 TARIKH SIAP ASAL : 26 JULAI 2024 TARIKH SIAP BAHARU : 26 JULAI 2026 HARGA KONTRAK ASAL : RM 74,789,899.00 KEMAJUAN KERJA : 21% (Jadual) / 30% (Sebenar)+9 ( 74 days) NSC MEKANIKAL : N/A SKOP KERJA MEKANIKAL % Jadual % Sebenar ACMV : 0 % 0 % FIRE FIGHTING & PROTECTION SYST. : 15 % 15 % INTERNAL COLD WATER & SANITARY PLUMBING SYSTEM : 20 % 20 % KITCHEN EQUIPMENT : 0 % 0 % EMERGENCY SHOWER & EYE WASHLIFT SYSTEM : 0 % 0 % FUME CUPBORD : 0 % 0 % MAINTENANCE DURING DLP : 0 % 0 % TEMPOH SIAP : 21 BULAN KAEDAH PERLAKSANAAN : REKA DAN BINA/TENDER TERBUKA P. PENGUASA : PENGARAH PEMBINAAN, PPK2 PELANGGAN : KEM. PENDIDIKAN MALAYSIA PERUNDING MEKANIKAL : PETAREKA PERUNDING Ir. DANNY WONG-0198811187 Cik AZIRA MISMAN-016-8025334 HODT : Ir. ISFANIZAM BIN ISMAIL 019-302 7070 WPP(M) : IR. ABDULDAN BIN ADTONG KOS KONTRAK MEKANIKAL : RM 2,130,130.00 STATUS PROJEK TERKINI: • Kerja pemasangan paip sanitari di Asrama L&P, Dewan makan, Admin, Kantin & Dewan Serbaguna. • pemasangan paip gi (breakglass) di gridline B-c Admin


Gambar Projek Terkini (PIC:PJ Helen)


PENGURUSAN FASILITI DAN PENYELENGGARAAN (FMM) DI PEJABAT BAHARU MENARA KASTAM SABAH, JALAN UMS, KOTA KINABALU, SABAH. . Tajuk Projek : KONTRAKTOR : FINCHO SDN. BHD NO KONTRAK : JKR/IP/CFSB/48/2021 TARIKH MILIK TAPAK : 1 APRIL 2021 TARIKH SIAP ASAL : 30 APRIL 2024 HARGA KONTRAK : RM 4,049,200.00 KEMAJUAN KERJA : 52 % (Jadual) / 52 % (Sebenar) NSC MEKANIKAL : - SKOP KERJA MEKANIKAL % Jadual % Sebenar ACMV : 55% 55% MECHANICAL ABOVE CEILING : BMS, HAND DRAYER, ROLLER SHUTTER : FIRE FIGHTING : LIFT SYSTEM : RAINWATER HARVESTING : SEWERAGE TREATMENT AND PUMPING STATION : COLD WATER AND BOOSTER PUMP : TEMPOH SIAP : 3.08 TAHUN / 37 BULAN KAEDAH PERLAKSANAAN : TENDER P. PENGUASA : PENGARAH PEMBINAAN, PPK2 PELANGGAN : JABATAN KASTAM DIRAJA MALAYSIA ZON SABAH HODT : N/A WPP(M) : IR. ABDULDAN BIN ADTONG KOS KONTRAK MEKANIKAL : RM 914,310.00 STATUS PROJEK TERKINI: • 13 FCA Mekanikal telah diluluskan dan telah dimaklumkam secara rasmi kepada kontraktor fm • Daripada 13 FCA yang telah diluluskan, hanya 5 yang telah siap sepenuhnya


Gambar Projek Terkini (PIC:PJ Helen)


KERJA-KERJA NAIKTARAF BANGLO NO.2 SERTA LAIN-LAIN KERJA BERKAITAN DI PANGKALAN TLDM SEPANGGAR KOTA KINABALU, SABAH. Tajuk Projek : KONTRAKTOR : LINDUNG ENTERPRISE NO KONTRAK : JKR/PPK2/28/2021 TARIKH MILIK TAPAK : 20 September 2021 TARIKH SIAP ASAL : 21 Februari 2022 TARIKH SIAP BAHARU : 21 FEBRUARI 2022 HARGA KONTRAK ASAL : RM 424,210.00 KEMAJUAN KERJA : 100 % (Jadual) / 100 % (Sebenar) NSC MEKANIKAL : KONTRAKTOR PAKAR MEKANIKAL BELUM DILANTIK SKOP KERJA MEKANIKAL % Jadual % Sebenar INTERNAL COLD WATER SYSTEM : 100% 100% INTERNAL SANITARY SYSTEM : 100% 100% AIR CONDITIONING SYSTEM, : 100% 100% TEMPOH SIAP : 22 MINGGU KAEDAH PERLAKSANAAN : SEBUTHARGA P. PENGUASA : Ir. PATRICK BASUN PELANGGAN : PANGKALAN TLDM KOTA KINABALU PERUNDING MEKANIKAL : N/A HODT : N/A WPP(M) : IR. ABDULDAN BIN ADTONG KOS KONTRAK MEKANIKAL : RM 30, 130.00 STATUS PROJEK TERKINI: • EOT No.1: 19/7/2022 • Penyerahan dibuat pada 2.9.2022


Gambar Projek Terkini (PIC:PJ Helen) Perspective view of TLDM Banglo No,.2


DAIF SABAH (2021)-PEMBINAAN BANGUNAN GANTIAN PENUH DI SK BUIT HILL PENAMPANG, SABAH (REKA DAN BINA) Tajuk Projek : KONTRAKTOR : BANGKIT ENERGY & PRO LOGISTIC (EM) SDN. BHD. NO KONTRAK : JKR/IP/CKUB/ TARIKH MILIK TAPAK : 27 DISEMBER 2022 TARIKH SIAP ASAL : 17 FEBRUARI 2025 TARIKH SIAP BAHARU : 17 FEBRUARI 2025 HARGA KONTRAK ASAL : RM 27,789,899.00 KEMAJUAN KERJA : 0% (Jadual) / 0% (Sebenar) NSC MEKANIKAL : N/A SKOP KERJA MEKANIKAL % Jadual % Sebenar INTERNAL COLD WATER SYSTEM : 0 % 0 % INTERNAL SANITARY SYSTEM : 0 % 0 % AIR CONDITIONING SYSTEM, : 0 % 0 % FIRE FIGHTING & BOOSTER PUMP : 0 % 0 % TEMPOH SIAP : 112 MINGGU KAEDAH PERLAKSANAAN : REKA DAN BINA/TENDER TERBUKA P. PENGUASA : PENGARAH PEMBINAAN, PPK2 PELANGGAN : KEM. PENDIDIKAN MALAYSIA PERUNDING MEKANIKAL : PETAREKA PERUNDING Ir. JASON LIM-0138641125 HODT : Ir. MOHD FADZIL B. RAHIM 017-777 7936 WPP(M) : IR. ABDULDAN BIN ADTONG KOS KONTRAK MEKANIKAL : RM 0.00 STATUS PROJEK TERKINI: • PEMBINAAN


Gambar Projek Terkini (PIC:PJ Helen)


CADANGAN PEMBINAAN OPERASI HADAPAN (FOB) DI PULAU MABUL, SEMPORNA, SABAH Tajuk Projek : KONTRAKTOR : HARTAMAS BORNEO SDN. BHD. NO KONTRAK : JKR/IP/CKUB/221/2020 TARIKH MILIK TAPAK : 04 JANUARI 2021 TARIKH SIAP ASAL : 13 JANUARI 2024 TARIKH SIAP BAHARU : - HARGA KONTRAK ASAL : RM 41,550,200.00 KEMAJUAN KERJA -JUN 2022 : 48.00% (Jadual) / 43% (Sebenar) NSC MEKANIKAL : SUASA CHEM SDN (KITCHEN & LPG) KOS KONTRAK MEKANIKAL : RM 360,000.00 NSC MEKANIKAL : HARTAMAS BORNEO SDN. BHD. (SISTEM PENYAMAN UDARA, SISTEM PENCEGAH KEBAKARAN & SISTEM BEKALAN MINYAK (BFI) KOS KONTRAK MEKANIKAL : RM4,087,680.00 SKOP KERJA MEKANIKAL % Jadual % Sebenar INTERNAL COLD WATER SYSTEM : 5 INTERNAL SANITARY SYSTEM : 20 FIRE PROTECTION SYSTEM : AIR CONDITIONING SYSTEM, : BULK FUEL : KITCHEN & LPG : TEMPOH SIAP : 36 BULAN KAEDAH PERLAKSANAAN : KONVENSIONAL PERUNDING P. PENGUASA : IR. JASMI BIN WAHAB PELANGGAN : KEMENTERIAN DALAM NEGERI PERUNDING MEKANIKAL : CAW. KEJURUTERAAN MEKANIKAL JKR HODT : - WPP(M) : IR. ABDULDAN BIN ADTONG VO. MEKANIKAL / OMISSION / RASIONALISASI:- 1. Perubahan Sistem Penyaman udara di Bilik Pusat Komunikasi. Kelulusan Perubahan Kerja (KPK) No. 1 telah dimajukan kepada ukurbahan pada 4 Mac 2022 berjumlah RM7,200.00. 2. QS Consultant mohon agar lukisan perubahan rekabentuk penyaman udara dikemukan untuk tujuan KPK. 3. Perbezaan lukisan pembinaan dan BQ dokumen kontrak (HDPE Rainwater Harvesting Collection, HDPE Domestic Tank dan Sistem Perpaipan dalaman & Sanitari di Jetty Head)