Gambar Projek Terkini (PIC:PJ Lazimih) Text ISU DI TAPAK: 1.PENGHAWA DINGIN TELAH SIAP DIPASANG (SK TIMBUA RANAU, SK PANDIWAN NABAWAN, SK PAGUOKON TENOM, SK TUN DATU HAJI MUSAPHA KUDAT, SK PEKAN SIPITANG DAN SMK PENGIRAN OMAR SIPITANG,SK PINAMBAWAN TUARAN , SK MALUBANG PITAS, SMK BANGGI DAN SK PADANG BANGGI) 2.PEMASANGAN FIRE EXTINGUISHER SEMUA TELAH DIPASANG SEMUA SEKOLAH 3. NCP TELAH DITUTUP SK TUN DATU HAJI MUSTAPHA SK PEKAN SIPITANG SMK PEMGIRAN OMAR SIPITANG 3. TIADA PEMASANGAN PENGHAWA DINGIN UNTUK SK BALAMBANGAN KUDAT( BEKALAN ELEKTRIK TIADA) MENGGUNAKAN SOLAR SAHAJA. 4. TESTING TELAH DI LAKUKAN DISEMUA SEKOLAH. 5. LAWATAN BERSAMA PELANGGAN TELAH DILAKUKAN DISEMUA SEKLOAH. 6. PENYARAHAN MAKMAL KOMPUTER TELAH DIBUAT OLEH JKR KEPADA PELANGGAN. STATUS PROJEK TERKINI: DALAM TEMPOH DLP SK TIMBUA RANAU SK MALUBANG PITAS,
Gambar Projek Terkini (PIC:PJ Lazimih) SMK BANGGI KUDAT SK PAGUOKON TENOM SK PANDIWAN NABAWAN SK PENIMBAWAN TUARAN SK PEKAN SIPITANG
Gambar Projek Terkini (PIC:PJ Lazimih) SMK PENGIRAN OMAR SIPITANG SK TUN HAJI MUSTPHA KUDAT SMK BANGGI KUDAT SK PADANG BANGGI KUDAT SK BALAMBANGAN KUDAT
PROJEK PEMBINAAN SEKOLAH BAHARU 18 BILIK DARJAH, 8 UNIT KURTERS, ASRAMA 300 MURID (150 LELAKI, 150 PEREMPUAN) DAN LAIN-LAIN KEMUDAHAN DI SMK ULU SAPI TELUPID, SABAH ( REKA DAN BINA). Tajuk Projek : KONTRAKTOR : DERRIDA (M) SDN.BHD NO KONTRAK : JKR/IP/CKUB/21377/2020 TARIKH MILIK TAPAK : 18 OKTOBER 2021 TARIKH SIAP ASAL : 06 OKTOBER 2024 TARIKH SIAP BAHARU : N/A HARGA KONTRAK ASAL : RM 58,925,001.00 KEMAJUAN KERJA : 6.50% NSC MEKANIKAL : TIADA SKOP KERJA MEKANIKAL % Jadual % Sebenar INTERNAL COLD WATER SYSTEM : 0% 0% INTERNAL SANITARY SYSTEM : 0% 0% FIRE PROTECTION SYSTEM : 0% 0% AIR CONDITIONING SYSTEM : 0% 0% KITCHEN EQUIPMENT SYSTEM : 0% 0% COLD ROOM 0% 0% EMERGENCY SHOWER& EYE WASH : 0% 0% FUME CUPBORD : 0% 0% TEMPOH SIAP : 155 MINGGU KAEDAH PERLAKSANAAN : TENDER (REKA DAN BINA) P. PENGUASA : PENGARAH PPK2 PELANGGAN : KEM. PENDIDIKAN MALAYSIA PERUNDING MEKANIKAL : ATL KONSULT SDN.BHD HODT : PENDIDIKAN & PENGAJIAN TINGGI (SPR)(CKM) WPP(M) : Ir. ABDULDAN BIN ADTONG KOS KONTRAK MEKANIKAL : NA
Gambar Projek Terkini (PIC:PJ Lazimih) STATUS PROJEK TERKINI: SKOP KERJA MEKANIKAL BELUM BERMULA/PERINGKAT REKABENTUK
PROJEK PEMBINAAN SEKOLAH BAHARU 24 BILIK DARJAH, 8 UNIT KURTERS, ASRAMA 200 MURID (100 LELAKI, 100 PEREMPUAN) DAN LAIN-LAIN KEMUDAHAN DI SEKOLAH MENENGAH KEBANGSAAN BATU SAPI II, SANDAKAN, SABAH ( REKA DAN BINA). Tajuk Projek : KONTRAKTOR : BANGKIT ENERGY & PRO LOGISTIC (EM)SDN.BHD NO KONTRAK : JKR/IP/CKUB/282/2021 TARIKH MILIK TAPAK : 07 - 10 - 2021 TARIKH SIAP ASAL : 02 - 10 - 2024 TARIKH SIAP BAHARU : N/A HARGA KONTRAK ASAL : RM61,789,899.00 KEMAJUAN KERJA : 7.50% NSC MEKANIKAL : - SKOP KERJA MEKANIKAL % Jadual % Sebenar INTERNAL COLD WATER SYSTEM : 0% 0% INTERNAL SANITARY SYSTEM : 0% 0% FIRE PROTECTION SYSTEM : 0% 0% AIR CONDITIONING SYSTEM, : 0% 0% KITCHEN EQUIPMENT SYSTEM : 0% 0% COLD ROOM : 0% 0% EMERGENCY SHOWER& EYE WASH : 0% 0% FUME CUPBORD TEMPOH SIAP : :0% 156 MINGGU 0% KAEDAH PERLAKSANAAN : TENDER (REKA DAN BINA) P. PENGUASA : PENGARAH PPK2 PELANGGAN : KEM. PENDIDIKAN MALAYSIA PERUNDING MEKANIKAL : PETAREKA PERUNDING (S)SDN.BHD HODT : PENDIDIKAN & PENGAJIAN TINGGI (SPR)(CKM) WPP(M) : IR. ABDULDAN BIN ADTONG KOS KONTRAK MEKANIKAL : NA
Gambar Projek Terkini (PIC:PJ Lazimih) STATUS PROJEK TERKINI: SKOP KERJA MEKANIKAL BELUM BERMUA/PERINGKAT REKABENTUK
NAIKTARAF FASILITI DAN KEMUDAHAN ASRAMA PELAJAR DI IKBN KINARUT, SABAH Tajuk Projek : KONTRAKTOR : RAZ ENTERPRISE LOT T22A, BLOK C TINGKAT 1 SERTA LIGHT INDUSTRIAL, BATU 2,9000 SANDAKAN SABAH NO KONTRAK/TENDER : JKR/IP/CSFB/T/19/2021 TARIKH MILIK TAPAK : 01 MAC 2022 TARIKH SIAP ASAL : 10 OKTOBER 2022 TARIKH SIAP BAHARU : 10 DISEMBER 2022 HARGA KONTRAK ASAL : RM1,296,645.00 KEMAJUAN KERJA : 100% NSC MEKANIKAL : TIADA SKOP KERJA MEKANIKAL % Jadual % Sebenar INTERNAL COLD WATER SYSTEM : 100% 100% INTERNAL SANITARY SYSTEM : 100% 100% VENTALITATION FAN : 100% 100% TEMPOH SIAP : 32 MINGGU KAEDAH PERLAKSANAAN : KONVENSIONAL DALAMAN P. PENGUASA : JURUTERA AWAM KANAN, PPK2 PELANGGAN : KBS( IKBAN KINARUT) PERUNDING MEKANIKAL : N/A HODT : WPP(M) : IR. ABDULDAN BIN ADTONG KOS KONTRAK MEKANIKAL : RM141,000.00
Gambar Projek Terkini (PIC:PJ Lazimih) ISU DI TAPAK: Dalam proses menanggal dan pemasangan kerja –perja skop mekanikal 1. KERJA PEMASANGAN COLDWATER DAN SANITARY DI ASRMA BLOK A DAN B TELAH SIAP DIPASANG. 2. PEMASANGAN EKZOS FAN ASRAMA BLOK A DAN BLOK B TELAH SIAP DIPASANG 3. TESTING DAN COMMISIONING TELAH DILAKUKAN. STATUS PROJEK TERKINI: DALAM PEMBINAAN (EOT 61 HARI)
NAIKTARAF FASILITI BSGI KURSUS BAHARU PEMASANGAN DAN PENYELENGGARAAN ELEKTRIK SATU FASA DAN TIGA FASA MENGGUANAKANPENSIJILAN DUAL IAITU SIJIL KEMAHIRAN MALAYSIA (SKM) DAN KNX DI IKBN KINARUT, SABAH. Tajuk Projek : KONTRAKTOR : SABAR IMAN ENTERPRISE Pejabat incubator, Lot 18,S11, tingkat 2, Wisma SEDCO, Costal Highway,88000 Kota Kinabalu Sabah NO KONTRAK : JKR/IP/CSFB/19/2020 TARIKH MILIK TAPAK : 01 MAC 2022 TARIKH SIAP ASAL : 10 OKTOBER 2022 TARIKH SIAP BAHARU : 10 OKTOBER 2022 HARGA KONTRAK ASAL : RM807,137.45 KEMAJUAN KERJA : 100% NSC MEKANIKAL : TIADA SKOP KERJA MEKANIKAL % Jadual % Sebenar INTERNAL COLD WATER SYSTEM : 100% 100% INTERNAL SANITARY SYSTEM : 100% 100% AIR CONDITIONING SYSTEM, : 100% 100% VENTALITATION FAN 100% 100% TEMPOH SIAP : 32 MINGGU KAEDAH PERLAKSANAAN : KONVENSIONAL DALAMAN P. PENGUASA : JURUTERA AWAM KANAN, PPK2 PELANGGAN : KBS(IKBN KINARUT) PERUNDING MEKANIKAL : N/A WPP(M) : IR. ABDULDAN BIN ADTONG KOS KONTRAK MEKANIKAL : RM117,110.00 STATUS PROJEK : DALAM TEMPOH DLP
Gambar Projek Terkini (PIC:PJ Lazimih) Tangki Air … ISU DI TAPAK: Dalam proses pemasangan kerja –perja skop mekanikal • KERJA PEMASANGAN COLDWATER DAN SANITARI TELAH SIAP DILAKUKAN DI BLOK S DAN BLOK G. • KERJA PEMASANGAN EKZOS FAN DI BLOK S DAN BLOK G DILAKUKAN DAN PEMASANGAN AIRCOND JUGA TELAH DILAKUKAN DI SEMUA BLOK . • TESTING DAN COMMISIONING TELAH DILAKUKAN. VO. MEKANIKAL / OISSION / RASIONALISASI:- 1. VO UNTUK COLDWATER TANDAS PEREMPUAN BLOK G DISEBABAKAN MEMPENGERUHI PEMASANGAN SISTEM CLOD WATER LELAKI BLOK G. STATUS PROJEK TERKINI: - VO TELAH DILULUSKAN OLEH JAWATANKUASA. RM3,160.30
SISTEM PENCEGAH KEBAKARAN DAN SISTEM MEKANIKAL BERKAITAN UNTUK PEMBANGUNAN SISTEM KESELAMATAN ELEKTRONIK BERSEPADU SKEB DI 18 PENJARA – PENJARA KOTA KINABALU, PENJARA WANITA KOTA KINABALU, SEKOLAH HENRY GURNEY KENINGAU, PENJARA TAWAU DAN PENJARA SANDAKAN Tajuk Projek : KONTRAKTOR : ELECTRICA TECHNOLOGY SDN BHD NO KONTRAK : JKR/IP/CKE/122/2022 TARIKH MILIK TAPAK : 04 MAC 2022 TARIKH SIAP ASAL : 25 JANUARI 2024 TARIKH SIAP BAHARU : N/A HARGA KONTRAK ASAL : RM36,999,999.00 KEMAJUAN KERJA : 32.83% NSC MEKANIKAL : MNA INTEGRATED RESOURCES (M) SDN BHD SKOP KERJA MEKANIKAL % Jadual % Sebenar INTERNAL COLD WATER SYSTEM : 0% 0% INTERNAL SANITARY SYSTEM : 0% 0% AIR CONDITIONING SYSTEM, : 2% 2% VENTILATION FAN : 0% 0% TEMPOH SIAP : 99 MINGGU KAEDAH PERLAKSANAAN : NSC P. PENGUASA : PENGARAH PERKHIDAMATAN PAKAR CAWANGAN KEJURUTERAAN ELEKTRIK IPJKR PELANGGAN : PENJARA MALAYSIA PERUNDING MEKANIKAL : N/A HODT : CKM WPP(M) : IR. ABDULDAN BIN ADTONG KOS KONTRAK MEKANIKAL : RM1,125,595.00
Gambar Projek Terkini (PIC:PJ Lazimih) ISU DI TAPAK: PIHAK KONTRAKTOR MENYIMPAN PERALATAN DI PEJABAT KONTRAKTOR TAPAK PKK. (PENGHAWA DINGIN) STATUS PROJEK TERKINI: NSC Telah dilantik dan kerja skop mekanikal belum dimulakan di tapak.
PEMBINAAN BAHARU 2, BLOK ASRAMA LELAKI DAN PEREMPUAN, RUMAH WARDEN, DEWAN MAKAN UNTUK 400 PELAJAR, PRABOT DAN LAIN-LAIN KEMUDAHAN DI SMK PINGGAN-PINGGAN, PITAS SABAH ( REKA DAN BINA). Tajuk Projek : KONTRAKTOR : JT CEMERLANG SDN.BHD NO KONTRAK : TARIKH MILIK TAPAK : 23 DISEMBER 2023 TARIKH SIAP ASAL : 18 DISEMBER 2025 TARIKH SIAP BAHARU : N/A HARGA KONTRAK ASAL : RM 27,380,000.00 KEMAJUAN KERJA : 0.00% NSC MEKANIKAL : - SKOP KERJA MEKANIKAL % Jadual % Sebenar INTERNAL COLD WATER SYSTEM : 0% 0% INTERNAL SANITARY SYSTEM : 0% 0% AIR CONDITIONING SYSTEM : 0% 0% FIRE PROTECTION SYSTEM : 0% 0% KITCHEN EQUIPMENT SYSTEM : 0% 0% COLD ROOM : 0% 0% EMERGENCY SHOWER & EYE WASH : 0% 0% FUME CUPBOARD : 0% 0% TEMPOH SIAP : KAEDAH PERLAKSANAAN : TENDER (REKA DAN BINA) P. PENGUASA : PENGARAH PPK2 PELANGGAN : KEM. PENDIDIKAN MALAYSIA PERUNDING MEKANIKAL : N/A HODT : PENDIDIKAN & PENGAJIAN TINGGI WPP(M) : IR. ABDULDAN BIN ADTONG KOS KONTRAK MEKANIKAL : N/A
Gambar Projek Terkini (PIC:PJ Lazimih) ISU DI TAPAK: STATUS PROJEK TERKINI:
SABAH
TABURAN PROJEK SARAWAK
CADANGAN PEMBINAAN KOMPLEKS AGENSI PENGUATKUASAAN MARITIM MALAYSIA (APMM) DAERAH MARITIM MIRI, SARAWAK (REKA DAN BINA) Tajuk Projek : KONTRAKTOR : BANGKIT ENERGY & PRO LOGISTIC (EM) SDN. BHD. NO KONTRAK : JKR/IP/CKUB/93/2020 TARIKH MILIK TAPAK : 19/6/2020 TARIKH SIAP ASAL : 15/12/2022 EOT 1 – 60 HARI (PKP) TARIKH SIAP BAHARU : 13/2/2023 HARGA KONTRAK ASAL : RM 118,289,899.00 KEMAJUAN KERJA : 65% (Jadual) / 78% -12 DAYS (Sebenar) NSC MEKANIKAL : N/A SKOP KERJA MEKANIKAL % Jadual % Sebenar INTERNAL COLD WATER SYSTEM : 47.10 % 47.10 % INTERNAL SANITARY SYSTEM : 68.13 % 68.13 % FIRE PROTECTION SYSTEM : 19.06 % 19.06 % AIR CONDITIONING SYSTEM : 49.10 % 49.10 % LIFT SYSTEM : 22.04 % 22.04 % KITCHEN EQUIPMENT : 0 % 0 % NATURAL GAS SYSTEM : 0 % 0 % FUEL DISPENSING SYSTEM / BULK FUEL INSTALLATION : 34.59 % 34.59 % HIGH PRESSURE PUMPING SYSTEM FOR VEHICLE WASH : 22.94 % 22.94 % OIL INTERCEPTOR 70% 70% BOAT SLIPWAY, CRADDLE & WINCH SYSTEM : 37.25 % 37.25 % TEMPOH SIAP : 31 BULAN 26 HARI KAEDAH PERLAKSANAAN : REKA DAN BINA/TENDER TERBUKA P. PENGUASA : PENGARAH PEMBINAAN, PPK2 PELANGGAN : KEM. DALAM NEGERI (KDN) PERUNDING MEKANIKAL : Perunding Malca Sdn Bhd Iir. Kuan Chin Jong – 019 8348978 Ir. Ahmad Husairi (RE) – 0193253597 HODT : Ir. AZIZAH KASIM & Ir. SHAHLAN 013-9359240 WPP(M) : En. Mohd Herman bin Abu Bakar KOS KONTRAK MEKANIKAL : RM 13,006,242.00
Gambar Projek Terkini (PIC:JMK HERMAN) STATUS PROJEK TERKINI: Surat mohon bukti pengesahan Bomba berkaitan pengeluaran skop hosereel di blok kuarter berketinggian 8 tingkat dengan lif lobi tertutup dan tangga yang tertutup.
PEMBINAAN BANGUNAN TAMBAHAN HOSPITAL MIRI, SARAWAK (REKA DAN BINA)- TENDER SEMULA Tajuk Projek : KONTRAKTOR : RIAPLUS SDN. BHD. NO KONTRAK : JKR/IP/ CKUB/94/2020 TARIKH MILIK TAPAK : 25/6/2020 TARIKH SIAP ASAL : 18/10/2023 TARIKH SIAP BAHARU : 17/12/2023 HARGA KONTRAK ASAL : RM 289,200,000.00 KEMAJUAN KERJA : 49.78% (Jadual) / 49.79% +3 DAYS (Sebenar) NSC MEKANIKAL : N/A SKOP KERJA MEKANIKAL % Jadual % Sebenar INTERNAL COLD WATER SYSTEM : 61.33 % 61.33 % INTERNAL SANITARY SYSTEM : 90.66 % 90.66 % FIRE PROTECTION SYSTEM : 55.85 % 55.85 % AIR CONDITIONING SYSTEM : 36.59 % 36.59 % LIFT, ESCALATOR & DUMBWAITER SYSTEM : 75.74 % 75.74 % MEDICAL GASES PIPELINE SYSTEM : 19.12 % 19.12 % STERILIZERS AND ASSOCIATED EQUIPMENT : 0 % 0 % HEAT PUMPS, BOILERS, CALORIFIERS AND STEAM/HOT WATER RETICULATION SYSTEM : 0 % 0 % LIQUIDIFIED PETROLEUM GAS (LPG) : 0 % 0 % DENTAL UNIT AND EQUIPMENTS 36.17 % 36.17 % BUILDING SUPERVISORY SYSTEM : 0 % 0 % LABORATORY EQUIPMENTS : 61.33 % 61.33 % TEMPOH SIAP : 41 BULAN 22 HARI KAEDAH PERLAKSANAAN : REKA DAN BINA/TENDER TERBUKA P. PENGUASA : PENGARAH PEMBINAAN, PPK2 PELANGGAN : KEM. KESIHATAN MALAYSIA PERUNDING MEKANIKAL : KVA CONSULT Iir. Pua - 0196622829 HODT : Ir. YATIM 019-302 7070 WPP(M) : IR. ABDULDAN BIN ADTONG KOS KONTRAK MEKANIKAL : RM 71,385,186.00
Gambar Projek Terkini (PIC:JMK Herman) STATUS PROJEK TERKINI: N/A
PEMBINAAN RUMAH KELUARGA ANGKATAN TENTERA (RKAT) DI KEM SRI MIRI, MIRI, SARAWAK - FASA 2 (REKA & BINA) Tajuk Projek : KONTRAKTOR : DERMAGA MAKMUR SDN BHD NO KONTRAK : JKR/IP/CKUB/37/2018 TARIKH MILIK TAPAK : 22/2/2018 TARIKH SIAP ASAL : 17/2/2021 EOT 1 – 56 HARI (PKP) EOT 2 – 58 HARI (PKPB) EOT 3 – 78 HARI (Isu Tenaga Kerja – Penutupan Sempadan - PKP) EOT 4 – 60 HARI (PKP) EOT 5 – 91 HARI (Isu Kesukaran mendapat bekalan perabot) TARIKH SIAP SEBENAR (CPC) : 26-01-2022 HARGA KONTRAK ASAL : RM 39,165,285.98 KEMAJUAN KERJA - SEPT 2021 : 100% (Jadual) / 97.33% -41 DAYS (Sebenar) LAD 1 – 43 Hari NSC MEKANIKAL : N/A SKOP KERJA MEKANIKAL % Jadual % Sebenar INTERNAL COLD WATER SYSTEM : 100 % 100 % INTERNAL SANITARY SYSTEM : 100 % 100 % PORTABLE FIRE EXTIGUISHER : 100 % 100 % VENTILATION SYSTEM : 100 % 100 % TEMPOH SIAP : 47 BULAN 5 HARI KAEDAH PERLAKSANAAN : REKA DAN BINA/TENDER TERHAD P. PENGUASA : PENGARAH PEMBINAAN, PPK2 PELANGGAN : KEM. PERTAHANAN (MINDEF) PERUNDING MEKANIKAL : PERUNDING WES SDN BHD kuan HODT : Ir. AZIZAH KASIM & Ir. SHAHLAN 013-9359240 WPP(M) : En. Mohd Herman bin Abu Bakar KOS KONTRAK MEKANIKAL : RM 1000,000.00
Gambar Projek Terkini (PIC:JMK Herman) STATUS PROJEK TERKINI: N/A
PEMBINAAN KEM 2 SKN RAJD, OYA, SIBU, SARAWAK (REKA & BINA) Tajuk Projek : STATUS PROJEK TERKINI: N/A KONTRAKTOR : WEKAJAYA SDN. BHD. NO KONTRAK : JKR/IP/CKUB/225/2020 TARIKH MILIK TAPAK : 16/12/2020 TARIKH SIAP ASAL : 13/6/2023 EOT 1 – 60 HARI (PKP) TARIKH SIAP BAHARU : 12/8/2023 HARGA KONTRAK ASAL : RM 38,800,000.00 KEMAJUAN KERJA : 46% (Jadual) / 47% +1 DAYS (Sebenar) NSC MEKANIKAL : N/A SKOP KERJA MEKANIKAL % Jadual % Sebenar INTERNAL COLD WATER SYSTEM : 0 % 0 % INTERNAL SANITARY SYSTEM : 10 % 10 % FIRE PROTECTION SYSTEM : 0 % 0 % AIR CONDITIONING SYSTEM : 0 % 0 % BOOSTER PUMP : 0 % 0 % TEMPOH SIAP : 32 BULAN KAEDAH PERLAKSANAAN : REKA DAN BINA/TENDER TERBUKA P. PENGUASA : PENGARAH PEMBINAAN, PPK2 PELANGGAN : KEM. PERTAHANAN (MINDEF) PERUNDING MEKANIKAL : Perunding UZL Ho Yong Kai – 013 8143008 HODT : Ir. AZIZAH KASIM & Ir. Naguib 012-6694799 WPP(M) : En. Mohd Herman bin Abu Bakar KOS KONTRAK MEKANIKAL : RM 1,850,000.00
Gambar Projek Terkini (PIC:JMK Herman)
PROJEK PEMBINAAN RKAT TAMBAHAN PELBAGAI KELAS KEM BATU 10 SIBU, SARAWAK (TENDER SEMULA) Tajuk Projek : KONTRAKTOR : ALAMGHIR SDN. BHD. NO KONTRAK : JKR/IP/CKUB/76/2022 TARIKH MILIK TAPAK : 07/4/2022 TARIKH SIAP ASAL : 31/7/2024 TARIKH SIAP BAHARU : 31/7/2024 HARGA KONTRAK ASAL : RM 30,975,775.00 KEMAJUAN KERJA : 6.09% (Jadual) / 5.23% -43 DAYS (Sebenar) NSC MEKANIKAL : N/A SKOP KERJA MEKANIKAL % Jadual % Sebenar INTERNAL COLD WATER SYSTEM : 0 % 0 % INTERNAL SANITARY SYSTEM : 0 % 0 % FIRE PROTECTION SYSTEM : 0 % 0 % AIR CONDITIONING SYSTEM : 0 % 0 % BOOSTER PUMP : 0 % 0 % TEMPOH SIAP : 28 BULAN KAEDAH PERLAKSANAAN : KONVENSIONAL PERUNDING/TENDER TERBUKA P. PENGUASA : PENGARAH PEMBINAAN, PPK2 PELANGGAN : KEM. PERTAHANAN (MINDEF) PERUNDING MEKANIKAL : CH Engineering Ir. Robert Tan Wei – 0128082338 Mustaqim – 0138085859 HODT : Ir. AZIZAH KASIM & Ir. Naguib 012-6694799 WPP(M) : Ir. Abduldan bin Adtong KOS KONTRAK MEKANIKAL : Dalam Proses Pakej (Anggaran RM500,000.00)
Gambar Projek Terkini (PIC:JMK Herman) STATUS PROJEK TERKINI: Pengalihan Lokasi Elevated Watertank Bersama dengan rumah pamnya. Pindaan Rekabentuk akan berlaku.
CADANGAN HOSPITAL BARU SRI AMAN, SARAWAK (108 KATIL) FASA 2: KERJA BANGUNAN DAN KERJA BERKAITAN. Tajuk Projek : KONTRAKTOR : FALTECH ENGINEERING SB JV WELFIELD SERVICES SB NO KONTRAK : JKR/IP/CKUB/216/2015 TARIKH MILIK TAPAK : 26 OKTOBER 2015 TARIKH SIAP ASAL : 25 OKTOBER 2018 EOT 1 – 282 HARI EOT 2 – 178 HARI EOT 3 – 261 HARI EOT 4 – 56 HARI EOT 5 – 58 HARI EOT 6 – 119 HARI EOT 7 – 207 HARI EOT 8 – 60 HARI TARIKH SIAP BAHARU : 27 FEBRUARI 2022 HARGA KONTRAK ASAL : RM 176,275,304.36 RM 181,476,154.45 (SEMASA) KEMAJUAN KERJA - FEB 2022 : SIAP NSC MEKANIKAL : - SKOP KERJA MEKANIKAL % Jadual % Sebenar INTERNAL COLD WATER SYSTEM : 100 % 100 % INTERNAL SANITARY SYSTEM : 100 % 100 % FIRE PROTECTION SYSTEM : 100 % 100 % AIR CONDITIONING SYSTEM : 100 % 100 % LIFT SYSTEM : 100 % 100 % HOT WATER : 100 % 100 % KITCHEN EQ & LPG : 100 % 100 % MEDICAL GAS : 100 % 100 % CSSD : 100 % 100 % MORTUARY : 100 % 100 % DENTAL : 100 % 100 % BAS : 100 % 100 % LAB EQ : 100 % 100 % RO WATER : 100 % 100 % TEMPOH SIAP : 76 BULAN 2 HARI KAEDAH PERLAKSANAAN : KONVENSIONAL PERUNDING P. PENGUASA : PENGARAH PEMBINAAN, PPK2 PELANGGAN : KEM. KESIHATAN MALAYSIA PERUNDING MEKANIKAL : UTAS KESTURI SB (IR. MOHD NORAZMAN BIN MOHD SHARKAWI 013-8018118) HODT : IR. YATIM SELAMAT BIN LATIB WPP(M) : Mohd Herman bin Abu Bakar KOS KONTRAK MEKANIKAL : RM 38,729,803.00
Gambar Projek Terkini (PIC:JMK Herman) VO. MEKANIKAL / OMISSION / RASIONALISASI:- 1. VO.1 – PINDAAN KITCHEN EQ LAYOUT (RM 0.00) 2. VO.2 – PINDAAN HOT WATER DI KITCHEN (RM 0.00) 3. VO.3 – PINDAAN SAIZ PINTU LIF DI KUARTERS (RM -3,735.20) 4. VO.4 – PINDAAN FF DI KITCHEN (RM 0.00) 5. VO.5 – PINDAAN ACMV DI KITCHEN (RM0.00) 6. VO.6 – PINDAAN KEPADA DUCTLESS FUME CABINET (RM -19,790.00) 7. VO.7 – PINDAAN MGPS BILIK MA4 (RM -7,918.00) 8. VO.8 – PINDAAN ACMV DISEBABKAN VO.6 & VO.7 (RM 0.00) 9. VO.9 – PINDAAN FF PERTAMBAHAN DINDING DI BLOK ELEKTRIK (RM 14,950.00) 10.VO.10 – PINDAAN ACMV PERTAMBAHAN DINDING DI BLOK ELEKTRIK (RM 2,456.00) 11.VO.11 – PINDAAN ACMV PERTAMBAHAN BILIK NOC (RM -5,945.00) 12.VO.12 – PINDAAN FF PERTAMBAHAN BILIK NOC (RM -36,585.00) 13.VO.13 – PINDAAN PERTUKARAN MODEL COOLING TOWER (RM 0.00) 14.VO.14 – PINDAAN ACMV EXHAUST FAN (RM -10,779.00) 15.VO.15 – PINDAAN ACMV PERUBAHAN CHILLED PIPE SIZE (DIBATALKAN) 16.VO.16 – PINDAAN CONTROL PANEL ACMV (RM 7671.20) TAMBAHAN = RM 25,077.20 PENOLAKAN = RM 87,972.20 STATUS PROJEK TERKINI: • ISU DLP : September 2022 - Telah berlaku Power Surge dari Sesco menyebabkan motor cooling tower terbakar dan chiller No.1 ditutup buat sementara waktu sehingga siasatan selesai. • ISU DLP : December – Empat aduan, iaitu bunyi diffuser bising di department IT, Kebocoran AHU dalam Siling, Lif dimasuki air dan isu kelemahan rekabentuk sterile room di Operation Theatre (OT) department Maklumbalas: Bunyi bising disebabkan oleh air balancing dan masalah vav box. Isu sterile store room sedang menunggu maklumbalas HODT
PEMBINAAN GANTIAN PENUH 30 BILIK DARJAH, ASRAMA 600 PELAJAR DAN RUMAH GURU 12 UNIT DAN LAIN-LAIN KEMUDAHAN DI SEKOLAH SK ABANG LEMAN, SARATOK, SARAWAK Tajuk Projek : KONTRAKTOR : ECOBINA TECHNOLOGIES SDN. BHD. NO KONTRAK : KPM/BP/2019/12 TARIKH MILIK TAPAK : 1 FEB 2020 TARIKH SIAP ASAL : 5 NOV 2022 EOT 1 – 56 HARI (PKP 1.0) EOT 2 – 58 HARI (PKP 2.0) EOT 3 – 60 HARI (PKP 3.0) EOT 4 – 206 HARI TARIKH SIAP BAHARU : 20 NOVEMBER 2023 HARGA KONTRAK ASAL : RM 42,000,000.00 KEMAJUAN KERJA : 61.20% (Jadual) / 61.31 % (Sebenar) +1 DAYS NSC MEKANIKAL : - SKOP KERJA MEKANIKAL (FASA 1) % Jadual % Sebenar INTERNAL COLD-WATER SYSTEM : 20.95 % 20.95 % SANITARY PIPING SYSTEM : 22.30 % 22.30 % FIRE PROTECTION SYSTEM : 21.02 % 21.02 % AIR CONDITIONING SYSTEM : 12.05 % 12.05 % KITCHEN EQUIPMENT : 50.96 % 50.96 % TEMPOH SIAP : 36 BULAN / 144 MINGGU KAEDAH PERLAKSANAAN : KONVENSIONAL PERUNDING P. PENGUASA : PENGARAH PEMBINAAN, PPK2 PELANGGAN : KEM. PENDIDIKAN MALAYSIA PERUNDING MEKANIKAL : JURUTERA IRIAZ SDN BHD HODT : - WPP(M) : JURUTERA IRIAZ SDN BHD KOS KONTRAK MEKANIKAL : RM 1,945,755.00 STATUS PROJEK : PEMBINAAN
Gambar Projek Terkini (PIC:PJ Hairi) VO. MEKANIKAL / OMISSION / RASIONALISASI 1. PERUBAHAN KLINIK GIGI-BLOK PENTADBIRAN (TINGKAT BAWAH) 2. MENGGANTIKAN PAM SISTEM HOSEREEL UNTUK MEMATUHI MS 2616 MENGIKUT KEHENDAK BOMBA. TINDAKAN /STATUS: 1. PERMOHONAN UNTUK T.O.P BANGUNAN ASRAMA PEREMPUAN & DEWAN MAKAN (ELECTRICAL SUPPLY) TELAH DIHANTAR KEPADA PIHAK MAJLIS DAERAH SARATOK PADA 24/2/22-MASIH MENUNGGU TINDAKAN/KEPUTUSAN DARI MD SARATOK
DAIF SARAWAK (2021) - PEMBINAAN GANTIAN DAN TAMBAHAN BANGUNAN DI SMK SG. PAOH, SARIKEI, SARAWAK (REKA & BINA) Tajuk Projek : STATUS PROJEK TERKINI: PEMBINAAN KONTRAKTOR : ASARAJAYA SDN. BHD. NO KONTRAK : JKR/IP/CKUB/254/2022 TARIKH MILIK TAPAK : 06-10-2022 TARIKH SIAP ASAL : 07-08-2024 TARIKH SIAP BAHARU : 07-08-2024 HARGA KONTRAK ASAL : 15,297,769.43 KEMAJUAN KERJA : 3.52% (Jadual) / 2.00 % (Sebenar) -8 DAYS NSC MEKANIKAL : N/A SKOP KERJA MEKANIKAL % Jadual % Sebenar INTERNAL COLD-WATER SYSTEM : 0 % 0 % SANITARY PIPING SYSTEM : 0 % 0 % FIRE PROTECTION SYSTEM : 0 % 0 % AIR CONDITIONING SYSTEM : 0 % 0 % TEMPOH SIAP : 22 BULAN KAEDAH PERLAKSANAAN : REKA DAN BINA/TENDER TERBUKA P. PENGUASA : PENGARAH PEMBINAAN, PPK2 PELANGGAN : KEM. PENDIDIKAN PERUNDING MEKANIKAL : CH ENGINEERING HODT : En. Mohd Nazril bin Mohamed WPP(M) : En. Mohd Herman bin Abu Bakar KOS KONTRAK MEKANIKAL : RM 15,297,769.43
Gambar Projek Terkini (PIC:JMK Herman)
PEMBANGUNAN SISTEM KESELAMATAN ELEKTRONIK BERSEPADU SKEB DI 18 PENJARA – PENJARA PUNCAK BORNEO (TAWARAN SEMULA) Tajuk Projek : STATUS PROJEK TERKINI: PEMBINAAN KONTRAKTOR : JM Letrik Sdn. Bhd NO KONTRAK : JKR/IP/CKE/20/2022 TARIKH MILIK TAPAK : 01-03-2022 TARIKH SIAP ASAL : 27-02-2023 TARIKH SIAP BAHARU : 27-02-2023 HARGA KONTRAK ASAL : RM 11,288,000.00 KEMAJUAN KERJA - SEPT 2022 : 29.42% (Jadual) / 34.99% +0 DAYS (Sebenar) NSC MEKANIKAL : N/A SKOP KERJA MEKANIKAL % Jadual % Sebenar INTERNAL COLD WATER SYSTEM : 0 % 0 % INTERNAL SANITARY SYSTEM : 0 % 0 % FIRE PROTECTION SYSTEM : 0 % 0 % AIR CONDITIONING SYSTEM : 0 % 0 % BOOSTER PUMP : 0 % 0 % TEMPOH SIAP : 26 BULAN KAEDAH PERLAKSANAAN : KONVENSIONAL PERUNDING/TENDER TERBUKA P. PENGUASA : Pengarah II Cawangan Kejuruteraan Elektrik PELANGGAN : KEM. KESELAMATAN DALAM NEGERI PERUNDING MEKANIKAL : - HODT : Khairul Azmir WPP(M) : Ir. Abduldan bin Adtong KOS KONTRAK MEKANIKAL :
Gambar Projek Terkini (PIC:JMK Herman/ JM Maritha)
PROJEK PEMBINAAN DAN PENYIAPAN HOSPITAL PENGAJAR DAN PUSAT KESIHATAN PRIMA (PKP) UNIVERSITI MALAYSIA SARAWAK (UNIMAS), KOTA SAMARAHAN, SARAWAK (REKA DAN BINA) Tajuk Projek : KONTRAKTOR : PERBENA EMAS SDN. BHD. NO KONTRAK : JKR/IP/CKUB/40/2021 TARIKH MILIK TAPAK : 24 MAC 2021 TARIKH SIAP ASAL : 18 MAC 2025 EOT 1 (60 HARI) EOT 2 (127 HARI) TARIKH SIAP SEMASA : 21 SEPTEMBER 2025 (EOT 2) HARGA KONTRAK ASAL : RM485,988,888.00 KEMAJUAN KERJA : 20.01% (Jadual) / 26.99% (Sebenar) Varian Siap: Awal 17 Hari TEMPOH SIAP : 48 BULAN KAEDAH PELAKSANAAN : REKA DAN BINA P. PENGUASA : PENGARAH PEMBINAAN, PPK2 PELANGGAN : KEM. PENGAJIAN TINGGI PERUNDING MEKANIKAL : AYA ENGINEERS SDN BHD (CIK NAZHIRAH – 0164974364) HODT : Ir. YATIM SELAMAT BIN LATIB WPP(M) : Ir. ABDULDAN BIN ADTONG KOS KONTRAK MEKANIKAL : RM 95,615,357.00 STATUS PROJEK TERKINI:
Gambar Projek Terkini (PIC:JM Maritha) PERINCIAN SKOP KERJA MEKANIKAL FASA 1 BLOK PKP SURAU CAFE CRECHE M&E PLANT ROOM % Jadual % Sebenar % Jadual % Sebenar % Jadual % Sebenar % Jadual % Sebenar % Jadual % Sebenar OVERALL MECHANICAL PROGRESS BY BLOCK 44.94% 47.23% 15.92% 26.30% 22.76% 25.90% 20.22% 43.56% 53.03% 26.54% INTERNAL COLDWATER SYSTEM 40.42% 66.96% 31.08% 39.49% 20.90% 48.61% 30.51% 50.42% 100% 71.93% INTERNAL SANITARY SYSTEM 40.42% 66.96% 31.08% 39.49% 20.90% 48.61% 30.51% 50.42% 100% 71.93% FIRE PROTECTION SYSTEM 39.39% 19.87% 0% 0% 31.82% 12.73% 0% 0% 16.45% 0% AIR CONDITIONING SYSTEM 59.84% 61.19% 0% 24.00% 22.76% 25.90% 0% 36.00% 58.60% 18.07% LIFT SYSTEM 14.55% 0.00 % NA NA NA NA NA NA NA NA MEDICAL GASES SYSTEM 34.42% 44.46% NA NA NA NA NA NA 11.97% 0% HOT WATER RETICULATION SYSTEM 0.00% 23.77% NA NA NA NA NA NA NA NA BUILDING SUPERVISORY SYSTEM 60.32% 29.40% NA NA NA NA NA NA 0% 5.00% MEDICAL EQUIPMENT NA NA NA NA NA NA NA NA NA NA LIPG NA NA NA NA 23.73% 9.46% NA NA NA NA KITCHEN EQUIPMENT NA NA NA NA 36.84% 0% NA NA NA NA
MENYIAPKAN BAKI KERJA TERBENGKALAI BAGI CADANGAN PEMBINAAN HOSPITAL PETRAJAYA (300 KATIL) PETRAJAYA, KUCHING, SARAWAK (REKA DAN BINA) - TENDER SEMULA Tajuk Projek : KONTRAKTOR : BLACKFOX ENGINEERING SDN. BHD. NO KONTRAK : JKR/IP/CKUB/231/2020 TARIKH MILIK TAPAK : 11 JANUARI 2021 TARIKH SIAP ASAL : 07 JANUARI 2024 EOT 1 – 07 MAC 2024 TARIKH SIAP BAHARU : 07 MAC 2024 HARGA KONTRAK ASAL : RM410,300,000.00 KEMAJUAN KERJA : 26.14% (Jadual) / 27.92% (Sebenar) Varian Siap: Awal 31 hari NSC MEKANIKAL : - SKOP KERJA MEKANIKAL % Jadual % Sebenar ACMV : % 38.00% Lifts & Escalators : % 0% Medical Gases Pipeline : % 9.00% Fire Protection Systems : % 22.50% LPG : % 0% Building Supervisory System : % 0% Hot Water Reticulation System : % 23.84% Pneumatic Tube System % 0% Kitchen Equipment & Central Plating % 0% Cold Room & Associated Equipment : % 0% Internal Cold Water ; % 24.89% Internal Sanitary & Wastewater System : % 31.00% Hydrotherapy Pool System : % 0% Reverse Osmosis (RO) Water System : % 0% Medical Equipment : 0% 0% Audiiometry Room (ENT) : 0% 0% Operation and Maintenance Manuals 0% 0% TEMPOH SIAP : 164 MINGGU KAEDAH PERLAKSANAAN : REKA DAN BINA P. PENGUASA : PENGARAH PEMBINAAN, PPK2 PELANGGAN : KEM. KESIHATAN MALAYSIA PERUNDING MEKANIKAL : DPI KONSULT (EN. IZAIDY – 017 582 4054) HODT : Ir. YATIM SELAMAT BIN LATIB WPP(M) : Ir. ABDULDAN BIN ADTONG KOS KONTRAK MEKANIKAL : RM 96,689,728.00
Gambar Projek Terkini (PIC:JM Maritha) VO. MEKANIKAL / OMISSION / RASIONALISASI:- Kerja pemasangan infra (perpaipan) untuk portable RO – kontraktor sedang menyediakan dokumen berkaitan (lukisan laluan paip) dan implikasi kos akan dikemukakan dalam masa terdekat. ISU DI TAPAK: 1) Kontraktor berhasrat untuk menggunapakai preinsulated chilled water pipes sediada di tapak. STATUS PROJEK TERKINI: 1) Surat WPPM telah dikeluarkan di mana pihak kontraktor perlu kemuka Laporan Teknikal keadaan paip berkenaan daripada pihak ketiga/ pembekal paip.
KERJA PENGGANTIAN LIF DI HOSPITAL UMUM SARAWAK, SARAWAK Tajuk Projek : ISU DI TAPAK: 1) Kerja kontraktor terutamanya di Blok Klinikal agak terjejas sekiranya terdapat aduan daripada end user untuk hentikan kerja bagi elak bunyi bising.Perkara ini berlaku apabila pembedahan sedang berlangsung STATUS PROJEK TERKINI: 1) Kontraktor diarah untuk merekod setiap stop work order yang berkaitan dengan tempoh masa. End user dinasihatkan supaya memaklumkan juga masa yang dibenarkan untuk mula kerja. KONTRAKTOR : DASACON SDN. BHD. NO KONTRAK : JKR/IP/CKM/88/2022 TARIKH MILIK TAPAK : 4 APRIL 2022 TARIKH SIAP ASAL : 3 APRIL 2023 TARIKH SIAP SEMASA : 3 APRIL 2023 HARGA KONTRAK ASAL : RM 2,788,420.00 KEMAJUAN KERJA : 64% (Jadual) / 63% (Sebenar) (LEWAT 65 HARI) *tracking menggunapakai Program Kerja Asal Kontraktor sedang dalam proses pindaan Program Kerja (EOT No.1) NSC MEKANIKAL : TIDAK BERKENAAN TEMPOH SIAP : 52 MINGGU KAEDAH PERLAKSANAAN : JKR IN-HOUSE P. PENGUASA : JURUTERA MEKANIKAL PENGUASA KANAN PELANGGAN : KEMENTERIAN KESIHATAN MALAYSIA PERUNDING MEKANIKAL : TIDAK BERKENAAN HODT : Ir. ZALINA BINTI MOHD YUSUF WPP(UTAMA) : MOHD HERMAN BIN ABU BAKAR KOS KONTRAK MEKANIKAL : RM 2,788,420.00
Gambar Projek Terkini (PIC:JM Maritha)
PEMBINAAN KOMPLEKS BATALION 10, PGA SARIKEI, SARAWAK) Tajuk Projek : ISU DI TAPAK: 1) Kontraktor memohon untuk laksana kerja-kerja di bawah sistem mekanikal (kecuali SR) STATUS PROJEK TERKINI: 1) Telah memohon kontraktor untuk mengemukakan salinan kepala bidang bagi kerja-kerja berkaitan untuk tindakan lanjut. KONTRAKTOR : MIRECONT SDN. BHD. NO KONTRAK : JKR/IP/CKUB/ TARIKH MILIK TAPAK : 8/3/2022 TARIKH SIAP ASAL : 3/3/2025 TARIKH SIAP BAHARU : 3/3/2025 HARGA KONTRAK ASAL : RM 212,430,647.58 KEMAJUAN KERJA : 6.50% (Jadual) / 4.40% (Sebenar) LEWAT 19 HARI NSC MEKANIKAL : MSK BUILDER HOLDINGS (M) SDN BHD – SR System SKOP KERJA MEKANIKAL % Jadual % Sebenar INTERNAL COLD WATER SYSTEM : 0 % 0 % INTERNAL SANITARY SYSTEM : 0 % 0 % FIRE PROTECTION SYSTEM : 0 % 0 % AIR CONDITIONING & VENTILATION SYSTEM : 0 % 0 % SHOOTING RANGE SYSTEM : 0 % 0 % LAB EQUIPMENT : 0 % 0 % KITCHEN EQUIPMENT : 0 % 0 % TEMPOH SIAP : 35 BULAN 23 HARI KAEDAH PERLAKSANAAN : KONVENSIONAL PERUNDING /TENDER TERBUKA P. PENGUASA : PENGARAH PEMBINAAN, PPK2 PELANGGAN : KEM. DALAM NEGERI (KDN) PERUNDING MEKANIKAL : Perunding MME SDN BHD Ir abg mohammad moasili bin hj naili Dayang Zainab – 013-8038700 HODT : Ir. AZIZAH KASIM & Ir. Naguib 012-6694799 WPP(M) : Ir. Abduldan bin Adtong KOS KONTRAK MEKANIKAL : -
Gambar Projek Terkini (PIC:JM Maritha)
PEMBINAAN BAHARU SEKOLAH MENENGAH PENDIDIKAN KHAS VOKASIONAL (SMPKV) PADAWAN, SARAWAK (REKA & BINA) Tajuk Projek : STATUS PROJEK TERKINI: PEMBINAAN KONTRAKTOR : HIMPUN DAYA SDN BHD NO KONTRAK : JKR/IP/CKUB/174/2021 TARIKH MILIK TAPAK : 06-08-2021 TARIKH SIAP ASAL : 30-01-2025 TARIKH SIAP BAHARU : 17-06-2025 HARGA KONTRAK ASAL : RM 78,999,000.00 KEMAJUAN KERJA : 9.44% (Jadual) / 5.06% (Sebenar) LEWAT 45 HARI NSC MEKANIKAL : N/A SKOP KERJA MEKANIKAL % Jadual % Sebenar INTERNAL COLD WATER SYSTEM : 0 % 0 % INTERNAL SANITARY SYSTEM : 0 % 0 % FIRE PROTECTION SYSTEM : 0 % 0 % AIR CONDITIONING SYSTEM : 0 % 0 % LIQUIDIFIED PETROLEUM GASES (LPG) SYSTEM : 0 % 0 % KITCHEN EQUIPMENT : 0 % 0 % BOOSTER PUMP : 0 % 0 % TEMPOH SIAP : 26 BULAN KAEDAH PERLAKSANAAN : REKA & BINA /TENDER TERBUKA P. PENGUASA : PENGARAH PEMBINAAN, PPK2 PELANGGAN : KEM. PENDIDIKAN MALAYSIA PERUNDING MEKANIKAL : Konsortium Bumi Consultant HODT : Ir. ZAINI & Pn. Ernawati WPP(M) : Ir. Abduldan bin Adtong KOS KONTRAK MEKANIKAL :
Gambar Projek Terkini (PIC:JM Maritha)
KERJA-KERJA PENGGANTIAN SISTEM PENYAMAN UDARA JENIS ‘AIR COOLED CHILLER’ DAN LAIN-LAIN KERJA BERKAITAN DI KOMPLEKS MAHKAMAH, KUCHING, SARAWAK Tajuk Projek : STATUS PROJEK TERKINI: PEMBINAAN KONTRAKTOR : TUAH KEKAL HOLDINGS SDN BHD NO KONTRAK : JKR/IP/CKM/190/2022 TARIKH MILIK TAPAK : 03 OGOS 2022 TARIKH SIAP ASAL : 02 OGOS 2023 TARIKH SIAP BAHARU : - HARGA KONTRAK ASAL : RM 5,677,948.00 KEMAJUAN KERJA - SEPTEMBER 2022 : 53% (Jadual) / 52% (Sebenar) Varian Siap: 0 HARI LEWAT NSC MEKANIKAL : - SKOP KERJA MEKANIKAL % Jadual % Sebenar PRELIMINARIES - - DISMANTLING WORKS - - AIRCOOLED CHILLER SYSTEM - - CIVIL WORK : - - ELECTRICAL WORK - - AIRCONDITIONER SYSTEMS RENTAL - - TEMPOH SIAP : 12 BULAN KAEDAH PERLAKSANAAN : KONVENSIONAL PERUNDING P. PENGUASA : PENGARAH PEMBINAAN, PPK2 PELANGGAN : Bahagian Hal Ehwal Undang-Undang (BHEUU, JPM) HOPT : CSFB (En. Ab Rahim bin Mohd@Mohktar , En Abdul Khalid Bin Mohamad Dol) HODT : CKM (En. Khairuddin B Ibrahim, En. Burqanuddin) SO : Mohd Herman bin Abu Bakar WPS : RM 400,000.00
Gambar Projek Terkini (PIC:JM Maritha)
CADANGAN PEMBINAAN BANGUNAN TAMBAHAN 10 BD DAN LAIN-LAIN KEMUDAHAN DI SMK PADAWAN, SARAWAK Tajuk Projek : STATUS PROJEK TERKINI: PEMBINAAN KONTRAKTOR : IZRA ENTERPRISE SDN BHD NO KONTRAK : JKR/IP/CKUB/58/2022 TARIKH MILIK TAPAK : 17/3/2022 TARIKH SIAP ASAL : 14/2/2024 TARIKH SIAP SEMASA : 14/5/2024 (EOT No.1) HARGA KONTRAK ASAL : RM 11,846,947.90 KEMAJUAN KERJA – 25 Jan 2023 : 24.23% (Jadual) / 19.00% (Sebenar)* LEWAT49 HARI * Berdasarkan Program Kerja Asal NSC MEKANIKAL : MERGE RESOURCES SKOP KERJA MEKANIKAL % Jadual % Sebenar INTERNAL COLD WATER & SANITART PLUMBING SYSTEM : 0 % 0 % AIR CONDITIONING & VENTILATION SYSTEM : 0 % 0 % FIRE PROTECTION SYSTEM : 0 % 0 % TEMPOH SIAP : 100 MINGGU KAEDAH PELAKSANAAN : KONVENSIONAL PERUNDING P. PENGUASA : PENGARAH PEMBINAAN, PPK2 PELANGGAN : KEM. PENDIDIKAN MALAYSIA (KPM) PERUNDING MEKANIKAL : UTAS KESTURI SDN. BHD. HODT : En. Ahmad Jalil Bin Jaafar WPP(M) : Maritha Demi Anak John KOS KONTRAK MEKANIKAL : RM 572,121,00
Gambar Projek Terkini (PIC:JM Maritha)
PEMBINAAN GANTIAN 18BD DAN LAIN-LAIN KEMUDAHAN DI SMK DALAT, DALAT, SARAWAK (REKA DAN BINA) Tajuk Projek : STATUS PROJEK TERKINI: PEMBINAAN KONTRAKTOR : WELFIELD SERVICES SDN.BHD. NO KONTRAK : JKR/IP/CKUB/ BELUM ADA MAKLUMAT - SKALA TARIKH MILIK TAPAK : 22/11/2022 TARIKH SIAP ASAL : 23/06/2025 TARIKH SIAP SEMASA : 23/06/2025 HARGA KONTRAK ASAL : RM 27,198,398.14 KEMAJUAN KERJA – Jan 2023 : TIADA MAKLUMAT NSC MEKANIKAL : TIDAK BERKENAAN SKOP KERJA MEKANIKAL % Jadual % Sebenar INTERNAL COLD WATER & SANITART PLUMBING SYSTEM : 0 % 0 % AIR CONDITIONING & VENTILATION SYSTEM : 0 % 0 % FIRE PROTECTION SYSTEM : 0 % 0 % TEMPOH SIAP : 135 MINGGU KAEDAH PELAKSANAAN : REKA DAN BINA / TENDER TERBUKA P. PENGUASA : PENGARAH PEMBINAAN, PPK2 PELANGGAN : KEM. PENDIDIKAN MALAYSIA (KPM) PERUNDING MEKANIKAL : HODT : Ir. MOHAMAD ZAINI BAKAR WPP(M) : Belum ada lantikan WPP(M) KOS KONTRAK MEKANIKAL :