CONFIDENTIAL AND PROPRIETARY EBIT - FINAL DASH 2023 Prepared by Suhana binti Razali Sept 2023 TNB Kuantan Deliverables • EBIT : RM2.63mil Suhana (L) Sauqi Wong Siti Adhlin KJ Affendi Logeswari Emilda


EBIT - FINAL DASH 2023 - UMT: RM 262.7M Result : RM97M / RM153M 1775.7 3044.1 3114.6 3049.3 1679.32710.4 2717.0 2668.3 97.0 166.2 277.8 262.8 153.3 262.8 262.8 262.8 JUL-23 ANN. FORECAST UMT PBT : FORECAST Revenue Cost PBT UMT PBT A B A . Annualise Jul 23, PBT result RM 166.2mil /RM262.8mil at MT. B. If forecast Capex RM2,808, PBT result RM277.8mil/RM262.8 mil at UMT.


EBIT - FINAL DASH 2023 - UMT: RM 262.7M Result : RM97M / RM153M 1775.7 3044.1 3114.6 3049.3 1679.32710.4 2717.0 2668.3 97.0 166.2 277.8 262.8 153.3 262.8 262.8 262.8 JUL-23 ANN. FORECAST UMT PBT : FORECAST Revenue Cost PBT UMT PBT A B A . Annualise Jul 23, PBT result RM 166.2m /RM262.8m at MT B. If forecast Capex RM2,808, PBT result RM277.8m/RM262.8m at UMT 49.14 24.37 24.78 31.73 11.59 20.13 20.07 -3.96 96.97 88.51 50.68 37.83 42.93 41.66 1.2721.8 153.24 SECTOR 1 SOUTH SELPJC SECTOR 2 NORTH EAST K L H Q SBU AD PBT JUL 23 & ANNUALISED BY ZONE PBT Jul 23 Monthly Target


Revenue (2022 vs 2023) Compared to Jul 22 total Revenue from Cost Saving decreased almost 50%. The current situation is caused by inadequate monitoring of Total Project before the project start until closed, resulting in costs burst Jan 2023 - Jul 2022 Jan 2023 - Jul 2023 FY22-FY21 = - / + Capex Utilization Voltage Total Voltage Total 11kV 682,258,900 11kV 953,450,120 271,191,220 39.75% 33kV 546,953,517 33kV 569,331,701 22,378,183 4.09% SJ-AD 124,640,038 SJ-AD 148,604,445 23,964,407 19.23% Grand Total 1,353,852,456 Grand Total 1,671,386,266 317,533,810 23.45% Cost Saving Voltage Total Voltage Total 11kV 179,710,645 11kV 75,618,073 -104,092,572 -57.92% 33kV 71,400,745 33kV 28,706,206 -42,694,540 -59.80% SJ-AD Grand Total 251,111,390 Grand Total 104,324,279 -146,787,112 -58.45% Total Capex + Cost Saving Voltage Total Voltage Total 11kV 861,969,545 11kV 1,029,068,193 167,098,648 19.39% 33kV 618,354,263 33kV 598,037,906 -20,316,356 -3.29% SJ-AD 124,640,038 SJ-AD 148,604,445 23,964,407 19.23% Grand Total 1,604,963,846 Grand Total 1,775,710,544 170,746,698 10.64%


DETAIL LIST OF ACTION REQUIRE BY ZONE Challenges Action Require PIC Dateline Expectation Outcome Cost Saving –ve balance • Bulk tender price > SJHT rate • Material cost increase • Material and contract cost not up to date in CPP • Additional cost CPC (asbuilt drawing & PE Endorsement • increase in permit costwang hangus SELPJCJ- proses baru KUSEL- Ada umap kos under KUSEL for both new permit application and CPC. Monitor & target project with high cost saving Zone & Sub Zone Monthly Increase PBT RM


Finding: Cost Barang dlm CPP vs Cost Barang Actual Cost barang dlm CPP (RM 57,039.01) Cost barang actual (RM 70,048.18)


Finding: Cost Contract dlm CPP vs Cost Contract Actual Cost contract dlm CPP (RM 162,545.60) Cost contract actual (RM 126,333.22)


Finding: Bulk vs SJHT Price (D-BBB-C20-7504) Bulk (RM709,997.60) vs SJHT (RM 398,142.70) – Variance RM 311,854.90


Finding: Bulk vs SJHT Price (RWG4119) Bulk (RM 3,025,054.00) vs SJHT (RM 1,285,499.70) – Variance RM 1,739,554.30)


Finding: TPC vs Actual Project Cost (Variance)


THANK YOU


CONFIDENTIAL AND PROPRIETARY PROFESSIONAL FEE - FINAL DASH 2023 Prepared by Suhana binti Razali Sept 2023 TNB Kuantan Deliverables • Professional Fees : 6.76% Suhana (L) Sauqi Wong Siti Adhlin KJ Affendi Logeswari Emilda


PROFESSIONAL FEE - UMT: RM 6.76% Result : 6.65% 194.4 2924.9 6.65% 194.4 Sum of AD Cost UMT2 186544896.3 116.9 6.92% SBU AD July 23 Annualised : Ad Cost & Capex Ann. ADCost Sum of Ann. Capex Sum of Ann. ADCost Gaps PF : A B Initiative: • Assuming if annualized cost RM194.4 is final cost and Forecast Capex RM2,808 the ideal cost is RM189.8. • To ensure ADCost as at Dec23 within RM189.8, RM5m need to be reduced from RM194.4. • From cost analysis, increased cost is due to increased of OT. • Monitor & Control to OT and make sure right charging through timesheet done effectively . • OT Capping at RM40.3 186.5 186.5 194.4 189.8 2759.5 2808.0 2808.0 2808.0 PF, 6.76% PF, 6.64% PF, 6.92% 6.76% Target 23 UMT ADCost / ForcstCpx ANN. ADCost /Forecst Cpx Required ADCost / ForcstCpx If Forecast Capex RM2.8b, what is ideal AD Cost ? AD Cost Capex PF AdCost UMT 186.5 Capex Apprv. 2759.1 %PF UMT; 6.76% ADCost Jul 23 113.4 Capex Jul 23 1706.2 %PF Jul23; 6.65% AdCost UMT Capex Apprv. %PF UMT ADCost Jul 23 Capex Jul 23 %PF Jul23 SBU AD PF : Target Vs Result at Jul 23 If Forecst Cpx RM2.8b with : A: UMT ADCost RM186m, PF will be at 6.64% /6.76% UMT. B: Based Annualized AD Cost RM194m. there is an increase in cost compared with UMT ADCost RM186m. PF will be at 6.92%/(6.76% ~ 7.55%) MT C: What is ADCost for Forecst Cpx RM2.8b ? The ideal Ad Cost is RM189m and PF will be at 6.76% /6.76% UMT.


Capex 113.4 194.4 186.5 COST JUL23 ANNUALISED UMT COST AD COST ADC… 108.2 5.3 185.4 9.0 176.2 10.4 STACOS OGE ANNUALISED : STACOS & OGE Cost Jul23 Annualised UMT Cost 162.5 83.6 46.3 11.4 2.416.9 1.4 .2.4 176.2 94.8 26.3 11.4 2.515.8 14.2 10.8 .2 SIGNIFICANT ELEMENT OF STAFF COSTS Annualised UMT Cost Forecast : Ad Cost = RM188.4m Capex = RM2,808b PF = 6.71% 2 elements most affect costs are OT & EPF/Socso. OT is within IM control. Target cost reduction is RM6m from RM194.4. 3 % to be reduce. OT capped at RM41.3mil (Aug-Dec 23). OT RM2mil. is allowed for each month from Aug to Dec. PROFESSIONAL FEE - UMT: RM 6.76% Result : 6.65% 27.0 29.7 32.3 35.0 37.6 40.3 JUL -23 AUG-23 SEP-23 OCT-23 NOV-23 DEC-23 OT (RM46.3-RM6M COST SAVING= RM40.3) 20.4 27.9 44.0 61.4 79.9 95.8 113.4 15.3 30.5 45.8 61.0 76.3 91.5 106.8 122.0 137.3 152.5 167.8 183.0 125.6 141.3 157.0 172.7 188.4 JAN FEB MAR APR MAY JUN JUL AUG SEPT OCT NOV DEC FY22 FY23 : AD COST FORECAST RM188.4 AdCost 23 Target AD Cost Forcst Forecast : Ad Cost = RM188.4m Capex = RM2,808b PF = 6.71%


Capex .06.27 1.53 .26 1.66 .06.79 .10 .07.46 2.62 .45 2.84 .10 1.35 .15 .18 .12 4.73 .57 3.80 .09 .00 SEGNEFICANT OGE'S ELEMENT Cost Jul23 Annualised UMT Cost 108.2 5.3 185.4 9.0 176.2 10.4 STACOS OGE ANNUALISED : STACOS & OGE Cost Jul23 Annualised UMT Cost • OGE elements also increased, • Element that can have an impact is Abandoned Capital Projects if the project cancellation paper is approved, and this cost can be removed from the AD PROFESSIONAL FEE - UMT: RM 6.76% Result : 6.65%


DETAIL LIST OF ACTION REQUIRE BY ZONE Challenges Action Require PIC Dateline Expectation Outcome Tools OT increased • IM run report subordinate OT planning weekly in order to cater justification for >104 hrs scope of work. IM & Champion Every week (start from 18 Sep 2023) Saving 2.0 mil per month • ESS Timesheet OT Planning • Manage numbers of talents attend OT shutdown job. IM BAU • ESS Timesheet OT Planning • Top 10 for every zone OT justification IM & KJ 30 Sep 23 N/A • Approval KJ for shutdown on weekend and public holiday IM & KJ BAU • ESS Timesheet OT Planning Training • Only proceed mandatory only IM & KJ BAU • People matter


OT Planning vs Actual


OT Planning vs Actual (Description of timesheet submitted)


THANK YOU


CONFIDENTIAL AND PROPRIETARY SAIDI - FINAL DASH 2023 Prepared by Farhana binti Harun Sept 2023 TNB Kuantan Farhana (L) Izzat Ekhwan Harith Imran Abdullah Jesvina Sharida Deliverables Performance of SAIDI 50 Activity FY 2023: 89%


SAIDI – as @ 31.07.2023 UMT: 48 min Result : 26.58 min (July), 30.22 (Aug) % Project Commission by Category 0 10 20 30 40 50 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2022 3.93 7.12 11.74 14.91 18.58 22.01 26.32 30.17 33.84 38.1 42.26 45.05 2023 2.59 5.24 9.55 13.87 17.97 20.08 3.93 7.1211.74 14.91 18.58 22.01 26.3230.17 33.84 38.142.26 45.05 2.59 5.24 9.55 13.87 17.97 20.08 Overall SAIDI Performance (Minutes) East KL North Selpjcj South Completed (July) 35 62 96 50 160 Target 128 184 240 162 347 35 62 96 50 160 128 184 240 162 347 0 100 200 300 400 SAIDI 50 performance by Zone Category Completed Target % Completion 11kV Fdr Injection Through New PMU/PPU 33 145 23% 33kV Feeder Injection Through New PMU 5 21 24% Civil Works For PPU & Mini PPU 4 34 12% Critical MSVT for WPF 22 64 34% ITC/Rehab 26 63 41% New Critical PPU 15 44 34% Replacement of Critical MV Cable Section 60 195 31% Replacement of F&G (No pressure gauge) 20 25 80% Replacement of MV ABC Old Design 4 15 27% Replacement of Oil-Type RMU 72 104 69% Replacement of VEI RMU 88 137 64% Replacement VCB EPE Secondary Contact 22 34 65% Resolve NTL 11kV Cable (Element) 22 115 19% Resolve NTL 33kV Source 6 41 15% S&S Replacement 2 11 18% Resolve NTL 33kV Cable (Element) 2 13 15% Total 403 1061 38% Zone Total Project Completed as @ 31st July 2023 Forecast Completion by December 2023 % Forecast Completion By FY 2023 Nos of Project to be CF to FY 2024 North 239 96 143 100% 0 K Lumpur 184 62 85 80% 37 East 128 35 74 85% 19 South 347 160 158 92% 29 Selangor 163 50 80 80% 33 Total 1061 403 540 89% 118


Zone August September October November December Total (by Zone) Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual North 24 17 28 (35) 3 30 29 32 143 Kuala Lumpur 20 16 19 (23) 5 8 15 23 85 East 10 5 9 (14) 4 10 7 38 74 South 30 16 30 (44) 4 41 28 29 158 Selangor 26 9 17 (34) 1 11 11 15 80 Total 110 63 103 (150) 17 100 90 137 540 Forecast : Monthly Commission Project (Aug 23– Dec 23) Plan project – in bracket : total monthly + planned from August Current Performance : 44% (466/1061) Planned Performance @ Aug : 48% Gap : 4% Forecast Target


DETAIL LIST OF ACTION REQUIRE BY ZONE Num Challenges Action Taken/Require PIC Dateline Expectation Outcome 1 Projek tidak dapat dijalankan atas isu wayleave, permit, contractor Majukan senarai & justifikasi kepada APO bagi permohonan pertukaran projek sistem yang tiada dalam list SAIDI • Wakil Zon 30 Sept 2023 Senarai projek SAIDI yang baru dengan tambahan projek sistem yang telah siap bagi meningkatkan - Senarai Projek SAIDI50 bagi FY24 perlu lengkap dan tiada masalah untuk dijalankan 2 Contract Performance - Bulk & KKB (Team tidak mencukupi untuk kerja dijalankan di tapak) - Kontraktor KKB Pencawang sharing dengan unit lain tetapi pasukan pekerja yang sama • Jalankan procurement proses mengikut tender individu – by projek bagi mengelakkan queue KKB/Bulk Kontraktor yg sama. • Majukan surat kepada P&SC berkaitan isu pasukan pekerja yang dikongsi bagi berlainan OA. • Transparent Daily Reporting & CASE Result with evidence on LKS • PO yang tidak dapat dijalankan oleh KKB, perlu majukan kepada P&SC untuk reallocate kepada KKB lain (telah dibuat oleh Zon Selpjcj) : bagi memberi signal isu kekurangan pasukan kerja ini kpd P&SC. - PIC Zon - Contract manager, Resource Manager BAU Kontraktor yang dilantik dapat beri komitmen untuk menjalankan kerja. 3 Isu OKST/KKT - Tiada OKST/KKT yang mencukupi bagi pasukan kerja di tapak - NTLSP sediada adalah terdiri daripada OKST juga • Had penurunan kuasa dari OKST kepada OBK (KKT & NTLSP) perlu disegerakan • Perlu segerakan juga pasukan KKB bagi mendapatkan kelayakan NTLSP (tidak terhad kepada OKST shj) • PI syndicate kontraktor berkenaan had penurunan kuasa dan keperluan KKT & NTLSP. - PMO HQ - Dalam proses sindikasi dengan Head AM - Seterusnya, Arahan Dalaman dari Head AD 30 Sept 23 Kontraktor boleh menubuhkan lebih banyak pasukan kerja. 4 Material Issue - Material tak lengkap (BC/RMU/Sgear) - Tx (30 MVA) : 10 projek Kiritikal PPU yang perlu Tx untuk mulatugas PPU. • Prioritize material mengikut progess projek (Utamakan projek dalam peringkat WIP >50%) • Majukan surat kpd P&SC berkaitan keperluan material secara berkala KJ Zon Project Implementor BAU Material diterima mengikut timeline projek yang sesuai 5 Kelewatan Permit • Sesi Engagement bersama PBT berkaitan kepentingan projek MSVT/Sistem yang sedang dijalankan • Close monitoring Permit Manager BAU Permit dapat dikeluarkan


Summary of 118 Projects to CF to FY 2024 Issue Nos of Project Remarks Wayleave 44 Kusel – (27), KUJ (18) , Others (2); dlm Tindakan APP Contract Issues 11 4 projects – Late delivery of S/G & Tx (Tamco & EPE); 3 projects – Evaluation Tender process (Tioman) 2 projects – Related to mobile (Allocation Diverted to PMU Mid Valley & Mobile defect requires direct nego for additional repair) 2 projects – Termination contract & reaward due to contractor performance in progress Legal Issue 2 1 Project – Legal Issue settled, WIP 3000m Cable installation 1 project – Project pending since 2021 due to flood & piping installed has been blocked. Building 3 3 Projects 11kV could not Commission if PPU Perindustrian Murni is still not energized. PPU Perindustrian Murni target to complete 31st Dec 23 due to late delivery of TX & SG. Permit 55 JKR (13), DBKL (28), Majlis (13), Others (1) Contractor Performance 3 Poor performance of contractor & forecasted will be completed in FY 23. Grand Total 118 KPI 4: SAIDI 50 Current Performance & Forecast by December 2023


Contract Issues Bil. Zone Project Number Project description Status 1 WPR D-KUL-S17-9242 REHABILITASI PERKAKASUIS 33KV & 11KV PPU SRI GOMBAK (MITSUBISHI) FY2019 - FULL REHAB Terdapat defect di mobile & perlu dibuat direct negoriation dengan EPE Switchgear. Quotatation telah dimajukan oleh EPE pada 17 Julai 23 & dalam proses sesi Direct nego sebelum mula kerja. 2 East D-TIO-S23-0115 MSVT PE CONDOTEL KE PE PAYA, PULAU TIOMAN(SEJAUH 2100M) Proses penilaian tender oleh P&SC. Tender tutup 17 Julai 2023 3 East D-TIO-S20-0101 SAVT KE PELADANG KE KONDOTEL(SEJAUH 6000M) Proses penilaian tender oleh P&SC. Tender tutup 17 Julai 2023 4 East D-TIO-S20-0100 MSVT PE KONDOTEL KE PE AMAN PAYA (SEPANJANG 2205M) Proses penilaian tender oleh P&SC. Tender tutup 17 Julai 2023 5 East D-PZD-S22-0446 TX3 33/11KV 30MVA DI PMU PANCHOR Pending SG Delivery. Pihak TAMCO dalam proses revise bulk tender dengan pihak P&SC, kerja-kerja di tapak tidak dapat dijalankan 6 East D-GEB-S20-0288 REHAB SSU MIECO Pending SG Delivery. Pembekalan SG jenis TAMCO hanya available hujung Ogos/awal September 2023. 7 East D-PZD-S19-0267 REHAB VCB 11kV (JENAMA MITSUBISHI, NON-MOTORISED) KEPADA VCB BARU (MOTORISED) DI PMU KOTA BHARU Pending SG Delivery. Pihak EPE dalam proses revise harga bulk tender dengan pihak P&SC. Kerja tidak dapat dijalankan di tapak. 8 South D-PZJ-S22-0933 Penubuhan Mobile PPU Yong Peng Pending TX delivery. PMU Yong Peng belum dimulatugas 9 South D-PZM-S15-9056 CIVIL - PPU Inds. Kelemak Termination of contract only issued end July. In the midst of preparing of tender document 10 South D-PZM-S22-9114 Penukaran 33kV Breaker di PMU Cheng 132/33kV Mobile has been diverted to PMU Mid Valley due to breakdown issue 11 Selangor D-SEL-S15-7415 REHAB PENCAWANG SEDIADA DENGAN MENGGANTIKAN PERKAKASUIS 11KV SEDIADA JENIS S&S TOPRANK DI PPU MASALAM, RAWANG, SELANGOR Isu kontrak PPU Masalam - Terminate & Retender semula kontraktor bagi kerja installation & Commissioning of Mobile (Trigger Power)


Legal Issues Bil. Zone Project Number Project description Status 1 Selangor D-PZB-S16-3211 MEMPERKUKUHKAN SISTEM 33KV DENGAN MERENTANG 1 litar KABEL 33KV, 630MMP AL(30MVA) DARI PMU BDR BOTANIK POTONG DAN SAMBUNG BAGI KABEL SEDIADA PPU TPG FTZ/SSU NEC, BANTING , SELANGOR DARUL EHSAN Legal Issue : pending 3km isu kecurian kabel (sepanjang laluan transmission line) , pihak kontraktor sedang memohon permit transmission kepada grid. Lawatan tapak bersama grid dibuat pada 21 Ogos 2023 2 Selangor D-SEL-S09-5708 PPU TAMAN PERINDUSTRIAN BUKIT JELUTONG (KERJA KABEL DARI PMU TMSY KE PPU TIBJ) Legal Issue (Stop work daripada Dis 2021 disebabkan banjir dan laluan exit pit HDD telah teranjak hampir 100m drp tempat asal. Dalam process untuk mendapatkan surat wayleave telco & JKR Petaling untuk lay kabel melalui flyover/jambatan monfort) Building Issues Bil. Zone Project Number Project description Status 1 South D-KLY-S22-3057 MSVT MERENTANG 1 LITAR KVT 3C 500MMP DARI PPU MURNI 07 KE SSU HITACHI DISPLAY JKU 07412 200M.TUJUAN MEWUJUDKAN PINDAHAN BEBAN DARI PMU SENAI IND. Pending Mulatugas PPU perindustrian Murni. Pending Tx & Swgr Allocation ke PPU ini. Target mulatugas PPU ini pada 31 Dec 23. 2 South D-KLY-S22-3053 MSVT MERENTANG 1 LITAR KVT 3 C 240MMP DARI PPU MURNI 03 KE PE BLESSPLUSS JKU 0851 SEJAUH 100M.(CAD. POTONG SAMBUNG LALUAN HADAPAN PPU MURNI)TUJUAN MEWUJUDKAN PEMBEKAL BARU ROMBAKAN SS LEMBARAN MURNI 1 Pending Mulatugas PPU perindustrian Murni. Pending Tx & Swgr Allocation ke PPU ini. Target mulatugas PPU ini pada 31 Dec 23. 3 South D-KLY-S22-3052 MSVT MERENTANG 1 LITAR KVT 1 C 500MMP DARI PPU MURNI CB 02 KE SSU SENAI JKU 91038 SEJAUH 250M.(CAD. POTONG SAMBUNG LALUAN HADAPAN PPU MURNI).TUJUAN MEWUJUDKAN PINDAHAN BEBAN DARI PMU SENAI IND. Pending Mulatugas PPU perindustrian Murni. Pending Tx & Swgr Allocation ke PPU ini. Target mulatugas PPU ini pada 31 Dec 23.


Wayleave Issues (KUSEL) • Project •Current Status •Challenges • Mitigation/Action •Forecast •Operational Mitigation (If any) Bil. Zone Project Number Project description Status 1 Selangor D-RWG-S22-0903 MSVT MERENTANG 1 KVT BARU 240MMP DARI PPU HILLPARK KE PE SBCR 1 UNTUK KURANGKAN BILANGAN PENCAWANG & WUJUDKAN N-1 SOURCE YANG BERDAYAHARAP. Dalam proses permohonan Wayleave kepada KUSEL oleh APP 2 Selangor D-SBR-S22-0062 MSVT 2 X INJECTION DARI PPU SG BESAR KE PE BAGAN 6 DAN PDT SG BESAR NO 2 UNTUK MENGURANGKAN BEBAN VCB 2 PMU SG BESAR. Dalam proses permohonan Wayleave kepada KUSEL oleh APP 3 Selangor D-KSL-S23-0624 MSVT KONFIGURASI SEMULA KVT 1C 500MMP SSU BDR BARU & SSU HOSPITAL ANTARA PMU KSL & PPU PASIR PENAMBANG UNTUK WUJUDKN N-1 SOURCE YANG BERDAYAHARAP Dalam proses permohonan Wayleave kepada KUSEL oleh APP 4 Selangor D-BAN-S22-0163 NEW INJECTION X2 UG KVT 240MMP SEPANJANG 3500 METER DARI CS TELOK PANGLIMA GARANG KE PE CHIN WOOD SERTA X1 UG KVT SEPANJANG 2000 METER DARI SSU FRANCESTLE CHOCOLATE KE PE CCHUAN JLN SEGENTING UNTUK MENGATASI MASALAH NTL ELEMENT PPU FTZ2 CB9 FDR TMN JAYA UTAMA (0.18MW) DAN PPU PJJM CB8 FDR MTD JLN SEGENTING (0.31MW) Dalam proses permohonan Wayleave kepada KUSEL oleh APP 5 Selangor D-BAN-S22-0164 MSVT RECONFIGURE SSU JUGRA DENGAN MERENTANG X1 UG KVT 240MMP DARI SSU JUGRA MENGHALA PE KG CANTIK SEPANJANG 3000 METER DAN MERENTANG X1 UG KVT 240MMP DARI KABEL SEDIADA PPU KOMA CB7 KE PDT B/B JLN SERAYA UNTUK MENGATASI MASALAH NTL ELEMENT SSU BANTING TOWN FDR TMN SETIA JAYA (1.82MW) DAN PPU BKOMA CB1 FDR SM SAINS BANTING (0.44MW) Dalam proses permohonan Wayleave kepada KUSEL oleh APP 6 Selangor D-RWG-S22-0923 MSVT MENUKAR SECTION KABEL BERMASALAH DI CB2 PPU PURA KE PE KIM HONG HUAT UNTUK MENGURANGKAN KEKERAPAN BREAKDOWN Dalam proses permohonan Wayleave kepada KUSEL oleh APP 7 Selangor D-RWG-S22-0883 MSVT MERENTANG 1 KVT BARU 240MMP DARI PPU AMAN PUTRI KE PE MINI STADIUM MBSA UNTUK ATASI MASALAH NTL ELEMENT CB7 PPU CLFD. Dalam proses permohonan Wayleave kepada KUSEL oleh APP 8 Selangor D-KSL-S21-0603 MSVT MERENTANG 1 X 240MMP 3C ABC DARI PPU PASIR PENAMBANG KE STS BELIMBING BAGI MENGURANGKAN BILANGAN PENCAWANG VCB 6 PPU SDBY. Dalam proses permohonan Wayleave kepada KUSEL oleh APP 9 Selangor D-PJY-S23-2118 MSVT MERENTANG KABEL 240MMP,3C,AL,XLPE SEPANJANG 1100METER DARIPADA PPU, SEAH CB11 KE PE TAMAN SEAHOUSING NO. 3, (BAGI MENGATASI MASALAH NTL ELEMENT KJYA CB06 & SEAH CB03) Dalam proses permohonan Wayleave kepada KUSEL oleh APP 10 Selangor D-KSL-S21-0601 MSVT MERENTANG 1 X SAVT 240MMP 3C XLPE DARI PPU PASIR PENAMBANG KE PE MASJID SG TERAP BAGI MENGURANGKAN BILANGAN PE VCB 6 PPU TG KARANG. Dalam proses permohonan Wayleave kepada KUSEL oleh APP 11 Selangor D-KSL-S22-0620 MSVT MERENTANG 1 X SAVT 240MMP DARI PPU SIMEDARBY KE SM BTG BERJUNTAI UNTUK MENGURANG BEBAN DAN NTL ELEMENT CB1 PPU SDBY. Dalam proses permohonan Wayleave kepada KUSEL oleh APP 12 Selangor D-KSL-S23-0641 MSVT MERENTANG 2 X KVT 240MMP 3C DARI PPU JLN KAPAR KE PE CARPENWISE DAN PE LAYHONG 7 BAGI MENGIMBANGI BEBAN VCB 6 DAN VCB 11 PMU KSGR Dalam proses permohonan Wayleave kepada KUSEL oleh APP 13 Selangor D-RWG-S21-0878 MSVT MERENTANG 2 X KVT 240MMP 3C XLPE DARI PPU HILLPARK KE PE JLN HILLPARK 1 1/ 2 DAN PE HILLPARK NO 3 UNTUK PECAHAN SISTEM NOP KSL DAN RWG. Dalam proses permohonan Wayleave kepada KUSEL oleh APP 14 Selangor D-KSL-S21-0600 MSVT MERENTANG 3 X 240MMP 3C XLPE DARI PPU PASIR PENAMBANG DENGAN MEMOTONG SAMBUNG KVT SEDIAADA PE MAHKAMAH KE PE LKIM DAN MERENTANG KE PE PEKAN KSL BAGI MEWUJUDKAN PUNCA SUABALIK YANG BERDAYA HARAP PEMBEKAL VCB 8, VCB 9 PMU KSGR DAN VCB 3 PPU TKMI. Dalam proses permohonan Wayleave kepada KUSEL oleh APP


Wayleave Issues (KUSEL) • Project •Current Status •Challenges • Mitigation/Action •Forecast •Operational Mitigation (If any) Bil. Zone Project Number Project description Status 15 Selangor D-RWG-S20-0858 MSVT MERENTANG 1 KVT 240MMP DARIPADA PPU AMAN PUTRI KE SS KG GOMBAK UNTUK MEWUJUDKAN N-1 SOURCE YANG BERDAYA HARAP KEPADA CB11 PMU LADANG KUNDANG Dalam proses permohonan Wayleave kepada KUSEL oleh APP 16 Selangor D-BAN-S23-0187 CADANGAN MSVT NEW INJECTION 1 X CIRCUIT 240MMP SEPANJANG 1500 METER DARI SSU BANTING TOWN SPARE KE PE TMN DELIMA NO 6 UNTUK MENGATASI NTL N-1 ELEMENT FEEDER SGMAS CB2 FDR McDONALD (0.37MW) DAN KOMA CB4 FDR MATRIKULASI NO2 (0.37MW) Dalam proses permohonan Wayleave kepada KUSEL oleh APP 17 Selangor D-RWG-S21-0882 MSVT MEROMBAK PENURUN 33/0.4KV KERLING INSTITUT TAHFIZ (LINK 234) KEPADA SISTEM 11KV, TNB RAWANG Dalam proses permohonan Wayleave kepada KUSEL oleh APP 18 Selangor D-RWG-S22-0907 MSVT MENUKAR KABEL LAMA KVT 185MMP 3C PILC & KVT 150MMP KEPADA KVT 240MMP 3C XLPE DARI PE RAWANG JAYA KE PE PENURUN HIJAU SEJAUH 900M Dalam proses permohonan Wayleave kepada KUSEL oleh APP 19 Selangor D-RWG-S22-0909 MSVT MENUKAR KABEL LAMA KVT 70MMP 3C PILC KEPADA KVT 240MMP 3C XLPE DARI PE TMN SRI HIJAU NO 1 KE PE RAWANG MUTIARA NO 2. Dalam proses permohonan Wayleave kepada KUSEL oleh APP 20 Selangor D-KSL-S22-0627 MSVT MENUKAR KABEL BERCAMPUR 240MMP XLPE DAN 185MMP 3C PILC YANG KERAP ROSAK KEPADA SAVT 240MMP 3C ABC DARI PE EMINANT FARM KE PE MUARA 1 (BAKI BELUM DITUKAR) Dalam proses permohonan Wayleave kepada KUSEL oleh APP 21 Selangor D-RWG-S22-0927 MSVT MEROMBAK PENURUN 33/0.4KV LADANG BUKIT BERUNTUNG KEPADA SISTEM 11KV, TNB RAWANG Dalam proses permohonan Wayleave kepada KUSEL oleh APP 22 Selangor D-SBR-S22-0066 MSVT MENUKAR PILC CABLE 70MMP DARI LINK PARIT 12 KE PE PARIT 10 GAMBUT DI CB6 PMU SBSR Dalam proses permohonan Wayleave kepada KUSEL oleh APP 23 Selangor D-BAN-S20-0119 MSVT MENUKAR KABEL 3C 185MMP PILC KEPADA 3C 240MMP XLPE SEPANJANG 5250 METER DI ANTARA F7 PPU MORIB KE P/E RM KANCHONG LAUT UNTUK INITIATIF WORST PERFORMANCE FEEDER DAN LILO PE KANCHONG LAUT UNTUK MENGURANGKAN PANJANG KABEL SEDIADA. Dalam proses permohonan Wayleave kepada KUSEL oleh APP 24 Selangor D-PJY-S22-2121 MSVT MERENTANG KABEL 240MMP BERJUMLAH 1000METER DARIPADA PE TROPICANA JTR 9/1 NO.2 KE PE TROPICANA NO.2 (BAGI MENGATASI MASALAH KABEL UNDERSIZE 70MMP,CU,3C,PILC) Dalam proses permohonan Wayleave kepada KUSEL oleh APP 25 WPR D-KLS-S22-6938 MSVT MENYELESAIKAN NTL ELEMENT PPU PHOENIX CB9 Dalam proses permohonan Wayleave kepada KUSEL oleh APP 26 WPR D-PZW-S20-8495 MSVT 33KV PU PVJL PMU PVJL - PPU PBJL (2x 350m) Dalam proses permohonan Wayleave kepada KUSEL oleh APP 27 Selangor D-SJY-S23-1137 CADANGAN MENGGANTIKAN KABEL PILC DAN REKONFIGUR SISTEM BAGI MENGATASI ISU KEROSAKAN BERULANG KABEL SEKSYEN PE SUBANG SAFETY GLASS SDN BHD KE PE TRUE FITNESS SDN BHD Dalam proses permohonan Wayleave kepada KUSEL oleh APP


Wayleave Issues (KUJ) • Project •Current Status •Challenges • Mitigation/Action •Forecast •Operational Mitigation (If any) Bil. Zone Project Number Project description Status 1 South D-PZJ-S20-0867 MSVT SSU CGP1 & CGP2 (MSVT PMU Danga Bay) Dalam proses permohonan Wayleave kepada KUJ oleh APP 2 South D-JBU-S22-0838 MSVT - PENUKARAN KABEL TRIPPING BERGANDA 22KV DARI P/E HANDEE EXPRESS KE P/E RUMAH PANGSA SURIA MUAFAKAT NO 2 SEPANJANG 1700 METER Dalam proses permohonan Wayleave kepada KUJ oleh APP 3 South D-JBU-S22-0843 MSVT - PENUKARAN KABEL TRIPPING BERGANDA 22KV DARI P/E FIRST UNITED KE P/E TOMY PACK SEPANJANG 1000 METER Dalam proses permohonan Wayleave kepada KUJ oleh APP 4 South D-JBU-S22-0742 CADANGAN MERENTANG KABEL 3C 500MMP 11KV DARI PPU SETIA ECO KE CADANGAN POTONG & SAMBUNG ANTARA KABEL SSU PULAI MUTIARA KE PPU TUNI 2 Dalam proses permohonan Wayleave kepada KUJ oleh APP 5 South D-KLU-S20-4224 MSVT MENUKAR KABEL VOLTAN TINGGI 11KV 3C300MMP PILC 1ST LEG DARI PMU KLID KE PE STARLET FOOD, MEWUJUDKAN N-1 SOURCE SERTA REKONFIGURASI SISTEM DENGAN MERENTANG XLPE 3C240MMP DARI SSU PROFIT POINT KE PE SOON FATT SEPANJANG 240 METER DI TNB KLUANG Dalam proses permohonan Wayleave kepada KUJ oleh APP 6 South D-KLU-S22-4435 MSVT NEW INJECTION KVT 11KV 240MMP 3C DARI SSU TAMAN SRI KLUANG CB 6 KE PE RUMAH PANGSA TAMAN SRI KLUANG SEPANJANG 1300 METER Dalam proses permohonan Wayleave kepada KUJ oleh APP 7 South D-KLU-S22-4436 MSVT NEW INJECTION KVT 11KV 240MMP 3C DARI SS CHAMEK KE PE LADANG CHAMEK SEPANJANG 1300 METER BAGI MEWUJUDKAN KABEL NOP DAN MENGATASI LOW VOLTAGE CONTIGENCY SISTEM Dalam proses permohonan Wayleave kepada KUJ oleh APP 8 South D-KLU-S22-4075 MSVT MENUKAR KVT PILC KE 240MMP ANTARA PE NO 1 MALAY REGIMEN CAMP KE NO 2 MALAY REGIMEN SERTA MEWUJUDKAN SISTEM SUAP BALIK ANTARA PE NO 2 MALAY REGIMEN KE PE AMMO DEPOT Dalam proses permohonan Wayleave kepada KUJ oleh APP 9 South D-KLU-S20-4225 MSVT MENUKAR KABEL VOLTAN TINGGI 11KV 300MMP PILC 3C 1ST LEG DARI PMU KLUANG NEW KE P/E, TMN EMAS JAYA NO 2 KEPADA 240MMP XLPE 3C SEPANJANG 1,550 METER DI TNB KLUANG Dalam proses permohonan Wayleave kepada KUJ oleh APP 10 South D-KLU-S21-4232 MSVT MENUKAR KVT 11KV 70MMP PILC 3C KEPADA KVT 11KV 150MMP 3C ANTARA S/S SETIA JAYA KE PE RESTORAN JAYA Dalam proses permohonan Wayleave kepada KUJ oleh APP 11 South D-KLU-S22-4076 MSVT MENUKAR KABEL PILC 25MMP ANTARA P/E NO 1 MALAY REGIMEN CAMP KE PE TAMAN FAJAR DI TNB KLUANG. Dalam proses permohonan Wayleave kepada KUJ oleh APP 12 South D-KLU-S22-4074 MSVT MENUKAR KABEL PILC 25MMP ANTARA P/E AMMO DEPOT KE PE NO 2 MALAY REGIMEN DI TNB KLUANG. Dalam proses permohonan Wayleave kepada KUJ oleh APP 13 South D-MSG-S20-0857 MSVT MENUKAR KVT JENIS PILC 300 MMP 3C AL KEPADA XLPE 240 MMP 3C AL, DARI PPU FELDA TENGGAROH CB 01 KEPADA P/E FELCRA SRI MERSING SEPANJANG, 1*1250 METER DI TNB MERSING., Dalam proses permohonan Wayleave kepada KUJ oleh APP 14 South D-KLU-S22-4394 MSVT PAT GSA CHAMEK- MENUKAR KVT 11KV PILC 120MMP 3C KEPADA ABC 3X150MMP / XLPE 11KV, 150MMP 3C ANTARA SS CHAMEK KE PAT GSA CHAMEK SERTA KONFIGURASI SISTEM SEPANJANG 2400, METER SERTA MEWUJUDKAN SISTEM SUAP BALIK DARI PAT GSA CHAMEK KE PE KG GSA MELAYU CHAMEK, SEPANJANG 4700 METER Dalam proses permohonan Wayleave kepada KUJ oleh APP


Wayleave Issues (KUJ) Bil. Zone Project Number Project description Status 15 South D-BPT-S22-3505 MSVT MERENTANG 1 LITAR 500MMP 3C 11KV DARI PMU PESERAI VCB 09 KE SPL PT HJ IBRAHIM ( JBP 52305 ) SEPANJANG 6900 METER UNTUK MEWUJUDKAN N-1 SOURCE DI TNB BATU PAHAT. Dalam proses permohonan Wayleave kepada KUJ oleh APP 16 South D-KLY-S23-2927 MSVT MERENTANG 1 LITAR KABEL 1C500MP XLPE 11KV DARI PPU TMN TEKNOLOGI KE SS ENG TEX NO.1 SEJAUH 670M UNTUK TUJUAN MENYELESAIKAN NTL DI SS ENGTEX. Dalam proses permohonan Wayleave kepada KUJ oleh APP 17 South D-BPT-S22-3465 MSVT MERENTANG 1 LITAR KABEL XLPE 3C 240MMP 11KV DARI PMU BT PAHAT VCB 11 KE PE TMN PUTERA NO 2 (JBP 53805) SEPANJANG 2,200 METER BAGI MENGATASI MASALAH LEBIHAN BEBAN PMU TKG PECAH VCB 10 FDR TMN INDAH BATU PAHAT. (PROJEK BERKAIT BPT 3464) Dalam proses permohonan Wayleave kepada KUJ oleh APP 18 South D-BPT-S22-3464 MSVT MERENTANG 1 LITAR KABEL XLPE 3C 240MMP 11KV DARI PMU BT PAHAT VCB 14 KE PE TMN PUTERI INDAH NO 2 (JBP 53614) SEPANJANG 1,900 METER BAGI MENGATASI MASALAH LEBIHAN BEBAN PMU TKG PECAH VCB 10 FDR TMN INDAH BATU PAHAT. (PROJEK BERKAIT BPT 3465) Dalam proses permohonan Wayleave kepada KUJ oleh APP


Permit Issues (JKR) • Project •Current Status •Challenges • Mitigation/Action •Forecast •Operational Mitigation (If any) Bil. Zone Project Number Project description Status/Isu 1 Selangor D-PJY-S20-2009 MSVT -CADANGAN PUNCA BEKALAN BARU UNTUK PE TOWER A AMCORP MALL, (CONSUMER) DENGAN MERENTANG KABEL 1X240MMP BERJUMLAH 450 METER DARIPADA, PPU PJ OLD OFFICE CB11 SERTA CADANGAN PUNCA BEKALAN BARU UNTUK PE TOWER, B AMCORP MALL (CONSUMER) DENGAN MERENTANG KABEL 1x240MMP BERJUMLAH, 650METER DARIPADA SSU PJ EXCHANGE HM SHAH. (BAGI MENGATASI FEEDER SPUR PPU MELAWANGI CB07 & CB08) Permit JKR – Pelebaran Jalan 2 Selangor D-PZB-S15-6810 MEMPERKUKUHKAN SISTEM 33KV DENGAN MERENTANG KABEL 33KV, 630MMP AL(30MVA) DARI PMU LADANG KUNDANG KE PPU BT16 , RAWANG. Permit JKR – Pelebaran Jalan 3 Selangor D-PZB-S18-8716 PROJEK MSVT 33kV DENGAN MERENTANG: I) 1 LITAR 33kV, 630mmp XLPE AL(30MVA), DARI PMU LADANG KUNDANG 10L5 KE PPU MASSALAM 1P5 DENGAN ANGGARAN PANJANG KABEL 19100 METER. II) 1 LITAR 33kV, 630mmp XLPE AL(30MVA), DARI PMU NEW RAWANG LAND 6L5 KE PPU BATU 16 DENGAN ANGGARAN PANJANG KABEL 1 X 50 METER. (MENYAMBUNG TERUS KABEL SEDIADA ANTARA NRWG 6L5/MSLM 1P5 & MSLM/BT16) Permit JKR – Pelebaran Jalan 4 South D-PON-S22-1962 MSVT MERENTANG 1 LITAR KABEL 1C500MP XLPE 11KV DARI PMU PEKAN NENAS KE PE TMN SENTOSA 1 SEPANJANG 4500M DAN MENAIKTARAF PENCAWANG DOUBLE CHAMBER KEPADA S/S UNTUK TUJUAN MEYELESAIKAN ISU NTL DI SSU JLN SAWAH. Pending Permit JKR 5 South D-PON-S20-1930 MSVT MERENTANG 1 LITAR KABEL XLPE 1C, 500MMP DARIPADA SSU JK WIRE (BPT) KE SSU PRT BETAK PADA JARAK SEJAUH 7000meter BAGI TUJUAN N1 SOURCE DI SSU PRT.BETAK. Pending Permit JKR 6 South D-KLU-S22-4362 MSVT NEW INJECTION KVT 11KV 240MMP 3C DARI PPU SAUJANA KE SPL MASJID PPM SEJAUH 8,200 METER Pending Permit JKR 7 South D-MSG-S22-0899 MSVT NEW INJECTION DARI PE NITAR TIMOR KE FELDA NITAR NO 2 SEPANJANG 15,600 METER DI SUB ZON TNB MERSING. Pending Permit JKR 8 South D-KLU-S20-4219 MSVT MENUKAR KABEL VOLTAN TINGGI 11KV 185MMP PILC 3C 1ST LEG DARI PMU RENGAM KE S/SUIS, LDG SEMBRONG NO 1 KEPADA 240MMP XLPE 3C SEPANJANG 8,850 METER DI TNB KLUANG Pending Permit JKR 9 East D-PZT-S24-0600 MSVT RECONFIGURE PMU KEMAMAN Pending Permit JKR 10 East D-PZC-S22-0944 MERENTANG TALIAN ABC 150MMP 33KV BAGI MENGGANTIKAN KABEL SEDIADA DI TALIAN ABC GUA MUSANG. Pending Permit JKR 11 East D-KTN-S23-4799 MSVT : MEWUJUDKAN SSU MAT KILAU DENGAN MERENTANG 2 X 3C 500MMP DARI PPU INDERA SEMPURNA SEJAUH 2000M Pending Permit JKR 12 East D-KTN-S22-4727 MSVT PENUKARAN KABEL LAMA HT11kV SECTION : PE TAMAN TIMUR KE PE TAMAN TIMUR JAYA (TUKAR KABEL SIZE 70MMP/150MMP KEPADA KABEL 240MMP JARAK 1600M) Pending Permit JKR 13 East D-KTN-S22-4724 MSVT PENUKARAN KABEL LAMA HT11kV SECTION : SSU KEMAS KE PE BUMIPUTERA HOUSING (TUKAR KABEL SIZE 185MMP/150MMP (PILC/XLPE) KEPADA KABEL XLPE 240MMP JARAK 500M Pending Permit JKR


Permit Issues (DBKL) • Project •Current Status •Challenges • Mitigation/Action •Forecast •Operational Mitigation (If any) Bil. Zone Project Number Project description Status/Isu 1 WPR D-KLS-S22-6980 MSVT MENYELESAIKAN NTL ELEMENT PPU TAMAN SEGAR-1 CB5 Permit DBKL - OSC requires new docs, road diplation report 2 WPR D-KLS-S22-6984 MSVT MENYELESAIKAN NTL ELEMENT PMU PUDU ULU CB1 & PPU SHAM CB12 Permit DBKL - OSC requires new docs, road diplation report 3 WPR D-KLB-S21-2848 2848-MSVT MULATUGAS 5 NOS KABEL 240 XLPE DARI PPU BKT AMAN VCB 3, 8, 9, 12 & 13 MENGHALA KE JLN RAJA (SAMB KLB 1030) (PE BANK PERTANIAN JLN RAJA; WKLB/PCE/J00825) (S BAMN 2848, 2839, 2831, 2829, 2849) Kelulusan permit belum diterima, task force meeting done and DBKL setuju untuk korekan 4 WPR D-KLB-S21-2839 2839-MSVT MULATUGAS 2 NOS KABEL 240 XLPE DARI PPU BKT AMAN VCB 2 & 10, SUNTIKAN KE PE DATARAN MERDEKA & SELANGOR CLUB (SAMB KLB 1030) (PE DATARAN MERDEKA JLN RAJA; WKLB/PCE/J00381) (S BAMN 2848, 2839, 2831, 2829, 2849) Kelulusan permit belum diterima, task force meeting done and DBKL setuju untuk korekan 5 WPR D-KLB-S21-2831 2831-MSVT MULATUGAS 2 NOS KABEL 240 XLPE DARI PPU BKT AMAN VCB 1 & 6, SUNTIKAN KE SSU MAJESTIC HOTEL (SAMB KLB 1627) (SSU MAJESTIC HTL J SULTAN HISHAMUDDIN; WKLB/PCE/J02483) (S BAMN 2848, 2839, 2831, 2829, 2849) Kelulusan permit belum diterima 6 WPR D-KLB-S21-2941 2941-MSVT WPF SHAR_VCB2 PENGGANTIAN KABEL PILC UZUR KE 240X ATR SEK MEN SRI HARTAMAS KE B/BOMBA SRI HARTAMAS (RFM, PILC, WPF SHAR_VCB2) Kelulusan permit belum diterima 7 WPR D-KLB-S21-3407 3407-MSVT RECONFIGURE SISTEM DARI PPU RIMBUNAN MELATI CB13 KE PE BLOK F TAMAN FADASON ; WKLB/PCE/J00085 , DAN PE JLN 2/17 TAMAN FADASON :WKLB/PCE/J02297 PPU SRI EDARAN CB 10. (DNMP 2022) Kelulusan permit belum diterima 8 WPR D-KLB-S22-3311 3311-MSVT RECONFIGURE SISTEM DARI PPU EMPIRE CITY CB 8 DAN PPU EMPIRE CITY CB 7 DI PE MOFAZ LOT 2810 SG PENCHALA (WKLB/PCE/J01869) DAN PE RUMAH PAM AIR KG SG PENCHALA ( WKLB/PCE/J00487) Kelulusan permit belum diterima 9 WPR D-KLB-S23-3433 3433-MSVT BANTU MPLX_VCB2 (146 A) , PSTR_VCB3 (195A) & PSTR_VCB10 (194 A), SUNTIKAN 240X DR PPU UMNO_VCB8 KE PE UMNO TABUNG HAJI (WKLB/PCE/J01344) DAN DR PPU UMNO_VCB9 KE PE SENTUL (WKLT/PCE/J00615) . MSVT BERKAITAN 3433, 3434, 3435 & 3436. Kelulusan permit belum diterima 10 WPR D-KLT-S19-1743 MSVT-SUNTIKAN BARU DARI PPU SETIAWANGSA CB1 KE PE MENARA SRI TANJUNG JLN 16/56 AU, TAMAN SETIAWANGSA Pending extension permit DBKL & KUSEL approval 11 WPR D-KLT-S19-1744 MSVT-SUNTIKAN BARU DARI PPU SETIAWANGSA CB2 & CB3 KE PE MENARA SRI CENGAL DAN PE MENARA SRI MAHANG, TAMAN SETIAWANGSA Pending extension permit DBKL & KUSEL approval 12 WPR D-KLT-S19-1745 MSVT-SUNTIKAN BARU DARI PPU SETIAWANGSA CB4, CB5 & CB6 KE PE JALAN JELATEK 2, PE JALAN 1C/1 DAN PE JALAN 1C/4L TAMAN KERAMAT PERMAI. Pending extension permit DBKL & KUSEL approval 13 WPR D-KLT-S19-1746 MSVT-SUNTIKAN BARU DARI PPU SETIAWANGSA CB7 KE PE KELUMPUK CEMPERLING Pending extension permit DBKL & KUSEL approval 14 WPR D-KLT-S19-1751 MSVT-SUNTIKAN BARU DARI PPU SETIAWANGSA CB8 KE PE JALAN AU 3/1A HULU KELANG Pending extension permit DBKL & KUSEL approval 15 WPR D-KLT-S19-1747 MSVT-SUNTIKAN BARU DARI PPU SETIAWANGSA CB9 & CB10 KE PE PUTRA APARTMENT JLN 2/55B DAN PE JALAN SETIAWANGSA 23 TAMAN SETIAWANGSA Pending extension permit DBKL & KUSEL approval


Permit Issues (DBKL) • Project •Current Status •Challenges • Mitigation/Action •Forecast •Operational Mitigation (If any) Bil. Zone Project Number Project description Status/Isu 16 WPR D-KLT-S21-7000 MSVT-SUNTIKAN KABEL 240MMP 3C DARI PPU SKY AWANI 3 CB10 KE SSU P/PURI PV21. Pending kelulusan permit DBKL 17 WPR D-KLT-S21-7001 MSVT-SUNTIKAN KABEL 240MMP 3C DARI PPU SKY AWANI 3 CB11 KE SSU P/PURI PV20. Pending kelulusan permit DBKL 18 WPR D-KLT-S21-7002 MSVT-SUNTIKAN KABEL 240MMP 3C DARI PPU SKY AWANI 3 CB01 KE PE CONTIPARK NARON JLN USAHAWAN. Pending kelulusan permit DBKL 19 WPR D-KLT-S21-7003 MSVT-SUNTIKAN KABEL 240MMP 3C DARI PPU SKY AWANI 3 CB02 KE PE BLOK D5 WANGSA MAJU. Pending kelulusan permit DBKL 20 WPR D-KLT-S21-7004 MSVT-SUNTIKAN KABEL 240MMP 3C DARI PPU SKY AWANI 3 CB04 KE SSU GIANT JLN KILANG. Pending kelulusan permit DBKL 21 WPR D-KLT-S21-7005 MSVT-SUNTIKAN KABEL 240MMP 3C DARI PPU SKY AWANI 3 CB03 KE PE SECONDARY VOKASIONAL SCHOOL. Pending kelulusan permit DBKL 22 WPR D-KLT-S21-7006 MSVT-SUNTIKAN KABEL 240MMP 3C DARI PPU SKY AWANI 3 CB09 KE PE NO.1 JLN DANAU NIAGA 1. Pending kelulusan permit DBKL 23 WPR D-KLT-S21-7008 MSVT - SUNTIKAN KABEL 500MMP 1C DARI PPU SKYAWANI 3 CB5 KE SSU P/PURI IRAMA WANGSA BLOK C SEK 10 Pending kelulusan permit DBKL 24 WPR D-KLS-S22-6936 MSVT MENYELESAIKAN NTL ELEMENT PPU SRI ENDAH CB2 Permit DBKL - OSC requires new docs, road diplation report 25 WPR D-KLS-S22-6978 MSVT MENYELESAIKAN NTL ELEMENT PPU SRI KELADI CB5 Permit DBKL - OSC requires new docs, road diplation report 26 WPR D-KLT-S21-7000 MSVT-SUNTIKAN KABEL 240MMP 3C DARI PPU SKY AWANI 3 CB10 KE SSU P/PURI PV21. Pending kelulusan permit DBKL 27 WPR D-KLT-S21-7001 MSVT-SUNTIKAN KABEL 240MMP 3C DARI PPU SKY AWANI 3 CB11 KE SSU P/PURI PV20. Pending kelulusan permit DBKL 28 WPR D-KLT-S21-7002 MSVT-SUNTIKAN KABEL 240MMP 3C DARI PPU SKY AWANI 3 CB01 KE PE CONTIPARK NARON JLN USAHAWAN. Pending kelulusan permit DBKL


Permit Issues (Majlis/Others) • Project •Current Status •Challenges • Mitigation/Action •Forecast •Operational Mitigation (If any) Bil. Zone Project Number Project description Status/Isu 1 WPR D-KLS-S22-6938 MSVT MENYELESAIKAN NTL ELEMENT PPU PHOENIX CB9 Dlm proses kelulusan permit KUSEL/MPKJ. 2 WPR D-KLS-S22-6974 MSVT MENYELESAIKAN NTL ELEMENT PPU PHOENIX CB11 Dlm proses kelulusan permit KUSEL/MPKJ. 3 WPR D-KLB-S21-2831 2831-MSVT MULATUGAS 2 NOS KABEL 240 XLPE DARI PPU BKT AMAN VCB 1 & 6, SUNTIKAN KE SSU MAJESTIC HOTEL (SAMB KLB 1627) (SSU MAJESTIC HTL J SULTAN HISHAMUDDIN; WKLB/PCE/J02483) (S BAMN 2848, 2839, 2831, 2829, 2849) Kelulusan permit belum diterima 4 WPR D-KLB-S21-2941 2941-MSVT WPF SHAR_VCB2 PENGGANTIAN KABEL PILC UZUR KE 240X ATR SEK MEN SRI HARTAMAS KE B/BOMBA SRI HARTAMAS (RFM, PILC, WPF SHAR_VCB2) Kelulusan permit belum diterima 5 WPR D-KLB-S21-3407 3407-MSVT RECONFIGURE SISTEM DARI PPU RIMBUNAN MELATI CB13 KE PE BLOK F TAMAN FADASON ; WKLB/PCE/J00085 , DAN PE JLN 2/17 TAMAN FADASON :WKLB/PCE/J02297 PPU SRI EDARAN CB 10. (DNMP 2022) Kelulusan permit belum diterima 6 WPR D-KLB-S22-3311 3311-MSVT RECONFIGURE SISTEM DARI PPU EMPIRE CITY CB 8 DAN PPU EMPIRE CITY CB 7 DI PE MOFAZ LOT 2810 SG PENCHALA (WKLB/PCE/J01869) DAN PE RUMAH PAM AIR KG SG PENCHALA ( WKLB/PCE/J00487) Kelulusan permit belum diterima 7 WPR D-KLB-S23-3433 3433-MSVT BANTU MPLX_VCB2 (146 A) , PSTR_VCB3 (195A) & PSTR_VCB10 (194 A), SUNTIKAN 240X DR PPU UMNO_VCB8 KE PE UMNO TABUNG HAJI (WKLB/PCE/J01344) DAN DR PPU UMNO_VCB9 KE PE SENTUL (WKLT/PCE/J00615) . MSVT BERKAITAN 3433, 3434, 3435 & 3436. Kelulusan permit belum diterima 8 WPR D-KLC-S21-6474 MSVT MERENTANG KABEL 240 XLPE DARIPADA PE PANDAN JAYA NO 7 KE PE PANDAN JAYA 6 BAGI MENYELESAIKAN OSF PPU PDNJ CB3 Dlm proses kelulusan permit KUSEL/MPAJ (dlm proses semakan dokumen oleh MPAJ) 9 WPR D-KLC-S21-6668 MSVT MERENTANG KABEL 240 XLPE DARIPADA PE PANDAN INDAH NO 5 KE PE PANDAN INDAH 1 BAGI MENYELESAIKAN OSF PPU PDNJ CB3 Dlm proses kelulusan permit KUSEL/MPAJ (dlm proses payment wang hangus/proses MPAJ) 10 East D-KTN-S22-4723 MSVT PENUKARAN KABEL LAMA HT11kV SECTION : PE TAMAN DATIN MAHARUM KE PE SMK AFZAN (TUKAR KABEL SIZE 120MMP/150MMP (PILC/XLPE) KEPADA KABEL 240MMP JARAK 1300M) Pending Kelulusan Permit 11 East D-KRI-S22-0008 MSVT - CADANGAN RECONFIGURE SISTEM 11KV DENGAN CADANGAN MERENTANG KVT, 150MMP, 3C, 11KV, XLPE, AL. DARI PE HJH. ROHANI KE PE GUCHIL 3 SEJAUH, 500M, DAERAH KUALA KRAI, KELANTAN DARUL NAIM. Pending Kelulusan Permit 12 East D-KBU-S22-0047 D-KBU-S22-0027 MSVT tukar PILC 1600m PE Kubang Kerian ke PE Ibusawat TELEKOM Pending Kelulusan Permit 13 East D-KBG-S19-1064 MSVT - MEROMBAK PAT PELANDAN DENGAN MENUKAR PENGALIR SAXCA ABC 11kV3X35MMP KEPADA KABEL XLPE 11kV AL. 3C 150MMP ANTARA P/E SEK MEN TERSAT KE CS PDI PELANDAN SEPANJANG 2000 METER, KUALA BERANG, TERENGGANU. (2.0KM) Pending Kelulusan Permit 14 East D-JEL-S22-0002 MSVT tukar ABC 3x70 kepada XLPE150 dari PE RISDA ke Loji Pembersihan Air sepanjang 200m, Jeli, Kelantan Pending Kelulusan Permit 15 East D-BCK-S19-0021 MSVT tukar PILC kepada XLPE240 dari PPU Beris ke PE Pasar Beris 300m dan ke PE Padat Taman Pura 700m, Bachok, Kelantan Pending Kelulusan Permit


Permit Issues (Majlis/Others) Bil. Zone Project Number Project description Status/Isu 16 NORTH D-KLM-S22-0680 MSVT- Merentang kabel 11kV 240mmp XLPE dari SS Ldg Sg Ular Div 2 ke PAT Ldg Sg Ular Div 2 sepanjang 1500m bagi menggantikan kabel sediada 25 Cu (8K5 Sg Ular) Melibatkan tanah persendirian. 17 NORTH D-BLG-S22-0695 MSVT- Merentang talian atas 11kV 240mmp ABC dari PBT Kg Iboi ke Kg Masjid Iboi sepanjang 1530m bagi menggantikan kabel sediada 70mmp PILC (BL3) Terlibat dengan perubahan laluan. Dalam proses kelulusan permit.


Contractor Performance Bil. Zone Project Number Project description Status 1 Selangor D-PZB-S18-6109 MEMPERKUKUHKAN SISTEM VOLTAN TINGGI 33kV DENGAN MERENTANG 1 LITAR KABEL 33KV (630MMP, AL, 30MVA) DARI PPU SEPANG 4P5 KE PPU TANJUNG RHU 1P5, BANTING, SELANGOR DARU EHSAN. Contractor Performance (HDD(anggaran) : *12911m/21700mtrOpen Cut : 0/ 300 mtrLay Cable : 2977mtr/22000m) 2 East D-PZT-S21-0556 CIVIL - MINI PPU KELULUT Poor Performance contractor Pembinaan trenches: 70% . Pembinaan Tx plinth: 80% . M&E: 0%. Kerja mengecat & Infras: 0%. Anticlimb fence: 0% 3 North D-LGK-S21-0572 MSVT Menukar kabel MV ABC Lama 95 MMP Di Antara Kg Teluk Sehingga JPS U. Melaka Tiada KKB Skop Kabel untuk Langkawi. Kerja-kerja di Langkawi dilaksanakan oleh KKB K1 (Perlis, Jitra,KNG). 4 North D-LGK-S17-0392 MSVT Pulau Tuba Dengan Menutup litar jejari P/E Selat Bagan Nyior di Pulau Tuba Dalam proses tender semula oleh PIC Langkawi


THANK YOU


CONFIDENTIAL AND PROPRIETARY NEW BUSINESS - FINAL DASH 2023 Prepared by Farhana binti Harun Sept 2023 TNB Kuantan Farhana (L) Izzat Ekhwan Harith Imran Abdullah Jesvina Sharida Deliverables New Business Performance to Achieve Target : 7.4M


Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total 2022 (RM) 113,338.70 659,783.12 521,033.89 441,582.63 675,496.00 521,221.92 3,263,713.09 418,285.59 743,874.60 - 7,358,329.51 2023 (RM) 333,934.00 1,113,680.0 0 1,968,991.1 2 671,820.35 911,298.29 - 364,295.89 5,364,019.65 Bil Zone State Month Status Customer Name Description Sales Order Amount Sales Order Num 1 NORTH PERAK Jan-23 WIP KINTA SAUJANA REALTY SDN BHD Permohonan merombak P/E Chemor 2 333,934.00 2 SELPJCJ SELPJCJ Feb-23 WIP PENGURUSAN ASET AIR BERHAD KERJA-KERJA PENGALIHAN KABEL 1C, 500MMP 196,378.38 10769028 3 SELPJCJ SELPJCJ Feb-23 WIP JABATAN KERJA RAYA MALAYSIA PERMOHONAN PENGALIHAN KABEL 11KV DAN KAB 917,301.62 10763217 4 KUALA LUMPUR KUALA LUMPUR Mar-23 WIP PENGURUSAN ASET AIR BERHAD KERJA-KERJA PENGALIHAN KABEL SISTEM 11KV 135,254.54 10774229 5 SELPJCJ SELPJCJ Mar-23 WIP HARBOUR HOME SDN BHD KERJA-KERJA PENYUISAN HENTITUGAS, PENGAL 169,318.20 10775544 6 KUALA LUMPUR KUALA LUMPUR Mar-23 WIP HARBOUR HOME SDN BHD KERJA-KERJA PENUKARAN KABEL 33KV TALIAN 787,683.88 10779872 7 NORTH PULAU PINANG Mar-23 WIP STC PROPERTY MANAGEMENT SDN. BHD. KERJA-KERJA PENGALIHAN KABEL DI SEBAHAGI 583,669.07 10781374 8 NORTH PULAU PINANG Mar-23 WIP STC PROPERTY MANAGEMENT SDN. BHD. KERJA-KERJA PENGALIHAN KABEL BAGI PEMBIN 293,065.43 10781448 9 SOUTH JOHOR Apr-23 WIP PERBADANAN PR1MA MALAYSIA PENGALIHAN WAYAR SERVIS, TIANG DAN KABEL 272,463.03 10794858 10 NORTH PERAK Apr-23 WIP R&R UNGGUL SDN. BHD. KERJA-KERJA PENGALIHAN TIANG DAN WAYAR 241,336.58 10794154 11 SELPJCJ SELPJCJ Apr-23 WIP GABUNGAN HKO SDN. BHD. KERJA-KERJA PENGALIHAN WAYAR SERVIS 158,020.74 10790169 12 NORTH PERAK May-23 WIP KING ONG & SONS SDN. BHD. KERJA-KERJA PENGALIHAN TIANG, MEROMBAK T 810,206.71 10786840 13 WPR KL May-23 WIP RENESAS SEMICONDUCTOR KL SDN. BHD. KERJA-KERJA PENGALIHAN KABEL, MERENTANG 101,091.58 10788908 14 SOUTH JOHOR Jul-23 WIP SEN HAI TIMBER SDN. BHD. KERJA-KERJA PENGALIHAN DAN RENTANGAN KAB 175,794.45 10808294 15 SOUTH NSE Jul-23 WIP BA URUS BINA (M) SDN. BHD. KERJA-KERJA PENYELIAAN DAN PENGALIHAN KA 188,501.44 10809909 Total 5,364,019.65 New Business Performance as at 31st July 2023. Total forecast by Dec 2023 is RM 9,969,885.20.


Forecast [September – October] *Sales Order Issued Zone Keterangan Kerja Kos Projek Kategori Status 1 NORTH RMK 12 - Pengalihan kabel bawah tanah mengantikan Jambatan FT001/709/40, Sungai Bogak , Bagan Serai , Perak. 576,177.00 RMK SALES ORDER ISSUED 2 NORTH KERJA-KERJA PENGALIHAN KABEL, PENYUISAN HENTITUGAS DAN PENYELIAAN DI TANAH LOT 20860, TAMAN KAMUNTING PUTRA, BUKIT JANA, PERAK. 129,052.15 PRIVATE SALES ORDER ISSUED 3 NORTH PENGALIHAN TIANG UNTUK TETUAN GARLAND DEVELOPMENT SDN BHD DI TELUK INTAN, PERAK 129,000.00 PRIVATE SALES ORDER ISSUED 4 SOUTH NTP RJO > 80K : RJO CGI SERAI BUKIT PT YAANI. 173,963.73 PRIVATE SALES ORDER ISSUED 5 SOUTH RJO Pelebaran Jalan di kawasan Taman Pelangi Indah 573,720.75 PRIVATE SALES ORDER ISSUED 6 SOUTH RJO - PERMOHONAN PENGALIHAN SAVR & KABEL BAWAH TANAH 11kV DI LADANG KIRBY PRIVATE SALES ORDER ISSUED 7 SOUTH PERMOHONAN RJO LEBIH RM80K- RJO FUDAK 452,799.76 PRIVATE SALES ORDER ISSUED 8 SOUTH Permohonan Pengalihan Link box 33kV di Balai Panjang 849,077.75 PRIVATE SALES ORDER ISSUED 9 SOUTH PENGALIHAN RJO > 80K (CHE ENG KHOR) 643,907.20 PRIVATE SALES ORDER ISSUED 10 SOUTH RJO-6340-29518 - PERMOHONAN MENGUBAH TALIAN ATAS BARE WIRE SEDIADA KEPADA UNDERGROUND 196,172.92 PRIVATE SALES ORDER ISSUED 11 SOUTH PENGALIHAN RJO > 80K (GREAT WALL) 123,807.22 PRIVATE SALES ORDER ISSUED 12 SOUTH RJO-6340-40685 - Lucky Export Malaysia Sdn Bhd 103,541.73 PRIVATE SALES ORDER ISSUED 13 SOUTH PENGALIHAN RJO > 80K (OROMEO) - WO: 10802754 211,025.67 PRIVATE SALES ORDER ISSUED 14 SOUTH RJO JALAN KOLAM AYER 240,049.00 PRIVATE SALES ORDER ISSUED 15 SOUTH PENGALIHAN RJO > 80K (MIAOW - MIAOW) TAMBAHAN 203,570.67 PRIVATE SALES ORDER ISSUED RM 4,605,865.55


Forecast [November – December] *Application Received/Estimation In Progress Zone Keterangan Kerja Kos Projek Kategori Status 1 SELPJCJ RJO PENGALIHAN SAVT 11KV, SAVR LVUG DI JALAN KERAYONG BUKIT KAPAR 85,229.17 PRIVATE APPLICATION RECEIVED/ESTIMATION IN PROGRESS 2 SELPJCJ RJO BERSKALA BESAR DI SEKSYEN 19 JALAN HARAPAN 160,506.73 PRIVATE APPLICATION RECEIVED/ESTIMATION IN PROGRESS 3 SELPJCJ RJO PENGALIHAN TIANG BAGI MASJID AL FALAH SG RAMAL, BANGI 87,610.49 PRIVATE APPLICATION RECEIVED/ESTIMATION IN PROGRESS 4 SELPJCJ RJO PENGALIHAN 203,026.10 PRIVATE APPLICATION RECEIVED/ESTIMATION IN PROGRESS 5 SELPJCJ RJO PENGALIHAN KABEL 33KV JALAN SG BUAYA 1,672,812.83 PRIVATE APPLICATION RECEIVED/ESTIMATION IN PROGRESS 6 SELPJCJ RJO PENGALIHAN KABEL 4 LITAR DI PERSIARAN IMPIAN PERDANA 144,525.28 PRIVATE APPLICATION RECEIVED/ESTIMATION IN PROGRESS 7 SELPJCJ RJO PENGALIHAN KABEL 33KV DI MUKIM IJOK, KUALA SELANGOR 493,282.38 PRIVATE APPLICATION RECEIVED/ESTIMATION IN PROGRESS 8 SELPJCJ RJO PENGALIHAN KABEL 33KV BESTARI JAYA 119,029.08 PRIVATE APPLICATION RECEIVED/ESTIMATION IN PROGRESS 9 SELPJCJ RJO PENGALIHAN KABEL TERLIBAT DENGAN KERJA-KERJA TEROWONG JALAN KE HOSPITAL SUNWAY 142,152.08 PRIVATE APPLICATION RECEIVED/ESTIMATION IN PROGRESS 10 SELPJCJ RJO PENYELIAAN DAN SDOWN DI BANDAR GAMUDA COVE, BANTING 129,876.49 PRIVATE APPLICATION RECEIVED/ESTIMATION IN PROGRESS 11 SOUTH Tetuan Daiman Development - BQ 33kV done - BQ 11kV WIP 991,502.89 PRIVATE APPLICATION RECEIVED/ESTIMATION IN PROGRESS 12 SOUTH Permas Jaya Sdn Bhd - Kickoff final harga done - pending persetujuan penerimaan harga dari pemaju 1,452,295.00 PRIVATE APPLICATION RECEIVED/ESTIMATION IN PROGRESS 13 SOUTH GJH Development (PONTIAN) - BQ pengalihan WIP 1,400,000.00 PRIVATE APPLICATION RECEIVED/ESTIMATION IN PROGRESS 14 SELPJCJ RJO PENGALIHAN SAVT 11KV, SAVR LVUG DI JALAN KERAYONG BUKIT KAPAR 85,229.17 PRIVATE APPLICATION RECEIVED/ESTIMATION IN PROGRESS 15 SELPJCJ RJO BERSKALA BESAR DI SEKSYEN 19 JALAN HARAPAN 160,506.73 PRIVATE APPLICATION RECEIVED/ESTIMATION IN PROGRESS RM 12,038,643.56


Forecast [November – December] *Application Received/Estimation In Progress Zone Keterangan Kerja Kos Projek Kategori Status 1 SOUTH Era Grand Development (PONTIAN) - BQ pengalihan WIP 1,800,000.00 PRIVATE APPLICATION RECEIVED/ESTIMATION IN PROGRESS 2 SOUTH Pengalihan Stesen Suis Utama - Teluk Sengat, Kota Tinggi, Johor Kerja-kerja melibat pengalihan struktur sivil dan elektrikal sedia ada, SS Johor Lama, SS Sungai Layau dan Transformer 750KVA. 558,524.78 PRIVATE APPLICATION RECEIVED/ESTIMATION IN PROGRESS 3 SOUTH RJO-6360-32117 - GCU - Tetuan Petronas Gas Berhad (33kV STAR) 161,805.02 PRIVATE APPLICATION RECEIVED/ESTIMATION IN PROGRESS 4 SOUTH RJO-PENGALIHAN KVT 240MMP, KVR 185MMP DAN SAVR UNTUK PROJEK CADANGAN PEMBANGUNAN BERCAMPUR(KONSEP BERPAGAR) DI ATAS LOT 542, MUKIM BALAI PANJANG, DAERAH MELAKA (PR1MA) 241,583.93 PRIVATE APPLICATION RECEIVED/ESTIMATION IN PROGRESS 5 SOUTH Penyerahan RJO Berprofil Tinggi - Kem Segamat (Usima Sdn Bhd) 118,954.79 PRIVATE APPLICATION RECEIVED/ESTIMATION IN PROGRESS 6 SOUTH RJO SIMPANG 3 KOTA TINGGI (DEPAN KFC) 247,726.48 PRIVATE APPLICATION RECEIVED/ESTIMATION IN PROGRESS 7 SOUTH RJO Pengalihan Kabel 33kV di Jalan Ismail Sultan 1 ,138,855.00 PRIVATE APPLICATION RECEIVED/ESTIMATION IN PROGRESS 8 SOUTH RJO YEKA PLASTICS INDUSTRIES SDN BHD 612,917.47 PRIVATE APPLICATION RECEIVED/ESTIMATION IN PROGRESS 9 SOUTH RJO Honda Tampin (Tetuan Greater Tampin Oto Sdn Bhd) 134,174.00 PRIVATE APPLICATION RECEIVED/ESTIMATION IN PROGRESS 10 SOUTH MS VENTURE INDUSTRIES SDN BHD 225,239.62 PRIVATE APPLICATION RECEIVED/ESTIMATION IN PROGRESS 11 SOUTH RJO Pengalihan Link Box 33kV - VSKI/4P5/LINK6/XB/JNBS/4P5 (6/11) 138,232.30 PRIVATE APPLICATION RECEIVED/ESTIMATION IN PROGRESS 12 SOUTH RJO Mc'Donald Jasin 540,603.47 PRIVATE APPLICATION RECEIVED/ESTIMATION IN PROGRESS 13 EAST KERJA-KERJA PENGALIHAN TIANG 10M BAGI PEMBANGUNAN SADDLE DAM NENGGIRI 177,033.18 PRIVATE APPLICATION RECEIVED/ESTIMATION IN PROGRESS 14 SOUTH Era Grand Development (PONTIAN) - BQ pengalihan WIP 1,800,000.00 PRIVATE APPLICATION RECEIVED/ESTIMATION IN PROGRESS RM 12,038,643.56


DETAIL LIST OF ACTION REQUIRE BY ZONE Challenges Action Require PIC Dateline Expectation Outcome Project Implementor occupied with system/supply SLA projects, RJO implemented not captured in KPI. Zone PIC to register project/RJO implemented at zone level Project Implementor, RJO Coordinator (HQ) BAU To capture value/project implemented manually to ABU AD annual performance. (For RJO with no profit margin)


THANK YOU


CONFIDENTIAL AND PROPRIETARY CIVIL WORKS - FINAL DASH 2023 Prepared by Muhamad Afdzal bin Ali 13 September 2023 TNB Kuantan Deliverables Capex Utilization : RM36 mil TECO Value : RM67mil Afdzal (L) Chin Yeit Yang Nurliyana Azmi Ida Suzana Siti Rohani


Performance CIVIL WORKS - OVERALL


SAIDI 50 – CIVIL WORKS FOR PPU & MINI PPU


FORECAST COMPLETION 9 2 3 8 13 1


FORECAST CAPEX & TECO Zone State No of Projects SAIDI50 Forecast CAPEX Utilization (RM) Forecast CAPEX Utilization (RM) Forecast No TECO Forecast TECO Value (RM) Forecast TECO Value (RM) East KEL 13 1 7,529,044.23 840,000.00 3 25,290,963.10 640,000.00 TRG 19 1 2,017,483.96 4 1,108,837.33 PAH 18 3 4,671,560.27 6 23,542,125.85 South JOH 18 3 10,473,286.50 3,445,266.46 6 12,178,270.30 7,297,612.46 NSE 10 3 5,828,020.00 2 2,237,950.00 MEL 6 2 1,200,000.00 1 2,642,707.81 WKL WKL 29 1 1,925,467.83 1,925,467.83 0 - SEL SEL 33 5 6,940,000.00 6,940,000.00 7 18,900,000.00 18,900,000.00 North PRK 0 3 9,735,830.84 1,870,000.00 2 11,088,341.00 3,530,000.00 PEN 0 1 2,189,965.12 1 2,990,000.00 KED 14 12 4,060,758.50 5 4,568,341.00 PER 3 1 1,615,107.22 0 - TOTAL 163 36 36,603,629.36 32 67,457,574.45