For ePTW applications:
Upload in Section 4
(before verification)
Conduct JHA site verification
(Action by RA/Work Leader)
Upload signed JHA into ePTW in
Section 4 or 8 during handback
Internal
Internal
Open
Internal
WHAT IS HAZARD
HAZARD :
The potential to cause harm. Harm including ill
health and injury, damage to property, plant,
products or the environment, production losses
or increased liabilities.
Internal
WHAT IS RISK
Risk is combination of the likelihood and severity of a specified
hazardous event occurring
RISK = Likelihood x Severity
where,
Likelihood:
event likely to occur within specified period or in specified circumstances
Severity:
outcome from an event such as severity of injury/health of
people/damage to property/insult to environment/any combination of
those caused by event
Internal
RISK MATRIX
Internal
Hazards need to be managed accordingly
Spillage
Electrical Wiring/Socket Moving Vehicle
Tripping Hazards
Rotating Parts
Internal
Internal
Internal
Internal
Internal
Internal
Internal
HAZARD MANAGEMENT
Internal
HAZARD IDENTIFICATION
COMMON MISTAKES IN
CONFINED SPACE OPERATION
Ventilation - OK
Manhole in open position
without proper signage – Not OK
Manhole in open position
without signage – Not OK
Manhole in open position
with signage – OK
Confined space entry (CSE)
without standby man – Not OK
Internal
HAZARD IDENTIFICATION
Man inside the confined space and
the hole watcher (standby person) was not at his place.
Internal
HAZARD IDENTIFICATION
NOT WEARING HARNESS!! HARNESS MUST BE HOOKED
TO A HIGHER POSITION!!
Internal
HAZARD IDENTIFICATION
Get it hooked, for your own safety..
Wearing harness means nothing
if you don’t hook it !!
Internal
HAZARD IDENTIFICATION
What kind of harness is this!!! This is NOT a place to relax!!!
???
Home made scaffold is NOT acceptable This is definitely NOT a place
to take a nap!!!
Internal
HAZARD IDENTIFICATION
Workers can easily fall down, and so are objects
which may fall down and hit workers.
Internal
HAZARD IDENTIFICATION
Unsafe condition – the scaffold’s base plates are unsafe and may cause
the scaffold to collapse
Internal
HAZARD IDENTIFICATION
WORK PLATFORMS MUST NOT HAVE EXCESSIVE (melebihi ) MATERIAL,STEELWORK/BEAMS
MUST NOT BE USED AS STORAGE-FALLING/DROPPED OBJECT HAZARD-ASK FOR STORAGE
BINS/BAGS
Internal
HAZARD IDENTIFICATION
Do not deploy the ladder on the Unstable ladder support
cable tray…
Internal
HAZARD IDENTIFICATION
BADLAPDRDAECRTIACCE-CLEASDSDER
AOCBCSETSRSUOCBTSETDRAUNCDTEPDOAONRD
CABLPEOOMRANCAAGBELME ENT
MANAGEMENT
GOOD PRACTICE-
ELECTRICAL INSPECTION IN
DATE AND SAFE CONDITION
Internal
HAZARD IDENTIFICATION
OPEN GRATINGS MUST HAVE HARD
BARRIER OR BE COVERED WITH
STURDY (kuat, tegap) BOARD-
FALLING/DROPPED OBJECT
HAZARD-IF WORKING NEAR
OPENINGS MUST BE CLIPPED ON-
PERMIT REQUIRED TO LIFT ANY
GRATING
Internal
HAZARD IDENTIFICATION
ELECTRICAL CABLE MUST
BE ELEVATED OUT OF
WATER AND HOLES IN
CONCRETE SLABS MUST BE
BACKFILLED
Internal
HAZARD IDENTIFICATION
ELECTRICAL DISTRIBUTION BOARDS CAN ONLY BE
ACCESSED BY ELECTRICIAN AND MUST BE CLOSED AT ALL
TIMES-ELECTROCUTION HAZARD
Internal
HAZARD IDENTIFICATION
“Is this the right outrigger pad
to balance and sustain the
load?“
Outrigger pad
without block
• Always Use Outriggers –
Fully Extended
• Use Pads to Distribute Loads
Internal
HAZARD IDENTIFICATION
No fire watcher during welding activity.
Internal
HAZARD IDENTIFICATION
Bad Housekeeping
Good Housekeeping
Internal
HAZARD IDENTIFICATION
Never roll up the
sleeves of your
coverall while
performing any job.
Internal
HAZARD IDENTIFICATION
Face shield was lifted leaving his face unprotected…..
Internal
HAZARD IDENTIFICATION
No canvas used while using the hydro jet pressure.
Internal
HAZARD IDENTIFICATION
Good practice
Bad practice
Internal
HAZARD IDENTIFICATION
Gas respirator hung at valve… the filter will
expire if it is not stored properly
Internal
HAZARD IDENTIFICATION
Unsafe act and misuses of forklift for transportation
Internal
HAZARD IDENTIFICATION
A DEATH TRAP – OPENING NOT
COVERED OR BARRICADED
Internal
HAZARD IDENTIFICATION
Internal
HAZARD IDENTIFICATION
Internal
HAZARD IDENTIFICATION
Spot the hazards, assess the risks
Internal
Internal
The status of all PTWs and Tier-1 Checklist can be referred
certificates shall be tracked and using available checklist under
recorded on a daily basis until L3 HSE Assurance_A01:
they are closed.
• Active PTW (Site) – 1/month
The Tier-1 assurance shall be • Closed PTW – 8/month
conducted by RA/RAR/AA/AAR.
Checklist for L3 Assurance can
be retrieved from OexMS 01.12
L3 HSE Assurance_A01
Internal
Item Compliance Requirement Evidence Required
Section 1 - Requisition
1.1 Is the PTW adequately specifies details of Check if scope activities is reflected based on Job
applicants name, department, staff no, Method Statement (JMS).
contact no etc.?
1.2 Is Location, Facility, Equipment no, Area Verify site location, equipment and SAP system
Classification and SAP W/O no.
specified?
1.3 Is date required and completions Verify date with site execution planning
specified?
Section 2 – Hazards Identification
2.1 Are work site hazards and hazardous Interview WL or RA by checking briefing attendance and
activities clearly identified by WL/RA? JHA communication
2.2 Site verification Verify site hazards with identified hazards in PTW.
Internal
Item Compliance Requirement Evidence Required
Section 3 – Personal Protective Equipment Refer PPE matrix and Job Method Statement
Verify by physical observation and interview
3.1 Does correct PPE identified for the work
by WL/RA/AA?
3.2 Does workers comply to PPE identify
3.3 Site verification Site observation
Section 4 – Supporting Certificates/Documents
4.1 Are work site hazards and hazardous Compare site hazards with identified hazard in PTW
activities clearly identified by WL/RA? Site observation
4.2 Site verification
4.3 Does the activity require Supporting Certificates, JHA, Method Statement, Pre-job MOM,
Certificates/Documents. Authority Clearance, Drawing no. etc
4.4 Does adequate Certificates/Documents Check with work description specific in PTW and site
attached to the PTW conditions.
Internal
Item Compliance Requirement Evidence Required
Section 4 – Supporting Certificates/Documents (Continue)
4.5 Does Certificates/Documents signed by Site verification
CAA and make available at site Interview workers who perform the job
Verify in PTW
4.6 Do workers understand/shared the
precaution stated in the JHA?
4.7 Does RA endorse this section?
Section 5 – Work Site Preparation/Precautions
5.1 Does correct precaution identified by AA? Verify JHA and site mitigation and control
5.2
5.3 Does correct site conditions implemented Site verification
by RA/WL
5.4
Does joint site visit before work start • Check if a copy of PTW is printed and signed at
Internal carried out by RA/RAR and AA/AAR?
Joint Site Visit column by AA/AAR before
commencement of work activity
• Appoint AAR to verify site condition before PTW
approval in system by respective AA
• Ensure detail JMS or Job pack is established, JHA
and risk mitigation reviewed in Pre-Job meeting
Does signature and date information are Verify date info with actual site visit
properly written by RA/RAR and AA/AAR?
Item Compliance Requirement Evidence Required
Section 6 – Approval
6.1 Does signature and date information are Verify PTW printed copy/ePTW
properly written by RA/RAR, AA and WL?
Section 7 – Revalidation
7.1 Is PTW validation being signed and dated Verify PTW printed copy/ePTW
correctly by WL/RA and AA?
7.2 Are revalidations not exceeding 7 Verify PTW printed copy and site execution
consecutive days?
7.3 Are join site visit conducted before each Appoint AAR to verify site condition before PTW
revalidation? approval in system by respective AA
7.4 Does the revalidation required night work Site verification and verify JHA scope
and does JHA cover such activity?
Section 8 – Hand Back
8.1 Does hand back being signed, date and Verify ePTW and handback execution
information are clearly written by WL/RA?
8.2 Not applicable for ePTW application – Ensure signed
Does this PTW have it 3 copies attached? JHA and gas test reading (for hot work) is uploaded
Internal
Item Compliance Requirement Evidence Required
Section 8 – Hand Back (Continue)
8.3 Does the permit closed on time by AA? Daily PTW closure tracking by respective RA to ensure
PTW application
Gas Test Requirements – For Hot Work/Confine Space Work only
1 Have gas test taken by competent AGT? Check with COC list
2 Does initial gas test result information are • Check if AAR have interface with AA for verifying
properly written by AGT? site condition after verify condition at site.
• Ensure AAR has communicate initial gas test results
to AA for approval to commence work activity.
3 Are frequencies of gas test specifies by Verify PTW printed copy/ePTW
HWAA?
4 Are there any special precautions specify Verify PTW printed copy/ePTW
by HWAA?
5 Does signature and date information are Verify PTW printed copy/ePTW
properly written HWAA?
6 Does CES certificate attached? Verify PTW printed copy supporting document.
7 Does CSE type of entry and condition to Verify site condition and ePTW
be implemented specify clearly?
Internal
All Assurance findings must be tracked and closed on a timely
manner.
Action item arising from Tier-1 Findings shall be registered in OE-
track as platform of monitoring closure.
The Assurance team shall specify the allocated duration for full
closure of findings.
The team shall also determine the acceptance criteria fulfilling
which will signify a closure of a finding
Internal
EXERCISE 2 :
Task: WL to fill-up and
present JHA (min. 3 step
of work activity).
Internal
Internal