WATER SYSTEM
MASTER PLAN
205 Executive Court CAPITAL IMPROVEMENT
PLAN
Little Rock, AR 72205
501-664-1552
www.cristengineers.com
June
2018
Crist Job No. 1560
Table 20
CITY OF HOT SPRING
WATER SYSTEM
CAPITAL IMPRO
No. Type Description
Water System Improvements - Water Supply and Treatment Improvements
OUACHITA WATER TREATMENT PLANT
1 Replace Sludge Collection Mechanisms in Sedimentation Basins 1
2 Replace Troughs in Sedimentation Basins 1-5
3 Chlorine Dioxide Feed System
4 Evaluate the Addition of Sludge Dewatering Facility
LAKESIDE WATER TREATMENT PLANT
1 Replace Filter Media
2 Add Combined Air and Water Backwash to Filters
3 Replace Filter Underdrains and Backwash Troughs
4 Replace Lime Feed with Liquid
5 Rehabilitate Pipe Gallery
6 Replace / Repair Lake Ricks Intake Gate Control Mechanisms
7 Instrumentation and Control for Plant Automation
8 Fluoride Feed System
9 Backwash Water Handling System
10 Raw Water Line Waste Valve
11 Sludge Collection Mechanism in Sedimentation Basin
12 Repair Clearwell 2 Liner
13 Repair Clearwell Vents
14 Replace Rapid Mix and Flocculation Mechanisms
Water System Improvements - Distribution System - Near Term Improvements
1 Tank 3,000,000 Gallon Elevated Water Storage Tank (Main Pressure Zo
Page 1
6/12/2018
GS WATER UTILITIES CAPITAL IMPROVEMENT PLAN
MASTER PLAN
Near Mid Long
OVEMENT PLAN
Term Term Term
Cost Estimate
($)
($) ($) ($)
1-5 $1,300,000 $1,300,000
$200,000 $200,000
$1,600,000 $1,600,000
$1,500,000 $1,500,000
$10,000,000 $10,000,000
one) $4,960,000 FUNDED
1 of 4
Table 20
CITY OF HOT SPRING
WATER SYSTEM
CAPITAL IMPRO
No. Type Description
2 Line 4,050' - 24" and 16" Water Main for 3.0 MG Elevated Tank
3 Line 11,160 - 12" Transmission Line (On Fontana, MLK Bypass to Coun
4 Zone Ouachita Pressure Zone Expansion
5 Line 1710' - 6" Northeast Grand Avenue Line (Gorge Road to Kriptal St
6 Line 4,500' - 12" Reinforcement Loop (Spring Street To Grand Ave)
7 Line 3,000' - 8" Kelton Street Loop (East Grand Avenue to Mill Creek R
8 Tank Hollywood Avenue Tank - TMS and Overflow Improvements
9 BPS Pine Street Booster Pump Station Replacement
10 Line 11,436' - 24" Bypass Extension (Carpenter Dam to Malvern Ave a
11 Tank Holly Street Tank - Tank Mixing System and Tank Repairs
12 Tank Twins Tanks - Install TMS and Tank Improvements
13 Tank Music Mountain Tank - Tank Mixing System and Overflow Improv
14 Tank Industrial Park Tank - Tank Repainting and Tank Mixing System
15 Tank Belvedere Tank - Install TMS
16 Tank Woodmere / Whittington Avenue Tank - Tank Mixing System
17 Line 2,667' - 12" Carpenter Dam Road Main (MLK Bypass To Malvern A
18 Line System Diagnostic Flow Meter - Malvern Avenue
19 Line System Diagnostic Flow Meter - Highway 270 West
20 Line System Diagnostic Flow Meter - Highway 290
21 Line Relocate Lowery PRV out of Malvern Avenue
22 Line 200' - 6" Santa Cruz Loop (Santa Cruz Dr To Silverspur St)
23 Line 2100' - 8" Twin Points Dr Loop (Connect two 8" Water Lines on T
24 Line 355' - 6" Fair Street Loop (Trivista Right to Langston St)
Page 2
6/12/2018
GS WATER UTILITIES
MASTER PLAN
OVEMENT PLAN
Cost Estimate CAPITAL IMPROVEMENT PLAN
($)
Near Mid Long
Term Term Term
($) ($) ($)
$1,110,000 FUNDED
$1,170,000
ntry Club Dr) $1,170,000
treet) $570,000
Road) $167,000 $570,000
along Bypass) $480,000
vements $326,000 $167,000
$848,000
Ave) $487,000 $480,000
$3,086,000
Twin Point Dr) $360,000 $326,000
$600,000
$350,000 FUNDED
$620,000
$130,000 FUNDED
$180,000
$681,000 $3,086,000
$50,000 $360,000
$50,000
$50,000 $600,000
$150,000
$39,000 $350,000
$147,000
$83,000 $620,000
$130,000
$180,000
$681,000
$50,000
$50,000
$50,000
$150,000
$39,000
$147,000
$83,000
2 of 4
Table 20
CITY OF HOT SPRING
WATER SYSTEM
CAPITAL IMPRO
No. Type Description
25 Line 740' - 6" Linden Park Loop (Linden St To Linden Park Lane)
26 Line 870' - 6" Gap on Greenwood (Afton St to Summer St)
27 Line 690' - 6" Patterson Street & IRA St Loop
28 Line 500' - 6" Pearl St Loop (Westover to Wood Street)
29 Line 1,200' - 6" Grand Ave & Shelby St Loop (Lacey to Beard & Grand A
Water System Improvements - Distribution System - Mid-Term Improvements
1 Tank Purchase Property adjacent to Hwy. 70 Tank for future Tank site
2 BPS Royal Pump Station - Install Flow Meter
3 Line 30' - 12" On Mission St (crossing Hobson Avenue @ Mission Stree
4 Tank 2,500,000 Gallon Elevated Water Storage Tank (Main Pressure Zo
5 Line 8,500' - 20" Parallel Line on Wood Street and Garland Ave (Maso
6 Line 2,300' - 8" Main on Ridgeway Street (Highland Park St to Pleasan
7 Line 2,100' - 12" Main on Amber Street ( Cedar Street to Park Avenue
8 Line 900' - 8" Kay Street Loop (Kay Street to Shady Grove Rd)
9 Line 1,620' - 6"Main on Rector Heights Dr (Albert Pike to Meadow @ P
10 Line 1,000' - 8" Quail Creek Parallel Line (6" south of Taylor to Ravenw
11 Line 2,650' - 8" Red Oak Loop (Farrs Landing to Twin Oaks)
12 Tank Oak Grove Tank - Tank Mixing System and Tank Improvements
13 Tank Crystal Springs Tank - Tank Mixing System and Tank Improvemen
14 Line 3,130' - 12" Greenwood Water Main (7th Street to Central Avenu
15 Line 3,400' - 8" Marion Anderson Parallel Line (Walkway St To Stoneg
16 Line 1,800' - 6" Airport Road Loop (Adlridge to Old Airport Road)
17 Line 826' - 6" Pinewood Leeper Loop (Patterson at St Louis)
Page 3
6/12/2018
GS WATER UTILITIES
MASTER PLAN
OVEMENT PLAN
Cost Estimate CAPITAL IMPROVEMENT PLAN
($)
Near Mid Long
Term Term Term
($) ($) ($)
$87,000 $87,000
$183,000
$125,000 $183,000
$105,000
$234,000 $125,000
$105,000
Ave to Etter ) $234,000
et) $100,000 $100,000
one) Hwy 70 $136,000 ROYAL
on to Central)
nt Valley Street) $45,000 $45,000
e) $5,180,000 $5,180,000
$2,852,000 $2,852,000
Patricia St)
wood Dr) $183,000 $183,000
$389,000 $389,000
nts $147,000 $147,000
ue) $309,000 $309,000
gate Shores) $203,000 $203,000
$287,000 $287,000
$620,000 ROYAL
$520,000 ROYAL
$650,000 $650,000
$275,000 $275,000
$140,000 $140,000
$156,000 $156,000
3 of 4
Table 20
CITY OF HOT SPRING
WATER SYSTEM
CAPITAL IMPRO
No. Type Description
18 Line 100' - 6" Wynn Street Loop
19 Line 2,000' - 6" Hammond Loop (6" on Hammond Drive to 6" on Hamm
20 Line 350' - 6" Winona Loop (Carson Street To Miller Street)
Water System Improvements - Distribution System - Long Term Improvements
1 Tank 500,000 Gallon Elevated Water Storage Tank (Industrial Park Pre
2 Line 1,500' - 12" Parallel Line on Malvern Ave (Bypass Off ramp to We
3 Line 2,200' - 10" Ravine Street Water Main ( Park Avenue to Ramble S
4 Line 500' - 8" Albert Pike Loop (Albert Pike Road @ Airport Road)
5 Line 24" Royal Transmission Line (Treasure Isle to Oakgrove)
6 Line 8,950' - 6" Sunshine Loop (Ware to Sagebrush)
7 Tank 300,000 Gallon Elevated Water Storage Tank (Royal Pressure Zon
8 Line 1,000' - 12" Belvedere Reinforcement Loop (Mountain Valley St t
9 Line 3,550' - 12" South Moore Road Parallel Line (Ranchester to Charm
10 Line 1,200' - Airport Road Parallel Line (Lakeshore Drive to Blackhawk
11 Line 250' - 6" Fleetwood Loop
12 Line 675' - 8" Sawtooth Oak Street Loop (Mote Street to Sawtooth Oa
13 Line 1,650' - 6" Ridgeway Street Loop (Ridgemont Street to Stacy Stre
14 Line 550' - 6" Shawnee Line Extension (Shawnee Street to Fox Run Cir
15 Line 620' - 6" Alysonview Loop (Riviera Street to Alysonview Street
16 Line 1,960' - 8" N Albert Pike Water Line (Rector Heights Drive to Miss
17 Tank 2,000,000 Gal. Elevated Water Storage Tank (Main Pressure Zone
* Cost estimates include construction costs, contingency, and other project costs for en
Page 4
6/12/2018
GS WATER UTILITIES
MASTER PLAN
OVEMENT PLAN
Cost Estimate CAPITAL IMPROVEMENT PLAN
($)
Near Mid Long
Term Term Term
($) ($) ($)
$42,000 $42,000
$341,000
mond Drive) $341,000
$81,000
$81,000
essure Zone) $1,730,000 $1,730,000
$300,000
estinghouse Rd) $300,000 $255,000
$120,000
Street) $255,000
ROYAL
$120,000 $486,000
$4,607,000 ROYAL
$233,000
$486,000 $714,000
$558,000
ne) $1,630,000 $75,000
$89,000
to Park Avenue) $233,000 $143,000
$93,000
ming Heights) $714,000 $71,000
$250,000
k Street) $558,000
$8,690,000
$75,000 $13,807,000
ak St) $89,000
eet) $143,000
rcle) $93,000
$71,000
sion Street) $250,000
e) Bald Mtn. $8,690,000
TOTALS $11,523,000 $24,480,000
ngineering, legal, environmental, etc.
4 of 4
NEAR TERM
IMPROVEMENTS
RED = NEAR TERM IMPROVEMENTS PIPE DIAMETERS
BLUE = MIDTERM IMPROVEMENTS
2 Inch 10 Inch 18 Inch
PURPLE = LONG TERM IMPROVEMENTS 4 Inch 12 Inch 20 Inch
6 Inch 14 Inch 24 Inch
8 Inch 16 Inch 30 Inch
DR MARTIN LUTHER KING JR
24-INCH WATER MAIN
CENTRAL «¬2 3,000,000 GALLLON ELEVATED
WATER STORAGE TANK IN
OUACHITA PRESSURE ZONE
O.F. = 710 FT MSL
!( «¬1
16-INCH WATER MAIN
«¬2
BUENA VISTA
DISTRIBUTION SYSTEM IMPROVEMENTS - IMPROVEMENTS #1 & #2
3 MILLION GAL. TANK & WATER MAINS
CITY OF HOT SPRINGS, AR CRIST ENGINEERS, INC.
WATER SYSTEM MASTER PLAN
Source: ECsOriN, SDUigLTitIaNlGG EloNbGeI,NGEEeRoSEye, ELIaTrTthLsEtaRrOGCeKo, gArRaKphAiNcSs,AS
0 115 230 460 690 920
CNES/Airbus DS, USDA, USGSJU, NAEe,ro2G01R8ID, IGN, and the GIS
Feet User Community
1 inch = 500 feet
CRIST ENGINEERS, INC.
JOB ESTIMATE COST SUMMARY
PROJECT: PH 1 IMPROVEMENT #1 - 3,000,000 GALLON WATER STORAGE TANK
OWNER: CITY OF HOT SPRINGS WATER UTILITIES
DATE: June 8, 2018 ESTIMATE BY: Matthew D. Dunn, P.E.
JOB NO: 1560
ESTIMATED
Item No. Description Unit Total Unit Cost Total Cost
Quantity
1 3.0 MG Elevated Water Storage Tank LS 1 $4,200,000
2 Tank Mixing System LS 1 $80,000
3 Yard Piping LS 1 $40,000
4 Site Work LS 1 $40,000
5 Logo LS 1 $60,000
6 Miscellaneous & Incidental LS 1
7 Telemetry LS 1 $5,000
8 Electrical LS 1 $40,000
9 Chain Link Fencing LS 1 $15,000
$20,000
Construction Cost $4,500,000
30% Contingency
$455,000
Engineering $4,960,000
TOTAL COST ESTIMATE
CRIST ENGINEERS, INC.
JOB ESTIMATE COST SUMMARY
PROJECT: PH 1 IMPROVEMENT #2 - WATER MAINS FOR 3.0 MG TANK
OWNER: CITY OF HOT SPRINGS WATER UTILITIES
DATE: June 8, 2018 ESTIMATE BY: Matthew D. Dunn, P.E.
JOB NO: 1560
ESTIMATED
Item No. Description Unit Total Unit Cost Total Cost
Quantity
1 24-inch DIP Water Transmission Line $110 $242,000
LF 2200
2 16-inch DIP Water Transmission Line LF 2700 $75 $202,500
3 24-inch Gate Valve EA 2 $22,000 $44,000
4 20-inch Gate Valve EA 3 $20,000 $60,000
EA 1
5 16-inch Gate Valve EA 1 $15,000 $15,000
EA 2
6 12"x12" Tapping Sleeve and Valve EA 7 $10,000 $10,000
7 Air Release Valve $3,500 $7,000
CY 1450
8 Fire Hydrant Assembly TON 700 $5,000 $35,000
LF 580
9 Rock Excavation LF 2700 $50 $72,500
LF 110
10 Granular Bedding Material LF $25 $17,500
11 Asphalt Driveway Surface Repair LS $75 $43,500
12 Asphalt Street Surface Repair LS $75 $202,500
13 Concrete Street Surface Repair LS $75
14 Route Clearing LS $15 $8,250
15 Seeding, Mulching, Final Cleanup LS $0
16 Miscellaneous & Incidental Work
17 Storm Water Permit & S.W.P.P.P. $10,000
18 Excavation & Trench Safety System $10,000
19 Bonds & Insurance $10,000
$2,000
$30,000
Construction Cost Estimate $1,022,000
20% Contingency
$88,000
Engineering $1,110,000
TOTAL COST ESTIMATE
PIPE DIAMETERS 18 Inch
2 Inch 10 Inch 20 Inch
4 Inch 12 Inch 24 Inch
6 Inch 14 Inch 30 Inch
8 Inch 16 Inch
MALVERN
CONNECT TO 12" SHADY GROVE
ON COUNTRY CLUB DRIVE
COUNTRY CLUB
12" WATER LINE
ALONG SHADY GROVE RD
GOLF LINKS CONNECT TO 8"
ON GOLF LINKS RD
GOLF LINKS
12" WATER LINE
ALONG FONTANA DRIVE
CONNECT TO 12" «¬3
ON TELEVISION HILL RD
FONTANA
DKLRIUNMTGHAJERRRTBINRODRICPKURRPEBLDLEU==ENL=OEMANRGIDTTTEEERRRMDMMRIIIMMMMAPPPRRRRTOIOONVVVLEUEEMTMMHEEEENNNRTTTKSISSNG JR
DISTRIBUTION SYSTEM IMPROVEMENTS - IMPROVEMENT #3
12" TRANSMISSION LINE
CITY OF HOLTPakRSeINGS, AR CRIST ENGINEERS, INC.
WATER SYSTHEaMmilMtonASTER PLAN
CONSULTING ENGINEERS LITTLE ROCK, ARKANSAS
0 230 460 920 1,380 1,840
JUNE, 2018
Feet
1 inch = 1,000 feet
CRIST ENGINEERS, INC.
JOB ESTIMATE COST SUMMARY
PROJECT: PH 1 IMPROVEMENT #3 - 12-INCH HOLLYWOOD WATER MAIN - MLK BYPASS TO COUNTRY CLUB
DRIVE
OWNER: CITY OF HOT SPRINGS
DATE: June 8, 2018 ESTIMATE BY: Matthew D. Dunn, P.E.
JOB NO: 1560
ESTIMATED
Item No. Description Unit Total Unit Cost Total Cost
Quantity
1 12-inch DIP Water Line LF $50 $558,000
11,160 $8
2 Route Clearing LF 3,300 $26,400
$2,800 $11,200
3 12-inch Gate Valve EA 4 $15,125 $30,250
2
4 12-inch Connection EA $210 $8,625
200 $90 $42,000
5 8-inch Connection LS 60 $75
770 $55 $5,400
6 20-inch Encasement, Bored - Hot Springs Creek X LF 20 $25 $57,750
37
7 12-inch Bore - Golf Links Rd Crossing LF 4 $4,500 $1,100
5 $4,000 $925
8 Ashpalt Resurfacing LF
$18,000
9 Concrete Resurfacing LF $20,000
10 Gravel Surface Repair LF
11 Fire Hydrant Assembly EA
12 Air Release Valve EA
Construction Cost Estimate $780,000
30% Contingency $234,000
$156,000
20% Engineering, Legal, Environmental, Admin.
$1,170,000
TOTAL COST ESTIMATE
6" WATER LINE
CONNECTION LOOPING
TWINS PRESSURE ZONE
CONVERT SYSTEM FROM TWINS ZONE
TO OAUIRAPCORHTITA ZONE
EXISTING PRESSURE ZONE BOUNDARY
«¬4 CENTRAL
12" WATER LINE FERRY
CONNECTION FROM HIGDON
BYPASS TO KIMERY PARK
DR MARTIN LUTHER
DISTRIBUTION SYSTEM IMPROVEMENTS - IMPROVEMENT #4
OUACHITA PRESSURE ZONE EXPANSION
CITY OF HOT SPRINGS, AR CRIST ENGINEERS, INC.
WATER SYSTEM MASTER PLAN
CONSULTING ENGINEERS LITTLE ROCK, ARKANSAS
0 345 690 1,380 2,070 2,760
JUNE, 2018
Feet
1 inch = 1,500 feet
PIPE DIAMETERS 18 Inch
2 Inch 10 Inch 20 Inch
4 Inch 12 Inch 24 Inch
6 Inch 14 Inch 30 Inch
8 Inch 16 Inch
HOLLYWOOD
«¬4 RED = NEAR TERM IMPROVEMENTS
BLUE = MIDTERM IMPROVEMENTS
PURPLE = LONG TERM IMPROVEMENTS
KEUKA PRV MALVERN
REMOVE FROM SERVICE
(OPEN BYPASS)
UTILIZE EXISTING VALVES FOR
3 PRESSURE ZONE ISOLATION GVRAALNVD ES
GOLF LINKS SPRING
«¬4
R KING JR RIDGEWAY WESTINGHOUSE
MLK
CONNECTION LOOPING
OUACHITA SYSTEM CARPENTER DAM
QUAIL CRREIEDKGEWAY TO WESTINGHOUSE
LAKESIDE
Lake Source: Esri, DigitalGlobe, GeoEye, Earthstar
Hamilton
WESTINGHOUGeSogErapRhicOs, CANDES/Airbus DS, USDA, USGS, AeroGRID,
IGN, and the GIS User Community
CRIST ENGINEERS, INC.
JOB ESTIMATE COST SUMMARY
PROJECT: PH 1 IMPROVEMENT #4 - OUACHITA PRESSURE ZONE EXPANSION
OWNER: CITY OF HOT SPRINGS WATER UTILITIES
DATE: June 8, 2018 ESTIMATE BY: Matthew D. Dunn, P.E.
JOB NO: 1560
ESTIMATED
Item No. Description Unit Total Unit Cost Total Cost
Quantity
1 12-inch DIP Water Line (Kimery Park Loop) LF 2,400 $50.00 $120,000
2 24-inch Connection LS $16,800
3 12-inch Connection $8,350
4 12x8 Tapping Sleeve and Valve LS $3,800
5 8-inch PVC Water Line (Westinghouse Loop)
6 8-inch Connection EA 1 $3,800 $36,000
$13,400
7 8-inch Slick Bore LF 1,200 $30
$11,375
8 6-inch PVC Water Line (Golf Links Road BN) EA 2
$16,200
9 6-inch PVC Water Line (Hot Springs Int Loop) LF 175 $65
10 6-inch Tapping Sleeve and Valve LF 540 $30
11 Asphalt Surface Repair
12 Route Clearing LF 630 $30 $18,900
13 Fire Hydrant Assembly
EA 2 $1,200 $2,400
LF 1,350 $75 $101,250
LF 3,000 $8
EA 2 $24,000
$4,500 $9,000
Construction Cost $381,000
30% Contingency $114,300
20% Engineering, Legal, Enviromental, Admin.
$76,200
TOTAL COST ESTIMATE
$570,000
RED = NEAR TERM IMPROVEMENTS PIPE DIAMETERS
BLUE = MIDTERM IMPROVEMENTS
2 Inch 10 Inch 18 Inch
PURPLE = LONG TERM IMPROVEMENTS 4 Inch 12 Inch 20 Inch
24 Inch
CONNECT TO 6" 6 Inch 14 Inch 30 Inch
ON GORGE ROAD 8 Inch 16 Inch
GORGE
KRIPTAL
ENTRANCE 1 E GRAND 6-INCH WATER LINE LOOP EXIT 2 E GRAND
EXIT 1 E GRAND
¬«5
ALABAMA
GRAND N FRONTAGE
GRAND
GRAND S FRONTAGE
PENNSYLVANIA CONNECT TO 6"
ON KRIPTAL STREET
MISSOURI Gulpha Creek
TENNESSEE CHAUCER
MISSISSIPPI
TEXAS CASTLEBERRY BLUESTONE
COLORADO
MILLCREEK
ILLINOIS KANSAS SPRING
DISTRIBUTION SYSTEM IMPROVEMENTS - IMPROVEMENT #5 ONTE
ESTELLE 6" NORTHEAST GRAND AVENUE LINE NORWALK
CITY OF HOT SPRINGS, AR BARRETT CRIST ENGINEERS, INC. ROSEMEAD
WATER SYSTEM MASTER PLAN Source: ECsOriN, SDUigLTitIaNlGGlEoNbGeI,NGEEeRoSEye, ELIaTrTthLsEtaRrOGCeKo,gArRaKphAiNcsS,AS
0 115 230 460 CLA69R0 A 920 CNES/Airbus DS, USDA, USGSJU, NAEe,ro2G01R8ID, IGN, and the GIS
Feet User Community
1 inch = 500 feet
CRIST ENGINEERS, INC.
JOB ESTIMATE COST SUMMARY
PROJECT: PH 1 IMPROVEMENT #5 - NORTHEAST GRAND AVENUE LOOP - GORGE ROAD TO KRIPTAL STREET
OWNER: CITY OF HOT SPRINGS
DATE: June 8, 2018 ESTIMATE BY: Matthew D. Dunn, P.E.
JOB NO: 1560
Item No. Description Unit Total ESTIMATED
Quantity Unit Cost Total Cost
1 6-inch PVC Water Line LF 1,710 $30 $51,300
2 6-inch Connection EA 2 $140 $12,400
3 12-inch Encasement, Bored LF 120 $40 $16,800
4 6-inch slick bore LF 200 $75
5 Ashpalt Street Repair LF 40 $25 $8,000
6 Gravel Surface Repair LF 140 $8 $3,000
7 Route Clearing LF 1,400 $3,500
8 Miscellaneous & Incidental Work LS $11,200
$5,000
Construction Cost Estimate $111,000
30% Contingency $33,300
$22,200
20% Engineering, Legal, Environmental, Admin.
$167,000
TOTAL COST ESTIMATE
HALK PIPE DIAMETERS
JULIAN RED = NEAR TERM IMPROVEMENTS 2 Inch 10 Inch 18 Inch
BLUE = MIDTERM IMPROVEMENTS
4 Inch 12 Inch 20 Inch
PURPLE = LONG TERM IMPROVEMENTS 6 Inch 14 InchFORES2T4 Inch
GRAND S FRONTAGE MAGIC SPRINGS 8 Inch 16 Inch 30 Inch
GRAND HIGHWOOD
DAVIS
LEGION BERTHA
JANETTE WHITE SULPHUR
ELLIOTT MILLCREEK
ACCESS
CLOUD REST
GRAND WHIPPOORWILL
ROSEMEAD KELTON
GREEN WILLOW
VERNEL BOUNDARYTONEY CONNECT TO 12" GRAND N FRONTAGGREAND POOLE
WADE SPRING WHIG NORTH OF GRAND AVE
HALIFAX
«¬6
MCCLENDON
JONITA BATES
LODEN MAYFAIR HEATON GRAND PRIVATE
Middle Branch Gulpha Creek FRONTAGE
PATRICK FESTIVAL
SMOKEYS
HONEYCUTT 12-INCH WATER LINE LOOP
CONNECT TO 8"
ON SPRING STREET
WAINE Gulpha Creek
CHATTANOOGA
REBECCA JINGLE KOLLER
DISTRIBUCTOINOESN SYSTEM IMPROVEMENTS - IMPROVEMENT #6JACOBS EAS MAN
12" REINFORCEMENT LOOP
CITY OF HOT SPRINGS, AR RHODES CRIST ENGINEERS, INC. STACY
WATER SYSTEM MASTER PLAN
Source: ECsOriN, SDUigLTitIaNlGGlEoNbGeI,NGEEeRoSEye, ELIaTrTthLsEtaRrOGCeKo,gArRaKphAiNcsS,AS
0 230 460 920 1,380 1,840
CNES/Airbus DS, USDA, USGSJU, NAEe,ro2G01R8ID, IGN, and the GIS
Feet User Community
1 inch = 1,000 feet
CRIST ENGINEERS, INC.
JOB ESTIMATE COST SUMMARY
PROJECT: PH 1 IMPROVEMENT #6 - 12-INCH WATER MAIN - SPRING ST TO EAST GRAND AVE
OWNER: CITY OF HOT SPRINGS
DATE: June 8, 2018 ESTIMATE BY: Matthew D. Dunn, P.E.
JOB NO: 1560
ESTIMATED
Item No. Description Unit Total Unit Cost Total Cost
Quantity
1 12-inch DIP Water Line $50 $225,000
LF 4,500 $2,800
2 12-inch Gate Valve EA 1 $15,125 $2,800
3 12-inch Connection EA 1 $15,125
4 8-inch Connection LS $80
LS $90 $8,625
5 6-inch Connection LF 160 $75
6 12-inch Slick Bore - Middle Fork Gulph Creek LF 60 $50 $8,125
7 12-inch Bore - Golf Links Rd Crossing LF 200 $55 $12,800
8 Ashpalt Street Resurfacing LF 220 $25
LF 180 $4,500 $5,400
9 Asphalt Drive Resurfacing LF 80 $15,000
10 Concrete Drive Resurfacing EA 1
11 Gravel Surface Repair $11,000
12 Fire Hydrant Assembly $9,900
$2,000
$4,500
Construction Cost Estimate $320,000
30% Contingency $96,000
20% Engineering, Legal, Environmental, Admin. $64,000
$480,000
TOTAL COST ESTIMATE
RED = NEAR TERM IMPROVEMENTS PIPE DIAMETERS
BLUE = MIDTERM IMPROVEMENTS
PURPLE = LONG TERM IMPROVEMENTS
HIGHWOOD
UNNAMED
WHITE SULPHUR
MILL CREEK
2 Inch 10 Inch 18 Inch
4 Inch 12 Inch 20 Inch
6 Inch 14 Inch THIN2C4LIAnDch
8 Inch 16 Inch 30 Inch
BLACKBEAR
MILLCREEK BLACK BEAR
CLOUD REST
CONNECTBTRUOML8EY"
ON MILL CREEK ROAD
RINGO DAVIS «¬7
WHIPPOORWILL Creek
KELTON 8-INCH WATER LINE LOOP
Gulpha
Branch
Middle
GRANGDRGARNADNNDFSRFORNOTNATGAE E POOLE
EXIT 4 E GRAND CONNECT TO 12"
ALONG EAST GRAND AVE
MCCLENDON
DISTRIBUTION SYSTEM IMPROVEMENPTRISVAT-E IMPROVEMENT #7
8" KELTON STREET LOOP
STIVAL
CITY OF HOT SPRINGS, AR
WATER SYSTEM MASTER PLAN CRIST ENGINEERS, INC.UCSENsoNeEurTrSCcR/eAAo:mNirEbCCmsuOErusiN,n4DSDitUEySigL,GTitUIaRNlSAGGDNlEoADNb,GeUI,NSGEGEeRoSJSUE, NAyeEe,,rEoL2GI0aT1rRTt8hLIDsEt,aRIrGOGCNeK,o,agAnrRadKpthhAieNcsSG,AISS
0 115 230 460 690 920
Feet
1 inch = 500 feet
CRIST ENGINEERS, INC.
JOB ESTIMATE COST SUMMARY
PROJECT: PH 1 IMPROVEMENT #7 - KELTON STREET WATER MAIN - E. GRAND TO MILL CREEK RD
OWNER: CITY OF HOT SPRINGS
DATE: June 8, 2018 ESTIMATE BY: Matthew D. Dunn, P.E.
JOB NO: 1560
ESTIMATED
Item No. Description Unit Total Unit Cost Total Cost
Quantity
1 8-inch PVC Water Line $30 $90,000
LF 3,000 $2,800
2 12-inch Gate Valve EA 1 $15,125 $2,800
3 12-inch Connection EA 1 $15,125
4 8-inch Connection LS $75
LF 1,000 $25 $8,625
5 Ashpalt Street Resurfacing LF 180
6 Gravel Surface Repair LF 2,000 $8 $75,000
7 Route Clearing EA 1 $4,500 $4,500
8 Fire Hydrant Assembly
$16,000
$4,500
Construction Cost Estimate $217,000
30% Contingency $65,100
20% Engineering, Legal, Environmental, Admin. $43,400
$326,000
TOTAL COST ESTIMATE
PIPE DIAMETERS 18 Inch
2 Inch 10 Inch 20 Inch
4 Inch 12 Inch 24 Inch
6 Inch 14 Inch 30 Inch
8 Inch 16 Inch
PRESSURE ZONE BOUNDARY
MALVERN
INSTALL TMS AND
MODIFY TANK OVERFLOW
PIPING
HOLLYWOOD
«¬8 !.
EXISTING
HOLLYWOOD AVENUE
1,000,000 GALLON ELEVATED
WATER STORAGE TANK
O.F. = 705 FT
RED = NEAR TERM IMPROVEMENTS
BLUE = MIDTERM IMPROVEMENTS
PURPLE = LONG TERM IMPROVEMENTS
DISTRIBUTION SYSTEM IMPROVEMENTS - IMPROVEMENT #8
HOLLYWOOD AVENUE TANK IMPROVEMENTS
CITY OF HOT SPRINGS, AR CRIST ENGINEERS, INC.
WATER SYSTEM MASTER PLAN
CONSULTING ENGINEERS LITTLE ROCK, ARKANSAS
0 115 230 460 690 920
JUNE, 2018
Feet
1 inch = 500 feet
CRIST ENGINEERS, INC.
JOB ESTIMATE COST SUMMARY
PROJECT: PH 1 IMPROVEMENT #8 - HOLLYWOOD TANK IMPROVEMENTS
OWNER: CITY OF HOT SPRINGS WATER UTILITIES
DATE: June 8, 2018 ESTIMATE BY: Matthew D. Dunn, P.E.
JOB NO: 1560
ESTIMATED
Item No. Description Unit Total Unit Cost Total Cost
Quantity
1 Insurance, Bonds, Mob., Demobilization LS 1 $15,000
2 Tank Mixing System LS 1 $80,000
3 Interior Coating Repairs LS 1 $140,000
4 Exterior Coating Repairs LS 1 $250,000
5 LOGO LS 1
6 Repairs & Improvements LS 1 $18,000
7 Disinfection LS 1 $50,000
8 Miscellaneous & Incidental LS 1
$7,000
$5,000
Construction Cost $565,000
30% Contingency $169,500
20% Engineering, Legal, Enviromental, Admin. $113,000
TOTAL COST ESTIMATE $848,000
RED = NEAR TERM IMPROVEMENTS PIPE DIAMETERS 18 Inch
BLUE = MIDTERM IMPROVEMENTS 2 Inch 10 Inch 20 Inch
4 Inch 12 Inch 24 Inch
PURPLE = LONG TERM IMPROVEMENTS 6 Inch 14 Inch 30 Inch
8 Inch 16 Inch
FULLY OPEN VALVE ON
WHITTINGTON AVENUE
THAT IS CURRENTLY BEING THROTTLED
CEDAR
PINE STREET BOOSTER «¬9
PUMP STATION
F.F. = 671' "/PINE
REPLACE
PINE STREET BOOSTER
PUMP STATION
CLOSE SYSTEM VALVE
FOR PRESSURE ZONE ISOLATION
3
TINGTON
DISTRIBUTION SYSTEM IMPROVEMENTS - IMPROVEMENT #9
PINE STREET BOOSTER PUMP STATION REPLACEMENT
CITY OF HOT SPRINGS, AR CRIST ENGINEERS, INC.
WATER SYSTEM MASTER PLAN
Source: ECsOriN, SDUigLTitIaNlGG EloNbGeI,NGEEeRoSEye, ELIaTrTthLsEtaRrOGCeKo, gArRaKphAiNcSs,AS
0 45 90 180 270 360
Feet CNES/Airbus DS, USDA, USGSJU, NAEe,ro2G01R8ID, IGN, and the GIS
User Community
1 inch = 200 feet
CRIST ENGINEERS, INC.
JOB ESTIMATE COST SUMMARY
PROJECT: PH 1 IMPROVEMENT #9 - PINE STREET BOOSTER PUMP STATION REPLACEMENT
OWNER: CITY OF HOT SPRINGS WATER UTILITIES
DATE: June 8, 2018 ESTIMATE BY: Matthew D. Dunn, P.E.
JOB NO: 1560
Item No. Description Unit Total ESTIMATED
Quantity
Unit Cost Total Cost
1 Trench & Excavation Safety Systems
$2,000
2 Insurance, Bonds, Mobilization, Demobilization $20,000
$286,000
3 Factory-Built Booster Pump Station $24,000
$14,000
4 Concrete Foundation $36,000
$34,000
5 Field-Installed Split-Face Rock Exterior $27,000
6 Site Improvements and Yard Piping
7 Demolition of Existing Structure
8 Electrical
TOTAL CONSTRUCTION COST $443,000
CONTINGENCY (10%) $44,300
TOTAL COST ESTIMATE $487,000
RED = NEAR TERM IMPROVEMENTS PIPE DIAMETERS 18 Inch
BLUE = MIDTERM IMPROVEMENTS 2 Inch 10 Inch 20 Inch
4 Inch 12 Inch 24 Inch
PURPLE = LONG TERM IMPROVEMENTS 6 Inch 14 Inch 30 Inch
8 Inch 16 Inch
CARPENTER DAM CONNECT TO 12"
MLKON MALVERN AVENUE
GLOINLKFS CONNECT TO 20"
WATER TRANSMISSION LINE
MALVERN Lake
Catherine
«¬10
Lake
DR MARTIN LUTHER KING JR Catherine
24-INCH WATER TRANSMISSION LINE
ALONG MLK BYPASS
DISTRIBUTION SYSTEM IMPROVEMENTS - IMPROVEMENT #10
CARPENTER
Lake Hamilton 24" BYPASS EXTENSION
CITY OF HOT SPRINGS, AR CRIST ENGINEERS, INC.
WATER SYSTEM MASTER PLAN Source: ECsOriN, SDUigLTitIaNlGGlEoNbGeI,NGEEeRoSEye, ELIaTrTthLsEtaRrOGCeKo,gArRaKphAiNcsS,AS
0 462.5 925 1,850 2,775 3,700 CNES/Airbus DS, USDA, USGSJU, NAEe,ro2G01R8ID, IGN, and the GIS
User Community
Feet
1 inch = 2,000 feet
CRIST ENGINEERS, INC.
JOB ESTIMATE COST SUMMARY
PROJECT: PH 1 IMPROVEMENT #10 - BYPASS EXTENSION - CARPENTER DAM ROAD TO MALVERN AVENUE
OWNER: CITY OF HOT SPRINGS WATER UTILITIES
DATE: June 8, 2018 ESTIMATE BY: Matthew D. Dunn, P.E.
JOB NO: 1560
ESTIMATED
Item No. Description Unit Total Unit Cost Total Cost
Quantity
1 24-inch DIP Water Line $145 $1,667,500
2 Route Clearing LF 11,500 $8 $89,112
3 36-inch Bore w/ Steel Encasement Pipe LF 11,139
4 20" Connection LF 170 $600 $102,000
$54,570
5 24-inch Gate Valve EA 4 $25,450
$101,800
6 12-inch Connection EA 4 $4,000 $18,000
7 Air Realease Valve LF 100 $25 $16,000
LF 100 $55 $2,500
8 Gravel Surface Repair
$5,500
9 Concrete Surface Repair
Construction Cost Estimate $2,057,000
30% Contingency $617,100
$411,400
20% Engineering, Legal, Environmental, Admin.
$3,086,000
TOTAL COST ESTIMATE
RED = NEAR TERM IMPROVEMENTS PIPE DIAMETERS 18 Inch
BLUE = MIDTERM IMPROVEMENTS 2 Inch 10 Inch 20 Inch
4 Inch 12 Inch 24 Inch
PURPLE = LONG TERM IMPROVEMENTS 6 Inch 14 Inch 30 Inch
8 Inch 16 Inch
LAKESIDE WTP
PULLMAN
HOLLY STREET
2,000,000 GALLON
GROUND STORAGE TANK
O.F. = 876 FT
«¬11 .! RUSSELL
TANK REPAIRS AND INSTALLBOWER
TANK MIXING SYSTEM
POPLAR
EDDY
HOLLY
GLADE GNOLIA
DISTRIBUTION SYSTEM IMPROVEMENTS - IMPROVEMENT #11
HOLLY STREET TANK IMPROVEMENTS PARK
CITY OF HOT SPRINGS, AR CRIST ENGINEERS, INC.
WATER SYSTEM MASTER PLAN
Source: ECsOriN, SDUigLTitIaNlGGlEoNbGeI,NGEEeRoSEye, ELIaTrTthLsEtaRrOGCeKo,gArRaKphAiNcsS,AS
0 115 230 460 690 920
CNES/Airbus DS, USDA, USGSJU, NAEe,ro2G01R8ID, IGN, and the GIS
Feet User Community
1 inch = 500 feet
CRIST ENGINEERS, INC.
JOB ESTIMATE COST SUMMARY
PROJECT: PH 1 IMPROVEMENT #11 - HOLLY STREET TANK IMPROVEMENTS
OWNER: CITY OF HOT SPRINGS WATER UTILITIES
DATE: June 8, 2018 ESTIMATE BY: Matthew D. Dunn, P.E.
JOB NO: 1560
ESTIMATED
Item No. Description Unit Total Unit Cost Total Cost
Quantity
1 Insurance, Bonds, Mob., Demobilization LS 1 $18,000
2 Tank Mixing System LS 1 $144,000
3 Interior Coating Repair LS 1 $50,000
4 Repairs & Improvements LS 1 $8,900
5 Disinfection LS 1 $14,000
6 Miscellaneous & Incidental LS 1 $5,000
Construction Cost $240,000
30% Contingency $72,000
20% Engineering, Legal, Enviromental, Admin. $48,000
TOTAL COST ESTIMATE $360,000
RED = NEAR TERM IMPROVEMENTS PIPE DIAMETERS 18 Inch
BLUE = MIDTERM IMPROVEMENTS 2 Inch 10 Inch 20 Inch
4 Inch 12 Inch 24 Inch
PURPLE = LONG TERM IMPROVEMENTS 6 Inch 14 Inch 30 Inch
8 Inch 16 Inch
TWINS GRAND
(2) 3,000,000 GALLON
GROUND STORAGE TANKS INSTALL TMS AND
O.F. = 869 FT SAFETY CLIMBING SYSTEM
FOR EACH TANK
«¬12
.! .!
WOOD
HOBSON
CAMPBELL
MASON
COOPER
GARDNER
MOUNTAIN VIEW
ALBERT PIKE
DISTRIBUTION SYSTEM IMPROVEMENTS - IMPROVEMENT #12
ERT PIKE
TWINS TANK IMPROVEMENTS
CITY OF HOT SPRINGS, AR ¬«10 CRIST ENGINEERS, INC.
WATER SYSTEM MASTER PLAN
Source: ECsOriN, SDUigLTitIaNlGGlEoNbGeI,NGEEeRoSEye, ELIaTrTthLsEtaRrOGCeKo,gArRaKphAiNcsS,AS
0 115 230 460 690 920
CNES/Airbus DS, USDA, USGSJU, NAEe,ro2G01R8ID, IGN, and the GIS
Feet User Community
1 inch = 500 feet
L
CRIST ENGINEERS, INC.
JOB ESTIMATE COST SUMMARY
PROJECT: PH 1 IMPROVEMENT #12 - TWINS TANK IMPROVEMENTS
OWNER: CITY OF HOT SPRINGS WATER UTILITIES
DATE: June 8, 2018 ESTIMATE BY: Matthew D. Dunn, P.E.
JOB NO: 1560
ESTIMATED
Item No. Description Unit Total Unit Cost Total Cost
Quantity
1 Insurance, Bonds, Mob., Demobilization LS 1 $15,000
2 Tank Mixing System (2) LS 1 $303,000
3 Interior Coating Repair (1) LS 1 $50,000
4 Repairs & Improvements LS 1 $19,440
5 Disinfection LS 1 $10,000
6 Miscellaneous & Incidental LS 1 $5,000
Construction Cost $402,000
30% Contingency $120,600
20% Engineering, Legal, Enviromental, Admin.
$80,400
TOTAL COST ESTIMATE
$600,000
PRESSURE ZONE BOUNDARY PIPE DIAMETERS 18 Inch
2 Inch 10 Inch 20 Inch
4 Inch 12 Inch 24 Inch
6 Inch 14 Inch 30 Inch
8 Inch 16 Inch
INSTALL TMS AND
SAFETY CLIMBING SYSTEM
MUSIC MOUNTAIN ¬«!. 13
3,000,000 GALLON
GROUND STORAGE TANK
O.F. = 710 FT
DR MARTIN LUTHER KING JR ALBERT PIKE
RED = NEAR TERM IMPROVEMENTS
BLUE = MIDTERM IMPROVEMENTS
PURPLE = LONG TERM IMPROVEMENTS
DISTRIBUTION SYSTEM IMPROVEMENTS - IMPROVEMENT #13
MUSIC MOUNTAIN TANK IMPROVEMENTS
CITY OF HOT SPRINGS, AR CRIST ENGINEERS, INC.
WATER SYSTEM MASTER PLAN
CONSULTING ENGINEERS LITTLE ROCK, ARKANSAS
0 115 230 460 690 920
JUNE, 2018
Feet
1 inch = 500 feet
CRIST ENGINEERS, INC.
JOB ESTIMATE COST SUMMARY
PROJECT: PH 1 IMPROVEMENT #13 - MUSIC MOUNTAIN TANK IMPROVEMENTS
OWNER: CITY OF HOT SPRINGS WATER UTILITIES
DATE: June 8, 2018 ESTIMATE BY: Matthew D. Dunn, P.E.
JOB NO: 1560
ESTIMATED
Item No. Description Unit Total Unit Cost Total Cost
Quantity
1 Insurance, Bonds, Mob., Demobilization LS 1 $13,250
2 Tank Mixing System LS 1 $144,000
3 Interior Coating Repair LS 1 $50,000
4 Repairs & Improvements LS 1 $9,720
5 Disinfection LS 1 $14,000
6 Miscellaneous & Incidental LS 1 $5,000
Construction Cost $236,000
30% Contingency $70,800
20% Engineering, Legal, Enviromental, Admin. $47,200
TOTAL COST ESTIMATE $350,000
PIPE DIAMETERS 18 Inch
2 Inch 10 Inch 20 Inch
4 Inch 12 Inch 24 Inch
6 Inch 14 Inch 30 Inch
8 Inch 16 Inch
MALVERN
PRESSURE ZONE BOUNDARY
EXISTING .! TANK REPAINTING, INSTALL TMS
INDUSTRIAL PARK AND MODIFY TANK OVERFLOW
500,000 GALLON ELEVATED «¬14 PIPING
WATER STORAGE TANK
O.F. = 537 FT
RED = NEAR TERM IMPROVEMENTS
BLUE = MIDTERM IMPROVEMENTS
PURPLE = LONG TERM IMPROVEMENTS
DISTRIBUTION SYSTEM IMPROVEMENTS - IMPROVEMENT #14
INDUSTRIAL PARK TANK IMPROVEMENTS
CITY OF HOT SPRINGS, AR Lake
LakWe ATER SYSTEM MASTER PLAN
CatherinCe RIST ENGINEERS, INC.
Cather0ine 115 230 460 690 920
Source: ECsOriN, SDUigLTitIaNlGG EloNbGeI,NGEEeRoSEye, ELIaTrTthLsEtaRrOGCeKo, gArRaKphAiNcSs,AS
Feet
CNES/Airbus DS, USDA, USGSJU, NAEe,ro2G01R8ID, IGN, and the GIS
1 inch = 500 feet User Community
CRIST ENGINEERS, INC.
JOB ESTIMATE COST SUMMARY
PROJECT: PH 1 IMPROVEMENT #14 - INDUSTRIAL PARK TANK IMPROVEMENTS
OWNER: CITY OF HOT SPRINGS WATER UTILITIES
DATE: June 8, 2018 ESTIMATE BY: Matthew D. Dunn, P.E.
JOB NO: 1560
ESTIMATED
Item No. Description Unit Total Unit Cost Total Cost
Quantity
1 Insurance, Bonds, Mob., Demobilization LS 1 $13,250
2 Tank Mixing System LS 1 $80,000
3 Interior Coating Repair LS 1 $100,000
4 Exterior Coating Repair LS 1 $200,000
5 Repairs & Improvements LS 1
6 Disinfection LS 1 $13,900
7 Miscellaneous & Incidental LS 1 $2,500
$5,000
Construction Cost $415,000
30% Contingency $124,500
20% Engineering, Legal, Enviromental, Admin.
$83,000
TOTAL COST ESTIMATE
$620,000
RIDGE ONE PIPE DIAMETERS
PARK 2 Inch 10 Inch 18 Inch
4 Inch 12 Inch 20 Inch
6 Inch 14 Inch 24 Inch
8 Inch 16 Inch 30 Inch
Country
Club
Lake
BELVEDERE
PRESSURE ZONE BOUNDARY
BELVEDERE
300,000 GALLON
GROUND STORAGE TANK
O.F. = 980 FT
INSTALL ¬«.!15
TANK MIXING SYSTEM
SLEEPY VALLEY
RED = NEAR TERM IMPROVEMENTS
BLUE = MIDTERM IMPROVEMENTS
PURPLE = LONG TERM IMPROVEMENTS
DISTRIBUTION SYSTEM IMPROVEMENTS - IMPROVEMENT #15
BELVEDERE TANK IMPROVEMENTS
CITY OF HOT SPRINGS, AR CRIST ENGINEERS, INC.
WATER SYSTEM MASTER PLAN
Source: ECsOriN, SDUigLTitIaNlGGlEoNbGeI,NGEEeRoSEye, ELIaTrTthLsEtaRrOGCeKo,gArRaKphAiNcsS,AS
0 115 230 460 690 920
CNES/Airbus DS, USDA, USGSJU, NAEe,ro2G01R8ID, IGN, and the GIS
Feet User Community
1 inch = 500 feet
CRIST ENGINEERS, INC.
JOB ESTIMATE COST SUMMARY
PROJECT: PH 1 IMPROVEMENT #15 - BELVEDERE TANK IMPROVEMENTS
OWNER: CITY OF HOT SPRINGS WATER UTILITIES
DATE: June 8, 2018 ESTIMATE BY: Matthew D. Dunn, P.E.
JOB NO: 1560
ESTIMATED
Item No. Description Unit Total Unit Cost Total Cost
Quantity
1 Insurance, Bonds, Mob., Demobilization LS 1 $15,000
2 Tank Mixing System LS 1 $45,000
3 Interior Coating Repair LS 1 $10,000
4 Repairs & Improvements LS 1
5 Disinfection LS 1 $5,000
6 Miscellaneous & Incidental Work LS 1 $3,500
$5,000
Construction Cost $84,000
30% Contingency $25,200
20% Engineering, Legal, Enviromental, Admin. $16,800
TOTAL COST ESTIMATE $130,000
PIPE DIAMETERS 18 Inch
2 Inch 10 Inch 20 Inch
4 Inch 12 Inch 24 Inch
6 Inch 14 Inch 30 Inch
8 Inch 16 Inch
SKYVIEW
WHITTINGTON
WALTER
SAINT GEORGE
WOODMERE
WOODMERE / WHITTINGTON TANK REPAIRS AND INSTALL
250,000 GALLON TANK MIXING SYSTEM
GROUND STORAGE TANK
O.F. = 869 FT
¬«.!
16
DISTRIBUTION SYSTEM IMPROVEMENTS - IMPROVEMENT #16
WOODMERE / WHITTINGTON AVENUE TANK
CITY OF HOT SPRINGS, AR CRIST ENGINEERS, INC.
WATER SYSTEM MASTER PLAN
Source: ECsOriN, SDUigLTitIaNlGGlEoNbGeI,NGEEeRoSEye, ELIaTrTthLsEtaRrOGCeKo,gArRaKphAiNcsS,AS
0 115 230 460 690 920
CNES/Airbus DS, USDA, USGSJU, NAEe,ro2G01R8ID, IGN, and the GIS
Feet User Community
1 inch = 500 feet
CRIST ENGINEERS, INC.
JOB ESTIMATE COST SUMMARY
PROJECT: PH 1 IMPROVEMENT #16 - WOODMERE / WHITTINGTON TANK IMPROVEMENTS
OWNER: CITY OF HOT SPRINGS WATER UTILITIES
DATE: June 8, 2018 ESTIMATE BY: Matthew D. Dunn, P.E.
JOB NO: 1560
ESTIMATED
Item No. Description Unit Total Unit Cost Total Cost
Quantity
1 Insurance, Bonds, Mob., Demobilization LS 1 $15,000
2 Tank Mixing System LS 1 $45,000
3 Interior Coating Repair LS 1 $50,000
4 Disinfection LS 1
5 Miscellaneous & Incidental LS 1 $3,500
$5,000
Construction Cost $119,000
30% Contingency $35,700
20% Engineering, Legal, Enviromental, Admin. $23,800
TOTAL COST ESTIMATE $180,000
PIPE DIAMETERS 18 Inch
2 Inch 10 Inch 20 Inch
4 Inch 12 Inch 24 Inch
6 Inch 14 Inch 30 Inch
8 Inch 16 Inch
GOLF LINKS MALVERN
CONNECT TO 8" «¬17
WATER LINE ON
MALVERN AVENUE
12" WATER MAIN
ALONG CARPENTER DAM
CONNECT TO 8" CARPENTER DAM CONNECT TO 24"
WATER LINE WATER TRANSMISSION LINE
ALONG BYPASS
DR MARTIN LUTHER KING JR
RED = NEAR TERM IMPROVEMENTS
BLUE = MIDTERM IMPROVEMENTS
PURPLE = LONG TERM IMPROVEMENTS
DISTRIBUTION SYSTEM IMPROVEMENTS - IMPROVEMENT #17
12" CARPENTER DAM RD LOOP
CITY OF HOT SPRINGS, AR CRIST ENGINEERS, INC.
WATER SYSTEM MASTER PLAN
CONSULTING ENGINEERS LITTLE ROCK, ARKANSAS
0 115 230 460 690 920
JUNE, 2018
Feet
1 inch = 500 feet
CRIST ENGINEERS, INC.
JOB ESTIMATE COST SUMMARY
PROJECT: PH 1 IMPROVEMENT #17 - CARPENTER DAM ROAD WATER MAIN - MALVERN AVE TO MLK BYPASS
OWNER: CITY OF HOT SPRINGS
DATE: June 8, 2018 ESTIMATE BY: Matthew D. Dunn, P.E.
JOB NO: 1560
ESTIMATED
Item No. Description Unit Total Unit Cost Total Cost
Quantity
1 12-inch DIP Water Line $50 $133,350
LF 2,667
2 24-inch Connection EA 1 $300 $18,470
3 12-inch Connection EA 1 $75 $7,400
4 8-inch Connection EA 1 $55 $6,100
5 24" Encasement, Bored Bypass Bore LF 800 $25
6 Ashpalt Resurfacing LF 500 $240,000
7 Concrete Resurfacing LF 100 $4,500 $37,500
8 Gravel Surface Repair LF 60 $5,500
EA 1 $1,500
9 Fire Hydrant Assembly
$4,500
Construction Cost Estimate $454,000
30% Contingency $136,200
20% Engineering, Legal, Environmental, Admin. $90,800
TOTAL COST ESTIMATE $681,000
EXIT 3 EB ON PIPE2DInIAchMETER10SInFcRhUITWO1O8DInch
SAN PABLO 4 Inch 12 Inch 20 Inch
MURDOCK
LAKEBSOHOLIRVAER 6 Inch 14 Inch 24 Inch
CORTEZ
8 Inch 16 InchIRONW3O0OIDnch
DR MARTIN LUTHER KING JR
BELLA ROSA
VILLAGE SAN MATEO SAN PEDRO
SANTA ANNA
SONORA
GRANADA SANTA FE
CONNECT TO 6"
ON SILVER SPUR
CONNECT TO 6" SAN JUAN OLD HICKORY PEACH BLOSSOM
ON SANTA CRUZ SILVER SPUR
¬«22 WILLOWBEND
SANTA CRUZ FOREST LAKES
6-INCH WATER LINE
LOOP
PINTO
RED = NEAR TERM IMPROVEMENTS
BLUE = MIDTERM IMPROVEMENTS
PURPLE = LONG TERM IMPROVEMENTS
S
DISTRIBUTION SYSTEM IMPROVEMENTS - IMPROVEMENT #22
T ROCKYRE
LITTLE OAK CENARK
6" SANTA CRUZ LOOP
CITY OF HOT SPRINGS, AR CRIST ENGINEERS, INC.
WATER SYSTEM MASTER PLAN
CONSULTING ENGINEERS LITTLE ROCK, ARKANSAS
0 115 230 460 690 920
Feet JUNE, 2018
1 inch = 500 feet
O F
CRIST ENGINEERS, INC.
JOB ESTIMATE COST SUMMARY
PROJECT: PH 1 IMPROVEMENT #22 - SANTA CRUZ LOOP - SANTA CRUZ TO SILVERSPUR ST
OWNER: CITY OF HOT SPRINGS
DATE: June 8, 2018 ESTIMATE BY: Matthew D. Dunn, P.E.
JOB NO: 1560
ESTIMATED
Item No. Description Unit Total Unit Cost Total Cost
Quantity
1 6-inch PVC Water Line $30 $6,450
2 6-inch Connection LF 215 $12,400
EA 2 $50
3 Asphalt Surface Repair LF 20 $8.00 $1,000
LF 120 $960
4 Route Clearing LS
5 Miscellaneous & Incidential $5,000
Construction Cost Estimate $26,000
30% Contingency $7,800
20% Engineering, Legal, Environmental, Admin. $5,200
$39,000
TOTAL COST ESTIMATE
PIPE DIAMETERS
2 Inch 10 Inch 18 Inch
DR MARTIN LUTHER KING JR 4 Inch 12 Inch EXIT22440EIInnBccOhhFF
6 Inch 14 Inch
8 Inch 16 Inch 30 Inch
BELLA ROSA VCK
SAN PEDRO
DONS
SAN MATEO SANTA ANNA SECTION LINE
PEACH BLOSSOM
UNNAMED
WILLOWBEND HICKORYCONNECT TO 8" CONNECT TO 8"
ON FOREST LAKES ON TWIN POINTS
OLD BLVD
FOREST LAKES «¬23 TWIN POINTS
PINTO HIGDON FERRY
8-INCH WATER LINE
LOOP
CONNECT TO 8"
ON TWIN POINTS
CENARK RED = NEAR TERM IMPROVEMENTS
BLUE = MIDTERM IMPROVEMENTS
PURPLE = LONG TERM IMPROVEMENTS
DISTRIBUTION SYSTEM IMPROVEMENTS - IMPROVEMENT #23
8" TWIN POINTS LOOP TEMPERANCE HILL
CITY OF HOT SPRINGS, AR CRIST ENGINEERS, INC.
WATER SYSTEM MASTER PLAN
CONSULTING ENGINEERS LITTLE ROCK, ARKANSAS
0 115 230 460 690 920
JUNE, 2018
Feet
1 inch = 500 feet
CRIST ENGINEERS, INC.
JOB ESTIMATE COST SUMMARY
PROJECT: PH 1 IMPROVEMENT #23 - TWIN POINTS LOOP - CONNECT 8-INCH LINES ON TWIN POINTS DR
OWNER: CITY OF HOT SPRINGS
DATE: June 8, 2018 ESTIMATE BY: Matthew D. Dunn, P.E.
JOB NO: 1560
ESTIMATED
Item No. Description Unit Total Unit Cost Total Cost
Quantity
1 8-inch PVC Water Line $30 $63,000
LF 2,100
2 8-inch Connection EA 3 $4,000 $12,000
3 8-inch Gate Valves EA 2 $1,500 $3,000
LF 240
4 Asphalt Surface Repair LF 320 $50 $12,000
LS $8.00 $2,560
5 Route Clearing $5,000
6 Miscellaneous & Incidential
Construction Cost Estimate $98,000
30% Contingency $29,400
$19,600
20% Engineering, Legal, Environmental, Admin.
$147,000
TOTAL COST ESTIMATE
OAKCLIFF PIPE DIAMETERS SHADY GROVE
ALCORN 2 Inch 10 Inch
4 Inch 12 Inch
WINONA 6 Inch 14 Inch
GREENW OOD 00011 8 Inch 16 Inch 18 Inch
SELMA 20 Inch
CHEROKEE00013 24 Inch
30 Inch
MILLER
CARSON
LASER VIRGINIA KAY
INDIANA
KENTUCKY
NEVADA
CENTRAL SAINT LOUIS TROUPE
TRIVISTA TRIVISTA LEFT CONNECT TO 6"
99008 ON TRIVISTA RIGHT
FAIR
TRIVISTA RIGHT
6-INCH WATER LINE
L0O10O0P2 ON FAIR ST.
LANGSTON
TALISMAN «¬24
LEVIN
CONNECT TO 6"
ON LANGSTON ST.
HOLLYWOOD
HALFMILE
IDA
TUGGLE
HIGHLAND
RED = NEAR TERM IMPROVEMENTS
BLUE = MIDTERM IMPROVEMENTS
PURPLE = LONG TERM IMPROVEMENTS
SELLERS
EWING
DELAWARE
CLAIRMONT
DISTRIBUTION SYSTEM IMPROVEMENTS - IMPROVEMENT #24
6" FAIR STREET LOOP
CITY OF HOT SPRINGS, AR CRIST ENGINEERS, INC.
WATER SYSTEM MASTER PLAN
CONSULTING ENGINEERS FAILRITMTOLENRTOCK, ARKANSAS
0 115 230 460 690 920
JUNE, 2018
Feet
1 inch = 500 feet
CRIST ENGINEERS, INC.
JOB ESTIMATE COST SUMMARY
PROJECT: PH 1 IMPROVEMENT #24 - FAIR STREET LOOP - TRIVISTA RIGHT TO LANGSTON
OWNER: CITY OF HOT SPRINGS
DATE: June 8, 2018 ESTIMATE BY: Matthew D. Dunn, P.E.
JOB NO: 1560
Item No. Description Unit Total ESTIMATED
Quantity
1 6-inch PVC Water Line Unit Cost Total Cost
2 6-inch Connection LF 355
3 Ashpalt Resurfacing EA 2 $30 $10,650
4 Miscellaneous & Incidental LF 355 $12,400
LS
$75 $26,625
$5,000
Construction Cost Estimate $55,000
30% Contingency $16,500
$11,000
20% Engineering, Legal, Environmental, Admin. $83,000
TOTAL COST ESTIMATE