Provision of Engineering, Procurement, Construction, Installation & Commissioning (EPCIC) for
Kasawari Gas Development Project.
KASAWARI GAS DEVELOPMENT PROJECT
E&I Tender Briefing for CPP & Jacket
DVEeatnleeuectrical and Instrumentation: 5 Aug 2020 Wednesday
: Auditorium Room, MMHE West Yard
Overview
Workshop and Fabrication Layout 2
Erection Area for Blasting &
CPP Topside(Fab Painting
No.4) Workshop
Fabrication Workshop 30
MRF 3 New Warehouse &
Cold Room
MRF 1
Bill of Quantity for CPP Topside 3
No Description Electrical Instrument/Telecom Total
155.5MT
1 Steel Works 7960 mtr 138.5MT 294MT
Fabrication and 81 nos 10664 mtr 18624 mtr
Installation
NA 52 nos 133 nos
2 Cable Ladder 1501 nos 7000 mtr 7000 mtr
Installation 2843 nos 4344 nos
193426 mtr
3 Panel Installation 229135 mtr 422561 mtr
6373 nos
4 Tubing Installation 6864 nos 13237 nos
and Leak Test
5 Junction Box and
Equipment
Installation
6 Multicore Cable
Installation
7 Multicore Cable
Connection (glanding
+ termination)
Room Priority 4
Switchgear Transformer Battery Room Instrument
Room Room (01Aug2021) Equipment Room
(15July2021) (27July2021) (07Aug2021)
Technical Building Location 5
Looking West
LQ Looking East
UD
UD
IER
Transformer Room EDG IER
MD Workshop
CD
SWG & MCC
MD
CD
Technical Building Location 6
TD Looking South
UD GTG
EDG IER
Mechanical, Electrical and Instrument Workshop
MD
Technical Building Location 7
Looking South
UD SWG and MCC Room
Lab and Battery Room
Transformer Room
MD
CD
Panel Installation Switchgear Room 3
Local Equipment Room
Door Fire wateDr poioper Maximum allowable Depth of
Frame iSnhsatlallblaetFihoronaldme panel is 1100mm
Shall Be
HOLD shall be - Scaffolding erection
required at same level
HOLD of rest floor of
Switchgear Room and
Battery Room to erect from lay down
area to Switch gear
Panel installation inside Battery & Room
Equipment Room will utilize - Will utilize lay down
area
Mezzanine Deck lay down area
9
Door Frame
Shall Be HOLD
Scaffolding
Shall Be erect
8
Description Installation Plan Date PO Status ETA Others Discipline
Sequence 1 15/07/21 to 25/07/21 Issued 05/03/2021 to 28/05/2021 Readiness:
Sequence 2 26/07/21 to 30/07/21 Issued 28/01/2021 to 19/03/2021 -Architectural Wall to
Sequence 3 31/07/21 to 11/08/21 Issued 11/12/2021 to 05/03/2021 Completely Installed
Sequence 4 12/08/21 to 18/08/21 Issued -Temporary HVAC shall be
Sequence 5 19/08/21 to 24/08/21 Issued 31/05/2020 ready
Sequence 6 25/08/21 to 30/08/21 Issued 26/02/2021 -Temporary scaffolding
Sequence 7 31/08/21 to 16/09/21 Issued 30/04/2021 platform shall be ready
Sequence 8 16/08/21 to 20/09/21 Issued 19/03/2021
19/03/2021
10
Sequence No Panel Description
Sequence 1
Sequence 2 - 400V low Voltage Swicthboard /MCC- MCC-7700
Sequence 3 - HVAC Control Panel – HCP-5001
Sequence 4
Sequence 5 - 400/230V Essential Motor & Cubicle Space Heater Distribution Board – DB-7760
- ENMCS/IMCS Panel – ENMCS-7710
Sequence 6 - Emergency Generator Control Panel – GCP-7700
Sequence 7
- 400V low Voltage Swicthboard /MCC- MCC-7710
Sequence 8 - Soft Starter Panel For G-7510,G-7520 , G-7530 Starter Motor – SP-7510 , SP-7520 , SP-7530
- Soft Starter Panel For KM-5410A,B,C Motor – SP-5410A , SP-5410B, SP-5410C
- 400/230V AC UPS Unit – UPS-7800A & UPS-7800B
- Bypass Transformer – UPS-7800C
- 400/230V AC Unit Power Distribution Board – DB-7800, DB7805, DB7806
- GTG Marshalling Panel – GB-7500
- GTG Generator Panel – GCP-7510, GCP-7520, GCP-7530
- GTG Unit Control Panel – UCP-7510, UCP-7520, UCP-7530
- Regeneration Gas Compressor Seal Gas Heater Panel – HCP-2211
- 6.6kV High Voltage Switchgear – SG-7500
- 400/230V AC Distribution Board – DB-7710, DB-7720, DB-7730, DB-7740, DB-7740,DB-7741
- Emergency Generator 24V DC Battery Charger – DU-7700A , DU-7700B
- 24VDC Charger/ DC Motor Starter – DU-7820,DU-7821,DU-7822
- 24VDC Battery Charger – DU-7840, DU7841, DU-7842
- Hp Compressor Heater Control Panel – HCP-K1-2411,HCP-K2-2411, HCP-K3-2411
- Fuel Gas Superheater Control Panel – HCP-6002A, HCP-6002B
- Fuel gas Pre-Heater Control Panel – HCP-6001
- ENMCS Portable Engineering Workstation
Panel Installation Inside Transformer Room 5
Switchgear Room
Laydown Coaming Transformer Area
shall be HOLD
- Sliding Door c/w Frame and wall
transformer room shall be HOLD
PRaonoeml iwnsiltlaulltaitliizoenTirnasniEdsDfeoGSrmwCoietarcmhlaginyegaSrhall be HOLD
down area
6
21
4 3
From Laydown Area - Slidding Door c/w Frame and
wall transformer room shall be
HOLD
- EDG Coaming shall be Hold
Description Installation Plan Date PO Status ETA Others Discipline
Sequence 1 23/07/2021 -24/07/2021 Issued 01/07/2021 Readiness:
Sequence 2 24/07/2021 -25/07/2021 Issued 01/07/2021 -Architectural Wall to
Sequence 3 25/07/2021 -26/07/2021 Issued 01/07/2021 Completely Installed
Sequence 4 26/07/2021 - 27/07/2021 Issued 01/07/2021 -Temporary HVAC shall be
ready
-Temporary scaffolding shall
be ready
Panel Installation Inside Battery Room 9
EquInipsmtreunmteRnotomFDraomore
Shall Be
Hold
Handrail and IER - Scaffold-inScgaeffroelcdtiinognprelaqtufoirremd at
Platform same leveerleocftrioenstrfeloqourired at
Staircase Shall - Will utilsizaemleayledvoewl onfadreecakLD-1
be HOLD
floor of Battery Room
14
12 3
4
5
- Door Frame and handrails
shall be HOLD
- Scaffolding platform erection
required at same level of deck
floor of Battery Room
Description Installation Plan Date PO Status ETA Others Discipline
Sequence 1 01/08/2021 -07/08/2021 PO on 23/10/2020 23/04/2021 Readiness:
Sequence 2 08/08/2021 -14/08/2021 PO on 23/10/2020 23/04/2021 -Architectural Wall to
Sequence 3 15/08/2021 -21/08/2021 PO on 23/10/2020 23/04/2021 Completely Installed
Sequence 4 22/08/2021 -28/08/2021 PO on 23/10/2020 23/04/2021 -Temporary HVAC/Blower
Sequence 5 29/08/2021 -30/08/2021 PO on 23/10/2020 23/04/2021 shall be ready
-Temporary scaffolding shall
be ready
15
Sequence No Panel Description
Sequence 1 - 24VDC Battery Bank – BT-7823, BT-7824, BT-7825
Sequence 2 - 24VDC Battery Bank – BT-7820, BT-7821, BT-7822
Sequence 3 - 400/230V AC UPS Battery Bank B – BT-7800B
Sequence 4 - 400/230V AC UPS Battery Bank A – BT-7800A
Sequence 5 - 24VDC Battery Bank For Nav Aid – BT-8900
16
Panel Installation Inside Instrument Equipment Room
Electrical Room
- Panel to be lift direct by - Heavy duty scaffolding to
Crane and landing on heavy be Erect same level of rest
duty scaffolding floor IER
- Partial Door Frame and
Wall shall be HOLD
17
FOR FUTURE 1
FOR FUTURE 2
3
4 6
5
7
- Panel to be lift direct by Crane and landing - Heavy duty scaffolding to be Erect same level
on heavy duty scaffolding of rest floor IER
- Partial Door Frame and Wall shall be HOLD
Description Installation Plan Date PO Status ETA Others Discipline
22/05/2021 to 09/07/2021 Readiness:
Sequence 1 07/08/21 to 14/08/21 Issued -Architectural Wall to
25/07/2021 Completely Installed
Sequence 2 13/08/21 to 20/08/21 Issued 01/06/2021 -Temporary HVAC shall be
01/06/2021 ready
Sequence 3 21/08/21 to 28/08/21 Issued 01/06/2021 -Temporary scaffolding
01/06/2021 to 01/10/2021 platform shall be ready
Sequence 4 29/08/21 to 06/09/21 Issued
Sequence 5 07/09/21 to 14/09/21 Issued
Sequence 6 15/09/21 to 22/09/21 Issued
Sequence 7 23/09/21 to 30/09/21 Issued 19/03/2021
18
Sequence No Panel Description
Sequence 1
- Hp Compressor UCP – UCP-K1-2401, UCP-K2-2401 , UCP-K3-2401
Sequence 2 - LAN & MISC Cabinet – TC-9261
Sequence 3 - CCTV System Cabinet – TC-9262
Sequence 4 - PAGA “B” System Cabinet – TC-9011
Sequence 5 - PAGA “B” MDF Cabinet – TC-9012
Sequence 6
- ARGU – Regen. Gas Compressor K-2211A UCP – UCP-2211A
Sequence 7 - ARGU – Regen. Gas Compressor K-2211B UCP – UCP-2211B
- Fire & Gas Marshalling Cabinet – MDF-8001 , MDF-8002, MDF-8003, MDF-8004, MDF-8005, MDF-8006
- Fire & Gas System Cabinet – FGDC-8001, FGDC-8002, FGDC-8003, FGDC-8004
- SIS Marshalling Cabinet – MDF-4501, MDF-4502, MDF-4503, MDF-4504
- SIS System Cabinet – SSC-4501, SSC-4502, SSC-4503
- DCS Marshalling Cabinet – MDF-4601, MDF-4602, MDF-4603, MDF-4604, MDF-4605, MDF-4607
- DCS System Cabinet – DCS-4601-, DCS-4602, DCS-4603
- DCS Network Cabinet – DCS-4611
- Gas Allocation Metering Cabinet – FMC-2610, FMC-2611
- Condensate Allocation Metering Cabinet – FMC-3210
- Instrument and Telecom Distribution Board – DB-7804, DB-7811, DB-7807
19
Cable Ladder Installation Under IER and Switchgear Room
1 Others Discipline
Readiness:
2 -Underside Painting shall be
3 ready
- Temporary scaffolding
4 platform shall be ready
Installation Cable Ladder
Sequence 1 : 14/02/2021
Sequence 2 : 12/03/2021
Sequence 3 : 10/04/2021
Sequence 4 : 08/05/2021
20
Cable Ladder Installation Below Main Deck Row A & B
65
Installation Cable Ladder
Sequence 5 : 15/05/2021
Sequence 6 : 22/05/2021
21
Cable Ladder Installation Below Main Deck Row A & B
65
Installation Cable Ladder
Sequence 5 : 15/05/2021
Sequence 6 : 22/05/2021
Bill of Quantity for Living Quarters 22
No Description Electrical Instrument/Telecom Total
25MT 31MT 56MT
1 Steel Works
Fabrication and 525 MTR 850 TR 1375 MTR
Installation 23 nos 16 nos 39 nos
2 Cable Ladder 1736 nos 1004 nos 2740 nos
Installation
64610 mtr 50247 mtr 114857 mtr
3 Panel Installation 8736 nos 5756 nos 14492 nos
4 Tubing Installation
and Leak Test
5 Junction Box and
Equipment
Installation
6 Multicore Cable
Installation
7 Multicore Cable
Connection (glanding
+ termination)
LQ Rooms Location 23
Roof Looking South
L4
L3 TER Switch Room
L2 CCR
L1
MD
Panel Installation LQ – Electrical Switch Room
5 4
2
31
No Description Installation Plan Date Po Status ETA
1 Sequence 1 15-July-21 to 12-Aug-21 15-May-2020 10-May-2021
2 Sequence 2 15-July-21 to 12-Aug-21 31-July-2021
3 Sequence 3 23-July-21 to 1-Sep-21 31-July-2021
4 Sequence 4 15-July-21 to 24-Aug-21 31-July-2021
5 Sequence 5 15-July-21 to 24-Aug-21
Panel Installation LQ – Telecom Equipment Room
1
3
2 No Description Installation Plan Date Po Status ETA
1 Sequence 1 18-Aug-21 to 13-Sep-21 26-June-2021
2 Sequence 2 15-July-21 to 12-Aug-21 26-June-2021
3 Sequence 3 15-July-21 to 24-Aug-21 31-July-2021
Panel Installation LQ – Layout for Panel Installation Level 3
Panel Installation LQ – CCR
57
2
4 6
31
No Description Installation Plan Date Po Status ETA
1 Sequence 1 16-Aug-21 to 22-Sep-21
2 Sequence 2 16-Aug-21 to 22-Sep-21 31-July-2021
3 Sequence 3 16-Aug-21 to 22-Sep-21 26-June-2021
4 Sequence 4 16-Aug-21 to 22-Sep-21 26-June-2021
5 Sequence 5 2-Sep-21 to 14-Oct-21
6 Sequence 6 16-Aug-21 to 22-Sep-21
7 Sequence 7 16-Aug-21 to 22-Sep-21
Panel Installation LQ – Layout for Panel Installation Level 2