STATE GOVERNMENT OF SABAH
JABATAN AIR NEGERI SABAH
Projek:
PENAMBAHAN KAPASITILOJI RAWATAN AIR
TELIBONG 2 TAMPARULI DARI 80 JLH KE 160 JLH
TERMASUK SALURAN PAIP UTAMA DAN TANGKI SIMPANAN
Contract No.:
JANS/HQ:2/2019(S)
Laporan Prestasi Kemajuan Setakat 24hb November 2021
Disediakanby:
PERUNDING TEKNIK GLOKAL SDN. BHD.
A) Projek : Penambahan Kapasiti Loji Rawatan Air Telibong II M) Skop kerja
B) Contract No. Tamparuli dari 80 JLH ke 160 JLH Termasuk
Saluran Paip Utama dan Tangki Simpanan
: JANS/HQ:2/2019(S)
C) Pelanggan/S.O. : Jabatan Air Negeri Sabah (JANS)/Pengarah
D) Wakil S.O : Timbalan Pengarah (Pembangunan)
E) Perunding : Perunding Teknik Glokal Sdn. Bhd. (PTG)
F) Kontraktor in association with SMHB Sdn. Bhd. (SMHB)
: Rintis Dinamik Sdn. Bhd. (RDSB)
G) Nilai Kontrak : RM 395,983,081.67
H) Tarikh Asal mula : 18hb March 2019
I) Tarikh Asal Siap : 18hb March 2021 (24 Bulan)
J) Tarikh Siap PK&LM (EOT) No. 1 : 10.07.2021
K) Tarikh Siap PK&LM (EOT) No. 2
: 17.03.2022
L) Plan layout keseluruhan projek
PIPELINE (MSCL)
Paip Pengepaman
INTAKE -WTP =0.90km
WTP- Balancing =1.45km
Labuaya Booster-Reservoir =0.66km
Nountun 1-Nountun2 =1.43
Paip Transmisi
Balancing -Nountun
= 25.6km
Paip Agihan
R16 -Tamparuli =3.69km
Gayang- Serusup =16.6km
Reservoirs falling main =14.71km
Jumlah keseluruhan : 65.04km
J) Prestasi Kemajuan : setakat 24hb November 2021
Item Penerangan (FIZIKAL) Jadual Sebenar Varians (+/-) L) ISU /MASALAH :
1
EOT No.2 (R2) 93.13 % 53.23 % - 39.90 % 1. Laluan paip Gayang ke Serusup
a. Bayaran pengambilan tanah (Land Acquisition) masih
(Based on consultant assessment up to EOT No. 2 - dalam proses tindakan JTU/PPHT – kerja tertangguh
Workable Area ) 1.5km
b. Isu teknikal bahan saluran pipe dasar laut (submarine
K) Ringkasan Kemajuan (Mengikut Skop ): Setakat 24hb November 2021 pipeline) yg terhad– 1KM (Sg. Mengkabung & Sg.
Tuaran.).
Item Penerangan Jadual Sebenar Varians JANGKAAN SIAP
(+/-) 2. Perubahan reka bentuk dan penjajaran semula laluan pipe
83.26% 40.00% (Pan Borneo WP07 & WP08 dan Simpang Jalan Tuaran Bypass
Intake & WTP 76.44% 28.33% -43.26% November 2022 ke Nountun)- Suspended
1 Intake Plant -48.11% November 2022
2 Water Treatment Plant 86.82% 52.67% 3. Menunggu kelulusan Wayleave JKR (KK) untuk kerja paip dari
Reservoirs 96.21% 87.98% -34.15% March 2022 Nountun 1 ke Nountun 2 dan ADC di sepanjang Jalan Bantayan
3 Balancing Res. (2x5MLD) 91.84% 59.64% -8.22% March 2022 - Minintod.
4 Telipok Res. (2x5MLD) 89.91% 64.81% -32.20% November 2022
5 Menggatal Res. (2x7.5MLD) 39.69% 6.00% -25.10% May 2022 4. Kelewatan permit kebenaran oleh pihak berkuasa (Polis)
6 Inanam Laut Res. (2x5MLD) -33.69% November 2022 untuk kerja-kerja khas ( blasting) disebabkan kekangan Post
7 Nountun-1 Res. (2x5MLD) - MCO compliance dan kekurangan pegawai bertugas
79.99% 47.30% -32.69% March 2022 (frontliner)
Suspended and has been lifted 96.25% 89.72% -6.53% May 2022
on 4th August 2021 87.21% 59.90% -27.31% June 2022 5. Kelewatan procurement, FAT, shipment, and delivery due to
8 Nountun-2 Res. (2MLD) March 2022 post MCO compliance and policy untuk peralatan M&E.
9 Labuaya Res. (2MLD) 94.56% 71.31% -23.25% March 2022
10 K3 Res. (2x5MLD) 6. Tapak ditutup atas Warrant KKM disebabkan terdapat
Pipelines Work has been suspended August 2022 pekerja binaan yang dijangkiti Covid-19– Tapak Muka Sauk
11 WTP to Balancing Res. (900m) July 2022 (intake), Logi (WTP), Tapak Tangki Telipok dan Inanam .
12 Balancing Res. to Nountun 85.06% 85.53% +0.47%
12* Balancing Res. Falling Main March 2022
(750m) Work has been suspended
13 R&F Telipok Res.
14 R&F Menggatal Res. Work has been suspended
15 R&F Inanam Laut Res.
16 Pipework for Nountun-1 Work has been suspended
17 Nountun-2 to Jln.Ban.Monitod
18 R16 to Tamparuli (3.6KM) Work has been suspended
19 Gayang to Serusop (16.6KM)
20 R&F Labuaya Res. (1.2KM) Work has been suspended
91.99% 59.77% -32.22%
96.03% 71.20% -24.83%
98.69% 98.21% -0.48%
FOTO-FOTO KEMAJUAN FIZIKAL KOMPONEN PROJEK (25 -12-2021)
i) MUKA SAUK (INTAKE)
Pemasangan Besi- Struktur Muka Sauk Bangunan SESB Aerial View – Muka Sauk (Intake)
(3rd lift wall panel at Raw Water Intake) (Finishing Completed)
ii) LOGI (WTP)
Staff Quarters- Painting and Internal finishing Aerial View of Flocculation Tank, Clarifier and Filter Aerial View of Chemical Building, Chlorine Building and Clear Water Tank
III) KERJA PAIP
Paip WTP-Balancing Paip Gayang-Serusup Paip R16- Tamparuli
(1000mm dia) (400mm dia) (300mm dia)
IV) PEMBINAAN TANKI SIMPANAN
Nountun 1 Inanam R8a Manggatal K3 (UA)
Labuaya Labuaya (Booter pump) Balancing Telipok