CENTRE STUDIES OF QUANTITY SURVEYING
FACULTY OF ARCHITECTURE, PLANNING AND SURVEYING
UNIVERSITI TEKNOLOGI MARA (UiTM)
MAIN CAMPUS SH AH ALAM
BQS 556
CONSTRUCTION ECONOMICS II
TITLE
PRELIMINARY ESTIMATE
PREPARED BY:
FATIN NAJIHAH BINTI ROSLANI 2020959963
MUHAMMAD HARIS BIN AHMAT SHARIFUDIN 2020959609
MOHAMAD ZAIRUL AMANI BIN MD ZUKRI 20209634836
NURIN NADHIRA BINTI ISWARI 2021190887
NUR YASMIN HAZWANI BINTI SA'AT 2020199191
NURHAFIZAH BINTI ABD KARI 2020975187
GROUP:
AP2244E
PREPARED FOR:
PROFESOR MADYA SR. HASMAWATI HARUN
TABLE CONTENT
1.0 Introduction. 1
2.0 Background information of the project. 2
3.0 Method for preparing the preliminary estimate for the proposed 5
project.
4.0 Types and sources of cost data for the proposed project. 5
4.1 Types of Cost Data. 5
4.2 Sources of Cost Data. 6
5.0 How cost data is used and reasons for the adjustments or 7
amendments.
5.1 How cost data is used. 7
5.2 Reasons for the adjustments or amendments. 8
6.0 Preliminary estimate for the construction cost of the proposed 10
project.
6.1 Superficial/floor area method. 10
6.2 Calculation for Floor Area Method. 11
6.3 Indices – cost index. 12
6.4 Calculation for Adjustment using Cost Indices/ Cost Index. 13
6.5 Construction Cost of the Proposed Building. 13
7.0 Comment on the limitation/difficulties in the collection, adjustments 14
and application of the cost data.
8.0 Conclusion. 14
9.0 References 16
1.0 INTRODUCTION
In general, preliminary estimate is the first indication of the cost of a proposed project
and is often the amount most remembered by the client. When it comes to the preliminary
estimate, it should not be too low as this may require some explanation as the design
develops, should the cost increase nor should it be too high as this may prohibit the design
proceeding further due to client’s lack of funds. It is very important to know the cost that is
going to be used for the project whenever any construction project is proposed by the client.
This is to ensure that no additional money will be required and still within the allocated
budget. This will include the expenses of site preparation, labour materials, machineries and
plants, professional fees, taxes and other charges including the expected maintenance costs
and operating costs for the new structure that is going to be built.
Therefore, our firm GLOBE SURVEYOR SDN.BHD provide a basic service to
prepare a preliminary estimate for the proposed project. Our company has been appointed
as a QS consultant for a new construction project which is residential house that is expected
to commence in June 2022. The title for our project is “CADANGAN PEMBANGUNAN
PERUMAHAN DI SEBAHAGIAN LOT 11185 (PT 7220) DAN LOT 8310 YANG
MENGANDUNGI 122 UNIT RUMAH TERES 1 TINGKAT (TYPE A) DI ATAS PT 1413 – PT
1534, DI BANDAR SPRINGHILL, PEKAN JEMIMA, DAERAH PORT DICKSON, NEGERI
SEMBILAN DARUL KHUSUS UNTUK TETUAN ECO PRIMA SDN. BHD”.
Along the way, we will use some types of method that involve in estimating the
preliminary budget of the construction project. This paper also includes the types of cost
data that should be identified according to the following breakdown which is building works,
external/infrastructure works and preliminaries. The estimate will be calculated in
accordance with the current industry’s best practices. Olatunji and Sher (2010) as cited in
Ismail (2018) stated that updated information in any construction projects greatly facilitates
the estimators to produce more reliable project costs.
1
2.0 BACKGROUND INFORMATION OF THE PROJECT
Project: Main Building Works Block E5 (Type A) for Cadangan Pembangunan Perumahan
di Sebahagian Lot 11185 (PT 7220) dan Lot 8310 yang Mengandungi 122 Unit Rumah Teres
1 Tingkat (Type A) di atas PT 1413 – PT 1534, di Bandar Springhill, Pekan Jemima, Daerah
Port Dickson, Negeri Sembilan Darul Khusus”.
1. Client Eco Prima Sdn. Bhd.
2. Location
The site of the work is located at Bandar Springghill, Lot 11185 (PT
3. Scope of 7220) and Lot 8310, Pekan Jemima, Mukin Jimah, Daerah Port
Works: Dickson.
4. Type of Main building works including internal M&E, TNB sub-station and guard
Contract: house.
PAM Form of Contract 2006 (with Quantities).
5. Brief Design
Front Elevation
Section A-A
2
6. Specifications: Section B-B
i. Roof
Concrete roofing tiles to be selected from “LAMA”. All fittings and
installation to supplier installation guide.
ii. Roof Trusses
Tenderers to quote using G. I. trusses and subject to engineer
approval (Contractor to submit shop drawing and to provide
warranty for five (5) years).
iii. Wall & Wall Finishes
Cement sand brick wall finished with cement plastering.
Bathrooms & Kitchen: Wall tiles (150 x 150) 1524mm high.
Plastering Works: Cement plaster and beam and soffit slab to be
skim coat.
iv. Ceiling
Compressed cement sheet ceiling.
v. Door Frames
Metal frames from “ECONFRAME” 150 width or equivalent. Metal
frames c/w 3 nos. stainless steel hinges. Construction Method as
per manufacturer instruction.
vi. Ironmongeries
a) ‘YALE’ Cylindrical locksets for all doors (or equivalent).
b) Indicator bolts for P. V. C. doors.
3
vii. Floor Finishes
Car porch & Apron: Cement rendered
Driveway: Concrete slab with groove lines.
Living, Dining & Bedrooms: Cement rendered.
Kitchen & Bathrooms: Floor tiles (300 x 300) from ‘White Horse’ or
equivalent (Contractor to request supplier to submit presentation
board). Skirting to be provided.
viii. Sanitary Fittings
Sanitary fittings to be from ‘INNO’ white color.
Sitting W. C – INNO – WC 1003 & PVC Link set cistern (Dual
Flush).
Basin – Eco lux Square Basin INNO – WB 2001.
Single bowl aluminum kitchen sink.
ix. Painting
Painting to be from ‘JOTUN’ or equivalent.
External Wall - Whether resistant exterior wall paint.
Internal Wall - Emulsion paint.
Timber & Metal Surface - Gloss Paint.
All paint works are to follow manufacturer’s specification and
working.
Instructions (2 coats and 1 layer undercoat).
x. Fencing
1524mm high cement sand brick wall.
4
3.0 METHOD FOR PREPARING THE PRELIMINARY ESTIMATE FOR THE PROPOSED
PROJECT
In this case, the most suitable for method that we use for preparing the preliminary
estimate for the proposed project is gross floor area. Generally, the gross floor area is the
sum of the floor areas of the spaces within the building. This includes most parts of the
building such as all the finished areas including supporting areas. The reason why we use
gross floor area is because the preliminary estimate will give insight into the cost of the
project before detailed plans are drawn up. It is easy to us provide the cost that can present
with confidence to our client, using calculations determined on the latest software. However,
this method excludes any area for common vertical circulation, such as lifts, stairs, pipe
trenches and storage etc. The method starts from using the provided CAD files of the
building design to validate that they were accurate, offer updates on changes that had been
made, and utilize this to precisely measure the Gross Floor Area. In relation to cost
estimating practiced by the Quantity Surveyors, the traditional process by Peurifoy and
Oberlender (2002) as cited in Ismail (2018) involves kick-off meeting, work plan
establishment, estimates preparation, estimates documentation, reviews and adjustments,
project execution, and feedbacks upon completed projects. Once all the all the information
gathered, simply multiply the plot ratio by the size of the land. This will help our company
examine the feasibility of the project in terms of finances and other important factors, such
as opportunity costs.
4.0 TYPES AND SOURCES OF COST DATA FOR THE PROPOSED PROJECT
4.1 Types of Cost Data
Cost indices was using as our type of cost data. It is a method of breaking down cost data
in past year constructed and completed projects, therefore data has to be updated to reflect
the current price or price in the years to come for the estimated price (Haji Ahmad, 2011).
Basically, changes to the building cost is greatly influenced by the cost labour and materials
used in the construction of the building and it has to be taken into consideration especially
in the preparation of the Cost Planning. The index numbers are used to measure the
changes in the price of the tender received at different times. Almost all of the cost data
used by the Quantity Surveyor are historical data and these data are used to prepare cost
plans or estimates and this information has to be adjusted using indices. These index
numbers are used to update the information of historical cost to the current value or to
forecast price trend and future cost incurred. The common uses of indices are for cost
5
planning, prediction whether the market condition and price are stable, as adjustment to
price fluctuation and others. By using this method, it already compromised all the elements
in a building such as building works, external/infrastructure works, and preliminaries.
4.2 Sources of Cost Data
The first sources of data that we obtained are through Bill of Quantities from our
project. A bill of quantities (BOQ) is a document used in tendering in the construction industry
in which materials, parts, and labour (and their costs) are itemised (Bill of Quantities BOQ,
n.d.). Data are obtained through elemental format analysis, basic price list of materials if
available also overall costs for use with a single price estimating method. Example unit, m2,
m3. By using BQ as our sources of data, it already compromised all the elements in a
building such as building works, external/infrastructure works, and preliminaries.
The second source of data that we obtained is through Information Services such as
Arcadis. Arcadis is the world's leading company delivering sustainable design, engineering,
and consultancy solutions for natural and built assets. So, Arcadis provides a broad and
extensive construction cost database as a result of our diverse project expertise, allowing
us to handle the simplest to the most complicated projects entrusted to us by clients who
recognized our value and dynamism (About Us Arcadis, n.d.). Through Arcadis, we obtained
information such as construction cost data and it helps in finding the new price/rate for the
current project.
Last but not least, the sources of data that we obtained are through Government
Publication from the Department of Statistics Malaysia (DOSM). In the Department of
Statistic Malaysia, we obtained the building material cost index by category of building and
region. That is referred to Special Release 1 (Civil Engineering Work) and Special Release
2 (for Building and Structural Works) for Peninsular Malaysia. These Special Releases are
published monthly and can be obtained directly or by subscribing (Haji Ahmad, 2011).
6
5.0 HOW COST DATA IS USED AND REASONS FOR THE ADJUSTMENTS OR
AMENDMENTS
5.1 How Cost Data Is Used.
1. Cost Index is used in this project to obtain the cost data. The index numbers are used to
track the price variations of tenders received at various times. The quantity surveyor
must monitor these indices, as well as prospective cost fluctuation patterns, and evaluate
variances based on location in order to make price adjustments to past cost data.
2. To make the cost plan work properly, the data must be updated using indices. So, using
the formulas that are generally used, the overall cost of the project, the rate of elements,
and so on could be updated. Example of the formula:
New price/rate (current) = Base price X Current index
Base index
3. From the above formula, the percentage of price change can be calculated through
this formula:
% Change = Current index - Base index X 100%
Base index
4. The data that we obtain at the Base price is through Arcadis (2020).
5. The data that we obtain at the Current index is through the Department of Statistic
Malaysia.
6. The data that we obtain at the Base index is through the Department of Statistic
Malaysia.
7
5.2 Reasons for the adjustments or amendments.
As explained above, Cost Index is used in this project to obtain the cost data and the
Quantity Surveyor must monitor everything included in order to make price adjustments to
past cost data. Therefore, the following are some of the reasons behind the project's
adjustment:
1. Location of Project/Construction
One of the multiplying factors used to alter the building cost to account for changes
in location is the location factor. Because this project will be developed in Negeri Sembilan
which is under region C, the most recent index for that region is 108.40. Furthermore, when
a construction project's site is far from accessible resources, the project's cost rises.
Transportation costs for workers, equipment, supplies, tools, and other items rise with
distance, adding to the project's cost (The Constructor, 2021).
2. Fluctuations
A construction project might last for years before it is finished. The cost of materials,
tools, labour, and equipment may fluctuate from time to time during the construction process.
During the cost estimating process, these price variations should be taken into
account. Moreover, for contracts containing fluctuation terms (i.e. contracts that give
allocations for increases in the cost of the contractor's resources such as materials, labour
costs, plant, and overheads), the index is used to determine the rise in the construction cost
(Khairani Haji Ahmad, 2011).
3. Labour costs
Wages for labour vary by location. As a result, the local pay rate should be properly
considered. If the project must begin after many months of cost estimation, the likely
fluctuation in labour rates must be factored into the estimate. It's possible that adjustments
will be required to account for both labour availability and the actual amount received and
depending on the task that is being done, operative output will likewise vary.
4. Market conditions
The construction sector is one of the industries that generates a lot of income for the
country, but the economy has been in decline from the beginning of Covid-19, including
rising market prices. As a result, adjustments must be made depending on current market
conditions and the country's and world's present situations (Hastings Chivetta, 2021). In
8
addition, the local supply of contracts and the demand for work by available contractors
determine the market's competitive status and the effect of the tendering market may also
have an impact on the pricing utilized.
5. Profit and overhead
Profit and overhead are computed as a percentage of the overall cost of a work and
covers a contractor’s time and expenditures. Each contractor's percent margin is different.
On modest work projects, up to 25% can be included in some situations. Apart from that,
some construction companies accept as little as 3% in order to keep costs down to a bare
minimum. This will be taken into account by an estimator in his rough estimate for every
project.
6. Material costs
Material costs, transportation costs, and any relevant taxes are all included in
construction material costs. As a result, while determining construction material costs, all of
these variables must be taken into account. This is also impacted by the state of the
economy and the government's policies. For example, the government may raise import
taxes to encourage the use of local materials in the construction sector so that it may
continue to function during a crisis.
9
6.0 PRELIMINARY ESTIMATE FOR THE CONSTRUCTION COST OF THE PROPOSED
PROJECT
6.1 Superficial/Floor Area Method
Figure 1: First Floor Plan of Proposed Project
10
Figure 2: Construction Building Cost/M2, Arcadis 2020
6.2 Calculation for Floor Area Method
Floor Area Length Width Total (M2)
(M) (M) (L x W)
Area A 12.02 2.93 35.22
(1st Floor)
10.43 2.93 30.56
Area B 16.73 0.31 5.19
(1st Floor) 2.98 2.93 8.73
Apron
Porch
GFA (M2) 79.70 Cost/M2 Cost/M2
(Similar (GFA x
79.70 Building) Cost/M2)
RM 1,440.00 RM 114,768.00
Table 1: Calculation for Floor Area Method
11
6.3 Indices – Cost Index
Figure 3: Cost index for original index, DOSM
Figure 4: Cost index for current index, DOSM
12
6.4 Calculation for Adjustment using Cost Indices/ Cost Index
Formulas:
i. New Price/Rate (Current) = Base Price X Current Index / Base Index
ii. Percentage Increase/Different = (Current Index – Original Index / Original Index) X
100
Cost/M2 of Proposed Building GFA Data
Base Index RM 114,768.00
Current Index 103.30
108.40
i. New Price = Base Index X Current Index / Original Index
= RM 114,768.00 X (108.40/103.30)
= RM 120, 434.18/M2
ii. Percentage = (Current Index – Original Index / Original Index) X 100
Increase/Different
= (108.40 - 103.30 / 103.30) X 100
= 5%
Total cost for 122 units:
= RM 120, 434.18/M2 X 122 units
= RM 14, 692, 970.00
6.5 Construction Cost of the Proposed Building
Building works RM 14, 692, 970.00
Mechanical & Electrical Services (Prime Cost RM 2, 082, 275.40
Sums)
Provisional Sum/ Contingencies RM 500, 000.00
Preliminaries RM 1, 091, 389.24
13
7.0 COMMENT ON THE LIMITATION/DIFFICULTIES IN THE COLLECTION,
ADJUSTMENTS AND APPLICATION OF THE COST DATA.
After going through some discussions and meetings, our group experienced a few
limitations or difficulties in the collection, adjustments and application of the cost data. First,
the difficulties we face is during the adjustment process that is the difficulty to find the latest
cost index for the proposed project used in this project. Other than that, we also face few
difficulties during application of cost data process, the difficult to find the latest cost for per
m2 for similar proposed building project which is semi-d houses. The limitation to find similar
location for cost per m2 for the proposed project estimation has been one of the reasons.
Next, our group found that the difficult to find cost index for base cost index and current cost
index for this project.
8.0 CONCLUSION
As expressed, the preliminary estimate is the initial indication of a project's cost and
is frequently the figure that the client remembers. When it comes to the preliminary estimate,
it should not be too low since this may necessitate some explanation as the design evolves,
should the cost rise, nor should it be too high because the design may be delayed according
to the client's lack of cash. When a customer proposes a building project, it is critical to
understand the cost that will be employed for the project. This is to guarantee that no more
funds are necessary and that the budget remains intact.
The most appropriate approach for calculating the preliminary estimate for the
proposed project in this scenario is gross floor area. The total floor area of a building is
usually equal to the sum of the floor areas of all the spaces inside it. This comprises the
majority of the structure, including all completed sections and supporting areas. For cost
data, we used cost indices. It is a way of analyzing cost data from previously constructed
and finished projects; as a result, data must be updated to represent current prices or future
prices for the estimated price. Meanwhile, the primary source of cost data comes from our
project's Bill of Quantities. A bill of quantities (BOQ) is a document used in construction
tendering that includes materials, components, and labour (along with their costs). We got
data from the second source using information services such as Arcadis. Arcadis is the
premier provider of sustainable design, engineering, and consulting services for natural and
14
built assets across the world. Last but not least, we received our data from the Department
of Statistics Malaysia through Government Publications (DOSM).
As previously stated, Cost Index is used to acquire cost data for this project, and the
Quantity Surveyor must keep track of everything included in order to make price
modifications based on previous cost data. As a result, the following are some of the reasons
for the project's adjustment which are location of projects/construction, fluctuations, labour
costs, material costs, market conditions and last but not least, profit and overhead.
15
REFERENCES
About us Arcadis. (n.d.). Arcadis. Retrieved December 28, 2021, from
https://www.arcadis.com/en/about-us
Bill of quantities BOQ. (n.d.). Designing Buildings. Retrieved December 28, 2021, from
https://www.designingbuildings.co.uk/wiki/Bill_of_quantities_BOQ
Department of Statistics Malaysia Offical Portal. (n.d.). DOSM. Retrieved December 26,
2021, from https://www.dosm.gov.my/v1_/
Haji Ahmad, K. (2011). Construction Economics (2nd ed.). Pearson Custom Sdn Bhd.
Ismail, N. A. A., Idris, N. H., Ramli, H., Sahamir, S. R., & Rooshdi, R. R. R. M. (2018).
Sustainable BIM-based cost estimating for quantity surveyors. Chemical
Engineering Transactions, 63, 235-240.
Kim, G. H., An, S. H., & Kang, K. I. (2004). Comparison of construction cost estimating
models based on regression analysis, neural networks, and case-based reasoning.
Building and environment, 39(10), 1235-1242.
Mishra, G. (2021, May 14). Factors Affecting Construction Cost Estimation. The
Constructor. https://theconstructor.org/construction/cost-estimation-factors/9316/
Zak, M. (2021, May 27). Current Market Impact on Construction Costs. Hastings+Chivetta
Architects. https://www.hastingschivetta.com/current-market-impact-on-
construction-costs/
16
APPENDICES
Temporary LALUAN (BY
Silt PEJALAN OTHERS)
Basin KAKI
B IL 7' TLK
6" PENGUNJUNG
13.75m KAWASAN
RTC LAPANG
B 22'
X RTC
70' 22'
X
70'
temporary RTC RTC JALAN RTC
earth 22' 22' 40' 22'
drain X X X
70' 70' 70'
JALAN
RTC RTC RTC
22' 22' 22'
X X X
70' 70' 70'
RTB RTB PE RTB JALAN RTB
20' 20' DC 20' 40' 20'
X X X55' X X
65' 65' 48' 65' 65
RTB RTB RTB
20' 20' 20'
X X X
65' 65' 65'
REZAB drain earth temporary RTB RTB RTB RTB
PARIT 20'
22m 20' JALAN2X0' X
20' X 40' 65' 65'
temporary X 65'
65' RTA RTA
20' 20'
40' JALAN E5RTA RTA X X
20' 60' 60'
20' X
X 60' RTA
60' 20'
X
JALAN RTA 60'
40' 20'
X
RTA RTA 60'
20'
20' X
X
60' JALAN60' RTA
20'
RTA 40' X
60'
20'
X
60'
RTA RTA
20'
X 20' JALAN
60'
X 40'
REZAB 60'
JALAN
66' A
REZAB M
PARIT
22m /
K
PE(1T0R0O')NAS
RTC J5A0L' AN ZON
22' 1P0E' NAMPAN
X
70' ek0.L8AK6PAAWNAGSAN
RTC KOMPLEKS
22' SEKOLAH
X
70'
RTC
22'
X
70'
RTB
20'
X
65'
B
'
5'
5J0A' LAN
SALURAN
PAIP
GAS
PETRONAS
(100')
AKSES 50'
MASUK
/
KELUAR
KH
0.21
ek
RM/m2
SERVICES
1 CONSTRUCTION COST DATABUILDINGTOTAL
CONSTRUCTION COSTS FOR KUALA LUMPURDOMESTIC1,580-2,230790 -1,0652,370-3,295
Detached houses (mass housing) 2,230 - 3,040 795 - 1,065 3,025 - 4,105
16 CONSTRUCTION COST DATADetached houses (high end)-1,135195 - - 1,440
Terraced houses 705 - 1,925 240 - 305 900 - 2,425
Average standard apartments, high rise 1,000 - 4,550 795 - 500 1,240 - 5,700
Luxury apartments, high rise 2,115 - 110 - 1,150 2,910 -
Low cost housing - 525 180 - 130 - 655
Low cost flats, low rise (<6 levels) 440 - 720 250 - 215 550 - 935
Low cost flats, high rise (<15 levels) 615 925 325 795 1,250
720 970
OFFICE / COMMERCIAL
Average standard offices, high rise 1,480 - 1,935 880 - 1,170 2,360 - 3,105
Prestige offices, high rise 2,150 - 3,505 1,400 - 1,735 3,550 - 5,240
Shopping centres 1,945 - 2,765 2,780 - 4,180
835 - 1,415
HOTELS
Resort hotels, inclusive of F.F.&E. 3,170 - 3,725 1,265 - 1,700 4,435 - 5,425
3-star budget hotels, ditto 3,295 - 4,630 875 - 1,210 4,170 - 5,840
5-star luxury hotels, ditto 6,115 - 7,830 - 2,350 7,935 - 10,180
1,820
Jadual 1B: Indeks kos bahan binaan bangunan mengikut kategori bangunan dan kawasan (termasuk bar keluli)
Table 1B: Building materials cost index by category of building and region (with steel bars)
(Julai 2017=100)
(July 2017=100)
Kategori bangunan Tempoh AB Kawasan EF
Category of building Period Region
CD
1.B.1 Bangunan (K.T.) 2020 Dis 104.0 102.9 103.3 99.2 102.6 101.0
Satu Tingkat 2021 Jan 105.7 103.1 103.9 99.2 103.5 102.2
Single - Storey (R.C.) 106.4 103.1 104.2 99.4 103.9 103.9
Building Feb 108.1 103.1 104.4 100.7 105.2 104.2
Mac 109.9 105.6 104.6 101.4 106.8 105.3
1.B.2 Bangunan (K.T.) Apr 111.0 107.7 104.9 101.5 107.5 106.1
2−4 Tingkat Mei 111.4 110.1 105.3 101.7 107.8 107.8
(Berbumbung Rata) Jun 112.9 112.2 105.3 101.6 109.9 109.5
2−4 Storey (R.C.) Jul 113.7 113.8 105.2 101.6 110.3 110.1
Building (Flat Roof) Ogos 114.1 114.8 106.0 101.7 110.9 110.7
Sep 114.3 116.7 106.9 101.7 111.9 110.8
1.B.3 Bangunan (K.T.) Okt 115.2 117.6 108.4 102.6 113.0 111.4
2−4 Tingkat Nov
(Berbumbung Curam) 105.1 103.6 104.9 98.7 102.1 100.0
2−4 Storey (R.C.) Dis 107.1 103.8 105.9 98.7 103.8 101.9
Building (Pitched Roof) 108.1 103.5 106.1 99.0 105.0 104.4
2020 Dis 110.4 103.4 106.2 100.7 107.0 104.7
2021 Jan 112.6 106.7 106.4 101.8 109.0 105.6
113.9 109.9 106.5 101.8 109.7 106.2
Feb 114.3 113.2 107.1 102.1 109.9 108.8
Mac 116.5 116.3 107.1 102.0 112.9 111.3
Apr 117.2 118.4 107.0 102.0 113.2 112.0
Mei 117.5 119.4 108.2 102.1 113.6 112.4
Jun 117.6 121.9 109.5 102.1 114.2 112.4
Jul 118.3 122.4 111.3 103.3 115.0 113.0
Ogos
Sep 105.4 103.6 104.9 98.9 102.4 100.5
Okt 107.3 103.8 105.8 98.9 103.8 102.1
Nov 108.2 103.4 106.0 99.2 104.6 104.3
110.3 103.3 106.1 100.9 106.4 104.6
Dis 112.4 106.4 106.2 101.8 108.3 105.6
113.6 109.3 106.4 101.9 109.0 106.2
2020 Dis 114.0 112.3 106.8 102.1 109.2 108.5
2021 Jan 116.0 115.1 106.8 102.0 112.1 110.9
116.8 117.0 106.7 102.0 112.6 111.6
Feb 117.1 118.1 107.9 102.1 113.0 111.9
Mac 117.3 120.6 109.0 102.1 113.8 112.0
Apr 118.0 121.2 110.9 103.3 114.7 112.7
Mei
Jun
Jul
Ogos
Sep
Okt
Nov
Dis
12
Jadual 1B: Indeks kos bahan binaan bangunan mengikut kategori bangunan dan kawasan (termasuk bar keluli)
Table 1B: Building materials cost index by category of building and region (with steel bars)
(Julai 2017=100)
(July 2017=100)
Kategori bangunan Tempoh AB Kawasan* E F
Category of building Period Region
100.2
CD 100.6
100.5
(1) Bangunan (K.T.) 2019 Dis 102.3 100.4 102.1 98.6 100.9 100.8
Satu Tingkat 2020 Jan 103.0 101.5 102.4 98.6 100.9 100.8
Single - Storey (R.C.) 103.3 102.4 102.6 99.3 101.3 100.9
Building Feb 103.3 102.7 102.6r 99.3 102.0 100.4
Mac 103.3 102.9 102.8 99.4 102.3 100.5
Apr 103.3 102.8 102.8 99.3 102.0 100.6
Mei 103.3 101.8 103.0 99.3 102.2 100.6
Jun 103.5 102.2 103.1 99.3 102.4 100.8
Jul 103.5 102.2 102.7 99.3 102.1 100.9
Ogo 103.6 102.5 102.7 99.2 102.3 101.0
Sep 103.7 102.8 102.7 99.2 102.5
Okt 103.7 102.8 102.7 99.1 102.5 99.2
Nov 104.0 102.9 103.3 99.2 102.6 99.6
Dis 99.5
99.9
(2) Bangunan (K.T.) 2019 Dis 103.5 100.2 103.6 98.4 101.5 99.9
2−4 Tingkat 2020 Jan 104.2 101.4 103.8 98.4 101.5 100.0
(Berbumbung Rata) 104.5 102.7 104.0 98.9 101.9 99.2
2−4 Storey (R.C.) Feb 104.6 103.2 104.0 98.9 102.6 99.3
Building (Flat Roof) Mac 104.6 103.6 104.2 99.0 102.9 99.3
Apr 104.6 103.4 104.2 98.9 102.0 99.2
(3) Bangunan (K.T.) Mei 104.6 102.1 104.5 98.9 102.0 99.5
2−4 Tingkat Jun 104.7 102.8 104.6 98.9 102.1 99.5
(Berbumbung Curam) Jul 104.7 102.8 104.0 98.9 102.0 100.0
2−4 Storey (R.C.) Ogo 104.9 103.1 104.0 98.8 101.8
Building (Pitched Roof) Sep 105.0 103.7 104.0 98.8 102.1 99.7
Okt 105.0 103.7 104.0 98.7 102.1 100.1
Nov 105.1 103.6 104.9 98.7 102.1 100.0
Dis 100.4
103.5 100.2 103.4 98.6 101.2 100.4
2019 Dis 104.3 101.6 103.6 98.6 101.2 100.5
2020 Jan 104.7 102.7 104.0 99.1 101.7 99.8
104.7 103.2 104.0r 99.1 102.6 99.9
Feb 104.7 103.6 104.1 99.2 103.0 99.9
Mac 104.7 103.4 104.2 99.1 102.2 99.8
Apr 104.7 102.2 104.5 99.1 102.3 100.1
Mei 104.8 102.8 104.7 99.1 102.3 100.1
Jun 104.8 102.8 104.0 99.1 102.1 100.5
Jul 105.1 103.1 104.0 99.0 102.0
Ogo 105.2 103.6 104.0 99.0 102.3
Sep 105.2 103.6 104.0 98.9 102.4
Okt 105.4 103.6 104.9 98.9 102.4
Nov
Dis
Nota/Note :
(1) K.T. = Konkrit Bertetulang/R.C. = Reinforced Concrete
(2) Mulai penerbitan Julai 2018, Indeks Kos Bahan Binaan Bangunan menggunakan tahun asas
(Julai 2017=100)
Starting from July 2018, Building Materials Cost Index is using (July 2017=100) as a base year
* Lihat nota kaki di hujung Jadual 1A/See footnotes at end of Table 1A
4