PM/PROGRESS TEST 2/MAR2020/QUESTION
Fundamentals Level – Skills Module
PERFORMANCE Paper PM
MANAGEMENT (PM)
Wednesday, 11 March 2020
9.00am – 12.00pm
ACCA
1
PROGRESS TEST 2
CA2A, CA2B, CA2C, CA2D, CA2E, CA2F, CA2G JJ2020
Time allowed (3 hours)
This paper is divided into three sections:
Section A – ALL 15 questions are compulsory and must be
attempted
Section B – ALL 15 questions are compulsory and must be
attempted
Section C – BOTH questions are compulsory and must be
attempted
Formula sheet is given on page 22.
Do NOT open this paper until instructed by the supervisor.
The Association of Chartered Certified Accountants
PM/PROGRESS TEST 2/MAR2020/QUESTION
Section A - All 15 questions are compulsory and MUST be attempted
Each question is worth 2 marks.
1. Alpha Co uses rolling budgeting, updating its budgets on a quarterly basis. After carrying out the last
quarter's update to the cash budget, it projected a large forecast cash deficit at the end of the year.
Consequently, the planned purchase of new capital equipment for Project A has been postponed. Alpha
Co has been working on a second project, Project B, and has developed a new product. The first batch
of 20 units will take 600 labour hours to produce. There will be an 80% learning curve that will continue
until 600 units have been produced. Batches after this level will each take the same amount of time as
the 30th batch. The batch size will always be 20 units.
Note. The learning index for an 80% learning curve is –0.3219
How long will Alpha Co take to produce the next 25 batches?
(round up your final answer to the nearest figure)
Hour
2. Match each of the following as either direct data capture costs, process costs or indirect costs
of capturing data.
(i) The use of bar codes and scanners
(ii) Storing information long after it is needed
(iii) Payroll department time spent processing and analyzing personnel costs
(iv) Information disseminated more widely than needed
3. Select ‘True’ or ‘False’ for the following statements on types of information systems.
Statements TRUE FALSE
(i) The components of a transaction processing systems (TPS) include
hardware, software and people.
(ii) Executive Information systems (EIS) draw data from the TPS and
allow communication with external sources of information.
(iii) Enterprise resource planning systems (ERP) integrate all processes
in an organization so that a dual system can serve all database
applications.
(iv) The benefits of customer relationship management (CRM) systems
are in regards to customer retention and targeted marketing.
2
PM/PROGRESS TEST 2/MAR2020/QUESTION
4. The following statements have been made about environmental cost accounting, select ‘True’ or
‘False’.
Statements TRUE FALSE
(i) Identifying environmental costs associated with individual products
and services can assist with pricing decisions.
(ii) The majority of environmental costs are already captured within a
typical organisation’s accounting system. The difficulty lies in
identifying them.
(iii) Input/output analysis divides material flows within an organization into
three categories: material flows, system flows and delivery and
disposal flows.
(iv) In flow cost accounting, any difference between the input and output
is called ‘waste’.
5. Pearl Co is setting up an online business importing and selling pearl headphones. The cost of each set
of headphones varies depending on the number purchased, although they can only be purchased in
batches of 1,000 units. It also has to pay import taxes which vary according to the quantity purchased.
Market research has revealed that the maximum demand for Pearl Co’s headphones in the USA is
76,000 units per year, and that demand will reduce by 8,000 units for every $5 that the selling price is
increased. Based on this information, Pearl Co has calculated that the profit maximizing level of sales
for its headphones, for the coming year, is 36,000 units.
Calculate the unit price at which these headphones will be sold.
$
6. BFF Co makes house signs. Three different styles of signs are made and the following unitary information
is available:
Square Oval Clover Leaf
$ $ $
4.00 5.00 6.00
Materials 2.00 3.00 4.00
Metal @$1/kg 14.00 10.00
9.00 12.00
Paint @ $4/litre
10.50 20.00
12.00 15.00
Labour
Manufacturing @ $4/hour 8.00
3.00
Painting @ $6/hour
7.00
13.00
Variable overhead
Fixed overheads
3
PM/PROGRESS TEST 2/MAR2020/QUESTION
Selling price 39.00 56.50 68.00
Maximum monthly demand 4,000 4,500 1,800
BFF has also been told that during that 2nd week, both the metal and the paint supplier will be willing to
supply 36,000 kg of metals and 4,500 litres of paints respectively. Painting labour is limited to 8,800
hours for the 2nd week as some of the workers will be away on a training course. BFF Co has decided to
concentrate its activities on the square and oval plates and temporarily shut down the clover leaf
production line.
Which of the following statements are false?
(1) Painting labour will have a positive shadow price.
(2) The objective function will be to maximize 15S +15O, where S is the number of square plates
produced and O is the number of Oval plates produced.
(3) If solved graphically, the optimal solution will be where the constraints for metal and painting labour
intersect.
(4) Paint will have a shadow price of zero.
A. (1) and (2)
B. (1), (2) and (3)
C. (1), (3) and (4)
D. (1) and (4)
7. De’ Suria an events management company is trying to decide whether or not to advertise an outdoor
concert. The sale of tickets is dependent on the weather. If the weather is poor it is expected that 5,000
tickets will be sold without advertising. There is a 70% chance that the weather will be poor. If the weather
is good it is expected that 10,000 tickets will be sold without advertising. There is a 30% chance that the
weather will be good.
If the concert is advertised and the weather is poor, there is a 60% chance that the advertising will
stimulate further demand and ticket sales will increase to 7,000. If the weather is good there is a 25%
chance the advertising will stimulate demand and ticket sales will increase to 13,000. The profit expected,
before deducting the cost of advertising, at different levels of ticket sales are as follows:
Number of tickets sold Profit/(loss) ($)
5,000 (20,000)
6,000 (5,000)
7,000 35,000
8,000 55,000
9,000 70,000
10,000 90,000
11,000 115,000
12,000 130,000
13,000 150,000
4
PM/PROGRESS TEST 2/MAR2020/QUESTION
The cost of advertising the concert will be $15,000. The decision tree has been drawn as below:
You are required to advise De’ Suria management as to their best course of action.
Decision: Expected Value: $
8. The Roti Boy Company (RBC) makes a range of breads for sale direct to the public. The production
process begins with workers weighing out ingredients on electronic scales and then placing them in a
machine for mixing. A worker then manually removes the mix from the machine and shapes it into loaves
by hand, after which the bread is then placed into the oven for baking. All baked loaves are then
inspected by RBC’s quality inspector before they are packaged up and made ready for sale. Any loaves
which fail the inspection are donated to a local food bank.
The standard cost card for RBC’s ‘Mixed Bloomer’, one of its most popular loaves, is as follows:
$
White flour 450 grams at $1.80 per kg 0.81
Wholegrain flour 150 grams at $4.20 per kg 0.63
Yeast 10 grams at $20 per kg 0.20
Total 610 grams 1.64
Budgeted production of Mixed Bloomers was 10,000 units for the month, although actual production
was only 9,500 units. The total actual quantities used, and their actual costs were:
5
PM/PROGRESS TEST 2/MAR2020/QUESTION
Kg $ per kg
White flour 4,085 1.90
Wholegrain flour 1,520 5.10
Yeast 100 20.50
Total 5,705
What is the total material usage variance for RBC for the last month?
$
9. In order to indicate to managers the trend and materiality of variances, C plc expresses them as
percentage as in the following:
July August September October November
Material usage as percentage of 3% F 2% A 6% A 10% A 12% A
standard total production cost
Material price variance as a percentage 1% A 2% A 7% F 8% F 9% F
of standard cost of material used
A - denotes adverse variance
F - denotes favorable variance
The following relates to recent operational events.
1. In September the buyer located a new supplier who charged a lower price that the previous supplier.
The material was found to be of low quality, however leading to a high level of waste.
2. The general trend is that all direct material variances are becoming more significant and are likely
to be worthy of management attention.
3. A change in the bonus payment scheme has improved the productivity of labour, who are now
processing material more effectively.
Which of the statements is /are consistent with results shown?
A. Statements 1 and 2
B. Statement 1 and 3
C. Statement 2 and 3
D. Statement 2 only
6
PM/PROGRESS TEST 2/MAR2020/QUESTION
10. A company makes many products, one of which is Product P. Extracts from the budget for the whole
company for June are set out below:
Budget category $ Cost driver details
Direct labour cost 64,000 8,000 direct labour hours
Set-up costs 22,000 44 set-ups
Quality testing costs 6,800 160 tests
General overheads 18,800 Absorbed using direct labour hours
Budgeted data for the manufacture of Product P in June as follows:
Budgeted output 200 units
Direct materials $18.00 per unit
Direct labour 0.4 hours per unit
Batch size 100 units
Set-ups 1 set-up per batch
Quality tests 2 test per batch
Calculate, using an activity-based costing approach, the budgeted cost per unit of Product P for
June. Round your answer to the nearest $.
$ per unit
11. A company produces two products, S and T, which pass through two production processes, X and Y.
The time taken to make each product in each process is:
Product S Product T
Process X 5 mins 7.5 mins
Process Y 18 mins 12 mins
The company operates a 15-hour day and the processes have an average downtime each day of:
Process X 1.5 hours
Process Y 1.0 hours
The costs and revenue for each product are:
Product S Product T
$ $
Direct materials 20.00 20.00
Direct labour 18.00 14.00
Variable overhead 4.00 4.00
Fixed costs 5.00 4.00
Total costs 48.00 42.00
Selling price 95.00 85.00
7
PM/PROGRESS TEST 2/MAR2020/QUESTION
Sales demand restricts the output of S and T to 50 and 80 units a day respectively.
Calculate the daily production plan that would maximise the throughput contribution.
12. Rightlight Ltd is an advertising company and has been asked to tender for a contract to increase public
awareness of global environmental issues as part of the government’s commitment to improving the
country’s eco-footprint.
Rightlight Ltd believes that the campaign work will take a period of six months.
Five advertising specialists would need to be recruited on an annual salary of $45,000. A project
manager would be needed to coordinate the campaign. An existing project manager would be used
whose annual salary is currently $55,000. He would be expected to devote 30% of his time on the new
contract.
The new employees would have to go through a ‘Environmental Awareness’ training programme in order
to get approval to work on government contracts. This would cost $3,000 per employee, but it is
anticipated that a grant of 20% towards this cost will be available.
Alternatively, Rightlight Ltd could subcontract the work (with the government’s agreement) to another
PR that it sometimes uses for joint venture projects. It is anticipated that the subcontract firm would
demand a fee of $135,000 to undertake the work.
What would be the relevant cost of labour in this contract?
A. $135,000
B. $253,500
C. $124,500
D. $141,000
13. Match the following statements with the budgetary type systems:
Statements Budgetary type
systems
This budgetary system is suitable for organizations that operate in a
stable environment where historic figures are reliable and are not
expected to change significantly.
Every item of expenditure has to be justified in its entirety in order to be
included in the next year’s budget.
In this budgetary system, planning and control will be based on a recent
plan which is likely to be far more realistic that a fixed annual budget
made many months ago.
8
PM/PROGRESS TEST 2/MAR2020/QUESTION
This budgeting concept move towards devolved networks rather than
centralized hierarchies.
This type of budget recognizes different cost behavior pattern and is
changed as the volume of output and sales changes.
14. Which of the following statement/s is/are true about cost volume profit analysis?
I. One of the limitations of CVP analysis is that uncertainty in the estimates of fixed costs and unit
variable cost is often ignored.
II. Production and sales are assumed to be the same, so that the consequences of any increase in
inventory levels or of ‘de-stocking’ are ignored.
III. The multi product P/V chart will only identify the company breakeven point and which product
should be expanded in output and which (if any) should be discontinued.
IV. Breakeven chart for multiple products can be drawn if a constant product sales mix is assumed.
A. I and II
B. I, II and III
C. I, II and IV
D. II, III and IV
15. Which following statement/s is/are true about short term decision making?
I. Employees morale and customer reaction are among quantitative factors that should be
considered in deciding to shut down operations.
II. Since both products incur the pre-separation cost, it is relevant to the further processing decision.
III. One of the reasons for trend towards outsourcing is the contractors have the capacity and
flexibility to start production very quickly to meet sudden variations in demand.
IV. Make or buy decisions should certainly be based exclusively on cost considerations.
A. I and III
B. III only
C. II and III
D. II and IV
9
PM/PROGRESS TEST 2/MAR2020/QUESTION
Section B – All 15 questions are compulsory and MUST be attempted
Each question is worth 2 marks.
The following scenario relates to questions 16-20.
Luna Lovegood (LL) is a manufacturing company within the DF group. LL has been asked to provide a
quotation for a contract for a new customer and is aware that this could lead to further orders. As a
consequence, LL will produce the quotation by using relevant costing instead of its usual method of full cost
plus pricing.
LL has spent $100 to obtain the following information for the new contract. The following information in
relation to the contract are as follows:
Material D
40 tonnes of material D would be required. This material is in regular use by LL and has a current purchase
price of $38 per tonne. Currently, there are 5 tonnes in inventory which cost $35 per tonne. The resale value
of the material in inventory is $24 per tonne
Labour hours
850 direct labour hours would be required. All direct labour within LL is paid on an hourly basis with no
guaranteed wage agreement. The grade of labour required is currently paid $10 per hour, but department W
is already working at 100% capacity. Possible ways of overcoming this problem are:
• Use workers in department Z, because it has sufficient capacity. These workers are paid $15 per
hour.
• Arrange for sub-contract workers to undertake some of the other work that is performed in
department W. The sub-contract workers would cost $13 per hour.
Specialist machine
The contract would require a specialist machine. The machine could be hired for $15,000 or it could be
bought for $50,000. At the end of the contract if the machine were bought, it could be sold for $30,000.
Alternatively, it could be modified at a cost of $5,000 and then used on other contracts instead of buying
another essential machine that would cost $45,000.
Supervisor
The contract would be supervised by an existing manager who is paid an annual salary of $50,000 and has
sufficient capacity to carry out this supervision. The manager would receive a bonus of $500 for the additional
work.
Development time
15 hours of development time at a cost of $3,000 have already been worked in determining the resource
requirements of the contract.
10
PM/PROGRESS TEST 2/MAR2020/QUESTION
Fixed overhead absorption rate
LL uses an absorption rate of $20 per direct labour hour to recover its general fixed overhead costs. This
includes $5 per hour for depreciation.
16. What are the figures to be included in the quote for Material D and Labour?
Material D $
Labour $
17. What figure should be included in the quote for the specialist machine and supervisor?
Specialist machine $
Supervisor $
18. What figures should be included in the quote for the development time and fixed overheads?
Development time $
Fixed overheads $
19. It is factory policy to add $1,500 per week to a project, for the duration of the project. This is to cover:
Factory rates $500
Interest on long term loan to purchase plant and equipment $400
Profit element $600
Which option correctly classifies these costs?
Factory rates Interest Profit
A Relevant Non-cash Committed
B Notional Committed Non-cash
C Non-cash Relevant Notional
D Committed Committed Non-cash
11
PM/PROGRESS TEST 2/MAR2020/QUESTION
20. State true or false for each of the following statements: TRUE FALSE
TRUE FALSE
TRUE FALSE
I. The $100 spent obtaining the cost information should be TRUE FALSE
included in the quote TRUE FALSE
TRUE FALSE
II. If LL charges the minimum price for a product or service based
on relevant costs, it will not improve its overall profitability
III. Timescale is not relevant and many fixed costs can be varied,
but only in the long term
IV. Fixed costs are always general in nature and therefore not
relevant
V. Avoidable costs would be saved if an activity did not happen and
so are relevant
VI. Common costs are only relevant if the viability of the whole
process is being assessed
12
PM/PROGRESS TEST 2/MAR2020/QUESTION
The following scenario relates to questions 21-25.
Yummy Yoghurt Co (YY) produces and sells frozen yoghurt in small tubs. The company has found that
demand for frozen yoghurt is weather dependent. Last summer the weather was poor and they ended up
throwing lots of frozen yoghurt away at the end of the summer. Using estimates about the probable weather
conditions and corresponding demand levels for weekends next summer, the following pay off table has been
produced to show all the possible contribution outcomes.
Number of tubes of frozen yogurt produced
10,000 8,000 4,000
Weather Probability $ $ $
Good 20% 3,000 2,400 1,200
Average 50% 1,900 2,400 1,200
Poor 30% (300) 200 1,200
YY has decided to sign an advance contract at one of the three levels to match forecast demand. It now
has to decide which level to select.
21. How many tubs should the company produce based on the maximin, maximax and minimax
regret decision rules?
Maximin Maximax Minimax regret rule
A. 10,000 4,000 8,000
B. 8,000 10,000 4,000
C. 4,000 8,000 10,000
D. 4,000 10,000 8,000
22. If FY applies the minimax regret rule, what kind of decision making is this?
A. Risk averse
B. Risk seeking
C. Risk neutral
D. Risk spreading
23. What is the expected contribution if 4,000 tubs are produced and how many tubs should the
company produce based on the expected value decision rules?
Expected contribution from 4,000 tubs Tubs to be produced using expected value rules
A. $1,460 10,000
B. $1,200 8,000
C. $1,460 8,000
D. $1,200 4,000
24. Calculate the maximum price that YY should pay for the state of demand.
$
13
PM/PROGRESS TEST 2/MAR2020/QUESTION
25. The following statements have been made about perfect information by a trainee at YY.
(1) Perfect information is guaranteed to predict the future with 100% accuracy.
(2) Perfect information means that the correct decision would always been made, but as this is in
hindsight it is not useful for calculations.
Which of the above statements is/are true?
A. (1) only
B. (2) only
C. Neither (1) nor (2)
D. Both (1) and (2)
14
PM/PROGRESS TEST 2/MAR2020/QUESTION
The following scenario relate to questions 26-30.
Petunia Dursley (PD) Co makes and sells lawnmowers. It has developed a new robotic lawnmower (the
Dudley), which is able to cut the grass automatically, i.e. it does not require an operator. Currently there are
no similar products in the market. Significant expenditure on research and development expenditure was
required to develop the Dudley, to date $2 million has been spent. The lawnmower is expected to have a
product lifecycle of three years. Market research has been carried out to establish a target selling price and
projected lifetime sales volumes for the product. Cost estimates have also been prepared, based on the
current design.
PD Co uses lifecycle costing to work out the target costs for its products. You are provided with the following
relevant information for the lawnmower:
Projected lifetime sales volume 1,000,000 units
Target selling price per unit $500
Target profit margin 30%
Note: Estimated lifetime cost per unit:
$ $
Manufacturing costs
Direct material 120
Direct labour 65
Machine costs 90
Quality control test costs 10
285
Non-manufacturing costs 110
Estimated lifetime cost per unit 395
PD Co is looking to address a possible cost gap and is considering direct material costs. All of the parts
currently proposed for the lawnmower are bespoke. However, it has been established that the majority of
parts can be replaced by parts used in other lawnmowers. The standard parts cost 60% less than the bespoke
parts, but four bespoke parts which account for 25% of the current direct estimated cost cannot be replaced.
These parts can however be sourced from an alternative supplier for 5% less than currently forecast.
26. What is the target cost per unit of the Dudley and the revised material cost per unit in light of the
new information to two decimal places?
Target cost per unit $
Revised material cost per unit $
15
PM/PROGRESS TEST 2/MAR2020/QUESTION
27. If F Co discovers that there is a cost gap, which of the following may be an appropriate strategy
to close the cost gap?
A. Increase the selling price of the RLM
B. Use skilled labour for the manual unskilled elements of production
C. Reverse the decision to use standard components
D. Redesign the lawnmower
28. Which of the following statement/(s) apply to F co?
(1) Life cycle costing should not be used by F Co, because lifecycle of the ‘RLM’ is short and the
development costs is too high.
(2) Life cycle costing should be used by F Co because it will provide the true financial costs of producing
the shoes.
(3) A higher price should be charged by F Co from the start, as the product is unique
A. (1) and (2)
B. (1) and (3)
C. (2) and (3)
D. (2) only
29. Select true or false for each of the follow statement.
In order to improve the financial results of the product over its lifecycle F co should TRUE FALSE
minimize its time to the market, minimize length of the lifecycle and minimize the
breakeven time
Lifecycle costing aims to ensure that profit is generated over the entire life of the TRUE FALSE
product
At the maturity phase of the lifecycle is where F Co’s product strategy should focus TRUE FALSE
on forecasting capacity requirements
In lifecycle costing all costs will be included as part of lifecycle cost in exception of TRUE FALSE
research and development costs incurred at the beginning as this is a sunk cost
30. PD co is planning to launch a new component, component Harry. Production volume will be
limited, with only 128 components to be produced in total.
PD co expects the manufacture of the first component to take 25 direct labour hours. It is
anticipated there will be a 90% learning curve that will continue until all 128 components have
been produced. Direct labour is paid at a rate of $15 per hour.
Non labour-related costs are expected to be $265 per component;; this will apply to all 128
components produced. There are no product-specific fixed costs associated with this new
component.
16
PM/PROGRESS TEST 2/MAR2020/QUESTION
PD is going to use a target costing approach for the new component. Based on the market
research it has undertaken, PD plans to sell the components for $530 each. PD requires an
average profit margin of 20% of the selling price over the life of this new component.
Note: The learning index for a 90% learning curve = -0.152
Calculate the learning rate required to close the cost gap in order to achieve the required
profit margin of 20%. Provide answer to the nearest whole percentage
%
17
PM/PROGRESS TEST 2/MAR2020/QUESTION
Section C – Both questions are compulsory and MUST be attempted.
Provide your answer for 31 (a) and (b) in the Excel Template, and 31 (c) and (d) in the Word Template.
31. A company produces trays of pre-prepared meals that are sold to restaurants and food retailers.
Three varieties of meals are sold: economy, premium and deluxe.
Extracts from the budget for last year are given below:
Economy Premium Deluxe
Sales quantity (trays) 180,000 360,000 260,000
Selling price per tray $2.80 $3.20 $4.49
Total sales revenue $504,000 $1,152,000 $1,167,400
Direct material cost per $1.00 $1.60 $2.20
tray
Total direct material cost $180,000 $576,000 $572,000
Direct labour cost per tray $0.50 $0.50 $0.50
Total direct labour cost $90,000 $180,000 $130,000
Overhead costs for the budget were estimated using the high-low method based on the total
overhead costs for the three previous years.
Output 720,000 trays 680,000 trays 840,000 trays
Total overheads $1,018,000 $992,000 $1,096,000
Actual results for last year were as follows:
Economy Premium Deluxe
Sales quantity (trays) 186,000 396,000 278,000
Selling price per tray $2.82 $3.21 $4.50
Total sales revenue $524,520 $1,271,160 $1,251,000
Direct material cost per tray $1.10 $1.50 $2.10
Total direct material cost $204,600 $594,000 $583,800
Direct labour cost per tray $0.52 $0.54 $0.48
Total direct labour cost $96,720 $213,840 $133,440
Variable overhead per tray $0.64 $0.66 $0.63
Total variable overheads $119,040 $261,360 $175,140
Actual fixed overheads: $546,000
18
PM/PROGRESS TEST 2/MAR2020/QUESTION
The company operates a just-in-times system for purchasing and production and does not hold
any inventory. Budgeted and actual fixed overheads will be apportioned to Economy, Premium
and Deluxe at a ratio 1:2:2.
Ignore inflation.
Required:
a) Calculate, for the original budget, the budgeted fixed overhead costs and the budgeted
variable overhead cost per tray
(2 marks)
b) Prepare a flexed budget for the company (using a marginal costing approach).
(6 marks)
c) Discuss the benefits of flexible budgeting for planning and control purposes.
You should use the figures calculated in (b) above to illustrate your answer.
(5 marks)
The modern dynamic business environment has been described as a “buyer’s market” in which
companies must react to the rapidly changing characteristics of the market and the needs of
customers. Many managers have criticised traditional forms of budgeting for being too restrictive
and for being of little use for performance management and control.
d) Describe the principle of “Beyond Budgeting”, and discuss the advantages that
organizations will gain from making a move to Beyond Budgeting.
(7 marks)
(Total: 20 marks)
19
PM/PROGRESS TEST 2/MAR2020/QUESTION
Provide your answer for 32 (a) and (c) in the Excel Template, and 32 (b), (d) and (e) in the Word
Template.
32. AVX Plc assembles circuit boards for use by high technology audio video companies. Due to the
rapidly advancing technology in this field, AVX Plc is constantly being challenged to learn new
techniques.
AVX Plc uses standard costing to control its costs against targets set by senior managers. The
standard labour cost per batch of one particular type of circuit board (CB45) is set out below:
Direct labour – 50 hours @$10/hour $500
The following labour efficiency variances arose during the first six months of the assembly of CB45:
Month Number of batches Labour efficiency
assembled and sold variance ($)
November 1 Nil
December 1 170 (F)
January 2 452.20 (F)
February 4 1,089.30 (F)
March 8 1,711.50 (F)
April 16 3,423 (F)
An investigation has confirmed that all of the costs were as expected except that there was a
learning effect in respect of the direct labour that had not been anticipated when the standard cost
was set.
Required:
(a) Calculate the monthly rates of learning that applied during the six months
(8 marks)
(b) Identify when the learning period ended and briefly explain the implication of your
finding for AVX Plc.
(2 marks)
AVX Plc initially priced each batch of CB45 circuit boards on the basis of its standard cost of $960
plus a mark-up of 25%. Recently, the company has noticed that, due to increasing competition, it
is having difficulty maintaining its sales volume at this price.
20
PM/PROGRESS TEST 2/MAR2020/QUESTION
The Finance Director has agreed that the long run unit variable cost of the CB45 circuit board is
$672.72 per batch. She has suggested that the price charged should be based on an analysis of
market demand. She has discovered that at a price of $1,200 the demand is 16 batches per month.
For every $20 reduction in selling price, there is an increase in demand of 1 batch of CB45 circuit
boards.
(c) Calculate the profit maximizing selling price per batch using the data supplied by the
Finance Director
(4 marks)
The Technical Director cannot understand why there is a need to change the selling price. He
argues that this is a highly advanced technological product and that AVX Plc should not reduce its
price as this reflects badly on the company. If anything is at fault, he argues, it is the use of
Standard Costing and he has asked whether Target Costing should be used instead.
(d) Explain the difference between standard costs and target costs
(2 marks)
(e) Explain the possible reasons why AVX Plc needs to reconsider its pricing policy now
given the fact that the CB45 circuit board has been available in the market for six
months.
(4 marks)
(Total: 20 marks)
21
PM/PROGRESS TEST 2/MAR2020/QUESTION
Formulae Sheet
Learning curve
Y = ax b
Where Y = cumulative average time per unit to produce x units
a = the time taken for the first unit of output
x = the cumulative number of units produced
b = the index of learning (log LR/log2)
LR = the learning rate as a decimal
Demand curve
P = a – bQ
b = change in price
change in quantity
a = price when Q = 0
MR = a – 2bQ
22