1ST EDITION
TEACHING MODULE :
DCC10022
Concrete Laboratory
KHAIRUNNISA ISLAMI AMBOTOLA
NORIKA KARIM
first edition
All rights reserved.
No part of this publication may be reproduced or transmitted in any form or by any
means, electronic or mechanical including photocopy, recording, or any information
storage and retrieval system without permission in writing from,
Politeknik Kota Kinabalu.
Published by:
POLITEKNIK KOTA KINABALU
No. 4, Jalan Politeknik, KKIP Barat
Kota Kinabalu Industrial Park
88460, Kota Kinabalu, Sabah.
Tel : 088-401800
Faks : 088-499960
Website : https://polikk.mypolycc.edu.my/
© Politeknik Kota Kinabalu
First Edition, 2022
DCC 10022
CONCRETE LABORATORY
KHAIRUNNISA ISLAMI AMBOTOLA
12 years experience of teaching in Civil Engineering Department
ACADEMIC BACKGROUND
UNIVERSITI TUN HUSSEIN ONN MALAYSIA
Master in Civil Engineering
Bachelor Degree in Civil Engineering
POLITEKNIK KOTA KINABALU
Diploma in Civil Engineering
NORIKA KARIM
20 years experience of teaching in Civil Engineering Department
ACADEMIC BACKGROUND
UNIVERSITI TEKNOLOGI MALAYSIA
Master in Civil Engineering
UNIVERSITI TUN HUSSEIN ONN MALAYSIA
Diploma in Civil Engineering with Academic Distinction
Bachelor Degree in Civil Engineering
Preface
A fundamental concept of practical works and principles relating to brickworks and concrete works, including the safety
exposure in workshop, is covered in BRICKWORKS AND CONCRETE LABORATORY.
Students in this course must actively engage in teamwork during the practical tasks.
The purpose of the laboratory activity, which includes of workshops and experiments, is to introduce students to
fundamental approaches for problem solving and experimentation.
Each student will participate in data gathering, analyze data, and interpret results.
The use of the experimental findings to a genuine civil engineering issue will be emphasized.
After completing the course, students should be able to conduct laboratory experiments and investigations in concrete,
develop measurement techniques, analyze data, and interpret results in written reports, and develop generic skills that
will improve their ability to participate successfully in a lab environment and work as a team.
REACH US!
Civil Engineering Department
Politeknik Kota Kinabalu
No. 4, Jalan Politeknik
KKIP Barat
Kota Kinabalu Industrial Park
88460 Kota Kinabalu Sabah
CONNECT WITH US!
TELEPHONE NO : 088-401800
FAXS : 088-499960
email : [email protected]
email : [email protected]
This E-Book was produced in collaboration with two authors, namely
Mrs. Khairunnisa Islami Ambotola and Mrs. Norika Karim.
First and foremost, all praise and thanks to God the Almighty, for His blessing, we were able to
complete the task to produce the Teacing Module : DCC10022 Concrete Laboratory's E-Book
successfully.
With this opportunity, we would like to express our special thanks and gratitude to
our Head of the Civil Engineering Department,
who has gave us this golden opportunity to do the task of producing this E-book.
We would also like to thank all parties involved in helping us to complete this task,
especially to Mr. Mohd Azman bin Mohd Noor, the Head of Civil Engineering Diploma
Programme; our sincere appreciation for your unwavering support and discretion in providing
guidance throughout this task.
The completion of this project could not have been accomplished without the support of the of
the Civil Engineering Department, E-Learning coordinator and evaluator, we extremely grateful
for what they had offered us.
Finally, to our caring, loving, and supportive family members: our deepest gratitude. Your
encouragement when the times got rough are much appreciated and
duly noted.
“ Verily with hardship comes ease " - Quran; 94:5-6
Acknowledgment
CONTENTS
General Rules for Workshop Safety 1
Course Outline 2
Rubric 4
7
Sieve Analysis Test 16
Sand Segregation Test 22
26
Concrete Mixture 34
Slump Test
41
Compressive Strength Test
References
general safety
for Workshop Safety
1. Clean up all spills immediately.
2. Ensure all machine guards are in place before use.
3. Do not wear loose clothing or jewellery around machinery.
4. Be sure everyone is in clear before starting equipment.
5. Check electrical equipment for defects before using.
6. Keep hand tools in good condition.
7. Never distract the attention of another person.
8. Observer and practice the safety procedures established for the job.
9. Keep workshop clean.
10. Observe No Smoking regulations.
11. Shut down your machine before cleaning repairing or leaving it.
12. Do not exceed a speed that is safe for existing conditions.
13. Always wear PPEs.
14. Practice good housekeeping.
15. Report all unsafe conditions.
CIVIL ENGINEERING DEPARTMENT
COURSE OUTLINE
1. NAME OF COURSE BRICKWORKS AND CONCRETE MATERIAL
COURSE CODE
DCC 10022
SYNOPSIS
BRICKWORKS AND CONCRETE LABORATORY covers a basic
2. concept of practical works and principles regarding the brickworks and
concrete works including the safety exposure in workshop. This course
emphasizes the related brick laying using mortar mixing 1:3 and student
needed to complete a selected mini project.
3. CREDIT VALUE As for concrete works the method of statement for concrete which
referred is BS1881. The cement to be used throughout the work shall be
Portland cement obtained from an approved manufacturers that comply
with MS 522. Fine and coarse aggregates shall comply with MS 29. All
testing specification were referred by MS EN 206. This course also need
students to participate actively in teamwork during the practical activities.
2
4. PREREQUISITE/ None
CO-REQUISITE (IF ANY)
COURSE LEARNING OUTCOMES (CLO):
Upon completion of this course, students should be able to:
CLO1 Perform practical activities using appropriate tools and techniques for
concrete works with safety awareness. (P3, PLO5)
CLO2 Complete a selected mini project on brickworks through group
participation. (P5, PLO5)
CLO3 Participate actively in a teamwork during practical activities.
(A3, PLO9)
PROGRAMME LEARNING OUTCOMES (PLO):
PLO 5 : Modern Tool Usage: Apply appropriate techniques, resources, and modern engineering and IT
tools to well-defined engineering problems, with an awareness of the limitations (DK6); ET -
ENGINEERING TOOL
PLO 9 : Individual and Team Work: Function effectively as an individual, and as a member in diverse
technical teams; (IT-INDIVIDUAL & TEAMWORK)
ASSESSMENT METHOD:
The course assessment consist of:
i. Continuous Assessment (CA) – 100%
6. ii. Final Examination (FE) – None
Assessment Quantity Percentage (%) Approach
Workshop Practical 2 50 % Face to Face - Labwork
2 50 % Face to Face - Labwork
Project
TEACHING SCHEDULE:
Topic Topic/Content Recommended Assessment Week
No. Contact Hours Method
W1
INTRODUCTION OF CIVIL ENGINEERING 24 None W2 – W14
(3 hrs Lecture W2 – W14
LABORATORY
per week)
1.0 This topic introduces the students to the
knowledge and preparation before
conducting any laboratory works.
BRICKWORKS
This topic covers about Stretcher Bond 24
2.0 brickwork, English Bond, Flemish Bond and (3 hrs Lecture Project
wall plastering work. per week)
7. CONCRETE WORKS AND LABORATORY 24 Workshop
3.0 This topic covers the testing of cement, sand (3 hrs Lecture Practical
and aggregate, fresh concrete and hardened
per week)
concrete in the laboratory (Compressive
Strength Test Cubes).
REFERENCES Main reference supporting the course
8. British Standards 1881 (2015). Testing Concrete. The British Standard
Institution.
Prepared by: Colin Fearn . et. al. (2014). The City & Guilds Textbook: Level 1 Diploma in
Plastering. City & Guilds.
Jon Collinson, (2012). Brickwork and Bricklaying: A DIY Guide. Crowood
Press.
https://www.astm.org/Standards/cement-and-concrete-standards.html
Malaysian Standard EN 206 (2016). Concrete – Specification, Performance,
Production and Conformity (Third Revision). Department Of Standard
Malaysia.
Additional references supporting the course
Peter Cartwright, (2002). Bricklaying. McGraw-Hill Education.
P. Kumar Mehta and Paulo J.M. Monteiro, (2014), Concrete: Microstructure,
Properties and Materials, 4th Edition. McGraw Hill.
Theodore Marotta. et. all. (2010). Basic Construction Materials (8th ed.),
UnitedKingdom. Pearson Prentice Hall.
R. Dodge Woodson, (2011). Concrete Portable Handbook. Butterworth-
Heinemann..
Verified by :
……………….………………………… …………………………………………………….
(Tandatangan dan Nama Pensyarah Kursus) ( Tandatangan dan Nama TP(A)/TP/KJ/KPro/KUPA/KK )
KHAIRUNNISA ISLAMI BINTI AMBOTOLA Date : MOHD AZMAN BIN MOHD NOOR
Pensyarah DH44 Ketua Program
Jabatan Kejuruteraan Awam Diploma Kejuruteraan Awam
Politeknik Kota Kinabalu Jabatan Kejuruteraan Awam
Date : Politeknik Kota Kinabalu
DCC10022 Rubrics for Practical Work
BRICKWORKS AND CON
CLO2 - Complete a selected mini project on brickworks through PLO5 Modern tools usage : Apply appropriate techniq
group participation to well-defined engineering problems, wit
Description of This rubrics is designed to assess practical w
Rubrics
Criteria POOR (1) FAIR (2) MOD
Taxonomy
Domain/Level Ability to recognize the nec
P1 Usage of Tools Student i s not a bl e to both Student knows a nd i s a bl e to Student knows a n
i denti fy a nd us e tool s i denti fy neces s a ry tool s for neces s a ry tool s f
compl eti on of the ta s k wi thout ta s k wi th s ome a
ma jor prompti ng
Ability to display the approp
P2 Housekeeping Very proa cti ve a nd s how good Proa cti ve a nd s how good i ni ti a ti ves Show a ccep
i ni ti a ti ves of neces s a ry of neces s a ry i nforma ti on / theory / i nforma ti on / t
ma teri a l s etc bef
i nforma ti on / theory / l a b l a b s heet / ma teri a l s etc before
s heet / ma teri a l s etc before produci ng a vi deo pres enta ti on p re s
produci ng a vi deo pres enta ti on
Ability to display adequate s
P3 La bora tory Mea s urements , s ki l l s or Mea s urements , s ki l l s or techni ques Mea s urements ,
Techni que techni ques a re i ncompl ete, a re s omewha t i na ccura te a nd a re mos
i mpreci s e.
i na ccura te a nd/or very
i mpreci s e
P3 Qua l i ty of Work Provi de compl ete ta s k/project Provi de compl ete ta s k/project wi th 4 Provi de compl et
or less
wi th more tha n 4 requi rement or l es s requi rement
Ability to construct
Not genui ne res ul ts wi th too Not genui ne res ul ts wi th too fa r Not genui ne re
P3 Di s pl a y of fa r from theoreti ca l predi cti on. from theoreti ca l predi cti on. from theore
Res ul ts Outcomes a re i ncl uded but not Outcomes a re i ncl uded but mi s s i ng Outcomes a re i n
label the i mporta nt l a bel s som
Ability to display adequate safety c
P3 Sa fety Cul ture Proper s a fety preca uti ons a re Proper s a fety preca uti ons a re often Proper s a fety
cons i s tentl y mi s s ed; mi s s e d genera l
ks (Concrete Laboratory)
NCRETE LABORATORY ASSESSMENT TOOL (%) : PRACTICAL WORKS (40%)
DP1 : Depth of Knowledge Required
que, resource and modern engineering and IT tools DP3 : Can Be Solved in Standardized Ways
th an awareness of the limitations (DK 6) DP5 : Extend of Applicable Codes
DK6 : Practical Engineering Knowledge
works for Concrete Laboratory Works
DERATE (3) GOOD (4) EXCELLENT (5) MARKS
/5
cessary tools and use to complete the task Student knows a nd a bl e to
i denti fy neces s a ry tool s to
nd i s a bl e to i denti fy Student knows a nd i s a bl e to i denti fy compl ete the ta s k
for compl eti on of the neces s a ry tool s for compl eti on of the
a s s i s ta nce ta s k wi th l es s a s s i s ta nce
priate response after completing the task
pta bl e neces s a ry Show few neces s a ry i nforma ti on / La ck of neces s a ry i nforma ti on / /5
theory / l a b s heet / theory / l a b s heet / ma teri a l s etc before theory / l a b s heet / ma teri a l s etc
fore produci ng a vi deo
s enta ti on produci ng a vi deo pres enta ti on before produci ng a vi deo
pres enta ti on
skills and precision to complete the task
Mea s urements , s ki l l s or
, s ki l l s or techni ques Mea s urements , s ki l l s or techni ques a re techni ques a re both a ccura te a nd /5 x 2
s tl y a ccura te. /5
a ccura te wi th rea s ona bl e preci s i on preci s e a nd ma y s how s ome
i nnova ti on.
te ta s k/project wi th 2 Provi des hi gh qua l i ty work wi th 1 or l es s Provi des work of hi gher qua l i ty
requi rement requi rement wi th no requi rement
diagrams/ tables/ graphs/ models
s ul ts but not too fa r A good genui ne res ul ts wi th rel eva nt An excel l ent genui ne res ul ts wi th /5
eti ca l predi cti on. from theoreti ca l predi cti on. rel eva nt from theoreti ca l /5
ncl uded but mi s s i ng predi cti on
me labels Cl ea r a nd rel i a bl e outcomes but
missing some labels Cl ea r a nd rel i a bl e outcomes wi th
compl ete l a bel s
culture/behavior throughout the practical session
Proper s a fety preca uti ons a re
y preca uti ons a re Proper s a fety preca uti ons di s pl a yed di s pl a yed very cons i s ta ntl y
l l y di s pl a yed mos t of the ti me
TOTAL /35 *40 %
4
DCC10022 Rubrics for Mini Pr
BRICKWORKS AND CO
CLO2 - Complete a selected mini project on brickworks PLO5 Modern tools usage : Apply appropriate techn
through group participation well-defined engineering problems, wi
Description of This rubrics is designed to asses
Rubrics
Criteria POOR (1) FAIR (2) MODER
Taxonomy
Domain/Level Student i s not a bl e to both Ability to recognize the nec
i denti fy a nd us e tool s
P1 Us a ge of Tool s Student knows a nd i s a bl e to Student knows a nd
Una ccepta bl e l evel i ng i denti fy neces s a ry tool s for neces s a ry tool s for
Una ccepta bl e a ngl e a t ri ght compl eti on of the ta s k wi thout
ta s k wi th s om
and left ma jor prompti ng
Ability to display com
P3 Fi ni s h & Wa l l cons tructed i s not l evel ed Wa l l cons tructed i
Appea ra nce Angl e a t ri ght a nd l eft i s not Angl e a t ri ght a nd
correct wi th l a rge number of
e rro rs wi th l a rge num
P5 Comformi ty La y bri ck not a ccordi ng to La y bri ck a ccordi ng to dra wi ng La y bri ck a ccordi n
dra wi ng. but not aligned. modera tel
Ability to perform sk
P5 Accura cy/ Mea s urements , s ki l l s or Mea s urements , s ki l l s or Mea s urements , s k
Preci s i on techni ques a re i ncompl ete, techni ques a re s omewha t a re mos tl y
i na ccura te a nd/or i mpreci s e i na ccura te a nd very i mpreci s e.
P5 Qua l i ty of Work Provi des work of poor qua l i ty Provi des work of fa i r qua l i ty Provi des work of m
(hori zonta l a nd verti ca l s pa n) (hori zonta l a nd verti ca l s pa n) (hori zonta l a nd
Ability to display safety culture/
P5 Sa fety Proper s a fety preca uti ons a re Proper s a fety preca uti ons a re Proper s a fety preca u
cons i s tentl y mi s s ed;
often mi s s ed displa
roject (Brickworks)
ONCRETE LABORATORY ASSESSMENT TOOL (%) : MINI PROJECT (40%)
DP1 : Depth of Knowledge Required
nique, resource and modern engineering and IT tools to DP3 : Can Be Solved in Standardized Ways
ith an awareness of the limitations (DK 6) DP4 : Familiarity of Issues
DK6 : Practical Engineering Knowledge
ss a mini project for Brickworks
RATE (3) GOOD (4) EXCELLENT (5) MARKS
cessary tools and use to complete the task
i s a bl e to i denti fy Student knows a nd i s a bl e to i denti fy Student knows a nd a bl e to /5
r compl eti on of the neces s a ry tool s for compl eti on of the ta s k i denti fy neces s a ry tool s to
me a s s i s ta nce
wi th l es s a s s i s ta nce compl ete the ta s k
mpetence during completion of task
i s nea r to l evel ed Wa l l cons tructed i s a l mos t l evel ed Wa l l cons tructed i s l evel ed /5
l eft i s not correct Angl e a t ri ght a nd l eft i s a l mos t correct wi th Angl e a t ri ght a nd l eft i s correct
mber of errors
very few errors
ng to dra wi ng but La y bri ck a ccordi ng to dra wi ng but s l i ghtl y La y bri cks a ccordi ng to dra wi ng /5
ly aligned. a l i gne d. a nd perfectl y a l i gned.
killfully with precision and accuracy
i l l s or techni ques Mea s urements , s ki l l s or techni ques a re Mea s urements , s ki l l s or /5 (x2)
y a ccura te. a ccura te wi th rea s ona bl e preci s i on techni ques a re both a ccura te a nd /5
/5
preci s e a nd ma y s how s ome
i nnova ti on.
modera te qua l i ty Provi des work of good qua l i ty (hori zonta l Provi des work of hi gher qua l i ty
d verti ca l s pa n) a nd verti ca l s pa n) (hori zonta l a nd verti ca l s pa n)
/behavior throughout the project completion
uti ons a re genera l l y Proper s a fety preca uti ons di s pl a yed mos t of Proper s a fety preca uti ons a re
di s pl a yed very cons i s ta ntl y
a yed the ti me
TOTAL /35 *40 %
5
DCC10022 Rubrics for Individu
BRICKWORKS AND CONCRET
CLO3 - Participate actively in a teamwork during practical activities PLO9 Individual and Teamwork: Function effective
diverse technical t
Description of This rubrics is designed to assess practical works and min
Rubrics
Criteria POOR (1) FAIR (2)
Taxonomy Ini ti a ti ve
Domain/Level INDIV
Ability to show great initiativ
A3
La ck of i ni ti a ti ve a nd ha ve l es s Show few i ni ti a ti ves to provi de the Show a ccept
i nters t on tea m engga gement
needed hel p for the tea m s a ti s fa cti on the needed
and enggagement s a ti s fa cti on
A2 He l pful ne s s Not helpful Helpful when asked Very hel pful
Ability to complete work with the qu
A3 Qua l i ty of Work La ck of qua l i ty work produced Produced qua l i ty of work bel ow Produce a cce
mi ni mun s ta nda rd wi thi n the m
TEAM
Ability to share
A3 Tea mwork Tea m demons tra ted l i tl e Tea m demons tra ted fa i rl y tea mwork. Tea m s howe
tea mwork.
Work Di s tri buti on Mos t work wa s done by 1 Mos t work wa s done by 1 or 2 member Team memb
member of tea m. of tea m. ta s k equa l l y
a bi l i ti es of e
ual and Teamwork ASSESSMENT TOOL (%) : MINI PROJECT/ PRACTICAL WORKS (10%)
TE LABORATORY
ely as an individual, and as member in
teams
ni project for Brickworks and Concrete Laboratory
MODERATE (3) GOOD (4) EXCELLENT (5) MARKS
VIDUAL ASSESSMENT /5
/5
ves and actively involved in a team engagement /5
ta bl e i ni ti a ti ves to provi de proa cti ve a nd s how good i ni ti a ti ves Very proa cti ve a nd s how grea t /5
i ni ti a ti ve to provi de the needed hel p /5
hel p for the tea m to provi de the needed hel p for the for the tea m s a ti s fa cti on a nd /25 *10 %
and engagement tea m s a ti s fa cti on a nd enga gement e nga ge me nt
l s ometi mes Very hel pful mos t of the ti me Very hel pful a l l the ti me
uality of work that reflects the expected achievements
epta bl e qua l i ty work Produced good qua l i ty a ccordi ng to Produce hi gh qua l i ty work beyond the
mi ni mum s ta nda rd
the qua l i ty s ta nda rd requi red s ta nda rd
MWORK ASSESSMENT Tea m s howed excel l ent tea mwork.
e tasks to complete the team goal
ed modera te tea mwork. Tea m s howed good tea mwork.
bers s el doml y s ha red the Mos t members s ha red the ta s k Al l tea m members s ha red the ta s k
y a nd di d not uti l i ze
ea ch tea m member equa l l y a nd uti l i ze a bi l i ti es of ea ch equa l l y a nd uti l i zi ng a bi l i ti es of ea ch
tea m member. tea m member.
TOTAL
6
CIVIL ENGINEERING DEPARTMENT
POLITEKNIK KOTA KINABALU
CONCRETE
LABORATORY
[ SIEVE ANALYSIS TEST ]
Name Matric Number
GROUP MEMBERS
Name Matric Number
Prepared by :
KHAIRUNNISA ISLAMI BINTI AMBOTOLA & NORIKA BINTI KARIM
LECTURER
CIVIL ENGINEERING DEPARTMENT
POLITEKNIK KOTA KINABALU
7
DCC 10022 – BRICKWORKS AND CONCRETE LABORATORY
SIEVE ANALYSIS TEST
OBJECTIVE
To determine the particle size distribution in a sample of aggregate which is called
gradation.
PURPOSE
To achieve high level of strength for concrete, good workability of aggregates contained in
the concrete mixture has to be graded. So that the size of aggregate contained within the
concrete mix has the right proportion and achieves the fixed limit.
THEORY
The aggregate being used in a concrete mixture must be three times the volume of
concrete. Aggregate can have an influence on the characteristics of concrete such as
durability and workability. The use of aggregate can make concrete more stable and last
longer. Aggregates are classified into two categories :-
i. Fine aggregates/sand - Passing sieve 5 mm Ø
ii. Coarse aggregates - Retained sieve 5 mm Ø
According to MS 30 phase D (i) and (ii) sets the content and size of aggregates that must be
present in a concrete mix base on the grading limit, such as JKR/QC/AO2/89.
This method describes the procedure for determining the relationship between the
particle size distribution of fine and coarse aggregate. The aggregate most of which passes
IS 475mm sieve is classified as fine aggregate and retained on 4.75mm sieve is classified as
coarse aggregate can be obtained. A sample may be well graded, poorly graded or uniformly
graded.
8
DCC 10022 – BRICKWORKS AND CONCRETE LABORATORY
APPARATUS
1. Pan Balance 2. Sieve Set 3. Mechanical Sieve Shaker
4. Container – Pan 5. Aggregate 6. 500 gm of sand
PROCEDURE
1. Obtain a sample from plant or as otherwise directed and mix sample well.
2. Nest the sieves with the finest sieve above the bottom pan and the coarsest sieve at the
top.
3. Weigh and note the starting weight of each sieve. Place the sample in the top sieve of a
stack of sieve.
4. Shake the stack for 10 minutes at a preset speed.
5. When shaking is complete, take each sieve one at a time and weigh this segment of
sample.
6. Record the weight and calculate the percent of sample remaining in each sieve.
7. Repeat the same procedure for the different material i.e. sand/aggregate.
9
DCC 10022 – BRICKWORKS AND CONCRETE LABORATORY
RESULT (EXAMPLE OF CALCULATION)
1. Table of Calculation
Sieve Sieve Sieve + Weight Cumulative Cumulative Cumulative
Size Weight Aggregate Retained Weight % Weight Percentage
Retained Retained
Weight Passing
20 mm 00 0 100
14 mm 00 0 100
10 mm
6.3 mm 6 6 ((6/15)*100) (100-40)
2.35 mm = 40 = 60
Pan 5 (6+5) = 11 ((11/15)*100) (100-73.3)
= 73.3 = 26.7
4 (11 + 4) = ((15/15)*100) (100-100) =
15 = 100 0
- - 100 0
TOTAL 15 KG 313.3 0
2. Fineness Modulus
Fineness Modulus can be used to indicate the fineness of aggregate/sand.
Types Fineness Modulus (FM)
Fine Sand 2.2 – 2.6
Medium Sand 2.6 – 2.9
Coarse Sand 2.9 – 3.2
Fineness Modulus = Cumulative Percentage Weight Retained
100
10
DCC 10022 – BRICKWORKS AND CONCRETE LABORATORY
RESULT
Sieve Size Sieve Sieve + Weight Cumulative Cumulative Cumulative
Weight Aggregate Retained Weight % Weight Percentage
Retained Retained Passing
Weight
20 mm
14 mm
10 mm
6.3 mm
2.35 mm
Pan
TOTAL
Fineness Modulus = Cumulative Percentage Weight Retained
100
=
11
DCC 10022 – BRICKWORKS A
AND CONCRETE LABORATORY
12
DCC 10022 – BRICKWORKS AND CONCRETE LABORATORY
DISCUSSION
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
CONCLUSION
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
13
DCC 10022 – BRICKWORKS AND CONCRETE LABORATORY
QUESTION
1. Why it is not suitable for all concrete mixture when the amount of fine aggregate and
coarse aggregate is fixed?
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
2. What is the importance of aggregate sieve test?
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
14
DCC 10022 – BRICKWORKS AND CONCRETE LABORATORY
Name : _____________________________________________
Reg. No. : _____________________________________________
Lab : _____________________________________________
Date : _____________________________________________
REFLECTION MARKING RUBRIC
No. Criteria Excellent Good Moderate Fair Unsatisfactory
4. Reflection 10 8 6 4 2
✓ The ability to ✓ The ability to ✓ The ability to ✓ The ability to ✓ The ability to
demonstrate a demonstrate a demonstrate a perform a basic perform a
thorough good sufficient understanding limited
understanding of understanding understanding of the practical understanding of
the practical work. of the practical of the practical work. the practical
work. work. work
REFLECTION
Write a reflection according to your practical work. Your reflection must include the following items:
1. Today’s accomplishment
2. The significance /importance of the practical work
3. The obstacles encountered during practical work.
A reflection must be submitted at the end of practical session.
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
Checked by :-
15
CIVIL ENGINEERING DEPARTMENT
POLITEKNIK KOTA KINABALU
CONCRETE
LABORATORY
[ SAND SEGREGATION TEST ]
Name Matric Number
GROUP MEMBERS
Name Matric Number
Prepared by :
KHAIRUNNISA ISLAMI BINTI AMBOTOLA & NORIKA BINTI KARIM
LECTURER
CIVIL ENGINEERING DEPARTMENT
POLITEKNIK KOTA KINABALU
16
DCC 10022 – BRICKWORKS AND CONCRETE LABORATORY
SAND SEGREGATION TEST
OBJECTIVE
This test is to determine the bulking factor of wet sand.
PURPOSE
When mixes are specified by volume, the sand is assumed to be dry. The volume of a given
weight of sand, however, varies according to its moisture content. Equal weights of dry and
inundated sand have practically the same volume but the same weight of sand in a damp
condition can occupy a volume as much as 40% greater. This phenomenon is known as 'bulking'.
THEORY
BS 1881 stated that the moisture content in the sand will cause the bulking of the volume.
Moisture forms a film around each particle and this film of moisture exerts surface tension which
keeps the neighbouring particles away from it. Therefore, when no point contact is possible
between the particles, this causes bulking of sand.
APPARATUS
500 ml measuring cylinder Stirring Rod
Tray
Scoop
17
DCC 10022 – BRICKWORKS AND CONCRETE LABORATORY
PROCEDURE
1. Fill the cylinder with water until 100 ml.
2. Slowly add some sand into the cylinder until water level increase to 150 ml.
3. Shake slightly the cylinder and put it aside in rest condition for 3 hours to allow
sedimentation.
4. Record the height of silt appears above the sand.
DIAGRAM
RESULT
No. of Sampel A B C D
Silt (ml)
Sand (ml)
Percentage of Silt
(%)
Average % of Silt (%)
Note : Sand is consider clean if content of turbidity is not exceed 8% (MS 30)
Percentage of Silt Content = Height of Silt (ml) x 100
Height of Sand (ml)
18
DCC 10022 – BRICKWORKS AND CONCRETE LABORATORY
DISCUSSION
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
CONCLUSION
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
19
DCC 10022 – BRICKWORKS AND CONCRETE LABORATORY
QUESTION
1. Why shall the test be carried out?
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
2. When shall the test be carried out?
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
20
DCC 10022 – BRICKWORKS AND CONCRETE LABORATORY
Name : _____________________________________________
Reg. No. : _____________________________________________
Lab : _____________________________________________
Date : _____________________________________________
REFLECTION MARKING RUBRIC
No. Criteria Excellent Good Moderate Fair Unsatisfactory
4. Reflection 10 8 6 4 2
✓ The ability to ✓ The ability to ✓ The ability to ✓ The ability to ✓ The ability to
demonstrate a demonstrate a demonstrate a perform a basic perform a
thorough good sufficient understanding limited
understanding of understanding understanding of the practical understanding of
the practical work. of the practical of the practical work. the practical
work. work. work
REFLECTION
Write a reflection according to your practical work. Your reflection must include the following items:
1. Today’s accomplishment
2. The significance /importance of the practical work
3. The obstacles encountered during practical work.
A reflection must be submitted at the end of practical session.
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
Checked by :-
21
CIVIL ENGINEERING DEPARTMENT
POLITEKNIK KOTA KINABALU
CONCRETE
LABORATORY
[ CONCRETE MIXTURE ]
Name Matric Number
GROUP MEMBERS
Name Matric Number
Prepared by :
KHAIRUNNISA ISLAMI BINTI AMBOTOLA & NORIKA BINTI KARIM
LECTURER
CIVIL ENGINEERING DEPARTMENT
POLITEKNIK KOTA KINABALU
22
DCC 10022 – BRICKWORKS AND CONCRETE LABORATORY
CONCRETE MIXTURE
OBJECTIVE
This Section describes the methods for the preparation of materials and the batching, mixing and
sampling of concrete in the laboratory.
PURPOSE
Batch is the quantity of concrete mixed in one cycle of operations of a mixer or the quantity
mixed by hand in one cycle of operations.
The purpose of concrete mix design is to ensure the most optimum proportions of the
constituent materials to fulfil the requirement of the structure being built. Mix design should
ensure following objectives –
• To achieve the designed/ desired workability in the plastic stage
• To achieve the desired minimum strength in the hardened stage
• To achieve the desired durability in the given environment conditions
• To produce concrete as economically as possible.
THEORY
Cement concrete mix design means, determination of the proportion of the concrete ingredients
i.e. cement , water, fine aggregate, coarse aggregate which would produce concrete possessing
specified properties such as workability, strength and durability with maximum overall economy.
MATERIAL
23
DCC 10022 – BRICKWORKS AND CONCRETE LABORATORY
PROCEDURE
1. For strength requirements, select the water to cement ratio by weight.
2. Before mixing concrete, be sure that the mixer has been "buttered" with a mixture of
cement, sand, and water.
3. Divide your water into two buckets, one with about 3/4 of the water. Put about half the
coarse aggregate and the 3/4-bucket of water.
4. Start the mixer.
5. Add about half the fine aggregate.
6. Carefully add all the cement with the mixer running. Try not to make a lot of dust!
7. Mix until all the cement is blended in.
8. Add the rest of the coarse and fine aggregate.
9. Mix for a while.
10. Add enough water from the final quarter of the water to produce a workable mix.
11. Mix for three minutes, followed by a three-minute rest, followed by a two-minute final
mixing.
12. Perform a slump test using the procedure given.
24
DCC 10022 – BRICKWORKS AND CONCRETE LABORATORY
MIX DESIGN
Concrete mix design are often given by ratio ----- cement : fine aggregate : coarse aggregate
Material Cement Fine Aggregate Coarse Aggregate
Ratio 1 1.5 3
Weight
4.8 kg 7.2 kg 14.4 kg
The Water Cement Ratio
Too much water and not enough cement means concrete will be weaker and less durable.
The water to cement ratio (W/C) is the weight of the water divided by the weight of cement.
The lower the ratio, the stronger the concrete.
SAMPLING AND CONCRETE TESTING
Tests on fresh concrete and the preparation of specimens for tests on hardened concrete shall
start as soon as possible after completion of mixing. The required operations shall be carried
out during a period of not more than one hour from the addition of the water to the cement.
The fresh concrete shall be protected against gaining or losing water. Provided that care is
taken to ensure that no water or other material is lost, the concrete used in workability and
density tests may be remixed with the remainder of the batch before making any specimen
for testing hardened concrete. The period of remixing should be as short as possible but
sufficient to produce a homogeneous mass.
Slump Test 3 samples
Cube Test 3 cubes
25
CIVIL ENGINEERING DEPARTMENT
POLITEKNIK KOTA KINABALU
CONCRETE
LABORATORY
[ SLUMP TEST ]
Name Matric Number
GROUP MEMBERS
Name Matric Number
Prepared by :
KHAIRUNNISA ISLAMI BINTI AMBOTOLA & NORIKA BINTI KARIM
LECTURER
CIVIL ENGINEERING DEPARTMENT
POLITEKNIK KOTA KINABALU
26
DCC 10022 – BRICKWORKS AND CONCRETE LABORATORY
SLUMP TEST
OBJECTIVE
Concrete slump test is to determine the workability or consistency of concrete mix prepared at
the laboratory or the construction site during the progress of the work. Concrete slump test is
carried out from batch to batch to check the uniform quality of concrete during construction.
PURPOSE
Get the consistency of concrete mix by measuring the slump after deformed as a frustum cone in
the site or laboratory to assure that the concrete mix components ratios are accurate. It is the
simplest test to achieve concrete quality control in mixing stations and in the sites.
THEORY
Generally concrete slump value is used to find the workability, which indicates water-cement
ratio, but there are various factors including properties of materials, mixing methods, dosage,
admixtures etc. also affect the concrete slump value.
Under the BS 1881, there are 3 methods to test the workability of concrete mixture. This method
gives the indication of the quality of concrete with respect to consistency, cohesiveness and the
proneness to segregation. The workability of concrete alone cannot assure the quality because it
depends on the compacting method either by hand or vibrator.
APPARATUS
27
PROCEDURE
1. Before commencing the test, the plat base and inner surface of the mould is wiped with
a damp cloth.
2. The slump cone is placed centrally on the plate with the small opening facing upward.
3. The slump cone is filled with concrete in 3 layers, each layer tamped lightly 25 times with
steel rod in definite pattern, working from outside into the middle.
4. Top up the cone till it overflows. Level off the surface with the steel rod using a rolling
action.
5. Cleaned off the plate base from any of concrete excess.
6. The cone is slowly raised vertically by the handles and allowed to fall in 5 to 10 seconds.
7. Turn the cone upside down and place the rod across the up-turned cone.
8. The slump is measured by using the ruler (difference in level between the height of the
mould and that of the highest point of the subsided concrete).
9. All slumps must be measured and recorded (if the sample slumping still persist due to
shear/collapse the test should be repeated).If the slump still persist, measure the height
and types of the slump.
10. Repeat the above procedure by using different water cement ratio.
NOTE:
The above operation should be carried out at a place free from Vibrations or shock and within
a period of 2 minutes after sampling.
28
DCC 10022 – BRICKWORKS AND CONCRETE LABORATORY
DIAGRAM
Types of Concrete Slump Test Result
Consistency Slump (mm)
Very Dry 0
Very Stiff
Stiff 0-15
Plastic Stiff 15-25
Plastic 25-50
Liquid 50-100
100-150
Very Liquid 150-200
29
DCC 10022 – BRICKWORKS AND CONCRETE LABORATORY
RESULT
The slump (Vertical settlement) measured shall be recorded in terms of millimetres of
subsidence of the specimen during the test.
Test No. Concrete Water- Slump (mm) Consistency Shape
Proportion Cement Ratio
1
2
3
Average
30
DCC 10022 – BRICKWORKS AND CONCRETE LABORATORY
DISCUSSION
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
CONCLUSION
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
31
DCC 10022 – BRICKWORKS AND CONCRETE LABORATORY
QUESTION
1. What is the ideal value of slump?
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
2. How much time one should take to raise the cone?
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
3. Explain types of concrete slump test below.
True Slump
Zero Slump
Collapsed Slump
Shear Slump
32
DCC 10022 – BRICKWORKS AND CONCRETE LABORATORY
Name : _____________________________________________
Reg. No. : _____________________________________________
Lab : _____________________________________________
Date : _____________________________________________
REFLECTION MARKING RUBRIC
No. Criteria Excellent Good Moderate Fair Unsatisfactory
4. Reflection 10 8 6 4 2
✓ The ability to ✓ The ability to ✓ The ability to ✓ The ability to ✓ The ability to
demonstrate a demonstrate a demonstrate a perform a basic perform a
thorough good sufficient understanding limited
understanding of understanding understanding of the practical understanding of
the practical work. of the practical of the practical work. the practical
work. work. work
REFLECTION
Write a reflection according to your practical work. Your reflection must include the following items:
1. Today’s accomplishment
2. The significance /importance of the practical work
3. The obstacles encountered during practical work.
A reflection must be submitted at the end of practical session.
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
Checked by :-
33
CIVIL ENGINEERING DEPARTMENT
POLITEKNIK KOTA KINABALU
CONCRETE
LABORATORY
[ COMPRESSIVE STRENGTH TEST ]
Name Matric Number
GROUP MEMBERS
Name Matric Number
Prepared by :
KHAIRUNNISA ISLAMI BINTI AMBOTOLA & NORIKA BINTI KARIM
LECTURER
CIVIL ENGINEERING DEPARTMENT
POLITEKNIK KOTA KINABALU
34
DCC 10022 – BRICKWORKS AND CONCRETE LABORATORY
COMPRESSIVE STRENGTH OF
CONCRETE CUBES
OBJECTIVE
To determine the strength and workability of concrete mixture.
PURPOSE
Concrete is used mostly for structural purposes such as foundations, columns, beams and floors
and therefore must be capable in taking the loads that will be applied (unless you’re just after a
large paperweight!). One of the methods of checking its fit for purpose is to carry out a concrete
cube test which measures the compressible cube strength of the concrete and relates directly to
the required design strength specified by the designer. Also is it is usually a minimum
requirement from the client to provide evidence of cube test results to ensure compliance with
the designers requirements.
THEORY
To determine the concrete fulfils the required specification, 2 types of testing to be conducted
are Wet Concrete Testing such as slump, compacting factor and Vebe Consistency while hard
concrete testing such as cube test and beam flexural strength. Hard concrete test were
conducted at the age of 3, 7, 14, 21 and 28 days after curing. The concrete strength increases
according to the age and the strength increment will continue for sometimes.
Nevertheless, for most of the work, the concrete strength on the 28 days is set as standard even
though it might be determined at a much earlier or longer period. The increment rate of the
concrete strength will depend on the temperature and moisture during hardening process.
APPARATUS
35
DCC 10022 – BRICKWORKS AND CONCRETE LABORATORY
PROCEDURE
1. The mould that will be used in the cube test must be cleaned internally using the wire
brush.
2. The interior surfaces of the assembled mould is required to be thinly coated with grease
oil to prevent adhesion of concrete.
3. Pour the ready mixed concrete with certain mix proportion into the mould in 3 layers and
each layer must be tamping 25 times using the compacting steel rod .Fill up the mould
until overflow and levelled the surface using the hand float.
4. The concrete will be left for 24 hours setting.
5. Record the date of the mixture for every cube and submerged all the 3 cube in the curing
tank at the temperature of 18 degree Celsius – 20 degree Celsius and test on the 7, 14
and 28 days.
6. Before placing in the water, the cube must be weighted while it is dry and record.
7. When the cube is fully matured it shall be weighted again and record.
8. Place the cube to be tested at the center plate of the compression machine. Ensure both
plates are in contact with the lower surface of the concrete plate. Release the load valve
to raise up the bottom plate until the cube touch the above plate. Record the maximum
load that will crush the tested cube.
9. Repeat the above step using the other cubes. Record the result accordingly.
Calculation and Expression of Result
Calculate the cross-section area of the cube face from the measured dimension. Calculate the
compressive strength of each by dividing the maximum load by the cross-sectional area.
DIAGRAM
36
DCC 10022 – BRICKWORKS A
RESU
Cube Size : 150 mm x
Cube Date of Date of Age During Cube
No. Cube Made Testing Testing
1
2
3
AND CONCRETE LABORATORY
ULT
x 150 mm x 150 mm
e Weight Fail Load (kN) Compressive Failure Diagram
(kg)
Strength
(kN/mm2)
37
DCC 10022 – BRICKWORKS AND CONCRETE LABORATORY
DISCUSSION
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
CONCLUSION
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
38
DCC 10022 – BRICKWORKS AND CONCRETE LABORATORY
QUESTION
1. Why the inner surface of the mould shall be coated with the grease oil?
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
2. How can the value of standard deviation describe the strength and quality of the
concrete?
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
39
DCC 10022 – BRICKWORKS AND CONCRETE LABORATORY
Name : _____________________________________________
Reg. No. : _____________________________________________
Lab : _____________________________________________
Date : _____________________________________________
REFLECTION MARKING RUBRIC
No. Criteria Excellent Good Moderate Fair Unsatisfactory
4. Reflection 10 8 6 4 2
✓ The ability to ✓ The ability to ✓ The ability to ✓ The ability to ✓ The ability to
demonstrate a demonstrate a demonstrate a perform a basic perform a
thorough good sufficient understanding limited
understanding of understanding understanding of the practical understanding of
the practical work. of the practical of the practical work. the practical
work. work. work
REFLECTION
Write a reflection according to your practical work. Your reflection must include the following items:
1. Today’s accomplishment
2. The significance /importance of the practical work
3. The obstacles encountered during practical work.
A reflection must be submitted at the end of practical session.
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
Checked by :-
40