The main civil contractor in the Abu Dhabi project parties is the owner, the engineer, and the contractor. The owner requirements are intimated to engineers

Discover the best professional documents and content resources in AnyFlip Document Base.
Search
Published by royalclassic.ae, 2021-06-22 02:55:59

Construction Civil Contractors

The main civil contractor in the Abu Dhabi project parties is the owner, the engineer, and the contractor. The owner requirements are intimated to engineers

Keywords: Construction Civil Contractors

Construction Civil Contractors

The main civil contractor in the Abu Dhabi project parties is the
owner, the engineer, and the contractor. The owner requirements are
intimated to engineers, who in turn, guide the owner in the mode of
construction civil, keeping in view the minimum safety requirements,
shortest possible period of completion, and minimum cost of
construction civil. A good proposal can be achieved by a team of
construction engineers, architects, general contractors, specialty
contractors, manufacturers, materials dealers, equipment distributors,
government bodies, and agencies.

The construction civil engineers' primary duty is to exercise quality
control during the execution of the project. Depending on the nature
of the work, a number of types of contracts are used in the building
industry. In projects where the execution of work is to be carried out
by the use of construction civil equipment, the following three types of
contracts are more popular.

1. Lump sum Contract

In this type of contract, all the details of the project have to be
properly designed and evaluated before the contractor is asked to
tender his rate. Hence this is the best type of contract. In this
contract, the owner pays a fixed sum of money for the complete
project. Thus, if the same type of construction is to be repeated time
and again and full details of the work are available then a lump sum
contract is most suitable.

2. Unit-Price Contract

In this contract, the contractor is asked to execute the various items
of work specified in the schedule at the tendered rates. The
contractor receives payment at specified intervals during the

execution of the work depending upon the value of work executed. This
type of contract is most common because it is possible to prepare
approximate quantities of various items of work on the basis of
complete measurement of similar structures.

3. Cost plus a Fixed Percentage Contract

In this contract, the contractor is required to execute the work as per
plans, specifications, and drawings which form the part of the contract
bond. The payment is made to the contractor on the basis of on-site
costs incurred by the contractor.

Source: https://royalclassicuae.blogspot.com/2021/06/construction-civil-contractors.html