JANUARY 13, 2022 UPDATES

JANUARY 13, 2022 UPDATES

Photo taken in December 2021

BBB TASK FORCE INITIATIVES
IN CAGAYAN VALLEY

Updates as of January 13, 2022

BAMBOO ESTABLISHMENTS IN REGION 2

585 hectares BBB TARGET

CENRO TOTAL AREA NO. OF BAMBOO
PLANTATION PLANTED (ha) PLANTED
Alcala
Aparri AREA (ha)
Sanchez
Mira 150 150 30,600
Solana
PENRO Sub- 150 150 30,600
office
TOTAL 50 50 10,200

135 135 27,540 Brgy. San Agustin, Abulug, Cagayan

100 100 20,400

585 585 119,340

BAMBOO ESTABLISHMENT IN REGION 2

PARTNER AREA TARGET AREA PLANTED

LGU Lasam (ha) (ha)

123.63 123.63

LGU Gattaran 26.37 26.37
LGU Abulug 3.5 3.5
LGU Pamplona 14 14

LGU Sanchez Mira 12.5 12.5

LGU Claveria 12 12

LGU Sta Praxedes 8 8 Memorandum of Agreement for the establishment of

bamboo plantation

BAMBOO ESTABLISHMENTS IN REGION 2

PARTNER TARGET AREA AREA PLANTED
(ha) (ha)
City Government of
Tuguegarao 60 60

LGU Penablanca 40 40 Brgy. Mabuno, Gattaran, Cagayan

LGU Enrile 73.61 73.61
LGU Solana 61.39 61.39
LGU Alcala
LGU Amulung 50 50
LGU Baggao
50 50
50 50

NATURAL RESOURCES ENFORCEMENT & REGULATORY PROGRAM

LAWIN PATROL

OFFICE TARGET (km) ACCOMPLISHMENT % ACCOMPLISHMENT
PENRO Cagayan 100%
PENRO Isabela 420 420 127%
PENRO Quirino 168%
PENRO Nueva Vizcaya 370 473.21 290%

210 353.01

210 609.98

TOTAL 1,210 1,856.2 153%

Soil and Water Conservation Measures Construction Progress

100% 69% 90% 80%

Gabion in Brgy. Dalin, SWIS in Santo Nino, SWIS in San Guillermo, SWIS in Villamor,
Baggao, Cagayan San Agustin, Isabela Isabela Cabarroguis, Quirino

The soil and water conservation Improvement of access Construction of Storage Construction of Storage Tank 2 is
constructions were already on-going
completed way/trail leading to SWIS site Tank and Intake/Check dam

and delivery of sand and gravel

*Program of work/schedule of completion is until March 2022

STATUS OF EASEMENT RECOVERY AND RETRIEVAL AS OF JANUARY 7, 2022

PROVINCE TARGET DISTANCE LOTS AFFECTED STRUCTURES NO. OF MARKERS REMARKS
(km) SURVEYED (No.) /Area AFFECTED ESTABLISHED
(Area/No.) Amulung, Alcala,
(km) 2,123 markers Gattaran, Sto. Nino,
Lasam, Camalaniugan,
Cagayan 457.63 457.63 4,410 lots/ 1,254 ha/ 2,285 markers
47 Signages Solana and Iguig
3,081.642 ha 4,820 structures
433 markers/ Delfin Albano,
Isabela 824.24 824.24 3,853 lots 1.8832 ha/ 9 signages Sto.Tomas and
5 structures 494 markers/
Nueva 12 signages Tumauini
Vizcaya 34.67 86.51 1,410 lots 5.3264 ha/ 5,335 markers/
Quirino 319 structures 68 signages Santa Fe and Magat
River
TOTAL 212.11 212.11 255 lots 3.158 ha/
1,528.65 1,580.49 From Gulac to Doῆa
9,928 lot/ 1,264.3676 ha/ Imelda, Diffun

3,081.642 ha 5,144 structures 103%

100% 100% 100% 249%

Cagayan Isabela. Quirino Nueva Vizcaya

Consultation Meetings with MENROs, barangay officials, and communities on the
delineation and demarcation of easement along the tributaries of Cagayan River

Tuao, Cagayan Sto. Nino, Cagayan Aparri, Cagayan
Roxas, Isabela
Luna, Isabela Quirino, Isabela

INFORMATION, EDUCATION, AND COMMUNICATION

Issue/Concern Agreement
Residential lots
that would be Residents who will be affected by the approval of
affected by the the CLUP in Tuao will be relocated. The LGU will
program scout the relocation site as part of the task force.
Planting and
harvesting after Planting and harvesting are permitted within the
the survey legal easement, provided that the farmers or owners
keep an eye on the markers that will be installed.
Dredging of Fugu When the area will be developed in the future, all
Island structures and plantations will be demolished.

IEC conducted in the municipalities of Tuao and The DPWH recommends that Fugu Island be
Sto. Nino, Cagayan dredged since it is a sandbar. However, the
individuals who rely on it for a living would be
covered under KRA 4: Restored Sustainable
Livelihood.

UPDATES ON KRA 2: Stronger Shelter and Resilient Settlements

▪ On November 15, the groundbreaking of the
seven hectares resettlement area was
conducted by the DHSUD, DENR and LGU
Enrile, Cagayan at Sitio Dapang in Brgy. San
Roque.

• The DENR handed over the approved Gss-af-
02-001374 Resettlement Area to Mayor
Miguel Decena with the presence of officials
of DHSUD and LGU. The survey plan covers
132 lots which is now ready for One-Stop-
Shop acceptance/processing of public land
application.

WAY FORWARD

1. Implementation of the Work and Financial Plan for 2022 with a budget of
P56 Million which will cover the continuing activities of 2021 that include
hiring of forest protection officers, production of bamboo stocks, plantation
establishment, and construction of soil conservation measures

2. Conduct of assessment and planning among the members of RBBBTF and
strengthened collaboration for the continued support to the activities

3. Coordination with LGUs concerned as to affected lots subject of the
easement recovery

4. Continuous support to LGU Amulung and LGU Baggao, in coordination with
DHSUD, for the completion of the requirements for the resettlement areas

5. Mobilization of LGUs, NGAs, other stakeholders, and residents along Cagayan
River for the planting of bamboos and indigenous species

Photo taken in December 2021