Laporan Profil Gedung PAU ITB Minggu Ke-2 (Konsultan)

Discover the best professional documents and content resources in AnyFlip Document Base.
Search
Published by Khalila Naura, 2024-06-18 09:02:44

Laporan Profil Gedung PAU ITB

Laporan Profil Gedung PAU ITB Minggu Ke-2 (Konsultan)

Tahun Anggaran 2024 Tahun Anggaran 2024 LAPORAN PROFIL PELAKSANAAN REVITALISASI TAHAP 2 GEDUNG PUSAT ANTAR UNIVERSITAS (PAU) INSTITUT TEKNOLOGI BANDUNG


Nama Kegiatan : Revitalisasi Tahap 2 Gedung Pusat Antar Universitas (PAU) Institut Teknologi Bandung Nama Pekerjaan : - Pengadaan Dan Pemasangan Sistem Electronic Telephone Dan IP Door Acces Gedung PAU ITB - Pengadaan Dan Pemasangan Sistem Elektrikal Dan UPS Gedung PAU ITB - Pengadaan Dan Pemasangan Sistem Tata Udara Steril Dan Non Steril Gedung PAU ITB Lokasi Pekerjaan : Gedung PAU ITB, Jl. Tamansari No.126, Coblong, Kota Bandung, Provinsi Jawa Barat Pemberi Tugas : Satuan Kerja Pelaksanaan Prasarana Permukiman Wilayah II Jawa Barat Penyedia Jasa : PT. Panghegar Raya Teknik (Elektronik & Tata Udara) CV. Limas Aji Prakarsa (Elektrikal) Nomor Kontrak : HK 0201/Cb12.5.4/PS/31/2024 (Elektronik) HK 0201/Cb12.5.4/PS/25/2024 (Tata Udara) HK 0201/Cb12.5.4/PS/44/2024 (Elektrikal) Jangka Waktu : 180 (Seratus Delapan Puluh) hari kalender Nilai Kontrak : Rp. 3.996.466.800,- (Elektronik) Rp. 10.785.174.000,- (Tata Udara) Rp. 5.404.018.000,- (Elektrikal) PROFIL PEKERJAAN REVITALISASI TAHAP 2 GEDUNG PUSAT ANTAR UNIVERSITAS (PAU) INSTITUT TEKNOLOGI BANDUNG


PROGRESS PEKERJAAN PENGADAAN DAN PEMASANGAN SISTEM ELECTRONIC TELEPHONE DAN IP DOOR ACCES GEDUNG PAU ITB PROGRESS PEKERJAAN MINGGU LALU (MG-7) MINGGU INI (MG-8) RENCANA 11,886% 24,763% REALISASI 16,791% 25,701% DEVIASI 4,906% 0,938% WAKTU PELAKSANAAN s.d. MG-8 WAKTU PELAKSANAAN 180 HK WAKTU TERPAKAI 56 HK SISA WAKTU 124 HK NO URAIAN PEKERJAAN REALISASI MATERIAL ON SITE JUMLAH (TERPASANG + MOS) CATATAN I. LANTAI 1 1. Pekerjaan Wifi dan Data - Acces Switch (L2 Switch D2124GP 24 port 1GE UTP, support POE/POE+/Hi POE, incld. 1GE SFP uplink) - Bobot = 1,453% - Prestasi = 11,765% - - Bobot = 1,453% - Prestasi = 11,765% 1 Mounted Rack dipasang 2 unit Access Switch II. LANTAI 2 1. Pekerjaan Wifi dan Data - Acces Switch (L2 Switch D2124GP 24 port 1GE UTP, support POE/POE+/Hi POE, incld. 1GE SFP) - Bobot = 0,799% - Prestasi = 6,471% - - Bobot = 0,799% - Prestasi = 6,471% 1 Mounted Rack dipasang 1 unit Access Switch


PROGRESS PEKERJAAN PENGADAAN DAN PEMASANGAN SISTEM ELECTRONIC TELEPHONE DAN IP DOOR ACCES GEDUNG PAU ITB NO URAIAN PEKERJAAN REALISASI MATERIAL ON SITE JUMLAH (TERPASANG + MOS) CATATAN III. LANTAI 3 1. Pekerjaan Wifi dan Data - Acces Switch (L2 Switch D2124GP 24 port 1GE UTP, support POE/POE+/Hi POE, incld. 1GE SFP) - Bobot = 1,453% - Prestasi = 11,765% - - Bobot = 1,453% - Prestasi = 11,765% 1 Mounted Rack dipasang 2 unit Access Switch IV. LANTAI 7 1. Pekerjaan Wifi dan Data - Acces Point RG-AP820-L(V3) - Bobot = 2,889% - Prestasi = 7,080% - - Bobot = 2,889% - Prestasi = 7,080% Terpasang 8 unit V. LANTAI 8 1. Pekerjaan Wifi dan Data - Acces Point RG-AP820-L(V3) - Bobot = 2,166% - Prestasi = 5,310% - - Bobot = 2,166% - Prestasi = 5,310% Terpasang 6 unit 2. Telepon set IP utk staff dosen eksekutif dan staff admin kantor - Bobot = 0,085% - Prestasi = 0,847% - - Bobot = 0,085% - Prestasi = 0,847% Terpasang 1 unit


INFO GRAFIS PEKERJAAN DI LAPANGAN AREA PEKERJAAN LANTAI 1 = Area Pekerjaan Access Switch


INFO GRAFIS PEKERJAAN DI LAPANGAN AREA PEKERJAAN LANTAI 2 = Area Pekerjaan Access Switch


INFO GRAFIS PEKERJAAN DI LAPANGAN AREA PEKERJAAN LANTAI 3 = Area Pekerjaan Access Switch


INFO GRAFIS PEKERJAAN DI LAPANGAN AREA PEKERJAAN LANTAI 7 = Area Pekerjaan Access Point


INFO GRAFIS PEKERJAAN DI LAPANGAN AREA PEKERJAAN LANTAI 8 = Area Pekerjaan Access Point = Area Pemasangan Telepon set IP


DOKUMENTASI PEKERJAAN ELEKTRONIK DI LAPANGAN Pemasangan Access Switch Lantai 1 Pemasangan Access Switch Lantai 1 Pemasangan Access Switch Lantai 2 Pemasangan Access Switch Lantai 2


DOKUMENTASI PEKERJAAN ELEKTRONIK DI LAPANGAN Pemasangan Access Switch Lantai 3 Pemasangan Access Switch Lantai 3 Pemasangan Access Point Lantai 7 Pemasangan Access Point Lantai 7


DOKUMENTASI PEKERJAAN ELEKTRONIK DI LAPANGAN Pemasangan Access Point Lantai 8 Pemasangan Access Point Lantai 8 Pemasangan Access Point Lantai 8 Pemasangan Telepon set IP Lantai 8


PROGRESS PEKERJAAN PENGADAAN DAN PEMASANGAN SISTEM ELEKTRIKAL DAN UPS GEDUNG PAU ITB PROGRESS PEKERJAAN MINGGU LALU (MG-5) MINGGU INI (MG-6) RENCANA 4,260% 8,661% REALISASI 7,065% 9,444% DEVIASI 2,805% 0,782% WAKTU PELAKSANAAN s.d. MG-6 WAKTU PELAKSANAAN 180 HK WAKTU TERPAKAI 42 HK SISA WAKTU 138 HK NO URAIAN PEKERJAAN REALISASI MATERIAL ON SITE JUMLAH (TERPASANG + MOS) CATATAN I. LANTAI BASEMENT 1 Pekerjaan Plambing - Pipa PVC AW Dia. 1.1/4" - Bobot = 0,002% - Prestasi = 40,000% - - Bobot = 0,002% - Prestasi = 40,000% - Pipa PPRPN 10 Dia. 25 mm Setara Dia. 3/4" - Bobot = 0,036% - Prestasi = 40,000% - - Bobot = 0,036% - Prestasi = 40,000% - Gate Valve 10K Dia. 25 mm Setara Dia. 3/4" - Bobot = 0,006% - Prestasi = 40,000% - - Bobot = 0,006% - Prestasi = 40,000% - Fitting dan Support - Bobot = 0,016% - Prestasi = 40,000% - - Bobot = 0,016% - Prestasi = 40,000%


PROGRESS PEKERJAAN PENGADAAN DAN PEMASANGAN SISTEM ELEKTRIKAL DAN UPS GEDUNG PAU ITB NO URAIAN PEKERJAAN REALISASI MATERIAL ON SITE JUMLAH (TERPASANG + MOS) CATATAN 2. Pekerjaan Elektrikal - NYY 3C X 6 mm2 - Bobot = 0,185% - Prestasi = 75,000% - Bobot = 0,185% - Prestasi = 75,000% - NYY 5C X 10 mm2 - Bobot = 0,143% - Prestasi = 75,000% - Bobot = 0,143% - Prestasi = 75,000% - NYY 5C X 16 mm2 - Bobot = 0,131% - Prestasi = 50,000% - Bobot = 0,131% - Prestasi = 50,000% Material On Site - Stop Kontak 16A/1 Phase - Bobot = 0,079% - Prestasi = 90,000% - Bobot = 0,079% - Prestasi = 90,000% - Stop Kontak 32A/3 Phase - Bobot = 0,022% - Prestasi = 12,727% - Bobot = 0,022% - Prestasi = 12,727% Material On SIte - Kabel Tray 200 x 100 mm - Bobot = 0,379% - Prestasi = 90,000% - Bobot = 0,379% - Prestasi = 90,000% - Kabel Tray 100 x 100 mm - Bobot = 0,128% - Prestasi = 75,000% - Bobot = 0,128% - Prestasi = 75,000% - Saklar Tunggal - Bobot = 0,004% - Prestasi = 75,000% - Bobot = 0,004% - Prestasi = 75,000% - Pengaktifan titik lampu - Bobot = 0,025% - Prestasi = 50,000% - Bobot = 0,025% - Prestasi = 50,000% 3. Pengadaan dan Pemasangan APAR - APAR / APAB CO2 25 Kg trolley – Fire Protection - Bobot = 0,191% - Prestasi = 100,00% - Bobot = 0,191% - Prestasi = 100,00%


PROGRESS PEKERJAAN PENGADAAN DAN PEMASANGAN SISTEM ELEKTRIKAL DAN UPS GEDUNG PAU ITB NO URAIAN PEKERJAAN REALISASI MATERIAL ON SITE JUMLAH (TERPASANG + MOS) CATATAN II. LANTAI 1 1. Pekerjaan Elektrikal - Saklar Tunggal - Bobot = 0,011% - Prestasi = 70,000% - Bobot = 0,011% - Prestasi = 70,000% - NYM 3C X 2.5 mm2 - Bobot = 0,256% - Prestasi = 90,000% - Bobot = 0,099% - Prestasi = 35,000% - Bobot = 0,355% - Prestasi = 62,500% Material On Site + Terpasang - Stop Kontak 16A/1 Phase - Bobot = 0,056% - Prestasi = 90,000% - Bobot = 0,017% - Prestasi = 35,000% - Bobot = 0,074% - Prestasi = 62,500% Material On Site + Terpasang 2. Pekerjaan Plambing - Pipa PVC AW Dia. 1.1/4“ - Bobot = 0,055% - Prestasi = 90,000% - Bobot = 0,055% - Prestasi = 90,000% - Pipa PPRPN 10 Dia. 25 mm Setara Dia. 3/4" - Bobot = 0,078% - Prestasi = 90,000% - Bobot = 0,078% - Prestasi = 90,000% - Gate Valve 10K Dia. 25 mm Setara Dia. 3/4" - Bobot = 0,014% - Prestasi = 90,000% - Bobot = 0,014% - Prestasi = 90,000% - Fitting dan Support - Bobot = 0,051% - Prestasi = 70,000% - Bobot = 0,051% - Prestasi = 70,000% III. LANTAI 2 1. Pekerjaan Plambing - Pipa PPRPN 10 Dia. 25 mm Setara Dia. 3/4" - Bobot = 0,045% - Prestasi = 50,000% - Bobot = 0,045% - Prestasi = 50,000% - Gate Valve 10K Dia. 25 mm Setara Dia. 3/4" - Bobot = 0,008% - Prestasi = 50,000% - Bobot = 0,008% - Prestasi = 50,000%


PROGRESS PEKERJAAN PENGADAAN DAN PEMASANGAN SISTEM ELEKTRIKAL DAN UPS GEDUNG PAU ITB NO URAIAN PEKERJAAN REALISASI MATERIAL ON SITE JUMLAH (TERPASANG + MOS) CATATAN - Fitting dan Support - Bobot = 0,030% - Prestasi = 50,000% - Bobot = 0,030% - Prestasi = 50,000% IV. LANTAI 3 1. Pekerjaan Plambing - Pipa PPRPN 10 Dia. 25 mm Setara Dia. 3/4" - Bobot = 0,068% - Prestasi = 75,000% - Bobot = 0,068% - Prestasi = 75,000% - Gate Valve 10K Dia. 25 mm Setara Dia. 3/4" - Bobot = 0,011% - Prestasi = 75,000% - Bobot = 0,011% - Prestasi = 75,000% - Fitting dan Support - Bobot = 0,045% - Prestasi = 75,000% - Bobot = 0,045% - Prestasi = 75,000% 2. Pekerjaan Elektrikal - Stop Kontak 16A/1 Phase - Bobot = 0,006% - Prestasi = 50,000% - Bobot = 0,006% - Prestasi = 50,000% V. LANTAI 7 1. Pekerjaan Plambing - Pipa PPRPN 10 Dia. 25 mm Setara Dia. 3/4" - Bobot = 0,001% - Prestasi = 0,909% - Bobot = 0,001% - Prestasi = 0,909% - Gate Valve 10K Dia. 25 mm Setara Dia. 3/4" - Bobot = 0,002% - Prestasi = 15,000% - Bobot = 0,002% - Prestasi = 15,000% - Fitting dan Support - Bobot = 0,009% - Prestasi = 15,000% - Bobot = 0,009% - Prestasi = 15,000%


PROGRESS PEKERJAAN PENGADAAN DAN PEMASANGAN SISTEM ELEKTRIKAL DAN UPS GEDUNG PAU ITB NO URAIAN PEKERJAAN REALISASI MATERIAL ON SITE JUMLAH (TERPASANG + MOS) CATATAN 2. Pekerjaan Elektrikal - Saklar Tunggal - Bobot = 0,004% - Prestasi = 15,000% - Bobot = 0,004% - Prestasi = 15,000% - Stop Kontak 16A/1 Phase - Bobot = 0,015% - Prestasi = 15,000% - Bobot = 0,015% - Prestasi = 15,000% - NYM 3C X 2.5 mm2 - Bobot = 0,080% - Prestasi = 15,000% - Bobot = 0,080% - Prestasi = 15,000% - NYM 4 x 6 mm - Bobot = 0,067% - Prestasi = 25,000% - Bobot = 0,067% - Prestasi = 25,000%


INFO GRAFIS PEKERJAAN DI LAPANGAN AREA PEKERJAAN LANTAI BASEMENT = Area Pekerjaan Instalasi Air Kotor = Area Pekerjaan Instalasi Air Bersih


INFO GRAFIS PEKERJAAN DI LAPANGAN AREA PEKERJAAN LANTAI BASEMENT = Area Pekerjaan Kabel Tray 200 x 100 = Area Pengaktifan Titik Lampu = Area Pekerjaan Kabel Tray 100 x 100


INFO GRAFIS PEKERJAAN DI LAPANGAN AREA PEKERJAAN LANTAI BASEMENT = Area Pekerjaan Stop Kontak 16A/1 Phase


INFO GRAFIS PEKERJAAN DI LAPANGAN AREA PEKERJAAN LANTAI 1 = Area Pekerjaan Instalasi Air Kotor = Area Pekerjaan Instalasi Air Bersih


INFO GRAFIS PEKERJAAN DI LAPANGAN AREA PEKERJAAN LANTAI 1 = Area Pekerjaan Saklar Tunggal = Area Pekerjaan Stop Kontak 16A/1 Phase


INFO GRAFIS PEKERJAAN DI LAPANGAN AREA PEKERJAAN LANTAI 2 = Area Pekerjaan Instalasi Air Bersih


INFO GRAFIS PEKERJAAN DI LAPANGAN AREA PEKERJAAN LANTAI 3 = Area Pekerjaan Instalasi Air Bersih


INFO GRAFIS PEKERJAAN DI LAPANGAN AREA PEKERJAAN LANTAI 3 = Area Pekerjaan Stop Kontak 16A/1 Phase


INFO GRAFIS PEKERJAAN DI LAPANGAN AREA PEKERJAAN LANTAI 7 = Area Pekerjaan Instalasi Air Bersih


INFO GRAFIS PEKERJAAN DI LAPANGAN AREA PEKERJAAN LANTAI 7 = Area Pekerjaan Stop Kontak 16A/1 Phase = Area Pekerjaan Saklar Tunggal


DOKUMENTASI PEKERJAAN ELEKTRIKAL DI LAPANGAN Pemasangan Pipa PPR PN-10 ¾” Lantai Basement Pemasangan Pipa PVC ¼” Lantai Basement Pemasangan Stop Kontak 16A/1 Phase Lantai Basement Pemasangan Kabel Tray Lantai Basement


DOKUMENTASI PEKERJAAN ELEKTRIKAL DI LAPANGAN Pemasangan Kabel Tray Lantai Basement Pemasangan Kabel Tray Lantai Basement Pengaktifan Titik Lampu Lantai Basement Pengaktifan Titik Lampu Lantai Basement


DOKUMENTASI PEKERJAAN ELEKTRIKAL DI LAPANGAN Pemasangan Stop Kontak 16A/1 Phase Lantai 1 Pemasangan Pipa PPR PN-10 ¾” Lantai 1 Pemasangan Pipa PPR PN-10 ¾” Lantai 2 Pemasangan Pipa PPR PN-10 ¾” Lantai 2


DOKUMENTASI PEKERJAAN ELEKTRIKAL DI LAPANGAN Pemasangan Stop Kontak 16A/1 Phase Lantai 3 Pemasangan Pipa PPR PN-10 ¾” Lantai 3 Pemasangan Pipa PPR PN-10 ¾” Lantai 7 Pemasangan Pipa PPR PN-10 ¾” Lantai 7


PROGRESS PEKERJAAN PENGADAAN DAN PEMASANGAN SISTEM TATA UDARA STERIL DAN NON STERIL GEDUNG PAU ITB PROGRESS PEKERJAAN MINGGU LALU (MG-9) MINGGU INI (MG-10) RENCANA 0,127% 1,815% REALISASI 2,030% 2,359% DEVIASI 1,903% 0,544% WAKTU PELAKSANAAN s.d. MG-10 WAKTU PELAKSANAAN 180 HK WAKTU TERPAKAI 74 HK SISA WAKTU 106 HK NO URAIAN PEKERJAAN REALISASI MATERIAL ON SITE JUMLAH (TERPASANG + MOS) CATATAN I. LANTAI BASEMENT 1. Pengadaan dan Pemasangan Ducting BJLS 0,6 tanpa Isolasi - 600 x 300 mm - Bobot = 0,147% - Prestasi = 30,000% - - Bobot = 0,147% - Prestasi = 30,000% - 500 x 300 mm - Bobot = 0,052% - Prestasi = 30,000% - - Bobot = 0,052% - Prestasi = 30,000% - 400 x 300 mm - Bobot = 0,048% - Prestasi = 30,000% - - Bobot = 0,048% - Prestasi = 30,000%


PROGRESS PEKERJAAN PENGADAAN DAN PEMASANGAN SISTEM TATA UDARA STERIL DAN NON STERIL GEDUNG PAU ITB NO URAIAN PEKERJAAN REALISASI MATERIAL ON SITE JUMLAH (TERPASANG + MOS) CATATAN II. LANTAI 1 1. Pengadaan dan Pemasangan Ducting BJLS 0,6 tanpa Isolasi - 600 x 300 mm - Bobot = 0,049% - Prestasi = 30,000% - Bobot = 0,049% - Prestasi = 30,000% Pabrikasi III. LANTAI 2 1. Bongkaran AHU Existing - Bobot = 0,008% - Prestasi = 50,000% - Bobot = 0,008% - Prestasi = 50,000% 2. Bongkaran Cooling Tower Existing - Bobot = 0,009% - Prestasi = 30,000% - Bobot = 0,009% - Prestasi = 30,000% IV. LANTAI 3 1. Bongkaran AHU Existing - Bobot = 0,008% - Prestasi = 50,000% - Bobot = 0,008% - Prestasi = 50,000% 2. Bongkaran Cooling Tower Existing - Bobot = 0,009% - Prestasi = 30,000% - Bobot = 0,009% - Prestasi = 30,000%


INFO GRAFIS PEKERJAAN DI LAPANGAN AREA PEKERJAAN LANTAI BASEMENT = Area Pekerjaan Ducting 400 x 300 = Area Pasangan Ducting 600 x 300 = Area Pekerjaan Ducting 500 x 300


INFO GRAFIS PEKERJAAN DI LAPANGAN AREA PEKERJAAN LANTAI 2 = Area Bongkaran AHU Eksisting


INFO GRAFIS PEKERJAAN DI LAPANGAN AREA PEKERJAAN LANTAI 3 = Area Bongkaran AHU Eksisting


DOKUMENTASI PEKERJAAN TATA UDARA DI LAPANGAN Pabrikasi Ducting BJLS Pabrikasi Ducting BJLS Pabrikasi Ducting BJLS Pabrikasi Ducting BJLS


DOKUMENTASI PEKERJAAN TATA UDARA DI LAPANGAN Pemasangan Ducting BJLS Lantai Basement Pemasangan Ducting BJLS Lantai Basement Pemasangan Ducting BJLS Lantai Basement Pemasangan Ducting BJLS Lantai Basement


DOKUMENTASI PEKERJAAN TATA UDARA DI LAPANGAN Pekerjaan Bongkaran AHU Lantai 2 Pekerjaan Bongkaran AHU Lantai 2 Pekerjaan Bongkaran AHU Lantai 2 Pekerjaan Bongkaran AHU Lantai 2


DOKUMENTASI PEKERJAAN TATA UDARA DI LAPANGAN Pekerjaan Bongkaran AHU Lantai 3 Pekerjaan Bongkaran AHU Lantai 3 Pekerjaan Bongkaran AHU Lantai 3 Pekerjaan Bongkaran AHU Lantai 3


TERIMA KASIH