1 TIME CAPSULE Edisi Julai 2020

CARTA ORGANISASI
BAHAGIAN PENGURUSAN PROJEK 5 (BPP 5), CKK

P3.3.5-309
Utama C
PENGARAH JUSA C
Ar. IDr. AZMAN BIN
MD. HASHIM

P3.3.5-310
JMPK J54
Ir. ABDULDAN BIN ADTONG

P3.3.5-312 P3.3.5-325
JAK J48(M) PSP N19
Ir. AHMAD SHAHRIL NURKHAIRUNNISA

BIN IDRIS KATNI

P3.3.5-313 P1-329
JA J44 AK J48
NUR IRDINA OH BINTI
Ir HANASHA BINTI ABDULLAH
ISMAIL
P3.3.5-313
P3.3.5-320 JA J44
PPSB/JA29 KOSONG
KHAIRIZAN
MOHD DEWA P3.3.5-316 P3.3.5-316
PPSB/JA36 PPSB/JA36
JAMALIAH BINTI DHARMASARI
MAT SOAD
JUFRI
P3.3.5-318 P3.3.5-320 P3.3.5-318 P3.3.5-320
PJA/JA29 PPSB/JA29 PJA/JA29 PPSB/JA29 P3.3.5-318
HAZIMAH MOHAMMAD KHAIRUL MOHD ABDUL AZIZ MOHD FUAD PJA/JA29
ABDUL LATIF NIZA MOHJI MOHAMED KOSONG
TOPA

Petunjuk: Butiran Hakiki Butiran Pengurusan Projek Butiran Kosong

Dikemaskini pada: 1 JULAI 2020

TIME CAPSULE Edisi Julai 2020 2

“ DUDUK ”

Setelah bulan syawal berlalu, tibanya bulan Zulkaedah. Zulkaedah ialah bulan ke 11
didalam Islam. Setiap bulan Islam akan ada kelebihannya. Zulkaedah

berasal dari perkataan “Zu Qa’adah”. Zu bermaksud “yang empunya” dan Qa’adah
bermaksud “duduk”. Manakala Zulkaedah ialah bulan untuk berehat dan ia juga

dipanggil bulan haram. Ia dipanggil bulan haram kerana diharamkan untuk
berperang dan satu dari empat bulan yang mulia. Selain bulan Zulkaedah
terdapat tiga lagi bulan haram iaitu bulan Zulhijjah, Muharram dan Rejab.
Dengan itu, masyarakat Arab Jahiliah tidak keluar untuk berperang pada bulan ini.

3 TIME CAPSULE Edisi Julai 2020

TIME CAPSULE Edisi Julai 2020 4

SABAH

5 TIME CAPSULE Edisi Julai 2020

TIME CAPSULE Edisi Julai 2020 6

7 TIME CAPSULE Edisi Julai 2020

TIME CAPSULE Edisi Julai 2020 8

9 TIME CAPSULE Edisi Julai 2020

TIME CAPSULE Edisi Julai 2020 10

11 TIME CAPSULE Edisi Julai 2020

TIME CAPSULE Edisi Julai 2020 12

13 TIME CAPSULE Edisi Julai 2020

TIME CAPSULE Edisi Julai 2020 14

15 TIME CAPSULE Edisi Julai 2020

TIME CAPSULE Edisi Julai 2020 16

17 TIME CAPSULE Edisi Julai 2020

TIME CAPSULE Edisi Julai 2020 18

19 TIME CAPSULE Edisi Julai 2020

TIME CAPSULE Edisi Julai 2020 20

21 TIME CAPSULE Edisi Julai 2020

TIME CAPSULE Edisi Julai 2020 22

LabuanWilayah Persekutuan

23 TIME CAPSULE Edisi Julai 2020

TIME CAPSULE Edisi Julai 2020 24

25 TIME CAPSULE Edisi Julai 2020

TIME CAPSULE Edisi Julai 2020 26

27 TIME CAPSULE Edisi Julai 2020

TIME CAPSULE Edisi Julai 2020 28

SARAWAK

29 TIME CAPSULE Edisi Julai 2020

LAPORAN KEDUDUKAN SEMASA PELAKSANAAN PROJEK
MENYIAPKAN BAKI KERJA TERBENGKALAI BAGI CADANGAN PEMBINAAN HOSPITAL PETRAJAYA (300
1 a. Nama Projek:
KATIL) PETRAJAYA,

b. Skop Projek: KUCHING, SARAWAK (REKA & BINA) - TENDER SEMULA
Pembinaan hospital bertaraf hospital pakar dan menyediakan komprehensif secondary care level yang

dilengkapi 300 buah katil ( bangunan 8 tingkat dengan tempat meletak kenderaan sub-basement) yang

melibatkan skop kerja;

Site Clearing & Earthwork, Komponen Bangunan sokongan ( Mortuary, Medical Store & Engineering

Department, Main Kitchen and Catering, Balai Pelawat & Cafeteria dan M&E Building), External Works,

M&E Services (18 Services), ICT Services, Medical Equipments, Environmental & Energy Efficiency &

Provisional Items ( Softscape Works for Internal Courtyard, Gazebos and Seating Benches for Hardscape

Works, Children Playground Equipment & Patient Monitoring System & Consumables)

d. Kod Projek: SKL0202/B11/16904/20974/0/TB/RB (Rujukan SKALA)

2 a. Siling Projek: RM 452,982,000.00 5 Jadual Pelaksanaan Projek
b. Kos Asal Projek: RM 495,000,000.00 a. Terima BPPP
28.04.2011

c. Kos Projek Semasa:RM 452,982,000.00 b. Lantikan HODT 16.05.2011

d. Kaedah PerlaksanaaRne: ka dan Bina c. Mesyuarat Permulaan Projek: 30.08.2018

e. Kaedah Perolehan: Tender Terbuka Pra Kelayakan d. Lawatan Tapak:

(B29 & Sijil Penyiap)

f. Perolehan RMK: RMK-10, RP1 IBS e. Preliminary Detailed Abstract(PD1A9):.12.2018

g. Kadar LAD/Hari: - f. Value Management (VM): 17.01.2011

h. Jumlah LAD Terkini: - g. Value Assessment (VA): -

i. Reka bentuk : Reka bentuk Baru Tanpa BIM h. Value Engineering (VE): -

3 a. HOPT: HOPT 5 i. Jangka Tender/Tarikh Tender: -

b. HODT j. Surat Setuju Terima: 15.10.2020 14.12.2020

-Arkitek: URBF Kesihatan 2, CA k. Tarikh Milik Tapak: 29.10.2020 28.12.2020
144 Minggu (36 Bulan)
-Awam & Struktur: CKAS l. Tempoh Pelaksanaan: -
m. Tarikh Siap Asal:
-Mekanikal: CKM 31.10.2023 27.12.2023
n. Tarikh Jangka Siap:
-Elektrikal: CKE -
o. Kebenaran Merancang: -
-Ukur Bahan: Bhg. Kesihatan (CKUB) p. Pelan Bangunan: -
c. Pegawai Penguasa: Pengarah Projek Khas 2 q. EOT: -
d. Wakil Peg. PenguasaP:engurus Besar Pembinaan r. LAD
6 Prestasi Kewangan -
4 Kontraktor :- a. Jadual: -
Perunding b. Sebenar:
-: -
-Arkitek :- 7 Prestasi Fizikal -
-Awam & Struktur a. Jadual:
b. Sebenar:
-Sivil dan Struktur : -

-Mekanikal -:

-Elektrikal -:

-Ukur Bahan -:

-Perunding Perubatan -:

-PSP - :

-Perunding ICT -:

8 Status Projek Terkini:
Dokumen Tender Pra-Bida telah selesai dicetak dan diserahkan kepada Pembida. Bermula pada 23 Jun 2020 sehingga 10 Julai

2020 Pembida diberi kemudahan untuk mengadakan lawatan tapak bagi kajian di tapak bina dan menyemak lukisan siap bina di
Pejabat PPK2.

TIME CAPSULE Edisi Julai 2020 30

STATUS PROJEK: PRA - PEMBINAAN Tarikh Kemaskini : 27.07.2020
9 Gambar Projek Sediada

Banguan Blok Hospital Utama

Bangunan Blok Sokongan - cafeteria
Bangunan SESCO

31 TIME CAPSULE Edisi Julai 2020

LAPORAN KEDUDUKAN SEMASA PELAKSANAAN PROJEK

1 a. Nama Projek: Cadangan Menaiktaraf Hospital Umum Sarawak Secara Public Private Partnership - Built Lease Maintain Transfer

b. Skop Projek: (1) Kompleks Diagnostik & Jagaan Harian;

- 7 O.T., 46 recovery beds, treatment bays with blood bank & Integrated pathology laboratory

(2) Penginapan dan Tempat Letak Kereta Bertingkat (Utara);

- 160 hotel rooms, 968 car park, 9 commercial outlets & 7 food courts

(3) Tempat Letak Kereta Bertingkat (Barat);

d. Kod Projek: - 821 car park & 1 unit roof top helipad (27mx27m)

2 a. Siling Projek: RM351,000,000.00 5 Jadual Pelaksanaan Projek

b. Kos Asal Projek: RM351,000,000.00 a. Terima BPPP -

c. Kos Projek Semasa: RM351,000,000.00 b. Lantikan HODT -

d. Kaedah Perlaksanaan:PFI c. Mesyuarat Permulaan Projek: -

e. Kaedah Perolehan: PFI d. Lawatan Tapak: -

f. Perolehan RMK: Swiss Challenge IBS e. Preliminary Detailed Abstract(PDA): -

g. Kadar LAD/Hari: - f. Value Management (VM): -

h. Jumlah LAD Terkini: -

3 a. Government PENGARAH KERJA g. Value Assessment (VA): -
Representative CAWANGAN
(Design & Planning): KESIHATAN

b. HODT h. Value Engineering (VE): -

-Arkitek: i. Jangka Tender/Tarikh Tender: -

-Awam & Struktur: j. Effective Date: 15.11.2017
-Mekanikal:
-Elektrikal: k. Construction Commencement Date:23.02.2018
-Ukur Bahan:
l. Tempoh Pelaksanaan: 36 Bulan

m. Construction Completion Date: 22.02.2021

Government PENGARAH PEMBINAAN n. Tarikh Jangka Siap: 22.02.2021
c. Representative PASUKAN PROJEK KHAS 2
(PPK2)
(Construction):

d. Authorised Officer: Kosong (Arkitek) o. Kebenaran Merancang: -
Kosong (Ukur Bahan) p. Pelan Bangunan: -
Dr. Ting Sie Chun (Tapak (Sivil & Struktur) -
Bina) EOT:
En. Syairul Izam Bin Ab. (Mekanikal) 84.54% (25/05/2020)
Ghani (Pindah) 6 Prestasi Kewangan 59.15% (25/04/2020)
a. Jadual: -
Ir. Anita Binti Sulaiman (Elektrik) b. Sebenar: RM 207,616,500.00
c. Bil. Bayaran Interim:
4 Konsesi ASALJURU WEIDA SDN. BHD. d. Jumlah Terkumpul:
Perunding

-Arkitek : Arkitek KDI Sdn. Bhd.

-Arkitek Lanskap : -

-Perancang Bandar : -

-Awam & Struktur : Concept P-Jurutera Sdn. Bhd.

-Mekanikal : KTA (SarawaK) Sdn. Bhd. 7 Prestasi Fizikal

-Elektrikal : KTA (SarawaK) Sdn. Bhd. a. Jadual (April 2020) : 95.14% (24/07/2020)

-Ukur Bahan : PUBM Quantity Surveyors Sdn. Bhd. b. Sebenar (Mac 2020) : 81.41% (24/07/2020)

-Perunding Perubatan: Perunding Mediconsult Sdn. Bhd. -13.73%

-Perunding Kecekapan VERITAS ENVIRONMENT SDN. BHD. Nota:
Tenaga:

-Perunding ICT : Oratis RX Sdn. Bhd.

8 Status Projek Terkini:

Pelaksanaan projek ini agak memberangsangkan oleh pihak konsesi dan kini mengalami kelewatan disebabkan oleh isu Wabak Pandemik. Kemajuan kerja sebenar

bagi Bangunan Kompleks Diagnostik & Jagaan adalah 82.12%, Bangunan Penginapan dan Tempat Letak Kereta Bertingkat (Utara) adalah 75.65% dan Bangunan

Tempat Letak Kereta Bertingkat (Barat) adalah 84.13%.

TIME CAPSULE Edisi Julai 2020 32

STATUS PROJEK: PEMBINAAN Tarikh Kemaskini : 24.07.2020
9 Gambar Projek Terkini

33 TIME CAPSULE Edisi Julai 2020

LAPORAN KEDUDUKAN SEMASA PELAKSANAAN PROJEK

1 a. Nama Projek: CADANGAN PEMBINAAN HOSPITAL LAWAS (80 KATIL), LAWAS, SARAWAK (REKA DAN BINA) FASA 2B : KERJA BANGUNAN DAN
KERJA-KERJA BERKAITAN - TENDER SEMULA

b. Skop Projek: Kerja pembinaan hospital baru yang menyediakan secondary care services oleh Pakar Residen dan Pegawai Perubatan dilengkapi
dengan lapan puluh katil (80 katil) dengan kemudahan tempat meletak kenderaan sub basement beserta kerja-kerja lain yang
berkaitan terdiri daripada: Bangunan Mekanikal dan Elektrikal, Kerja-kerja Dalaman : i. Kerja Mekanikal (13 perkhidmatan) ii.
Kerja Elektrikal (LV & ELV, Medical Equipment - Group 1), iii. Kerja ICT, Kerja Luaran, Loose Furniture, Environmental & Energy
Efficiency Works , Kerja Wang Peruntukan Sementara, Medical & Non-Medical Euipment (Group 3 & 4) & Kerja Penyelenggaraan.

d. Kod Projek: SKL0202/B11/19809/16815/0/TB/RB (Rujukan SKALA)

2 a. Siling Projek: RM203,000,000.00 (Fasa 1,2A & 5 Jadual Pelaksanaan Projek
2B)
a. Terima BPPP
b. Kos Asal Projek: RM175,402,100.00 (Fasa 2B) b. Lantikan HODT 16.08.2011
c. Mesyuarat Permulaan Projek: 21.03.2013
c. Kos Projek Semasa: RM165,000,000.00 d. Lawatan Tapak:
e. Preliminary Detailed Abstract(PDA): 04.10.2018 (lulus)
d. Kaedah Perlaksanaan: Reka dan Bina f. Value Management (VM): 20.01.2016
g. Value Assessment (VA): 5.03.2018
e. Kaedah Perolehan: Pre-Q (Tender Terbuka) -
f. Perolehan RMK: RMK-11, RP4 Bukan IBS 15.02.2019
g. Kadar LAD/Hari: - 30.04.2020
30.06.2020
h. Jumlah LAD Terkini: - 182 Minggu
-
i. Reka bentuk : Reka bentuk Baru Tanpa BIM h. Value Engineering (VE): 26.12.2023
-
3 a. HOPT: HOPT 5 i. Jangka Tender/Tarikh Tender: -
-
b. HODT j. Surat Setuju Terima:
-
-Arkitek: URBF Kesihatan 2, CA k. Tarikh Milik Tapak: -
-
-Awam & Struktur: CKAS l. Tempoh Pelaksanaan: -

-Mekanikal: CKM m. Tarikh Siap Asal: -
-
-Elektrikal: CKE n. Tarikh Jangka Siap:

-Ukur Bahan: Bhg. Kesihatan (CKUB) o. Kebenaran Merancang:

c. Pegawai Penguasa: Pengarah Projek Khas 2 p. Pelan Bangunan:

d. Wakil Peg. Penguasa: Pengurus Besar Pembinaan q. EOT:

4 Kontraktor : MCS Management Sdn. Bhd. 6 Prestasi Kewangan
: United Consultants Architect Sdn. Bhd.
Perunding a. Jadual:
-Arkitek b. Sebenar:
c. Bil. Bayaran Interim:

-Arkitek Lanskap : - d. Jumlah Terkumpul:

-Perancang Bandar : -
-Awam & Struktur : VED Engineers Sdn. Bhd.

-Mekanikal : Sdn Bhd 7 Prestasi Fizikal
-Elektrikal J. Roger Preston (Malaysia)
a. Jadual:
:

-Ukur Bahan : KSK and Partners Sdn. Bhd. b. Sebenar:

-Perunding Perubatan: Pro Edge Engineering Sdn. Bhd.

-PSP : United Consultants Architect Sdn. Bhd.

-Perunding ICT : 10 Creative Solutions Sdn. Bhd.
Envisar Perintis Sdn. Bhd.
-Alam Sekitar :

8 Status Projek Terkini:

Mesyuarat Akhir Memuktamadkan Pelan Susunatur Dalaman akan diadakan pada 10 sehingga 12 Ogos 2020. Lukisan pengemukaan kepada State Planning
Authority (SPA) untuk Kelulusan Merancang akan dikemukakan kepada SPA selewat-lewatnya pada

TIME CAPSULE Edisi Julai 2020 34

STATUS PROJEK: PRA - PEMBINAAN Tarikh Kemaskini : 20.06.2020
9 Gambar Projek Sediada

Pelan Tapak

Kerja Awalan - Site Clearing sedang dilaksanakan

35 TIME CAPSULE Edisi Julai 2020

LAPORAN KEDUDUKAN SEMASA PELAKSANAAN PROJEK

1 a. Nama Projek: PEMBINAAN BANGUNAN TAMBAHAN HOSPITAL MIRI, SARAWAK (REKA DAN BINA) - TENDER SEMULA

b. Skop Projek: Pembinaan bangunan hospital bertaraf hospital pakar major dan hospital rujukan yang dilengkapi dengan 328 buah katil dengan
kemudahan tempat meletak kenderaan sub basement, Kerja Bangunan Mekanikal dan Elektrikal, Kerja Mekanikal ( 13 services) & Medical
d. Kod Projek: Euipment (Group 1), Kerja Elektrikal (LV & ELV, Medical Equipment Group 1) & ICT, Kerja Luaran, Loose Furniture
Environmental & Energy Efficiency Works, Kerja Wang Peruntukan Sementara, Medical & Non-Medical Euipment (Group 3 & 4) (perolehan
2 a. Siling Projek: oleh KKM) & Kerja Penyelenggaraan

b. Kos Asal Projek: SKL0202/B16/24557/19647/0/TB/RB (Rujukan SKALA)
c. Kos Projek Semasa:
d. Kaedah Perlaksanaan: RM350,000,000.00 5 Jadual Pelaksanaan Projek 15.01.2016
e. Kaedah Perolehan: RM340,000,000.00
f. Perolehan RMK: a. Terima BPPP
g. Kadar LAD/Hari:
h. Jumlah LAD Terkini: RM289,200,000.00 b. Lantikan HODT 07.04.2016

Reka dan Bina c. Mesyuarat Permulaan Projek:

Pre-Q (Tender Terbuka) d. Lawatan Tapak:

RMK-11, RP1 (IBS) e. Preliminary Detailed Abstract(PDA): 22.12.2016

- f. Value Management (VM): -

- g. Value Assessment (VA): 31.10.2016

i. Reka bentuk : Reka bentuk Baru Tanpa BIM h. Value Engineering (VE): 13.02.2017

3 a. HOPT : HOPT 5 i. Jangka Tender/Tarikh Tender: 01.11.2018
j. Surat Setuju Terima: 12.06.2020
b. HODT : URBF Kesihatan 2, CA k. Tarikh Milik Tapak: 25.06.2023
- Arkitek: CKAS l. Tempoh Pelaksanaan: 173 Minggu
- Awam & Struktur: CKM m. Tarikh Siap Asal: 18.10.2023
- Mekanikal: CKE n. Tarikh Jangka Siap:
- Elektrikal: Bhg. Kesihatan (CKUB) o. Kebenaran Merancang: -
- Ukur Bahan: Pengarah Projek Khas 2 p. Pelan Bangunan: -
Pengurus Besar Pembinaan q. EOT: -
c. Pegawai Penguasa : r. LAD -
d. Wakil Peg. Penguasa:
6 Prestasi Kewangan -
4 Kontraktor : Riaplus Sdn. Bhd. -
a. Jadual:
Perunding b. Sebenar: -
0.15%
-Arkitek : Perunding Alam Bina Sdn. Bhd. 7 Prestasi Fizikal

-Awam & Struktur : Konsortium Malaysia (KM) a. Jadual:
b. Sebenar:
-Sivil dan Struktur : VED Engineers Sdn. Bhd.

-Mekanikal : KVA Konsult
-Elektrikal : KVA Konsult
-Ukur Bahan : Zul-Qs Consult

-Perunding Perubatan : Perunding Alam Bina (PAB)
Affrin Arcitect & Assoc.
-PSP :

-Perunding ICT :

8 Status Projek Terkini:

21 - 23 Julai 2020 - Mesyuarat Pengesahan Zoning dan Susunatur Dalaman diadakan dengan penglibatan semua stakeholders . Status semasa di tapak bina - Progress

Bulanan semasa pada 25 Julai 2020

Jadual % : 0.00

Sebenar % : 0.15

Varian % : +0.15 Kerja-kerja site clearing, earthworks, pemasangan

hoarding board dan wash through (perlaksanaan kerja-kerja awalan dan item preliminaries ) sedang giat dilaksanakan. Pengemukaan dokumen kepada State Planning

Authority (SPA ) dilaksanakan pada 29.07.2020 bagi tujuan Kelulusan Merancang.

TIME CAPSULE Edisi Julai 2020 36

STATUS PROJEK: PRA - PEMBINAAN Tarikh Kemaskini : 27.07.2020
9 Gambar Projek Sediada

Pandangan Drone - 200716

Pelan Tapak

Pandangan Drone - 200716

Gambaran Perspektif Bangunan Tambahan Hospital Miri

37 TIME CAPSULE Edisi Julai 2020

LAPORAN KEDUDUKAN SEMASA PELAKSANAAN PROJEK

1 a. Nama Projek: KLINIK KESIHATAN (JENIS 5) DENGAN KUARTERS SIMPANG SIMUNJAN, SARAWAK

b. Skop Projek: Membina Klinik Kesihatan (Jenis 5) dengan kuarters 16G berserta perolehan peralatan perubatan dan bukan
perubatan.

2 a. Siling Projek: RM26,000,000.00 5 Jadual Pelaksanaan Projek

b. Kos Asal Projek: RM26,000,000.00 a. Terima BPPP 13.12.2019

c. Kos Projek Semasa: RM26,000,000.00 b. Lantikan HODT

d. Kaedah Perlaksanaan: Konvensional c. Mesyuarat Permulaan Projek:

e. Kaedah Perolehan: Tender Terbuka d. Lawatan Tapak: 13.02.2020

f. Perolehan RMK: RMK-11, RP4 e. Preliminary Detailed Abstract(PDA):

g. Kadar LAD/Hari: - f. Value Management (VM):

h. Jumlah LAD Terkini: - g. Value Assessment (VA):

i. Reka bentuk : PAP (tambahan skop ABC, x-ray dan h. Value Engineering (VE):
sick bay)

3 a. HOPT: HOPT 5 i. Jangka Tender/Tarikh Tender: 21.12.2020
b. HODT
j. Surat Setuju Terima: 07.04.2021

-Arkitek: k. Tarikh Milik Tapak: 21.04.2021

-Awam & Struktur: l. Tempoh Pelaksanaan: -
-Mekanikal: m. Tarikh Siap Asal: -
-Elektrikal: n. Tarikh Jangka Siap: -
-Ukur Bahan: o. Kebenaran Merancang: -
c. Pegawai Penguasa: JKR Sarawak p. Pelan Bangunan:
d. Wakil Peg. Penguasa: JKR Sarawak q. EOT: -
r. LAD -
4 Kontraktor : 6 Prestasi Kewangan -
a. Jadual: -
Perunding b. Sebenar:
c. Bil. Bayaran Interim: -
-Arkitek : d. Jumlah Terkumpul: -

-Arkitek Lanskap : 7 Prestasi Fizikal
a. Jadual:
-Perancang Bandar : b. Sebenar:

-Awam & Struktur :

-Sivil dan Struktur :

-Mekanikal :

-Elektrikal :

-Ukur Bahan :

-Perunding Perubatan :

-PSP :

-Perunding ICT :

8 Status Projek Terkini:

Lukisan Piawai PAP KK5 Stella Borneo ini masih belum dimuktamadkan. HODT Arkitek di dalam tempoh pindaan dan penyediaan
lukisan dan dijangka akan kemukakan semula kepada KKM pada 13.07.2020. Mesyuarat Koordinasi akan diadakan pada 25.06.2020
untuk menyelesaikan isu berbangkit. Projek dimasukkan dalam senarai NOC bagi pengesahan skop dan kos.

TIME CAPSULE Edisi Julai 2020 38

STATUS PROJEK: PRA - PEMBINAAN Tarikh Kemaskini : 27.07.2020
9 Gambar Projek Sediada

39 TIME CAPSULE Edisi Julai 2020

LAPORAN KEDUDUKAN SEMASA PELAKSANAAN PROJEK

1 a. Nama Projek:

CADANGAN HOSPITAL BARU SRI AMAN, SARAWAK (108 KATIL) FASA 2 : KERJA BANGUNAN DAN KERJA BERKAITAN

b. Skop Projek: Kerja-kerja pembinaan hospital baru beserta kerja-kerja lain yang berkaitan terdiri daripada ; Hospital (108
katil), Kuarters (D-2, F-8, G-8) berserta bangunan sokongan

d. Kod Projek: SKL0202/B11/19804/16745/15534/TH/KP (rujukan SKALA)

2 a. Siling Projek: RM 222,000,000.00 5 Jadual Pelaksanaan Projek

b. Kos Asal Projek: RM176,275,304.36 a. Terima BPPP 23.06.2011
c. Kos Projek Semasa: 21.03.2013
d. Kaedah Perlaksanaan: RM180,846,202.83 (APK 1-69, PHK 1-12) b. Lantikan HODT
e. Kaedah Perolehan: 17.09.2014 (lulus)
f. Perolehan RMK: Konvensional Perunding c. Mesyuarat Permulaan Projek: 17.02.2014
g. Kadar LAD/Hari:
h. Jumlah LAD Terkini: Pre-Q d. Lawatan Tapak: -
17.02.2014
3 a. HOPT: RMK-10, RP2 Bukan IBS e. Preliminary Detailed Abstract(PDA): 30.03.2015

b. HODT RM33,081.80 f. Value Management (VM):

-Arkitek: -

HOPT 5 g. Value Assessment (VA):

h. Value Engineering (VE):

URBF Kesihatan 2, CA i. Jangka Tender/Tarikh Tender:

-Awam & Struktur: CKAS j. Surat Setuju Terima: 18.09.2015

-Mekanikal: CKM k. Tarikh Milik Tapak: 26.10.2015
-Elektrikal: CKE l. Tempoh Pelaksanaan:
-Ukur Bahan: Bhg. Kesihatan (CKUB) m. Tarikh Siap Asal: 25.10.2018
c. Pegawai Penguasa: Pengarah Projek Khas 2 n. Tarikh Jangka Siap: 06.02.2021
d. Wakil Peg. Penguasa: Pengurus Besar Pembinaan o. Kebenaran Merancang:
p. Pelan Bangunan: No. 1 - 26.10.2018 sehingga 03.08.2019
(282 hari)
EOT: No. 2 - 04.08.2019 sehingga 28.01.2020
(178 hari)
4 Kontraktor : Faltech Engineering S/B JV Welfield Services 6 Prestasi Kewangan No. 3 - 29.01.2020 sehingga 15.10.2020
(261 hari)
Perunding S/B a. Jadual: No. 4 - 16.10.2020 sehingga 10.12.2020
(56 hari)
-Arkitek : Perunding Alam Bina S/B b. Sebenar: No. 5 - 11.12.2020 sehingga 06.02.2021
(58 hari)
-Arkitek Lanskap : - c. Bil. Bayaran Interim:
90.80% (24/07/2020)
82.43% (24/07/2020)

Bil. 56

-Perancang Bandar : - d. Jumlah Terkumpul:
Konsortium Malaysia (KM)
-Awam & Struktur : RM 145,325,800.00 (sehingga Interim
No.56)

-Mekanikal : Utas Kesturi Sdn. Bhd. 7 Prestasi Fizikal

-Elektrikal : Konsortium Bumi Consultants & Services S/B a. Jadual : 91.00% (24/07/2020)

-Ukur Bahan : KPK Quantity Surveyor Srwk b. Sebenar : 82.70% (24/07/2020)

-Perunding Perubatan: Perunding Alam Bina S/B -8.30 % (Lewat 95 hari)

-PSP : Affrin Architect & Assoc. S/B

-Perunding ICT : Nota:
1. Kemajuan jadual adalah berdasarkan Program Kerja manakala kemajuan sebenar
berdasarkan nilai kerja diperakukan (Bayaran Interim)

8 Status Projek Terkini:

1. Lanjutan Masa No.5 dengan tempoh tambahan sebanyak 58 hari telah diluluskan pada 10 Julai 2020. Lanjutan masa ini merangkumi tempoh PKPB dan faktor kesediaan
tapak serta mobilisasi jentera dan pekerja bagi mematuhi SOP yang ditetapkan. Maka, tarikh siap semasa mengikut kontrak telah dilanjutkan ke 6 Februari 2021.
2. Projek disyorkan diangkat ke Mesyuarat PSG berdasarkan emel pihak CKK yang diterima oleh pejabat tapak pada 27 Julai 2020 bagi menentukan hala tuju projek.

TIME CAPSULE Edisi Julai 2020 40

STATUS PROJEK: PEMBINAAN Tarikh Kemaskini : 27.07.2020
9 Masalah/Punca Kelewatan

41 TIME CAPSULE Edisi Julai 2020

AKTIVITI
BULANAN

TIME CAPSULE Edisi Julai 2020 42

43 TIME CAPSULE Edisi Julai 2020

TIME CAPSULE Edisi Julai 2020 44

45 TIME CAPSULE Edisi Julai 2020

TIME CAPSULE Edisi Julai 2020 46

47 TIME CAPSULE Edisi Julai 2020

TIME CAPSULE Edisi Julai 2020 48

49 TIME CAPSULE Edisi Julai 2020

TIME CAPSULE Edisi Julai 2020 50