The words you are searching are inside this book. To get more targeted content, please make full-text search by clicking here.
Discover the best professional documents and content resources in AnyFlip Document Base.
Search
Published by lpenrose, 2019-07-19 07:43:22

Design Risk Analysis CDM

DESIGN RISK ANALYSIS
CONSTRUCTION, USE, FUTURE ALTERATION, DEMOLITION AND MAINTENANCE

This form is to be used by Waterman Group designers to enable them to record design decision that have been taken to eliminate, reduce or manage risks that are
presented by their designs. There are certain design features that designers will routinely avoid or seek to include. These are listed on the attached ‘Red, Amber and
Green List’. Designers do not have to mention any of these standard features in their design risk analysis.

PROJECT: University of Huddersfield, Science Laboratories JOB No: 12786

RISK ANALYSIS BY: JR DATE: 14.08.2018 CHECKED BY: PL DATE: 14.03.2018

Hazard Design Element Phase when hazard is relevant (e.g. Description of hazard Action taken to eliminate, reduce or
Ref Construction, Use, Maintenance, Asbestos/ substances hazardous to health manage risk
Alteration, Demolition)
Installation of data Construction Existing duct work adjacent to Joseph
cables to connect to Priestley Building contain hazardous
Joseph Priestley materials including asbestos an contains
Building Asbestos/ substances hazardous to health.
1 Contractor to ensure the asbestos survey is
fully understood and to install new duct/
containment that is completely separate to
existing. Existing duct work is to be left alone.

Working at Height Construction Risk of falling and injuring yourself or Ensure safe perimeter around the area where
2 others in close proximity. Tools or work is being done. Check ladders and
equipment falling from height. Mobile tower scaffold aren't damaged prior to
Working close to Construction use.
risers Risk of falling: severely injury or death.
3 Ensure harness is used when working in the
risers and a suitable barrier is in position
when not in use.

Working on roof top Construction Trips and falls, Weather extremities, high No Survey works to be carried out on room in
winds, heavy rain causing surfaces to high winds or rain. Step-overs to be used.
4 become slippy, materials can be lifted from Walk ways to be used.
roof by wind. Difficult egress due to tight Quality level of ingress and access to be
Working near loud Construction walkways and step over platforms. provided by client.
equipment
5 Partial or Permanent Hearing Loss if Wearing suitable ear protection rated to noise
exposed for extended periods of time. level in question.

SWP003_SF_01 Design Risk Analysis CDM Page 1 Revision 1

DESIGN RISK ANALYSIS
CONSTRUCTION, USE, FUTURE ALTERATION, DEMOLITION AND MAINTENANCE

Hazard Design Element Phase when hazard is relevant (e.g. Description of hazard Action taken to eliminate, reduce or
Ref Construction, Use, Maintenance, Electric shock from faulty equipment. manage risk
Working with or near Alteration, Demolition)
6 electrically powered Construction Ensure any 230 volt tools are connected to a
equipment residual current device, or ensure building
site is using a 110 volt connection. Check all
equipment and cables before use.

Heavy lifting Construction Personal Injury from incorrect lifting form or If heavy lifting is required, use suitable
7
exceeding capable lifting weight transport equipment such as wheelbarrow or

trolley.

Accidental Construction Inhaling harmful gases Ensure COSHH assessment has been
Harmful GWP to environment. completed and removal/fitting of equipment is
discharge of done with care and any necessary respiratory
Objects falling from height and injuring equipment is worn/available at scene.
8 refrigerant gases. pedestrians Use leak detection/warning devices at scene.

Lifting new plant Construction Ensure correct lifting devices are used and
to/from the roof area underneath is clear when lifting.
9

Obstructed Construction Pedestrians could trip or fall, damage to Ensure waste and equipment stored securely
vehicles. and outside areas of public access
pathways or public

10 access

Chemical treatment Construction Come in contact with harmful materials Ensure suitable protection is worn to prevent
of piped services contact with the chemicals.
11

Builders work Enabling/ Construction Dust created from drilling/ chasing into the Ensure all dust is kept to a minimum and wet
12 building structure drilling is used unless near live electrical
equipment. Ensure that a suitable protective
SWP003_SF_01 Design Risk Analysis CDM Page 2 barrier is put into place when work occurs to
prevent the spread of dust to other areas.
Ensure suitable adequate PPE is issued to
the work force to work prior to working in the
environment.

Revision 1

DESIGN RISK ANALYSIS
CONSTRUCTION, USE, FUTURE ALTERATION, DEMOLITION AND MAINTENANCE

Hazard Design Element Phase when hazard is relevant (e.g. Description of hazard Action taken to eliminate, reduce or
Ref Work in public areas Construction, Use, Maintenance, manage risk
Alteration, Demolition) Risk to the public from falling objects/ slips
Enabling/ Construction and trips. Ensure that the centre is closed and an
agreement with the centre management is in
13 place prior to work starting within the public
area. Ensure that no equipment and
materials are left within the public area whilst
the centre is open. Once work takes place
ensure that the public area is swept and
cleaned prior to the centre reopening.

High level services Maintenance Fall from height Suitable access equipment is to be used for
14 maintenance, as is the case with the current
centre.

Unverified existing All To be considered at time as it depends Contractor to physically verify information by
Information upon service. site survey.

15

SWP003_SF_01 Design Risk Analysis CDM Page 3 Revision 1

Red, Amber and Green List

Red, amber and green lists are practical aides to designers on what to eliminate/avoid, and what to encourage. This list has been taken from the HSE website. If your
design avoids red or amber items, or includes green items, you do not need to refer to them in your Risk Analysis: Your Risk Analysis should concentrate on what you
are doing above and beyond these common design features.

Red Lists: Hazardous procedures, products and processes that should be eliminated from the project where possible. If your design is to include one of these
features, seek advice from Waterman Group Construction Safety Advisors.

• Lack of adequate pre-construction information, eg asbestos surveys, geology, obstructions, services, ground contamination etc.
• Hand scabbling of concrete (‘stop ends’, etc);
• Demolition by hand-held breakers of the top sections of concrete piles (pile cropping techniques are available);
• The specification of fragile roof lights and roofing assemblies;
• Processes giving rise to large quantities of dust (dry cutting, blasting etc.);
• On-site spraying of harmful substances;
• The specification of structural steelwork which is not purposely designed to accommodate safety nets;
• Designing roof mounted services requiring access (for maintenance, etc), without provision for safe access (eg. barriers).
• Glazing that cannot be accessed Safely, All glazing should be anticipated as requiring cleaning and replacement, so a safe system of access is essential.
• Entrances, floors, ramps, stairs and escalators etc not specifically designed to avoid slips and trips during use and maintenance, including effect of rain water and
spillages.
• Design of environments involving adverse lighting, noise, vibration, temperature, wetness, humidity and draughts or chemical and/or biological conditions during use
and maintenance operations.
• Designs of structures that do not allow for fire containment during construction

Amber Lists: Products, processes and procedures to be eliminated or reduced as far as possible and only specified/allowed if unavoidable. Including amber items
would always lead to the provision of information to the Principal Contractor. If you wish to include one of these features in your design you must justify it on your
design risk analysis and seek approval or comments from a senior designer within Waterman Group.

• Internal manholes / inspection chambers in circulation areas;
• External manholes in heavy used vehicle access zones;
• The specification of “lip” details (i.e. trip hazards) at the tops of pre-cast concrete staircases;
• The specification of shallow steps (i.e. risers) in external paved areas;
• The specification of heavy building blocks i.e. those weighing > 20kgs;
• Large and heavy glass panels;
• The chasing out of concrete / brick / blockwork walls or floors for the installation of services;
• The specification of heavy lintels (the use of slim metal or hollow concrete lintels being alternatives);
• The specification of solvent-based paints and thinners, or isocyanates, particularly for use in confined areas;
• Specification of curtain wall or panel systems without provision for the tying (or raking) of scaffolds;
• Specification of blockwork walls >3.5 metres high using retarded mortar mixes.

SWP003_SF_01 Design Risk Analysis CDM Page 4 Revision 1

Green Lists: Products, processes and procedures to be positively encouraged.

• Adequate access for construction vehicles to minimise reversing requirements (one-way systems and turning radii);
• Provision of adequate access and headroom for maintenance in plant rooms, and adequate provision for replacing heavy components;
• Thoughtful location of of mechanical / electrical equipment, light fittings, security devices etc. to facilitate access and away from crowded areas;
• The specification of concrete products with pre-cast fixings to avoid drilling;
• Specify half board sizes for plasterboard sheets to make handling easier;
• Early installation of permanent means of access, and prefabricated staircases with hand rails;
• The provision of edge protection at permanent works where there is a foreseeable risk of falls after handover;
• Practical and safe methods of window cleaning (eg. from the inside);
• Appointment of a Temporary Work Coordinator (BS 5975);
• Off-site timber treatment if PPA- and CCA-based preservatives are used (Boron or copper salts can be used for cut ends on site).
• Off site fabrication and prefabricated elements to minimize on site hazards.
• Encourage the use of engineering controls to minimize the use of Personal Protective Equipment

SWP003_SF_01 Design Risk Analysis CDM Page 5 Revision 1


Click to View FlipBook Version