GREAT P1 HSE INDUCTION

Cover for PLNG2 and PT2SB Briefing.

Keywords: HSE

Portable Equipment Temporary Installation (PETI)

SHIFT SUPV SECURITY CHECK PROCEED FOR
SITE WORK

INPECTION CHECKLIST +
PETI CERT OF FITNESS +
STICKERS

PTW

AUTHORIZED PETI EQUIPMENT OWNER +
INSPECTOR GENERATOR

© 2019 Petroliam Nasional Berhad (PETRONAS) |

Open

Role & Responsibilities

EQUIPMENT OWNER To own the equipment

To prepare the equipment prior to the inspection

To get and issue for the inspection checklist and
PCF
To identify the location of the installed equipment

To hand in the equipment to PETI Inspector for
the inspection
To monitor the validity and compliancy of the
certificate and checklist
To request for certificate re-validity

48

© 2019 Petroliam Nasional Berhad (PETRONAS) |

Open

PETI Stickers

© 2019 Petroliam Nasional Berhad (PETRONAS) |

Open

Electrical Portable Equipment

ELECTRICAL PORTABLE EQUIPMENT

18 February 48
© 2019 Petroliam Nasional Berhad (PETRONAS) |
Internal

2014

Open

Electrical Temporary Installation

© 2019 Petroliam Nasional Berhad (PETRONAS) |

Open

PETI Validity Peroid

The validity periods for PETI certificates shall be as follows:-

DOCUMENT DAYS / MONTH

INSPECTION CHECKLIST 1 MONTH
+ STICKER

PETI CERT OF FITNESS + 7 DAYS
STICKER

Note:-
1. The equipment owner must arrange for re-inspection of PETI upon expiry of the

above certificates.
2. For the project which the duration is more than 2 weeks, a dedicated PETI

Inspection team or personnel shall be established.
3. A memo shall be issued in case of any deviation due to special situation /

requirement agreed by management.

© 2019 Petroliam Nasional Berhad (PETRONAS) |

Open

Radiography Test

Radiography Testing (RT)

• Only certified RPO is allowed to certify RT work and approve by RGTSU

AA before PTW issuance.

• RT only during night shift otherwise specify.
• Any RT to be carried out outside the above period shall be approved by

Terminal Manager

© 2019 Petroliam Nasional Berhad (PETRONAS) |

Open

Scaffolding

• Erection shall be carried out by certified erector and inspected by qualified scaffolding

Inspector.

• Contractor shall submit names of inspector to RGTSU for endorsement.
• Scaffolding shall be inspected before use, weekly (after 7 days) , after heavy weather,

after modification and after any incident involving the scaffolding.

• No throwing of scaffolding materials. Down - up or vice versa.
• Scaffolding Tag. All inspected scaffolding must be tag with Green Tag.

© 2019 Petroliam Nasional Berhad (PETRONAS) |

Open

Scaffolding and Staging

• Access ladder must extend 1.07 meters, above the landing.
• Scaffold must be erected on firm ground.
• Working platform must be fully boarded, fitted with double rails and toe-board.
• All scaffold must be kept clear of debris and unused material.
• Any scaffold extending more than 40 meters shall be designed by a professional

engineer and the design shall be approved by DOSH.

© 2019 Petroliam Nasional Berhad (PETRONAS) |

Open

Hand Tools

• Defect or home made hand tools is not allowed.
• Wear correct size of glove ie cotton gloves, semi leather or rubber

gloves .

• Do not use bare hand to lift heavy or sharp object .
• No not use chisel for hammering.
• Only copper hammer allow in the process area

© 2019 Petroliam Nasional Berhad (PETRONAS) |

Open

Hand Tools

• Razor knife is not allowed to be used as cutting tools. Use cutter.
• Air manifold should be installed with pressure gauge and RV.
• Workbench must be cleared of debris.
• Protruding nails must be pulled out.
• Moving parts shall be guarded.

© 2019 Petroliam Nasional Berhad (PETRONAS) |

Open

Grating and Handrills

Any grating / handrails / stairway removal OR
modification work request shall be made
through PTW.

Removing and installing grating / false floor
/ handrails:-

• The handrail / grating shall be secured by means of rope
or wire to prevent it from falling.

• Grating shall be lifted/lowered by lanyard (not by hand)

The area surrounding the opening shall have
hard barricades installed.

Where temporary access is required -
temporary platform and handrail shall be
fitted as deemed necessary by Owner.

© 2019 Petroliam Nasional Berhad (PETRONAS) |

Open

Lifting Activity Crane Operator
Signalman & Rigger
Lifting / Rigging Supervisor
Crane Operator © 2019 Petroliam Nasional Berhad (PETRONAS) |
Rigger
Signalman

Open

Rigging and Lifting

HOOK WITHOUT SAFETY LATCH

NO PROPER OUT RIGGER SUPPORT© 2019 Petroliam Nasional Berhad (PETRONAS) |

Open

Manual Lifting and Handling

• Bend your knees.
• Keep your back

straight, even
when you’re

putting down the

load.
• Hold the load

close to your body

and use a slow,

steady lifting

motion.
• Don’t twist while

carrying

something.

© 2019 Petroliam Nasional Berhad (PETRONAS) |

Open

Housekeeping

• All work areas shall be kept clean and tidy at all time.
• Contractor shall be responsible in conducting housekeeping.
• Contractor shall assigned a team to maintain housekeeping.
• Place all rubbish at designated DISPOSAL BIN/LOCATION.
• The collection (at the disposal location) and disposal of the

Domestic waste will be managed by EPCC contractor.

© 2019 Petroliam Nasional Berhad (PETRONAS) |

Open

Waste Management

Domestic Waste Types of waste Scheduled Waste
generated by
Normal garbage in the Waste that is listed in the
forms of paper, plastic refinery First Scheduled of the
glass, food residues, Environment Quality
scrap metal and other (Scheduled Wastes)
biodegradable materials Regulations 2005 which
which can be disposed only can be disposed at
at the municipal landfills prescribed premises.

or recycled.

© 2019 Petroliam Nasional Berhad (PETRONAS) |

Open

Schedule Waste Notification To DOE

Kod Kategori Punca Buangan1 Nama Buangan Komponen Kuantiti (Tan
Buangan Buangan2 Metrik/Bulan)3

SW305 Aktiviti operasi & Spent Lube Oil/ Mineral oil, 0.43
selenggara Transformers Oil Wear metal
0.02
SW410 Aktiviti operasi & Spent filters and Mineral oil, Diesel
SW422 selenggara membranes 0.42
Mineral oil, Diesel,
Aktiviti operasi & Contaminated Trash Acid
selenggara

Contaminated

Oil sludge container Waste oil

© 2019 Petroliam Nasional Berhad (PETRONAS) |

Open

Applicable Legal Requirements

© 2019 Petroliam Nasional Berhad (PETRONAS) |

Open

Applicable Legal Requirements

© 2019 Petroliam Nasional Berhad (PETRONAS) |

Open

Applicable Legal Requirements

© 2019 Petroliam Nasional Berhad (PETRONAS) |

Open

Applicable Legal Requirements

© 2019 Petroliam Nasional Berhad (PETRONAS) |

Open

Video Safety Video 1 – High Risk
Safety Video 2 - WAH

Safety Video 3 – Team Work

© 2019 Petroliam Nasional Berhad (PETRONAS) |

Open

Compliance to:

© 2019 Petroliam Nasional Berhad (PETRONAS) |

Open

Thank you for your passion!