ROCKS HSE PERFORMANCE REPORT @
DECEMBER 2019 (21.11.2019 TO 20.12.2019)
© 2019 Petroliam Nasional Berhad (PETRONAS)
All rights reserved. No part of this document may be reproduced in any form possible, stored in a retrieval system, transmitted and/or disseminated
in any form or by any means (digital, mechanical, hard copy, recording or otherwise) without the permission of the copyright owner.
Internal
Contents
HSE STATISTIC, ANALYSIS & CHART
HSE PROMOTION, PROGRAM &
TRAINING
PICTURES PROGRAM
© 2019 Petroliam Nasional Berhad (PETRONAS) | 2
Internal
HSE Statistic, Analysis
& Chart
Internal
Man-hours
December 2019 YTD 2019 ACCUMULATIVE LTI FREE DAYS
SINCE Dec. 2018:
8,795 73,568 Note:
74,334
Statistics
00 0 Top Risk Activities
00 0
00 0 •
•
•
0 recordable incident 0 Major Spill 0 Major Fire 0 Major Incident
Internal © 2019 Petroliam Nasional Berhad (PETRONAS) |
UAUC (Target 2019 – 1:250)
1:351December 2019 Ratio 25Dec. 2019 Submission 508Cumulative
Ratio
Safe Unsafe
Condition, Act, 7, 13 1:46
6, 24% 28%
Safe Act, Unsafe 33
7, 28% Condition, 2 22
ROP PPE POP TE PO
5, 20%
PF
ROP : Reaction of People / PPE : Personnel Protective Equipment / POP : Position of People / TE : Tools & Equipment's / PO : Procedure & Orderliness / PF : Positive Findings
Category Dec. Jan. Feb. Mar. Apr. May. Jun. July. Aug. Sep. Oct. Nov. Dec. Total
2018 2019 2019 2019 2019 2019 2019 2019 2019 2019 2019 2019 2019
PTSSB / 9631
GPD 174 380 488 581 720 773 713 1090 1068 896 916 836 996 64703
74334
Contractor 592 2688 3440 3416 3296 4571 7170 6312 6400 6092 6500 7200 7799
& Sub-cont
766 3,068 3928 3997 4016 5344 7883 7402 7468 6988 7416 8036 8795
TOTAL
Manhours
Project Award (29.11.2018), Engineering (Nov. 2018) , Construction (May. 2019)
© 2019 Petroliam Nasional Berhad (PETRONAS) |
Internal
Incident Category – PTS Pyramid
Unsafe 5 Unsafe Act 7
Condition
0 Property 0 Minor 0 Serious of
Damage Injury Fatality
Injury
0Near
Miss BS - PTS
12 Serious of Fatality Injury
1
UAUC
Minor Injury
10
Property Damage
30
No Injury or Damage (NM)
600
Substandard practices and conditions (PTS60.2111-Unsafe Acts) Substandard practices and conditions
(PTS60.2111-Unsafe Acts)
Internal
© 2019 Petroliam Nasional Berhad (PETRONAS) |
Leading Indicator
(2)
(0) (1)
HSE Weekly Walkabout
Project HSE Penalty HSE Management
Disciplinary Walkabout (8)
(0) ZERO Rules HSE Tier 1 Audit
(0) NCR JMS (0)
(0) SDN JHA (0) KPI
Actual
Emergency Response (5)
(1) Exercise HSE Induction
Toolbox Talk (Daily + Mass (1)
(24) TBM) Training - Inhouse
(Awareness)
HSE Meeting Training - External (e.g.
OGSP, CIDB, etc)
(2) Inspection Tools,
(1)
Equipment & machinery
(10)
Target PTD : Cumulative KPI Need Improvement Excellent
© 2019 Petroliam Nasional Berhad (PETRONAS) |
Internal
HSE Promotion, Program
& Training
Internal
This Month Program Achieved NOVEMBER 2019
No. Description Actual
1
2
3
4
5
6
© 2019 Petroliam Nasional Berhad (PETRONAS) |
Internal
Pictures Program
Internal
© 2019 Petroliam Nasional Berhad (PETRONAS) |
Internal
© 2019 Petroliam Nasional Berhad (PETRONAS) |
Internal
© 2019 Petroliam Nasional Berhad (PETRONAS) |
Internal
© 2019 Petroliam Nasional Berhad (PETRONAS) |
Internal
Next Month Program Planning – JANUARY 2020
No. Description
1 Mass Toolbox Talk
2 Inspection Tools, Machinery & Equipment
3 HSE Monthly Meeting with Progress Meeting
4 HSE / Management Walkabout
5 HSE Tier 1 Audit – First Line Assurance
6 HSE Observation
7 HSE Campaign
8 MCF Gap Assessment
9 Awareness Training
© 2019 Petroliam Nasional Berhad (PETRONAS) |
Internal
Thank you for your passion!