REPORTDMS PERFORMANCE CARD
2020
SCADA NETWORK MANAGEMENT
DISTRIBUTION SYSTEM OPERATOR
Table of Contents My DMS
01 | Core 1 : Our History 5 2
Teamwork Cross The Border 6
Commitment What We Do 7
02 | Core 2 :
Digital Data Reform of the DMS Data Management 9
Management
03 | Core 3 : Network Application Advance Tuning Workshop 11
Cultivate PSI Data Model Extraction Class 11
Education and Primary MV Data Extraction Training 11
Knowledge Philosophy of Modelling Transducer Class, Setting and Case Study 12
Culture Data Cable Extraction 12
Modelling MV New Element For Primary Substation 12
04 | Year 2020
Highlights Operational Passive Data Parameter Entry 14
Data Network Verification (CMS) 17
NA Data Model Error and Network Modelling Devices Rectification 18
Technical Losses Reduction Initiative 20
State Estimation Availability 23
Benefit to DSO 24
Irregularity Report Raised 25
Contribution - Others 26
Core 1 t
o
Commitment
My DMS
OUR HISTORY
Beginning in November 2016, the DMS journey began
as a lesser-known unit in DSO and may be seen as an
underdog.
Three adapted core values of DMS governance are
namely Teamwork Commitment, Digital Data
Management and Education and Knowledge
Cultivation.
With new objective and high commitment from DMS
team members, many achievements and tasks have
been completed successfully.
The enthusiasm and determination shown by entire
DMS team members has proven that a well-planned
and implemented task will lead to a success. DMS
team members are confident that concerted effort,
clear direction, motivation, and efficient work together
with high innovation and creativity would
yield in excellent results.
With this, we are presenting our DMS
Performance Report Card for Year 2020.
5
WE CROSS THE BORDER My DMS
DMS Nur Hidayah bt. Ghazali
Noridayu Rosli TEAM MEMBER
DMS NERCC
NERCC
Ahmad Aizzuddin Zainon
Senior Engineer DMS
Nurul Munira bt. Zulkifli
Nur Hidayah MSRCC
Ghazali
Nur Shamimi bt. Elias
DDMMS SNEteRaCmC is led by senior engineer and four
data technicians. Officially, two data technicians Noridayu bt. Rosli 6
are responsible for the MSRCC system while the
rest are in charge of NERCC system.
We believe…. We need to work together,
across boundaries, alone, we can do so little;
together, we can do so much.”
My DMS
WHAT WE DO
Manage passive operational data parameter in PSI SCADA Master
system. The data needed are transformer data, cable data, substation
data and maximum demand.
Continuously monitor active data quality at PMU level. Active data
quality focuses on Amp, kV, MW and MVAR readings at the primary
substation.
Check and monitor the network model in the PSI SCADA Master system
network topology. The purpose is to allow the calculated parameters to
be translated into state estimation calculations.
Actively executed the fine tuning network for State Estimation (SE)
function in the PSI SCADA Master System. SE is an application to estimate
the electrical state of a network by eliminating inaccuracies and errors
from measurement data.
7
Core 2 t
o
Data Management
DMS DATA MANAGEMENT My DMS
REFORMED
At present, we have a Beforehand, the huge data are Previously, the format report
well organized process scattered and not organized. Now was inconsistent. The
with One Stop Centre database, reporting is now
for operational data
verification. DMS operational data from synchronised across the
NERCC, MRCC and SRCC are region and DMS team able
9 collected and stored in order.
to monitor progress via
Online Dashboard.
Core 3 t
o
&Knowledge Culture
Through learning, we My DMS
recreate ourselves
01
Network Application Advance
Tuning Workshop
Tan Hei Fong
PSI In Control Tech
24 March 2020
02
PSI NA Data Model Extraction
Class
Jane Jasantha
Master System RO1
9 April 2020
03 11
Primary MV Data Extraction
Training
Nur Hafizah Suhada Mokhtar
PSI In-Control Tech
9 Sept 2020
Through learning, we able break My DMS
the barriers and limitations to
deliver the undeliverable.
04
Philosophy of Modelling Transducer
Class, Setting and Case Study Training
Nasrol Firdaus Abdul Wahab
Subject Matter Expert, ADMS Project
10 September 2020
05
Data Cable Extraction Tutoring
Nur Hidayah Ghazali
DMS, SNM-DSO
23 November 2020
06
Modelling MV New Element For
Primary Substation Tutoring
Nur Hidayah Ghazali
DMS, SNM-DSO
4 Dis & 8 Dis 2020
12
Y2020 t
o
The Year at a Glance
OPERATIONAL PASSIVE DATA My DMS
PARAMETER ENTRY COMPLETED
Y2016 Y2017 Y2018 OperaYtio2n0a1l9passive Y2020
November 2016 : Operational Operational passive data for Pahang, Operational passive
Began a feasibility passive data for data for Kuala N.Sembilan, data for Perlis.
Putrajaya was Melaka, Pulau Kedah, Kelantan,
study to find a Lumpur, Selangor, Pinang were Terengganu and
method to meet the completed. Johor were completed. Perak were
SRCC done. accomplished.
passive data accomplished. NERCC done.
requirements of the
PSI SCADA Master MRCC done.
System.
Unavailability operational passive data in PSI SCADA Master System
completed in 4 years.
14
OPERATIONAL PASSIVE DATA My DMS
PARAMETER ENTRY COMPLETED
15
TRANSFORMER
Ɨ TOTAL MRCC SRCC Ȯ NERCC
417 494
Primary 1,459 548
substations for 83,895 28,757 27,855
PMU and PPU 27,283
SUBSTATION
Secondary All data on the primary transformer and secondary substation have
substations been reviewed. Data registered in the PSI SCADA Master System,
DSO (November 2020).
OPERATIONAL PASSIVE DATA My DMS
PARAMETER ENTRY COMPLETED
CABLE 174,973 KM MRCC
Total Power Line 34,208 cable section
Cable Length with 58,541 KM
105,746 total SRCC
section 35,576 cable section
throughtout DSO with 54,158 KM
NERCC
35,962 cable section
with 62,273 KM
The results obtained after the data cables were reviewed by DMS. Distribution
cable network data as registered in the PSI SCADA Master System, DSO
16 (November 2020).
ALL NEW PASSIVE DATA My DMS
REGISTERED HAVE BEEN VERIFIED
MRCC SRCC NERCC
TOTAL CMS TOTAL CMS TOTAL CMS
2197 2218 2548
6722 out of 6963 CMS (96%) was verified by DMS for year 2020 which involved
operational passive data changes.
Our priority was to ensure the date registered comply the requirements of PSI
SCADA Master System.
17
My DMS
NETWORK APPLICATION (NA) DATA
MODEL ERROR RECTIFIED
CELCOM STAY SAFE As much as 11,406 NA
data model errors have
been reduced to 98
errors year-round.
The NA data model works behind
the network devices model. The
NA data model error cause the
State Calculation / Power Flow to
not work properly.
18
ERRORS IN NETWORK MODELING My DMS
DEVICES HAVE BEEN CORRECTED
311 network modelling errors have been fixed in year 2020. The effected
elements include the wrong element picture variable (PV), the incorrect
connectivity and incorrect mapping of connectivity to the devices in the model. It
caused residuals in the SE results.
19
My DMS
TECHNICAL WE ACHIEVE THE GOAL SET BY
LOSSES DSO MANAGEMENT!
REDUCTION • As per DSO’s target, 1,504 distribution network feeders
ACHIEVEMENT • were simulated in year 2020.
Six states namely Kuala Lumpur, Selangor, Putrajaya,
Negeri Sembilan, Melaka dan Johor were focused to carry
out the AFOR test.
20
TECHNICAL My DMS
LOSSES
REDUCTION 20,814 OPERATIONAL DATA
ACHIEVEMENT HAVE BEEN REVIEWED.
• Around 370 primary substations were reviewed including
10,222 secondary substations and 10,222 cable sections .
• Passive operational data was reviewed from the first leg of
incoming feeder up to the feedback feeder .
• The quality of operational active data was checked for 370
primary substations.
21
TECHNICAL My DMS
LOSSES
REDUCTION AFOR SUGGESTED TO CHANGE
ACHIEVEMENT NOP FOR 180 FEEDERS.
• The results obtained via AFOR was recorded and
forwarded to SPOS section for further analysis on the
suitability to perform NOP changes on site.
• Technical losses savings was 26,704kWh per day and a
total of 9,613,440kWh recorded for year 2020.
Month Kuala Selangor Putrajaya Negeri Melaka Johor
Lumpur Sembilan
January 0 0 0 000
February 0 0 0 000
0 18 0 000
March 0 0 0 090
April 0 5 0 040
May 8 0 000
June 2 67 0 0 0 10
July 0 4 0 000
August 12 10 0 000
September 6
9 0 003
October 20 0 0 000
November 0
0 0 000
December 0
121 0 0 13 13
22 TOTAL 40
My DMS
DAILY MONITORING OF THE STATE
ESTIMATION (SE) APPLICATION
MRCC SRCC NERCC
236 ONLINE 236 ONLINE 150 ONLINE
0 OFFLINE 0 OFFLINE 52 OFFLINE
100% ONLINE 100% ONLINE 74% ONLINE
• SE functionality is reviewed by daily basis (Working
days only).
• About 26% SE in NERCC was unable to run due to
error as it has insufficient operational passive data.
• The state estimation application need to run
without offline as it is vital for the SCADA network
applications.
23
My DMS
Impact Data Reliability
DSO Has New Facilitate operation by providing reliable
Norm! passive data which aid DSO to operate
confidently while conducting operational
DSO's passive data verification has analysis.
become the new 'norm' whereby a well-
organized process/method is used for
passive data verification.
DSO as a Information at
Reference Source Fingertips
TNB distribution network passive data is a Completion of passive data parameter
reference point for GIS and it is ready for provide just-in-time information to
new system implementation. operation section that helps analyse for
operation decision.
24
WE START MONITOR THE QUALITY My DMS
OF ACTIVE DATA
25
160 148 7 7
IRREGULARITIES IR SCADA IR PROTECTION IR SCADA
Re-raised as the
REPORT RAISED RAISED IR was closed
RAISED without rectifying
the error
1 Focuses on Amp, kV, MW and MVAR readings
for PMU and SCADA breaker status.
2 60% (95 IRs) related to the availability of
reading.
3 41% (65 IRs) related to breaker status in
unknown position.
Publishing DMS
Infographic
Others
5 DMS infographics were published throughout year 2020 and shared with
DSO via email.
26
Publishing DMS
Articlc
Others
DMS join hand with SPOS to produce an article called Technical Losses
Initiative and published in DSO Annual System Operation Report.
27
DN Technical DMS
Losses
Others
DMS work together with SPOS has contributed on DN-Distribution
Technical Losses initiative for year 2020.
28
Healthy DMS
Lifestyle
Others
All DMS team members participate in BookDoc (TNB Vibrant Living 29
Program) to promote a healthy lifestyle. One of DMS team member
was awarded 3 times as the top 10 female with highest step for year
2020.
Workshop DMS
Others
The final workshop on the verification of operational 30
passive parameter data organized by DMS together with
APP HQ, AD and O&M was held on 6 January 2020 at
TNB Ulu Kinta and NERCC.
Thanks for your
support and
being part of
Our Story…
Competency and System Regional Master System Team,
Technical Support Performance Operation SCADA Network
Management
and
Operation Studies.
Thank you
DMS Reporting
http://bit.ly/2Ylifo1
Address 1.: Address 2: This report is provided by:
MSRCC, Ground Floor, TNB Transmission NERCC, Aras 5, No 3031, Jalan Tenaga, Ahmad Aizzuddin bin Zainon
Building,129, Jalan Bangsar, PO BOX 11050, Seberang Jaya 13700 Perai, Pulau Pinang, DMS,
59200 Kuala Lumpur, Malaysia Malaysia. Distribution System Operator,
Tenaga Nasional Berhad.