PROJECT MANAGEMENT
A CASE STUDY
PREPARED BY
NORATIKA SHAHIRA BINTI ABDUL RONI
2017806216
BOKOR CPP PHASE-3 REDEVELOPMENT PROJECT
ABBREVIATIONS
CPP – Central Processing Platform
ESP – Electrical Submersible Pump
FEED – Front and Engineering Design
MMHE – Malaysia Marine and Heavy
Engineering
PCSB – Petronas Cari Gali Sdn Bhd
PMBOK – Project Management Body of
Knowledge
PTW – Permit To Work
QAQC – Quality Assurance and Quality
Control
WBS – Work Breakdown Structure
BOKOR CPP PHASE-3 REDEVELOPMENT PROJECT
WELCOME
CONTENTS
PROJECT
PHOTOS
PROJECT
SUMMARY
SUCCESSFUL
FACTORS
REFLECTIONS
REFERENCES
BOKOR CPP PHASE-3 REDEVELOPMENT PROJECT
PROJECT
PHOTOS
BOKOR CPP PHASE-3 REDEVELOPMENT PROJECT
PROJECT MANAGEMENT
PROJECT PHOTOS
BOKOR OIL FIELD IN BARAM DELTA
REGION, SARAWAK, MALAYSIA
BOKOR CPP AT FABRICATION YARD
IN MMHE WEST YARD, JOHOR
BOKOR CPP PHASE-3 REDEVELOPMENT PROJECT
PROJECT MANAGEMENT
PROJECT PHOTOS
BOKOR CPP AT FABRICATION YARD
IN MMHE WEST YARD, JOHOR
BOKOR CPP PROJECT FIRST STEEL
CUTTING CEREMONY
BOKOR CPP PHASE-3 REDEVELOPMENT PROJECT
PROJECT
SUMMARY
BOKOR CPP PHASE-3 REDEVELOPMENT PROJECT
PROJECT
SUMMARY
Bokor oil field located in the complex reservoirs. During
the year 2009, a total of three
Baram Delta offshore, ESPs were installed in the
field. The installation of ESPs
Sarawak, Malaysia with the had made a great
achievement as the oil field
depth of approximately 67m. managed to add
approximately 2.8 million
This shallow-water oil field barrels of oil without any
substantial rising in water cut.
was first discovered in the
1970s, based in approximately
45km northwest from the
offshore of Lutong, Sarawak.
Bokor oil field is owned by
Petronas Carigali Sdn Bhd
(PCSB) and Sarawak Shell Before coming to the Phase 3
Berhad, with PCSB as the Redevelopment Project,
main operator. In 1982, Bokor Bokor field was initially
oil field produced its first oil, equipped with three drilling
at which the oil recovery was platforms which were BODP-
taken place using a A, BODP-B, and BODP-C that
conventional gas lift process worked under solar power.
at the initial time. However, Other than that, Bokor field
the conventional method was was also had a satellite
not able to cope with the platform named BOK-A, that
increasing of oil demands was powered by a 400kW
each year (Offshore generator and was connected
Technology, 2019). It was then to BODP-C by a subsea power
coming to a redevelopment cable. At the BOK-A platform,
phase in 2007 to amend the a transformer was equipped
conventional gas lift process to step up the voltage to
to artificial lift technologies. 6.6kV for the reduction of
Electrical Submersible Pump subsea transmission losses. In
(ESP) was installed in the the other way around, BODP-
field to help in increasing the C was consisting of Light
capacity of the production Electrical Room (LER) that
because ESP was believed to housed a surface equipment,
be reliable and have great lighting facilities and safety
flexibility in handling system.
BOKOR CPP PHASE-3 REDEVELOPMENT PROJECT
The construction works for Meanwhile, Malaysia Marine
Bokor Phase 3 and Heavy Engineering
Redevelopment Project was (MMHE) was granted with a
began in the year of 2018 and contract for the EPCIC of CPP.
completed with a great The contract was cost RM1
success in 2020. It widen the Billion ($226.7 M) by PCSB.
Bokor field by developing The fabrication of the CPP
three new wellhead was being held at MMHE
platforms, BOKOR-D, West Yard in Pasir Gudang,
BOKOR-E and BOKOR-F, as Johor. For the transportation
well as a brand new Central and float-over installation,
Processing Platform (CPP). MMHE given the subcontract
ESPs were installed in these to Boskalis in July 2018.
wellhead platforms for Furthermore, Jurunature Sdn
enhancing the oil recovery Bhd was the fabrication
production. partner of MMHE, meanwhile
Labuan Shipyard and
On 12 April 2017, Brooke Engineering handled the yard
Dockyard and Engineering
Works Corporation was given services for helideck storage.
a contract for the
Engineering, Procurement, For the FEED and detailed
Construction, Installation and
Commissioning (EPCIC) for engineering design of Bokor
the three topsides, BOKOR-D,
BOKOR-E and BOKOR-F, as Phase 3 Redevelopment
well as the Front and
Engineering Design (FEED) Project, Berachah Group was
contract.
contracted. The Bokor CPP
Topside was reported to be
sailed away on 3 August
2020.
BOKOR CPP PHASE-3 REDEVELOPMENT PROJECT
SUCCESSFUL
FACTORS
BOKOR CPP PHASE-3 REDEVELOPMENT PROJECT
INITIATION
PHASE
"In a project, initiation
phase is where
everything will come to
a starting line."
During this phase, the especially for project
problem statement and
needs identification are manager. One of the items in
carried out to find what are
to be achieved by the end of project integration
this project. From the
problem statement or management is project
business needs, various
solutions and opportunities charter. The development of
are brainstormed together in
a team as an objective to project charter allows us to
access the direction of the
project (Lucid Content Team, know exactly what the
n.d.). At the same time, the
major deliverables of the direction of the project is
project are identified so that
the factors affecting it can be entirely. It includes the
figured out. Other than that,
initiation phase is very crucial project objectives,
because it is where the scope,
time, and cost baselines of methodologies to be carried
the project are being
identified at whole. Without out to achieve the objectives,
initiation phase, the project
will not have any direction and most importantly, who
towards the successful of it.
are the stakeholders that will
With that, project integration
management is important in take part in the project
the starting line. Before the
planning phase, it is a must (Wrike, n.d.). In fact, project
for the organizations under
the project to have a clear charter is vital in planning
vision on the project
and managing the project life
cycle. In this project, project
charter was documented by
PCSB after knowing the need
for further expansion and
redevelopment of Bokor oil
field. As the increasing of oil
demands through the years,
more oil rigs are needed to
produce more oil to the
world. The problem
statement for this project was
noted by PCSB, then they
gave the redevelopment
authority to MMHE for
applying the organizational
BOKOR CPP PHASE-3 REDEVELOPMENT PROJECT
resources and conducting the Throughout the project,
project activities. Without
project charter, the objectives stakeholder’s opinions and
will not be understanding
and it will be hard for the needs must be addressed so
owner of the project to
attract contractors for that every stakeholder
conducting the project
activities. participated in the project
will be happy with the result.
Such as in this project, PCSB
was the client while MMHE
was the main contractor.
Other than that, MMHE
Moreover, in this phase, contracted Brooke Dockyard
project stakeholder and Engineering Works,
management is important to Boskalis, Labuan Shipyard
identify the organizations or and Engineering, and
individuals that will take part Jurunature Sdn Bhd as the
into the completion of the subcontractor to help them
project. It is a must for the in managing and conducting
project manager and its team the project activities.
to identify the list of
stakeholders and prioritize
their concerns to the project.
This is crucial as to make sure
that each stakeholder’s needs
and expectations are met by
the end of the project. With
that, it can also be said that
the commitment of
stakeholders might be the
reason of the success or
failure of a project.
BOKOR CPP PHASE-3 REDEVELOPMENT PROJECT
PLANNING
PHASE
"Planning phase is the continuation of initial
phase when the project is approved and the
stakeholders involved under the project are
identified."
When the project is allowed especiallyProject scope is also
to be moved forward,
planning phase is carried out important in identifying the
to plan the project entirely,
especially on deciding the Work Breakdown Structure
project life cycle for the
successful of the project (WBS) for the project as we
schedule. This project life
cycle must possess the scope, are decomposing the big
time, and cost baselines to
ensure that the product to be project into smaller
delivered is within the
customer’s need and finish manageable tasks (Westland,
according to the required
time without overbudgeting. 2019). Stakeholders deserved
Usually, one of the planning
activities in this phase to be to approve the deliverables of
carried out is decomposing
the bigger project into certain task regularly, so it is a
smaller tasks so that it will be
more manageable and can must for the project manager
be performed simultaneously,
hence saving the tasks time. to manage the project scope
Before creating the project ahead of a time. In this
life cycle, project scope is first
identified. The project scope project, MMHE was
need to be managed because
we need to know and responsible to manage the
understand it so that all
solutions or decisions making project scope as a main
to be performed are
according to the scope to be contractor. The WBS for this
achieved.
project was developed and
the tasks were divided
among the subcontractors
that were hired by MMHE.
From here, the tasks were
performed simultaneously
and more efficient. It is best
believed that they managed
to consider project scope
management because the
product outcome was
according to PCSB needs. At
the end of the project, Bokor
CPP was developed
successfully and managed to
function well.
BOKOR CPP PHASE-3 REDEVELOPMENT PROJECT
In any project, time is the quarter of 2020. Nevertheless,
due to the success of project
most crucial part. As schedule development and
creation of buffers to tackle
everything is revolve around the wasted void, MMHE
managed to complete the
the matter of time, it is a project by the third quarter of
the year.
must for the project manager
to ensure that the project can
be done according to the
required time. The project
time management need to
be applied especially when As an addition, resources are
things are constantly important in project to
changing over the phases in ensure that it can be kicked
any project. In managing the off into a start. One of the
time, project schedule is crucial resources are
made to arrange all tasks in materials because without
one document including materials, any task cannot be
appointed the responsible started. Thus, it is a must to
person for the certain task. make sure that the materials
With the development of are managed such as
project schedule, every task according to the project
to be done will have their procurement management.
own start dates and Procurement involves the
deadlines. Eventually, all obtaining of raw materials,
tasks managed to be done supplies, and services for any
according to the required task in the project. The
duration. Regardless, the management of these project
sequenced tasks must be procurement can help in
assigned along with ensuring that there will be no
resources such as manpower problems on the raw
and material. Gantt chart is a materials that can delay the
famous tool in managing the completion of any project
project schedule, as well as task. In this project, project
visualizing the resources and procurement management
budget for each task. For was applied to manage all
Bokor Phase 3 the raw materials and
Redevelopment Project, CPP services involved. It can be
by MMHE, we can see that seen by the development of
MMHE managed to apply Material Receiving Note
project time management as (MIRN) as the raw materials
the project was done by the entering the warehouse, and
required time. Even so, MMHE Mill Certificate for the raw
was actually faced a crisis materials to ensure that the
due to the COVID-19 standard is according to
outbreak, where MMHE was client’s requirement.
forced to close the
fabrication yard in the second
BOKOR CPP PHASE-3 REDEVELOPMENT PROJECT
EXECUTION
PHASE
"In project management, execution phase is a
little bit challenging than any other phases
because it is where everything needs to get at
work."
After developing the plan for ensure that the project
the whole project, it is come communication is managed
to an execution phase where throughout the project.
every planning is conducted Especially for the clients,
according to the planned project manager must ensure
methodologies. The that every decision and
responsibility of project solution made is being
management in this phase informed to them in order to
become increase as the avoid any confusion between
project manager needs to client and contractor. The
keep every work conducted is communication between the
on track by managing the team members is also vital to
working timelines, as well as make sure that every task
organize an efficient team so being done is following the
that the work done will be planned project scope and
according to the original schedule. For an instance, at
plan. Bokor Phase 3
Redevelopment Project,
Communication is one of the MMHE had prioritized the
mediums that connect a importance of project
person with another. Even in communication
project manager, management in the project.
communication between the Such as before conducting
stakeholders is very any work, they hold a
important to ensure that ‘Toolbox Talk’ to brief their
every information is delivered team members on the things
in detailed. For any that need to be done on that
miscommunication certain day. All problems that
happened during the were issued on the day
execution phase, it might before were also being
affect the process at a whole delivered in this ‘Toolbox Talk’
and create a delay at certain so that such problems would
timeline. Hence, it is project not happen again.
manager’s responsibility to
BOKOR CPP PHASE-3 REDEVELOPMENT PROJECT
Regardless, sometimes these Time Injury (LTI). Which
means, they highly prioritized
people are hard to be the safety of their workers
during the project.
managed, especially in a
project that consists of many
individuals within. Therefore,
project human resource Other than that, execution
management is a need in a phase is the phase where
project to ensure that every many risks will come to the
important resource is being condition. There are many
given the best and make factors that can lead to the
them work in a comfortable initiation of risk at the certain
environment. Human task. Thus, project risk
resources also help to find management is important to
the roles and identify the identify the possible risks that
requirements of those can happen in any phase in
positions that could fit in the the project and outline the
structure of the project. respective mitigation
When the roles are identified, countermeasures. An
then we can fill them into a execution of project risk
project team. Moreover, management in this phase
human resources responsible can help us on what to do
in providing the training and when such risk is coming to
induction course to all the life. For an example, it
workers so that they know all helps the worker to find the
Standard Operational resource person for such risk
Procedures (SOP), practices, every time when the
and job scope to be followed. problems happened. The
This item can be seen in resource person is
Bokor Project where MMHE responsible to properly
considered the need of identify and handle that
training to the future workers. certain risk. With that, the
Before starting the task, all risks happened during the
workers were required to execution phase can be
attend a safety training controlled and managed. In
course to brief on the Health, Bokor Project, project risk
Safety and Environment management was handled
(HSE) practices that needed well by MMHE. Especially
to be followed throughout during the COVID-19
the project. Besides, the new outbreak that forced them to
workers also need to pass a close the fabrication yard,
Permit To Work (PTW) license they managed to tackle all
for them to be able to risks related to the closing of
conduct any related job. In their yard and finish the
fact, Bokor Project had project within the scheduled
succeeded a Total Man-hours time.
of 8,687,748 without Lost
BOKOR CPP PHASE-3 REDEVELOPMENT PROJECT
EXECUTION PHASE
PROJECT PHOTOS
BOKOR CPP PROJECT FIRST
EXECUTION PHASE
BOKOR CPP PROJECT FIRST
EXECUTION PHASE
BOKOR CPP PHASE-3 REDEVELOPMENT PROJECT
EXECUTION PHASE
PROJECT PHOTOS
BOKOR CPP PLATFORMS
INSTALLATION
BOKOR CPP HEAVY PLATFORM
LIFTING
BOKOR CPP PHASE-3 REDEVELOPMENT PROJECT
MONITORING &
CONTROLLING
PHASE
"Project monitoring and controlling phase is the
phase that run simultaneously with execution
phase."
It helps to analyse execution Their famous motto was
phase so that any potential “Today’s quality, for
problems related to any tomorrow’s safety”, showing
certain task can be how important quality to
recognized and managed it ensure the safety of the
throughout the execution individuals within. Moreover,
phase of the project. As a MMHE Quality Policy was
matter of fact, the primary applied entirely throughout
goal of monitoring and the execution of the phase to
controlling phase is to be ensure that the project was
actively in identifying conducted with high quality
problems and take manner as well as meeting
countermeasure actions the applicable requirements.
(Hassib, 2018). With that, the All employees were also in
project plan can be ensured compliance of this policy and
to be accepted within the it was their responsibility to
variances of standards and promote and implement this
specifications from the client. policy in every phase of the
One of the important items of project, especially in
this phase in Bokor Project execution phase.
was the project quality
management. Since offshore
structures are very critical, the
quality of every aspect must
be prioritized to ensure that
the structures are believed to
be in the top notch quality. In
MMHE, there were various
quality policies that were
followed to ensure that the
project can be finished with
the best quality.
BOKOR CPP PHASE-3 REDEVELOPMENT PROJECT
As an addition, MMHE had applied inspection was NDT
because the product was
Quality Control and Quality obviously could not be
destructed. Some of the
Assurance (QAQC) teams that inspections that fall under
NDT were Ultrasonic Testing,
focused on ensuring the Magnetic Particle Inspection
and Visual Testing. All of
quality of the product. In these inspections were
carried out on some parts of
Bokor Project, various the product to ensure that
the product was according to
inspections and testing under the specifications and
required standard.
QAQC team that were
conducted to inspect on the
quality of the product. The
inspections were consisted of
Destructive Testing (DT) and
Non-Destructive Testing
(NDT). Nevertheless, the most
MMHE QUALITY POLICY
BOKOR CPP PHASE-3 REDEVELOPMENT PROJECT
MONITORING AND CONTROLLING PHASE
PROJECT PHOTOS
QUALITY CHECK: VISUAL
TESTING
QUALITY CHECK: ULTRASONIC
TESING
BOKOR CPP PHASE-3 REDEVELOPMENT PROJECT
CLOSING
PHASE
"This phase is where the final deliverables is
provided, project resources release, and
determination of the success of the project."
When all project tasks have This Bokor CPP Phase-3
completed and the product Redevelopment Project
has come to a full structure managed to be finished by
that is within the scope, the MMHE within the project
closing phase will be entered. scope, where a CPP weighed
Again, the success of the at 18,995 MT in total was
project is based on the scope, delivered to the client
time, and cost baselines according to the planned
(Jordan, 2014). Hence, those project duration. Even
baselines are reviewed again though they faced a crisis
in this phase to ensure the during COVID-19 outbreak,
success of the project. Project but they able to control the
manager responsible to risk and managed it well. The
review the project load out and sail off the
performance to determine Bokor CPP was held on 3rd
whether the project is August 2020 successfully.
completed within the project
scope, project duration, and
under planned budgets. The
closing documentations of
the project such as post-
implementation review,
accountancy report, and
project report are also made
in this phase so that any
future project can review it as
a reference.
BOKOR CPP PHASE-3 REDEVELOPMENT PROJECT
CLOSING PHASE
PROJECT PHOTOS
BOKOR CPP LOAD OUT
PROCESS
BOKOR CPP
CROSSOVER
BOKOR CPP PHASE-3 REDEVELOPMENT PROJECT
REFLECTIONS
BOKOR CPP PHASE-3 REDEVELOPMENT PROJECT
OVERALL FACTORS
REFLECTIONS
Once completion of this
project, Bokor CPP was
successfully sailed away
to its field in Baram Delta
offshore, Sarawak. The
project managed to be
done within the planned
duration from April 2017,
until its sailing ceremony
in August 2020. The
completion of this CPP
Project has increased the
oil production as to cope
with the higher demands
of oil from the whole
world. From the success
of this project, Bokor CPP
is one of the most
operating CPPs by PCSB
at the offshore. There are
many factors that led to
the success of this project.
Most importantly, it is well
defined that they
implemented 10 Project
Management Body of
Knowledge (PMBOK)
while executing this condition that are exposed to the possibility of
corrosions, stress concentrations, biofouling effects
project and came to a and fatigue, the project could be considered as
high risk because many parameters needed to be
success point. considered. Without quality management, the
product would not come out in the best quality
One of the most and might be affected once it was operated at the
offshore field. Hence, throughout this project,
highlighted items in this quality management was highly prioritized and
utilized to ensure that the quality of the product
project that led to the was regularly monitored and controlled. If they
have not applied this project quality management,
success of this project
was the success of their
QAQC management.
Since offshore structures
are so critical due to its
BOKOR CPP PHASE-3 REDEVELOPMENT PROJECT
OVERALL FACTORS
REFLECTION
the specifications and standards of the product taken quality
would be declined from the client, which was
PCSB because obviously, quality was important for management in the
them too. In fact, the quality of the product can
also affect the safety of the resources within highest priority because
especially for the humans that are working inside
the offshore structure. In current days, we have they knew that the
seen many incidents that happened due to the
collapse and sinking of oil structures in the quality of the product was
offshore. This is so critical as it might affect many
losses such as human life and costs. Thus, MMHE the most important
parameter.
Moreover, MMHE
appointed skilful and
trained workers to
conduct any task within
the phase in the project.
In fact, every worker that
was involved in the
project must attend an
induction course that
outlined all policies and
safety precautions that
needed to be followed
while committing in this
project. With the
induction course, all
workers managed to
know how to take care of
themselves so that a safe
working environment
could be adapted. Other
than that, MMHE
provided training to the
workers that needed an
expert to work on high
risk task such as welding,
rigging, painting, blasting,
and more. The training
allowed them to have
their own PTW, so that
they could do the work
under high degree of
BOKOR CPP PHASE-3 REDEVELOPMENT PROJECT
OVERALL FACTORS
REFLECTIONS
training. A professional
and expert worker can
contribute efficiently to
the job to be done and
consequently, a quality
product that met the
standard requirement can
be produced.
A success of project risk
management also led to
the success of this project.
Since this project was
held during the COVID-19
outbreak, the project was
forced to be halted due to
Movement Restricted
Order (MCO) that closed
all industries. However,
with the top-tier risk
management and
creation of buffers in the
project schedule, this
project managed to be
done despite the time
loss. The risk
management was also
taken into the platform. It was to make sure that the equipment
used to rig and lift the big platform could
consideration at which withstand its weight, so that it would not collapse
during the lifting process.
planning on the safety of
Other than that, the project structure was clearly
the offshore structure. The defined in this project. Every project scope was
explained in detail manners to the stakeholders.
identification of The project structure also was being planned
thoroughly to ensure that all tasks were done
prominent risks was according to the project schedule. The
implementation of WBS documentation in this
made in this project to
ensure that the safety and
quality of Bokor CPP. For
an example, a strict
calculation was made
before the lifting of the
BOKOR CPP PHASE-3 REDEVELOPMENT PROJECT
OVERALL FACTORS
REFLECTION
project had allowed many tasks to be done in a As a conclusion, it can be
time hence eased the completion of the project.
All workers had clear vision on their job scope and seen that MMHE
what to be done by the end of that certain day.
For an instance, every subcontractor had their own implemented 10 PMBOK
work scope such as Jurunature Sdn Bhd for the
fabrication of Bokor CPP and First Oil Engineering while conducting this
Sdn Bhd for the fabrication of jacket and bridge
for Bokor CPP. project. The success of 10
PMBOK implementation
had led to the success of
this project. From here, it
is obvious on how
important of 10 PMBOK in
deciding the success of
failure of a project.
Without implementation
of 10 PMBOK, the project
will face a huge loss, and
the project might not be
able to finish within the
detailed project scope
under the planned
duration. Therefore, every
project must prioritize the
implementation 10
PMBOK so that the
project can be chartered
successfully.
BOKOR CPP PHASE-3 REDEVELOPMENT PROJECT
REFERENCES
BOKOR CPP PHASE-3 REDEVELOPMENT PROJECT
REFERENCES
Hassib, A. (2018, May 16). Project Monitoring and Control.
Retrieved from PM Documents:
https://pmdocuments.com/project-monitoring-and-control/
Jordan, A. (2014, November 11). Three Steps to Success in
Delivering Your Offshore Project. Retrieved from InfoQ:
https://www.infoq.com/articles/three-steps-success-ofshoring/
Jurunature Sdn Bhd. (n.d.). Gallery. Retrieved from Jurunature
Sdn Bhd: https://www.jurunature.com/gallery.php
Lucid Content Team. (n.d.). The 4 Phases of the Project
Management Life Cycle. Retrieved from Lucid Chart:
https://www.lucidchart.com/blog/the-4-phases-of-the-project-
management-life-cycle
MHB: Malaysia Marine and Heavy Engineering Holdings Berhad.
(2020). Annual Report. Kuala Lumpur.
Offshore Technology. (2019, December 13). Bokor Phase 3
Redevelopment Project. Retrieved from Offshore Technology:
https://www.offshore-technology.com/projects/bokor-phase-3-
redevelopment-project/
Westland, J. (2019, November 27). The 10 Project Management
Knowledge Areas (PMBOK). Retrieved from Project Manager:
https://www.projectmanager.com/blog/10-project-management-
knowledge-areas
Wrike. (n.d.). What Is Project Integration Management? Retrieved
from Wrike Project Management:
https://www.wrike.com/project-management-guide/faq/what-is-
project-integration-management/