DOBLE ENGINEERING
Marlborough, Massachusetts
PROJECT INFORMATION Engineer
WB Engineers & Consultants
Project Size: 66,000SF 155 Seaport Blvd. | Boston, MA 02210
Project Value: $1.80 Million
Schedule Duration: 6 Months 617.443.4950
Location: 123 Felton St | Marlborough, MA
This project included the installation of all new
PROJECT TEAM lighting, switchgear, and installation of power to an
existing generator. The existing building was
General Contractor converted into the new Doble Engineering
J Calnan & Associates headquarters
3 Batterymarch Park, Quincy, MA 02169
(617) 801-0200
jcalnan.com
Architect
Visnick & Caulfield
222 Berkely Street | Boston, MA
617.457.0990
vca-arch.com
DECIPHERA PHARMACEUTICALS
Waltham, Massachusetts
PROJECT INFORMATION Engineer
Project Size: 71,500SF Combined) WB Engineers & Consultants
Project Value: $2.94 Million (Phase 1 & 2) 155 Seaport Blvd. | Boston, MA 02210
Schedule Duration: 12 Months (Phase 1 & 2 617.443.4950
Location: 200 Smith St | Waltham, MA
PROJECT TEAM This was a two phase project. Phase I included the
1st floor & Mezzanine interior alterations. Base
General Contractor building structural steel design. New raised access
J Calnan & Associates open flooring system, 35’ exposed ceilings.
3 Batterymarch Park, Quincy, MA 02169 Polished concrete throughout. Exterior excavation/
trenching for conduit runs for new INTERNET
(617) 801-0200 service provider cabling & fiber runs AV/Media wall
jcalnan.com with new structural steel for interior tiered seating
atrium.
Architect
SGA Phase 2 included the Expansion of Phase 1 - Office
200 High St # 2, Boston, MA 02110 spaces and work stations including new lighting
and lighting control systems.
(857) 300-2610
sga-arch.com
ABT ASSOCIATES Engineer
WB Engineers & Consultants
Cambridge, Massachusetts
155 Seaport Blvd. | Boston, MA 02210
PROJECT INFORMATION 617.443.4950
Project Size: 80,000SF
Project Value: $1.9 Million Project consisted of a 5 floor fit up including
Schedule Duration: 6 Months high-end finishes, lighting, patio renovation, HVAC
Location: 10 Fawcett St. | Cambridge, MA equipment and controls, and a stairwell between
floors.
PROJECT TEAM
General Contractor
Chapman Construction | Design
84 Winchester St, Newton, MA 02461
(617) 630-8408
chap-con.com
Architect
IA Interior Architects
One International Place, 100 Oliver St Suite 210,
Boston, MA 02110
(617) 380-0777
interiorarchitects.com
NETSCOUT Engineer
WB Engineers & Consultants
Westford, Massachusetts
155 Seaport Blvd. | Boston, MA 02210
PROJECT INFORMATION 617.443.4950
Project Size: 150,000SF
Project Value: $1.5 Million Project included the renovation and expansion of
Schedule Duration: 8 Months Netscout’s existing Server Lab while it remained in
Location: 31 Littleton Road | Westford, MA service. It also included a new 3000amp service and
switchgear to the Netscout building.
PROJECT TEAM The project also consisted of a complete renovation
of their building’s Café area. New lighting, lighting
General Contractor controls and fire alarm equipment were provided
J Calnan & Associates throughout.
3 Batterymarch Park, Quincy, MA 02169
(617) 801-0200
jcalnan.com
Architect
Margulies Perruzzi Architects
308 Congress St, Boston, MA 02210
(617) 482-3232
mparchitectsboston.com
MERCHANTS ROW
Hanover, Massachusetts
PROJECT INFORMATION Engineer
Project Size: 61,000SF AHA Engineers
Project Value: $1.4 Million 24 Hartwell Ave. Lexington, MA
Schedule Duration: 7 Months
Location: 2053 Washington Street | Hanover, MA (781) 372-3000
aha-engineers.com
PROJECT TEAM
The project provided new “streetscape retail”
General Contractor including the ground up construction of 3 new
J Calnan & Associates buildings and electrical service in all 3 buildings
3 Batterymarch Park, Quincy, MA 02169 including (1) at 2500amps, (1) at 2000amps and (1) at
800amps. Fire alarm systems were installed for all
(617) 801-0200 buildings.
jcalnan.com
Architect
TROIKA
15 Channel Center Street, Boston, MA 02110
(857)991-1021
studiotroika.com
OCEAN SPRAY HEADQUARTERS
Lakeville, Massachusetts
PROJECT INFORMATION All new building wide Lutron lighting control system,
high end lighting, new electrical distribution throughout
Project Size: 160,000SF and a brand new fire alarm system was installed while
Project Value: $2.7 Million maintaining the existing system throughout
Schedule Duration: 2.5 Years construction.
Location: 1 Ocean Spray Drive | Lakeville, MA
PROJECT TEAM
General Contractor
J Calnan & Associates
3 Batterymarch Park, Quincy, MA 02169
(617) 801-0200
jcalnan.com
Architect
Margulies Perruzzi Architects
308 Congress St, Boston, MA 02210
(617) 482-3232
mparchitectsboston.com
CHANDRA OCC RELOCATION PROJECT
Burlington, Massachusetts
PROJECT INFORMATION Engineer
RDK Engineers
Project Size: 30,000SF 70 Fargo Street, Boston, MA
Project Value: $1.38 Million
Schedule Duration: 4 Months 617.345.9885
Location: 15 Wayside Road | Burlington, MA nv5.com
PROJECT TEAM Project included the tenant fit out for entire 3rd
floor which included office space, labs and server
General Contractor rooms. Also included was the installation of a 150kw
Chapman Construction | Design UPS and a 350kw generator with load bank and ATS
84 Winchester St, Newton, MA 02461 (Automatic Transfer Switch) Fire alarm systems were
installed including a pre-action system for their
(617) 630-8408 state of the art server room.
chap-con.com
Architect
Hudson Design Group
45 Beechwood Drive, N. Andover, MA
978.557.5553
hudsondesigngroupllc.com
S&W PROJECT TEAM
ANDREW MATT
TAVARES SYLVIA
Project Manager Principal
Andrew has been a part Matt is a Co-Founder and
of the S&W team for 12 Principal of S&W. He will
years as a Project Manager. be heavily involved in the
Trough out his tenure with management of this
S&W he has lead a variety project.
of projects ranging in value
and scale. Andrew will be Contact Matt
the Project Manager for
this contract. [email protected]
P. 508.697.9680 EXT. 11
Contact Andrew C. 508.982.4990
[email protected]
P. 508.697.9680 Ext. 13
C. 774.930.1045