Final Schematic Design

S/n Description of Works Count Budget Cost Remarks
4.0 Block 11 - 1F and 2F Lift lobby
2 -$ 331,000.00-

Renovate existing Block 11 lift lobby

Demolish existing floor tiles 2 -$ 2,200.00-
1,200.00- assumed 3m high
Demolish existing glass partition including support 2 -$
-  - omitted as per comment
Demolish existing wall tiles 2 -$ 500.00-
2,000.00-
Demolish existing mail box 1 -$ 5,900.00-
30,800.00- 2.4m high
Demolish existing bulkhead 2 -$
2,040.00- No fins above glass partition
Demolition Works -$
20,000.00- 24m2
Supply and install new glass partition 2 -$ 19,200.00- $400/no. Supplier's quote is $350/no

Screen Wall in 150x300 fins made of dry wall 22,000.00- assuming PC supply rate of $90/m2

construction using metal faming and calcium silicate 2 -$ 21,600.00- installation rate considreed at $120/m2

boards 6,400.00-

Construct new curved wall as entrance to stairs 2 -$ 600.00-

Construct new mail box 1 -$ 5,500.00-

Supply and install new travertine stone look alike tiles to 2 -$ 10,000.00-
floor including screed and waterproofing quote from HMH electro painters for 1250 per set.

Apply special paint finish on top of the existing wall tiles 2 -$ 5,800.00- (+6590121096, Rafoob).
to achieve travertine look Considered lift doors

Supply and install new ceiling similar to current in paint 2 -$ 15,600.00-
finish

Supply and install metal trimming for ceiling 1 -$

Demolish existing and then reconstruct new ramp with 1 -$
SS tactile inserts

Electrical Works ie light fitting and sensor for entrance 2 -$

Polish and make good existing stainless steel doors and 2 -$
panels

Contingency (10%) -$

LIFT LOBBIES

BASIC FINISHES SPECIFICATIONS


S/n Description of Works Count Budget Cost Remarks
5.0 Lowrise Building - Basement Lift Lobby
13 -$ 387,400.00- to confirm quantity

Renovate existing basement lift lobby

Demolish existing floor tiles -$ 300.00-
Demolish existing wall tiles -$ 200.00- assumed 3m high
-$ 500.00-
Demolition Works -$ 660.00- assumed 3m high
cables at 50 centers with creepers
Supply and install new floor tiles including screed and -$ 2,700.00- assuming PC supply rate of $90/m2

waterproofing -$ 1,500.00- As per designer's comment; installation rate at
$120/m2
Apply special paint finish on top of the existing wall tiles
-$ 1,000.00-
Renovate ceiling in calcium sylicate board and paint
finish -$ 800.00-

Supply and install new plasterboard to the perimeter of -$ 500.00-
the new ceiling in metalic carpaint and trimming -$ 1,200.00-
-$ 1,500.00-
Skim coat and paint to walls as shown on the drawing
Supply and install new signage in SS finish -$ 6,500.00- including 3 new bollards

Electrical Works ie light fitting and light sensor quote from HMH electro painters for 1250 per set.
Demolish existing and then reconstruct new ramp with -$ 1,500.00- (+6590121096, Rafoob).

SS tactile inserts Considered lift doors

Polish and make good existing stainless steel doors and -$ 3,600.00-
panels
-$ 5,000.00- Consider creepers along the metal fins, two trees, two
Hacking of old mail boxes and installatin of new mail stainless steel planter edge, 150tall, 1500dia.
box with a front panel in SS finish for all low blocks
-$ 2,800.00-
Landscape
-$ 1,068,400.00-
Contingency (10%)

Total Excluding 7% GST

LIFT LOBBIES

BASIC FINISHES SPECIFICATIONS


S/n Description of Works Count Budget Cost Remarks
1.0 Site Preliminaries
2.0 Block 9 - 1st Floor Entrance ($ 68,900.00) subject to final project cost (10%)

1 ($ 97,400.00)

Renovate existing Block 9 1st floor entrance

Hack off existing floor finish to entrance ($ 3,300.00)
Demolish existing entrance stairs and ramp ($ 1,500.00)
($ 1,800.00)
Demolish existing ceiling ($ 12,000.00) 1nr
Construct new ramp ($ 7,200.00) assumed 1m high

Supply and install new railing to ramp ($ 32,500.00) assuming PC supply rate of $90/m2

Supply and install new travertine look-alike tiles to floor as shown in the photo including screed ($ 6,000.00)
and waterproofing ($ 2,400.00)
($ 5,000.00)
Supply and install false ceiling like current ($ 9,200.00)
Supply and install new plasterboard to the perimeter of the new ceiling in metalic carpaint and ($ 4,600.00) For Wiring, DB termination, motion sensors and labour to install

trimming lights
Skim coat and paint to walls as shown on the drawing ($ 3,000.00)
Provisional Sum to supply new light fittings (Dimmable where necessary)
($ 8,900.00)
Electrical Works
Seat at the entrance along the platner and near the stairs for waiting

New landscape (as shown in the drawing)
Contingency (10%)

CONNECTING LOBBIES

BASIC FINISHES SPECIFICATIONS


S/n Description of Works Count Budget Cost Remarks
3.0 Block 9 - 1st Floor lobby 1 ($ 180,000.00)

Renovate existing Block 1st Floor lobby

Hack off existing floor finish to drop off ($ 6,000.00)
Demolish existing ceiling ($ 4,800.00)
($ 500.00)
Demolish existing ceiling to 1F counter ($ 200.00)
Demolish existing railing to replace with new curved glass railing ($ 1,000.00)
($ 59,800.00) assuming PC supply rate of $90/m2
Demolish existing counter ($ 12,000.00)
Supply and install new travertine look-alike tiles to floor as shown in the photo including screed ($ 4,320.00)
($ 4,200.00)
and waterproofing
Supply and install new ceiling in calcium sylicate in paint finish ($ 7,600.00) Assumed PC supply rate of $140/m2
Supply and install new plasterboard to the perimeter of the new ceiling in metalic carpaint and
($ 15,500.00)
trimming
Screen wall in dry wall construction of 300x150 fins behind the counter ($ 400.00)
($ 5,500.00)
Supply and apply new plaster and special paint in 2 textures (grainy and smooth) to walls at the ($ 15,000.00)
counter as shown on the drawing
($ 11,500.00)
skim coat and paint for existing columns and walls
($ 6,900.00) For Wiring, DB termination, motion sensors and labour to install
Change chrome finish to buff finish lights
Supply and install new green cables across the counter as shown on the drawing
($ 15,600.00)
Supply and install new built-in counter as shown on the drawing

Provisional Sum to supply new light fittings (Dimmable where necessary)

Electrical Works

Contingency (10%)

CONNECTING LOBBIES

BASIC FINISHES SPECIFICATIONS


S/n Description of Works Count Budget Cost Remarks
5.0 Block 11 - 2nd Floor lobby 1 ($ 140,000.00)

Renovate existing Block 1st Floor lobby

Hack off existing floor finish to drop off ($ 4,500.00)
Demolish existing ceiling ($ 3,600.00)
($ 500.00)
Demolish existing ceiling to 1F counter ($ -  ) assumed that existing railing are not to be replaced
Demolish existing railing ($ 1,000.00)
Demolish existing counter ($ 46,800.00) assuming PC supply rate of $90/m2

Supply and install new travertine look-alike tiles to floor as shown in the photo including screed ($ 13,500.00)
and waterproofing ($ 4,320.00)
($ 2,400.00)
Supply and install new ceiling in calcium sylicate in paint finish
Supply and install new plasterboard to the perimeter of the new ceiling in metalic carpaint and ($ 4,400.00) Assumed PC supply rate of $140/m2

trimming ($ 8,900.00) Assumed PC supply rate of $50/m2
Screen wall in dry wall construction of 300x150 fins behind the counter
Supply and apply new plaster and special paint in 2 textures (grainy and smooth) to walls at the ($ 2,300.00) assumed that existing railing are not to be replaced

counter as shown on the drawing ($ 15,000.00)

skim coat and paint for existing columns and walls ($ 11,500.00)

handrailling buff finish ($ 6,900.00) For Wiring, DB termination, motion sensors and labour to install
Supply and install new built-in counter as shown on the drawing lights
Provisional Sum to supply new light fittings (Dimmable where necessary)
($ 12,600.00)
Electrical Works

Contingency (10%)

CONNECTING LOBBIES

BASIC FINISHES SPECIFICATIONS


S/n Description of Works Count Budget Cost Remarks
6.0 Block 11 - Lobby Courtyard 1 ($ 180,700.00)

Renovate existing basement lift lobby

Demolish existing floor tiles ($ 8,900.00)

Supply and install new travertine look-alike tiles to floor as shown in the photo including screed ($ 70,000.00) assuming PC supply rate of $90/m2
and waterproofing
($ 15,000.00)
Supply and lay granite chips ($ 8,800.00)
Supply and install new plasterboard ceiling as per drawing ($ 9,000.00) assuming PC supply rate of $105/m
($ 27,900.00) Assumed PC supply rate of $50/m2
Supply and install new plasterboard to the perimeter of the new ceiling in metalic carpaint and ($ 11,200.00)
trimming ($ 6,400.00)

skim coat and paint for existing columns and walls ($ 3,500.00)
Prepare and apply new EPDM flooring ($ 3,500.00) For Wiring, DB termination, motion sensors and labour to install

Supply and install new green cables screening the parking and going to upper level as shown on lights
the drawing ($ 16,500.00)

Provisional Sum to supply new light fittings (Dimmable where necessary)
Electrical Works

Contingency (10%)

CONNECTING LOBBIES

BASIC FINISHES SPECIFICATIONS


S/n Description of Works Count Budget Cost Remarks
1.0 Block 11 - 1st Floor Entrance
1 ($ 90,000.00)

Renovate existing Block 11 1st floor entrance

Hack off existing floor finish to entrance ($ 3,300.00)
Demolish existing entrance stairs and ramp ($ 1,500.00)
($ 3,600.00)
Demolish existing ceiling ($ 12,000.00) 1nr
Construct new ramp ($ 7,200.00) assumed 1m high

Supply and install new railing to ramp ($ 16,250.00) assuming PC supply rate of $90/m2
Supply and install new travertine look-alike tiles to floor as shown in the photo including screed
($ 6,000.00)
and waterproofing
Supply and install new ceiling in calcium sylicate in paint finish ($ 3,000.00)
Supply and install new plasterboard to the perimeter of the new ceiling in metalic carpaint and
($ 9,500.00)
trimming
Supply and apply new plaster and paint to existing walls as shown on the drawing ($ 9,200.00)

Provisional Sum to supply new light fittings (Dimmable where necessary) ($ 4,600.00) For Wiring, DB termination, motion sensors and labour to install
Electrical Works lights

Contingency (10%) ($ 7,700.00)

Total Excluding 7% GST ($ 757,000.00)

CONNECTING LOBBIES

BASIC FINISHES SPECIFICATIONS


UPGRADED FINISHES

ITEM COUNT RATE TOTAL DESCRIPTION

BLOCK 9 2 $107,700 $215,400 Area around the lift upto the glazing
Block 9 Lift lobby,
Drop-off Level Area around the lift upto the glazing and
Block 9 Lift 1 $70,400 $70,400 the landscaped courtyard
Lobby, Carpark
Levl 1 $210,000 Area connecting the two lift lobbies
Block 9, 1 $118,200 $210,000 inclusive of security desk
Connecting lobby,
Drop-off level Area from Drop-off to the connecting
lobby, on two sides with ramps/stairs and
Block 9, Entrance $118,200 landscape
near drop off
$614,000
Total for Block 9

BLOCK 11 2 $90,700 $181,400 Area around the lift upto the glazing
Block 11 Lift
lobby, Drop-off Area around the lift upto the glazing and
Level 2 $90,700 $181,400 the landscaped courtyard
Block 11 Lift
Lobby, Carpark Area connecting the two lift lobbies
Levl 1 $210,000 $210,000 inclusive of security desk
Block 11,
Connecting lobby, 1 $193,400 Area connecting the two lift lobbies
Drop-off level 1 $100,000 $193,400 inclusive of landscape areas
Block 11,
Connecting lobby, Area from Drop-off to the connecting
Parking level lobby, on one side with ramps/stairs (Not
Block 11, $100,000 seen in the quote)
Entrance near
drop off $866,200

Total for Block 11

LOW RISE Includes lobbies around the lift and the
BLOCKS 13 $33,900 $440,700 landscape behind the lift
Low Rise block
lobbies $440,700

Total for Low Rise
blocks

Total Budget for construction $1,920,900 15%
Add 10% preliminaries $288,135
Total Budget for construction
$2,209,035

Not included:
False Ceiling in areas other than what is above the designed areas.
Loose furniture items
GST
Soft landscape other than the one at the entrance (block 9) and courtyards (block 9 and low-rise)

OVERVIEW

UPGRADED FINISHES SPECIFICATIONS


S/n Description of Works Count Budget Cost Remarks
1.0 Site Preliminaries
2.0 Block 9 - 1F Lift lobby -$ 163,400.00- subject to final project cost (15%)

2 -$ 215,400.00-

Renovate existing Block 9 1st floor lift lobby

Demolish existing floor tiles -$ 1,100.00-
Demolish existing glass partition including support -$ 600.00- assumed 3m high
-$ -  - omitted as per comment
Demolish existing wall tiles -$ 500.00-
Demolish existing mail box -$ 1,000.00-
Demolish existing bulkhead -$ 3,200.00-
-$ 15,400.00- 2.4m high
Demolition works
Supply and install new glass partition -$ 7,020.00- Cost includes panel above curved glass. Finish
Screen Wall in 150x300 fins made of dry wall changed to special paint
construction using metal faming and calcium silicate
-$ 10,000.00- 24m2
boards
Construct new curved wall as entrance to stairs -$ 19,200.00- $400/no.
Construct new mail box, front panel in metal paint
lacquered finish with one notice board (750 x 1000) -$ 12,700.00- assuming PC supply rate of upto $140/smt
Supply and install new travertine stone look alike tile to
-$ 10,800.00- installation rate considreed at $120/m2
floor including screed and waterproofing
Apply special paint finish on top of the existing wall tiles -$ 5,700.00- Finish changed to special paint

to achieve travertine look -$ 600.00-
Supply and install new ceiling in calcium sylicate in
-$ 10,000.00- Considering more expensive and elaborate lighting-
paint finish estimated without design
Supply and install metal trimming for ceiling
quote from HMH electro painters for 1250 per set.
Electrical Works ie light fitting and sensor for entrance
-$ 2,900.00- (+6590121096, Rafoob).
Polish and make good existing stainless steel doors and
panels Considered lift doors

Contingency (10%) -$ 10,100.00-

LIFT LOBBIES

UPGRADED FINISHES SPECIFICATIONS


S/n Description of Works Count Budget Cost Remarks
3.0 Block 9 - Basement Lift lobby
1 -$ 70,400.00-

Renovate existing Block 9 Basement floor lift lobby

Demolish existing landscape -$ 700.00-
Demolish existing floor tiles -$ 1,300.00-
Demolish existing glass partition including support -$ 400.00-
Demolish existing wall tiles -$ -  - omitted as per comment
-$ 2,400.00-
Demolition works -$ 5,200.00-
Supply and install new glass partition -$ -  - included on the item below
Supply and install new wall feature (black)
Apply special paint finish on the walls to achieve -$ 21,100.00- installation rate considreed at $120/m2

travertine look -$ -  - omitted as per comment
Construct new bench
Supply and install new travertine stone look alike tiles to -$ 14,600.00- assuming PC supply rate of upto $140/smt
floor including screed and waterproofing
Renovate ceiling in calcium sylicate boards -$ 3,500.00-

Electrical Works ie light fitting and sensor for entrance -$ 7,000.00- Considering more expensive and elaborate lighting-
estimated without design
New landscape (chips and trees)
-$ 7,000.00-
Polish and make good existing stainless steel doors and
panels quote from HMH electro painters for 1250 per set.

Contingency (10%) -$ 2,900.00- (+6590121096, Rafoob).

Considered lift doors

-$ 6,700.00-

LIFT LOBBIES

UPGRADED FINISHES SPECIFICATIONS


S/n Description of Works Count Budget Cost Remarks
4.0 Block 11 - 1F and 2F Lift lobby
2 -$ 362,800.00-

Renovate existing Block 11 lift lobby

Demolish existing floor tiles 2 -$ 2,200.00-
1,200.00- assumed 3m high
Demolish existing glass partition including support 2 -$
-  - omitted as per comment
Demolish existing wall tiles 2 -$ 500.00-
2,000.00-
Demolish existing mail box 1 -$ 5,900.00-
30,800.00- 2.4m high
Demolish existing bulkhead 2 -$

Demolition Works -$

Supply and install new glass partition 2 -$

Screen Wall in 150x300 fins made of dry wall Cost includes panel above curved glass. Finish
changed to special paint
construction using metal faming and calcium silicate 2 -$ 3,060.00-

boards

Construct new curved wall as entrance to stairs 2 -$ 20,000.00- 24m2
19,200.00- $400/no. Supplier's quote is $350/no
Construct new mail box 1 -$

Supply and install new travertine stone look alike tiles to 2 -$ 25,400.00- assuming PC supply rate of upto $140/smt
floor including screed and waterproofing

Apply special paint finish on top of the existing wall tiles 2 -$ 21,600.00- installation rate considreed at $120/m2
to achieve travertine look

Supply and install new ceiling similar to current in paint 2 -$ 11,400.00- Finish changed to special paint
finish

Supply and install metal trimming for ceiling 1 -$ 600.00-

Demolish existing and then reconstruct new ramp with 1 -$ 5,500.00-
SS tactile inserts

Electrical Works ie light fitting and sensor for entrance 2 -$ 15,000.00- Considering more expensive and elaborate lighting-
estimated without design

Polish and make good existing stainless steel doors and quote from HMH electro painters for 1250 per set.
panels
2 -$ 5,800.00- (+6590121096, Rafoob).

Considered lift doors

Contingency (10%) -$ 17,100.00-

LIFT LOBBIES

UPGRADED FINISHES SPECIFICATIONS


S/n Description of Works Count Budget Cost Remarks
5.0 Lowrise Building - Basement Lift Lobby
13 -$ 440,700.00- to confirm quantity

Renovate existing basement lift lobby

Demolish existing floor tiles -$ 300.00-
Demolish existing wall tiles -$ 200.00- assumed 3m high
-$ 500.00-
Demolition Works -$ 660.00- assumed 3m high
cables at 50 centers with creepers
Supply and install new floor tiles including screed and -$ 3,100.00- assuming PC supply rate of upto $140/smt

waterproofing -$ 1,500.00- As per designer's comment; installation rate at
$120/m2
Apply special paint finish on top of the existing wall tiles
-$ 1,800.00- Finish changed to special paint
Renovate ceiling in calcium sylicate board and paint
finish -$ 800.00-

Supply and install new plasterboard to the perimeter of -$ 1,000.00- finish changed to special paint
the new ceiling in metalic carpaint and trimming
-$ 1,200.00-
Skim coat and paint to walls as shown on the drawing
Supply and install new signage in SS finish -$ 3,500.00- Considering more expensive and elaborate lighting-
estimated without design
Electrical Works ie light fitting and light sensor
-$ 6,500.00- including 3 new bollards
Demolish existing and then reconstruct new ramp with
SS tactile inserts quote from HMH electro painters for 1250 per set.
-$ 1,500.00- (+6590121096, Rafoob).
Polish and make good existing stainless steel doors and
panels Considered lift doors

Hacking of old mail boxes and installatin of new mail -$ 3,600.00-
box with a front panel in SS finish for all low blocks
-$ 5,000.00- Consider creepers along the metal fins, two trees, two
Landscape stainless steel planter edge, 150tall, 1500dia.

Contingency (10%) -$ 3,200.00-

Total Excluding 7% GST -$ 1,252,700.00-

LIFT LOBBIES

UPGRADED FINISHES SPECIFICATIONS


S/n Description of Works Count Budget Cost Remarks
1.0 Site Preliminaries
2.0 Block 9 - 1st Floor Entrance ($ 124,800.00) subject to final project cost (15%)

1 ($ 118,200.00)

Renovate existing Block 9 1st floor entrance

Hack off existing floor finish to entrance ($ 3,300.00)
Demolish existing entrance stairs and ramp ($ 1,500.00)
($ 1,800.00)
Demolish existing ceiling ($ 12,000.00) 1nr
Construct new ramp ($ 7,200.00) assumed 1m high

Supply and install new railing to ramp ($ 39,000.00) assuming PC supply rate of upto $140/smt

Supply and install new travertine look-alike tiles to floor as shown in the photo including screed ($ 10,800.00) Finish changed to special paint
and waterproofing ($ 2,400.00)
($ 5,000.00)
Supply and install false ceiling like current ($ 13,800.00) Considering more expensive and elaborate lighting-estimated
Supply and install new plasterboard to the perimeter of the new ceiling in metalic carpaint and ($ 4,600.00) wFoitrhoWuitridnegs,igDnB termination, motion sensors and labour to install

trimming lights
Skim coat and paint to walls as shown on the drawing ($ 3,000.00)
Provisional Sum to supply new light fittings (Dimmable where necessary) ($ 3,000.00)
($ 10,800.00)
Electrical Works
Seat at the entrance along the platner and near the stairs for waiting

New landscape (as shown in the drawing)
Contingency (10%)

CONNECTING LOBBIES

UPGRADED FINISHES SPECIFICATIONS


S/n Description of Works Count Budget Cost Remarks
3.0 Block 9 - 1st Floor Connecting lobby 1 ($ 210,000.00)

Renovate existing Block 1st Floor lobby

Hack off existing floor finish to drop off ($ 6,000.00)
Demolish existing ceiling ($ 4,800.00)
($ 500.00)
Demolish existing ceiling to 1F counter ($ 200.00)
Demolish existing railing to replace with new curved glass railing ($ 1,000.00)
($ 71,700.00) assuming PC supply rate of upto $140/smt
Demolish existing counter ($ 21,600.00) Finish changed to special paint
Supply and install new travertine look-alike tiles to floor as shown in the photo including screed ($ 4,320.00)
($ 6,300.00) Finish changed to special paint
and waterproofing
Supply and install new ceiling in calcium sylicate in paint finish ($ 7,600.00) Assumed PC supply rate of $140/m2
Supply and install new plasterboard to the perimeter of the new ceiling in metalic carpaint and
($ 15,500.00)
trimming
Screen wall in dry wall construction of 300x150 fins behind the counter ($ 400.00)

Supply and apply new plaster and special paint in 2 textures (grainy and smooth) to walls at the ($ 5,500.00)
counter as shown on the drawing
($ 15,000.00)
skim coat and paint for existing columns and walls
($ 17,300.00) Considering more expensive and elaborate lighting-estimated
Change chrome finish to buff finish without design
Supply and install new green cables across the counter as shown on the drawing
($ 6,900.00) For Wiring, DB termination, motion sensors and labour to install
Supply and install new built-in counter as shown on the drawing lights

Provisional Sum to supply new light fittings (Dimmable where necessary) ($ 18,500.00)

Electrical Works

Contingency (10%)

CONNECTING LOBBIES

UPGRADED FINISHES SPECIFICATIONS


S/n Description of Works Count Budget Cost Remarks
5.0 Block 11 - 2nd Floor Connecting lobby 1 ($ 210,000.00)

Renovate existing Block 1st Floor lobby

Hack off existing floor finish to drop off ($ 4,500.00)
Demolish existing ceiling ($ 3,600.00)
($ 500.00)
Demolish existing ceiling to 1F counter ($ -  ) assumed that existing railing are not to be replaced
Demolish existing railing ($ 1,000.00)
Demolish existing counter ($ 90,000.00) assuming PC supply rate of upto $140/smt

Supply and install new travertine look-alike tiles to floor as shown in the photo including screed ($ 24,300.00) Finish changed to special paint
and waterproofing ($ 4,320.00)
($ 3,600.00) Finish changed to special paint
Supply and install new ceiling in calcium sylicate in paint finish
Supply and install new plasterboard to the perimeter of the new ceiling in metalic carpaint and ($ 4,400.00) Assumed PC supply rate of $140/m2

trimming ($ 8,900.00) Assumed PC supply rate of $50/m2
Screen wall in dry wall construction of 300x150 fins behind the counter
Supply and apply new plaster and special paint in 2 textures (grainy and smooth) to walls at the ($ 2,300.00) assumed that existing railing are not to be replaced

counter as shown on the drawing ($ 15,000.00)

skim coat and paint for existing columns and walls ($ 14,400.00) Considering more expensive and elaborate lighting-estimated
wFoitrhoWuitridnegs,igDnB
handrailling buff finish ($ 6,900.00) lights termination, motion sensors and labour to install
Supply and install new built-in counter as shown on the drawing
Provisional Sum to supply new light fittings (Dimmable where necessary) ($ 18,400.00)

Electrical Works

Contingency (10%)

CONNECTING LOBBIES

UPGRADED FINISHES SPECIFICATIONS


S/n Description of Works Count Budget Cost Remarks
6.0 Block 11 - Car Park Level-Connecting Lobby 1 ($ 193,400.00)

Renovate existing basement lift lobby

Demolish existing floor tiles ($ 8,900.00)

Supply and install new travertine look-alike tiles to floor as shown in the photo including screed ($ 80,700.00) assuming PC supply rate of upto $140/smt
and waterproofing
($ 15,000.00)
Supply and lay granite chips ($ 8,800.00)
Supply and install new plasterboard ceiling as per drawing
($ 9,000.00) assuming PC supply rate of $105/m
Supply and install new plasterboard to the perimeter of the new ceiling in metalic carpaint and
trimming ($ 27,900.00) Assumed PC supply rate of $45/m2

skim coat and paint for existing columns and walls ($ 11,200.00)
Prepare and apply new EPDM flooring
($ 6,400.00)
Supply and install new green cables screening the parking and going to upper level as shown on
the drawing ($ 4,400.00) Considering more expensive and elaborate lighting-estimated
without design
Provisional Sum to supply new light fittings (Dimmable where necessary)
($ 3,500.00) For Wiring, DB termination, motion sensors and labour to install
Electrical Works lights
Contingency (10%)
($ 17,600.00)

CONNECTING LOBBIES

UPGRADED FINISHES SPECIFICATIONS


S/n Description of Works Count Budget Cost Remarks
1.0 Block 11 - 1st Floor Entrance 1 ($ 100,000.00)

Renovate existing Block 11 1st floor entrance

Hack off existing floor finish to entrance ($ 3,300.00)
Demolish existing entrance stairs and ramp ($ 1,500.00)
($ 3,600.00)
Demolish existing ceiling ($ 12,000.00) 1nr
Construct new ramp ($ 7,200.00) assumed 1m high

Supply and install new railing to ramp ($ 19,500.00) assuming PC supply rate of upto $140/smt
Supply and install new travertine look-alike tiles to floor as shown in the photo including screed
($ 10,800.00) Finish changed to special paint
and waterproofing
Supply and install new ceiling in calcium sylicate in paint finish ($ 3,000.00)
Supply and install new plasterboard to the perimeter of the new ceiling in metalic carpaint and
($ 9,500.00)
trimming
Supply and apply new plaster and paint to existing walls as shown on the drawing ($ 11,500.00) Considering more expensive and elaborate lighting-estimated
FwoitrhoWuitridnegs,igDnB
Provisional Sum to supply new light fittings (Dimmable where necessary) ($ 4,600.00) lights termination, motion sensors and labour to install
Electrical Works
($ 8,700.00)
Contingency (10%)
($ 956,400.00)
Total Excluding 7% GST

CONNECTING LOBBIES

UPGRADED FINISHES SPECIFICATIONS


WAVE
design consultants pte. ltd
114 Lavender street #05-51, 338729 Singapore

[email protected]
www.wave.global
+65 6493 5151

THIS PROJECT FALLS ENTIRELY UNDER THE LEGISLATION OF THE AUTHORS RIGHTS;
IT CANNOT BE REALIZED IN WHOLE NOR IN PART IN ITS FUNCTIONAL, STRUCTURAL,
TECHNICAL OR AESTHETIC CONCEPT WITHOUT THE EXPRESSED CONSENT.


Click to View FlipBook Version