Fagen, inc.
1
mission statements
company mission
To be the construction
company most admired
by our customers for our
people, partnerships,
performance and finished
product, ultimately building
a better world for tomorrow.
safety mission
Fagen, Inc. is committed
to safety and views our
employees as our most
valuable resource. Our goal
is to provide an accident/
injury free environment.
With a commitment from
management, supervision
and field employees, we as a
team will achieve our safety
goal.
safety facts
2018
LTRIR 0.24 TRIR 2.16
EMR 0.65 HOURS 1.6 MM
2017
LTRIR 0.35 TRIR 1.05
EMR 0.61 HOURS 1.1 MM
2016
LTRIR 0.13 TRIR 1.05
EMR 0.75 HOURS 1.5 MM
Fagen, inc.
2
Wind experience
“Thank you to the
Fagen staff and their
dedication to get this
project done. We en-
joyed the experience
and look forward to
working with Fagen
again.“
–Nathan Biediger
Senior Vice
President,
Engineering &
Construction
Cotton Plains Wind
fagen, inc. wind experience
Fagen, Inc. is a second generation family owned organization that
routinely executes EPC projects from $5 million up to $450 million as a
non-union contractor. We have a customer base of clients that is one
of the most respectable in the industry. We bring expertise from our
industrial plant background that provides every project with unmatched
safety and quality.
Our wind construction experience shows a proven track record of safe
and quality driven projects.
We own enough main pick and support cranes to construct up to 5
(200MW+) projects per year. Our inventory has allowed us to provide
reliability and flexibility to meet the demands of our customers.
Fagen, Inc. is proud to state that we have met or exceeded the
contractual obligations on every wind project that we have built to date.
Our schedule and delivery systems are driven to successfully complete
projects to meet or exceed our contract obligations. We stand behind the
success of our projects as a testament to our great track record building
projects within tight time constraints.
Fagen, inc.
3
crane fleet
Lattice Boom crawLers:
2 – Manitowoc 18000 – 500 Ton (US) cap.
(#44 Luffing Jib Available)
1 – Manitowoc 16000WA – 440 Ton (US) cap.
1 – Manitowoc MLC 300 – 300 Ton (US) cap.
6 – Manitowoc 999 – 275 Ton (US) cap.
1 – Manitowoc 12000 – 120 Ton (US) cap.
2 – Manitowoc 10000 – 100 Ton (US) cap.
rough terrain:
1 – Grove RT9130E – 130 Ton (US) cap.
2 – Grove RT9100E - 100 Ton (US) cap.
7 – Grove RT880E –80 Ton (US) cap.
2 – Grove RT875E –75 Ton (US) cap.
1 – Grove RT865B – 65 Ton (US) cap.
2 – Grove RT700E – 60 Ton (US) cap.
1 – Grove RT 635C – 35 Ton (US) cap.
2 – Grove RT535E – 35 Ton (US) cap.
carry deck:
3 – Broderson IC200-2F – 15 Ton (US) cap.
3 – Broderson IC200-2E – 15 Ton (US) cap.
2 – Shuttlelift 5540F – 15 Ton (US) cap.
1 – Broderson IC-35-2B – 4 Ton (US) cap.
Fagen, inc.
4
total Wind experience
proJect
name Minwind III Grant County Valley View Moraine II Idaho Wind
Location Beaver Creek, MN Hoffman, MN Chandler, MN Woodstock, MN Burley, ID
turBine type Vestas Suzlon Gamesa GE GE
size of
turBine 1.65MW 2.1 MW 2.0 MW 1.5 MW 1.5 MW
numBer of
turBines 7 10 5 33 122
totaL mw 12 MW 21 MW 10 MW 50 MW 183 MW
significant In 2002, this was One of the Negotiated Erected Fagen, Inc.
notes the first wind first Suzlon repeat turbines in one built this
project Fagen, Inc. 2.1 MW business. of the coldest project in
built. It was also turbines winters in MN 6 months
the largest Vestas installed for Iberdrola. from start
turbine installed and with no to finish.
at the time. punchlist This was the
items. fastest GE
has put up
the 1.5 MW
platform.
Project was
a rock job
with blasting
of roads and
foundations.
Fagen, inc.
5
total Wind experience
proJect Cotton Plains /
name Big Blue Peak View Latigo Old Settler
Location Blue Earth, MN Walsenburg, CO Monticello, UT Floydada, TX
turBine type Gamesa GE GE GE
size of
turBine 2.0 MW 1.79 MW 2.3 MW 2.4 MW
numBer of
turBines 18 34 27 84
totaL mw 36 MW 61 MW 62 MW 202 MW
significant Fagen, Inc. Invenergy could Fagen, Inc. This project was
notes
took over this not be more installed built over 2.5
project when the complimentary and commissioned months ahead of
developer was not on Fagen, Inc.’s the first 2.3 MW schedule.
able to pay. performance of this platform GE
project. Art Fletcher, turbine
Sr. VP of Renewable on this project
Engineering & Project with
Management, has no punchlist
stated that we items.
are one of the best
contractors he has
worked with.
Fagen, inc.
6
total Wind experience
proJect
name Campbell County Bloom Wind Palmer’s Creek Saratoga Project
Location Pollock, SD Bloom, KS Granite Falls, MN Saratoga, IA
turBine type GE Vestas GE Vestas
size of
turBine 1.73 MW 3.3 MW 2.5 MW 2.0 MW
numBer of
turBines 55 54 18 33
totaL mw 95 MW 178 MW 45 MW 66 MW
significant Fagen, Inc. Fagen, Inc. is only Fagen, Inc. was
notes developed this the 2nd contractor one of the first
project, obtained to put up this companies to take
a PPA from Basin platform of turbine delivery of the 2.5
Electric and sold in the industry. MW GE turbine.
the project to
ConEdison
Development.
Fagen, inc.
7
recent Wind projects
campBeLL county wind farm, LLc
proJect summary
Fagen, Inc. was the BOP EPC
contractor for the installation of 55 GE
1.73 MW turbines. The project scope
for this 95 MW wind farm included
substation, service roads, O&M
building, collection system, turbine
foundations, turbine erections and
turbine tower wiring.
notice to proceed
June 11, 2015
suBstantiaL compLetion
December 15, 2015
primary contact
John Labiak
Development Managing Director of
Construction
(917) 328-6122
zero
Lost time
incidents
Fagen, inc.
8
recent Wind projects
campBeLL county wind farm, LLc
fuLL epc scope incLuded:
- 55 GE 1.73 MW turbines
- 80 meter towers with 103 meter rotor
diameter
- 17.8 miles of service roads
- 33 miles of underground collection
- O&M site work and building
- Substation site work and installation
- Installation, temporary tap and
permanent connection to WAPA
transmission line
- Turbine erection and tower wiring
Fagen, inc.
9
recent Wind projects
peak View wind energy, LLc
“Fagen performed proJect summary
very well for us on Fagen, Inc. was the BOP EPC contractor for the installation
our recent Peak View of 34 GE 1.7 - 100 turbines with 100 meter rotor diameter and
project in Colorado. 80 meter towers. The project scope included site preparation,
Though this was a roads, foundations, tower erection, and down tower wiring.
difficult project which
presented numerous notice to proceed
challenges, the March 2, 2016
Fagen team stepped
up in response to suBstantiaL compLetion
those challenges and August 26, 2016
delivered a quality
project on schedule primary contact
and on budget. We Art Fletcher, P.E.
were very happy with Sr. Vice President - Renewable Engineering and
their professionality Project Management
and “can do” attitude (312) 582-1502
throughout.”
Art Fletcher, P.E.
Fagen, inc.
10
recent Wind projects
peak View wind energy, LLc
Lightning strikes
“Last night I received so many “thank yous,”
handshakes, words of appreciation, etc. that it became
On July 19, 2016, a lightning embarrassing. We happened to be in the right spot, we
strike ignited a prairie fire had the right equipment and operators, etc. that it was
across the highway adjacent just plain the right thing to do. I would hope that any
to the Peak View Wind project. other organization would have done the same. All of the
A lightning stand down was locals said if we had not been there the fire would have
gone out of control, possibly endangering houses, etc. I
quickly initiated on-site. Fagen did not mention that somewhere on the back side of the
Field Management Staff heard hill is a subdivision under construction.
several radio calls reporting
smoke and flames at that The bottom line is that last night’s events were
successful. Many of us are tired today but are all back
location. After verifying, Fagen to work as normal.”
staff initiated a 911 call to
notify emergency responders. Marlin Conry
Fagen, Invenergy, and an on- Graywold Consulting - Invenergy
site subcontractor collaborated
and prepared to assist. Three water tankers and two water trucks were staged at the
site entrance, while a small team determined how best to make a path to the fire. During
this time three motor graders, one scraper, and a D6 dozer were mobilized and staged
approximately 400 yards west of the project entrance, waiting on direction from the fire
Fagen, inc.
11
recent Wind projects
peak View wind energy, LLc
- continued
department. The equipment was directed to
establish a fire break around the entire fire,
which took a few hours and ultimately stopped
the fire. Fagen staff assisted at the entrance by
keeping a sign-in sheet for all personnel who
entered the location to ensure everyone was
accounted for. The Fagen Emergency Action
Plan was put in place in the event that the fire
would cross the highway. All Fagen vehicles
were moved to the seven acre laydown yard fagen, inc. was responsiBLe for:
approximately three miles away. Computers • Installation of 15 miles of new roads
were gathered up in preparation for an • 34 turbine erection pads
• Installation and procurement of 34
evacuation. Years of experience and adherence turbine foundations.
to our company’s policies and procedures • Handling / Offloading of 34 GE
prepared our Field Management Staff to turbines
respond quickly and effectively to this serious • Erection of 34 turbines
• Grouting, conduit, and wiring of
situation. turbines
Fagen, inc.
12
recent Wind projects
cotton pLains / oLd settLer wind farms
notice to proceed proJect summary
July 18, 2016 Fagen, Inc. was awarded the balance-of-plant
construction for a total of 201.4 MW involving two
suBstantiaL compLetion adjacent wind farms in Floydada, Texas. Cotton Plains
Cotton Plains - January 13, 2017 Wind (50.4MW) will be part of a hybrid energy system
Old Settler - March 3, 2017 (wind and solar) which will supply energy to Fort Hood,
the largest active-duty armored post in the United
primary contact States. Old Settler Wind (151.2 MW) will generate
John Stone enough clean electricity to power an additional 51,000
Senior Director average U.S. homes. The projects together consist of
Project Management 84 - 2.4 MW GE wind turbines.
Apex Clean Energy, Inc. zero
(423) 774-6008
Lost time
incidents
Fagen, inc.
13
recent Wind projects
cotton pLains / oLd settLer wind farms
“Thank you to the Fagen staff and their
dedication to get this project done.
We enjoyed the experience and look
forward to working with Fagen again.”
Nathan Biediger
Senior Vice President, Engineering &
Construction
Cotton Plains Wind
fuLL Bop epc scope incLuded:
- Civil and Electrical Design
- Roads and Crane Pads
- Foundations
- Turbine Erection (GE 2.4 MW)
- Turbine Electrical Wiring
- Collection Systems
- Substation and Interconnection
point of interest
Severe wet weather was
encountered through much of
the initial foundation and roads
segment of the project. The Fagen
team was still able to receive all
turbine deliveries and complete
both projects ahead of schedule.
Fagen, inc.
14
Fagen, inc.
15
recent Wind projects
BLoom wind
cLient
Capital Power
Location
Bloom, KS
scope
Fagen, Inc. was the BOP EPC contractor for a
178.2 MW Wind Farm utilizing (54) Vestas V117-
3.3 MW WTG with 117m rotors & hub height of
91.5m.
start date
8/3/2016
suBstantiaL compLetion
5/19/2017
Fagen, inc.
16
recent Wind projects
BLoom wind
Fagen, inc.
17
recent Wind projects
BLoom wind
Fagen, inc.
18
recent Wind projects
BLoom wind
Fagen, inc.
19
recent Wind projects
BLoom wind
Fagen, inc.
20
recent Wind projects
Latigo wind park
cLient
Latigo Wind Park, LLC
Location
Monticello, UT
scope
Fagen, Inc. was the BOP EPC contractor for
a 62 MW wind farm utilizing 27 - 2.3 MW GE
turbines.
start date
7/20/2015
suBstantiaL compLetion
2/5/2016
Fagen, inc.
21
recent Wind projects
Big BLue wind farm
cLient
Big Blue Wind
Location
Blue Earth, MN
scope
Fagen, Inc. was the BOP EPC contractor for a
36 MW wind farm utilizing 18 - 2.1 MW Gamesa
turbines.
start date
10/17/2011
suBstantiaL compLetion
12/12/2012
Fagen, inc.
22
recent Wind projects
ge idaho wind proJect
cLient
XRG Development Partners, LLC
Location
Twin Falls, ID
scope
Fagen, Inc. was the BOP EPC contractor for
a 183 MW wind farm utilizing 122 - GE 1.5MW
wind turbines.
start date
11/30/2009
suBstantiaL compLetion
1/1/2011
Fagen, inc.
23
recent Wind projects
ge idaho wind proJect
scope detaiLs
• Civil and Electrical Design
• Roads and Crane Pads
• Foundations
• Erection
• Turbine Electrical Wiring
• Collection Systems
• Substantial and Interconnection
Fagen, inc.
24
recent Wind projects
ge idaho wind proJect
Fagen, inc.
25
recent Wind projects
ge idaho wind proJect
Fagen, inc.
26
additional completed projects
grant county wind proJect
cLient
Juhl Wind, Inc.
Location
Grant County, MN
scope
Fagen, Inc. was the BOP EPC contractor
for a 21 MW wind farm utilizing 10 - 2.1
Suzlon turbines. Our scope included roads,
foundations, erection, collection systems, and
substations.
start date
9/14/2009
suBstantiaL compLetion
2/28/2010
moraine ii wind farm
cLient
Iberdrola Renewables
Location
Woodstock, MN
scope
Fagen, Inc. was the BOP EPC contractor for
a 50 MW wind farm utilizing 33 - 1.5 MW
GE turbines. Our scope included roads,
foundations, and tower erection.
start date
10/10/2008
suBstantiaL compLetion
12/22/2008
Fagen, inc.
27
additional completed projects
minwind iii - ix proJect
cLient
Minwind Energy, LLC
Location
Beaver Creek, MN
scope
Fagen, Inc. installed 7 - 1.65 MW Vestas
wind turbines. Our scope included roads,
foundations, tower / turbine erection
and electrical.
start date
7/12/2004
suBstantiaL compLetion
11/11/2004
VaLLey View wind farm
cLient
Juhl Wind, Inc.
Location
Chandler, MN
scope
Fagen, Inc. was the BOP EPC contractor
for a 10 MW wind farm utilizing 5 - 2 MW
Gamesa turbines. Our scope included
roads, foundations, collection systems,
and tower erection.
start date
10/4/2010
suBstantiaL compLetion
12/1/2010
Fagen, inc.
28
Bop epc Wind references
apex cLean energy, inc.
Nathan Biediger
Sr. VP, Engineering & Construction
Phone: (434) 220-6136
Email: [email protected]
capitaL power
Steve Owens, P.E.
VP, Construction and Pre-Operations
Phone: (780) 392-5437
Email: [email protected]
ge renewaBLe energy
Christy Guthman
Sales Director, Western US and Mexico
Phone: (518) 596-6265 (M)
Email: [email protected]
madison gas & eLectric
Steve Pitts
Construction Engineering Manager
Phone: (608) 252-7935
Email: [email protected]
inVenergy, LLc
Art Fletcher, P.E.
Sr. VP, Renewable Engineering and Project Management
Phone: (312) 582-1502
Email: [email protected]
Vestas
Lou Castino, PMP
Sr. Project Manager - Civil Works
Phone: (503) 265-6864
Email: [email protected]
Fagen, inc.
29