LUBRICATE BEFORE USE
Treat the formwork panels regularly with a suitable release agent. Apply a thin
and even film of release agent and smoothen it. Excess amount has to be removed
with a cloth or a wiping mop. You can achieve the best results with high-quality
concrete release agents such as PERI Clean, PERI Plasto Clean or PERI Bio Clean.
TESDA-CAR- CARPENTRY NC II Date Developed: 3-20-20 Revision No.2
PTC-IFUGAO Issued by: FN LUNAG 2nd 3-20-20
Fabricating, Installing
and Removing Wooden Developed by: Page 48 of 63
Mr. Frazier N. Lunag
Formworks
SELF CHECK 2.6-1
Enumeration:
1. Enumerate type of smoothing agent to be used in wooden forms/plywood.
2. What are tools in cleaning used forms?
3. What is safest way of storing forms?
TESDA-CAR- CARPENTRY NC II Date Developed: 3-20-20 Revision No.2
PTC-IFUGAO Issued by: FN LUNAG 2nd 3-20-20
Fabricating, Installing
and Removing Wooden Developed by: Page 49 of 63
Mr. Frazier N. Lunag
Formworks
ANSWER KEY 2.6-1
1. Used oil
2. Garbage bag cellophane
3. Hammer
4. Cold chisel
5. Steel brass
6. Store the panels on level ground to avoid deflection.
TESDA-CAR- CARPENTRY NC II Date Developed: 3-20-20 Revision No.2
PTC-IFUGAO Issued by: FN LUNAG 2nd 3-20-20
Fabricating, Installing
and Removing Wooden Developed by: Page 50 of 63
Mr. Frazier N. Lunag
Formworks
JOB SHEET 2.6-1
CLEANING OF FORMS FOR COLUMN
TOOLS:
Claw hammer, Cold chisel, Hard broom
MATERIALS:
Metal/Wooden Forms
PROCEDURE:
1. Pile the used forms according to sizes
2. Prepare the tools need
3. Use PPE according to job requirements
4. With
CRITERIA:
● Workmanship = 60%
● Accuracy
● Speed = 10%
● Safety = 10%
● Proper handling = 10%
of tools and materials = 10%
100%
TESDA-CAR- CARPENTRY NC II Date Developed: 3-20-20 Revision No.2
PTC-IFUGAO Issued by: FN LUNAG 2nd 3-20-20
Fabricating, Installing
and Removing Wooden Developed by: Page 51 of 63
Mr. Frazier N. Lunag
Formworks
ASSESSMENT CRITERIA
EVIDENCE CHECKLIST
Competency standard: CARPENTRY NC II
Unit of competency: FABRICATE, INSTALL AND REMOVE WOODEN
FORMWORKS
Title of Module FABRICATING, INSTALLING AND REMOVING WOODEN
FORMWORKS
Ways in which evidence will be collected: Observation
[tick the column] Questioning
Third party
Report
Demonstrati
on
Portfolio
Written
LO1. Prepare materials, tools and equipment
1. Personal protective equipment (PPE) is used in
accordance with Rule 1080 of Occupational
Safety and Health Standards
2. List of materials, hand tools and equipment are
secured and followed according to job
requirements
3. Materials, tools and equipment are selected,
inspected and prepared consistent with job
requirements.
4. Work area is cleaned according to safety and
environmental regulations (e.g. PD 1152 Section
6, 8 & 42)
5. Required output is completed as specified by the
immediate supervisor based on work schedule.
LO2. Lay-out and cut dimension of form sheathing and stiffeners
1. Form sheathing and stiffeners are measured and
marked according to job specifications
2. Form sheathing and stiffeners are laid out and
cut according to required dimensions.
3. Work area is cleaned according to safety and
environmental regulations
4. Required output is completed as specified by the
immediate supervisor based on work schedule.
LO3. Assemble and erect form panels and components
1. Sheathings are positioned and fixed to stiffeners
2. Assembled form panels are checked for
squareness, levelness, plumbness and
alignment.
3. Primary and secondary supports are positioned
and fixed to hold assembled form panels as per
CARPENTRY NC II Date Developed: 3-20-20 Revision No.2
Issued by: FN LUNAG 2nd 3-20-20
TESDA-CAR- Fabricating, Installing Developed by: Page 52 of 63
PTC-IFUGAO and Removing Wooden Mr. Frazier N. Lunag
Formworks
drawings.
4. Assembled form panels are checked for
compliance with job requirements.
5. Work area is cleaned according to safety and
environmental regulations
6. Required output is completed as specified by the
immediate supervisor based on work schedule.
LO4. Erect wooden scaffolds
1. Soleplates/ timber planks are prepared, placed
and spaced accordingly considering ground
surface conditions based on design
requirements
2. Wooden scaffold components are erected,
plumbed and leveled based on design
requirements
3. Wooden scaffolds systems are checked based on
design requirements
4. Lifeline for fall protection devices (harness) are
installed in accordance with job specification
and OSHS requirements.
5. Work area is cleaned according to safety and
environmental regulations
LO5. Strip form panels and dismantle scaffold
1. Tools, equipment and staging area are prepared
2. Bracing, supports and form panels are removed
as scheduled accordingly
3. Shores and scaffolds are removed according to
schedule
4. Panels and other components are sorted, clean
and stored for the next reuse
5. Work area is cleaned according to safety and
environmental regulations (e.g. PD 1152 Section
6, 8 & 42)
LO6. Clean and store reusable form panels and components
1. Materials such as scaffolding and formworks are
recovered and stockpiled according to company
rules and procedures
2. Work area is cleaned according to safety and
environmental regulations (e.g. PD 1152 Section
6, 8 & 42)
3. Tools, equipment and other materials are
cleaned after use.
4. Required output is completed as specified by the
immediate supervisor based on work schedule.
NOTE: *Critical aspects of competency
Prepared by: FRAZIER N. LUNAG Date:
TESDA-CAR- CARPENTRY NC II Date Developed: 3-20-20 Revision No.2
PTC-IFUGAO Issued by: FN LUNAG 2nd 3-20-20
Fabricating, Installing
and Removing Wooden Developed by: Page 53 of 63
Mr. Frazier N. Lunag
Formworks
Checked by: Date:
Science, Technology, Engineering and Math (STEM)
QUALIFICATION TITLE: Carpentry NC II
Module Title: FABRICATING INSTALLING AND REMOVING WOODEN FORMWORKS
Learning Assessment Technology Science Math Engineering Learning
Outcomes Criteria 1. Using PPE Activities
LO1. Prepare 2.Following Properties of Approved Strength of
materials, tools 1.1 Personal company rules and Materials working materials Receiving and
and equipment protective regulations appropriate for drawings, handling
equipment (PPE) 3. Organizing indoor/outdoor Productivity materials, tools
LO2. Lay-out is used in materials to be or exposure to work and equipment
and cut accordance with used weather measurements at workplace
dimension of Rule 1080 of 4. Handling and materials and , Applying Identifying,
form sheathing Occupational use of materials, use the right tool mensuration checking and
and stiffeners Safety and Health tools and for the right Job. inspecting
Standards equipment materials, tools
1.2 List of 5. Implementing and equipment
materials and tools 3R and 5S Practicing 3R
are secured and and 5S
followed according 1.Reading and
to job understanding 1. Use the right 1. Conversion Measuring and
requirements sketches, drawings tool for the right of units marking
1.3 Material, tools and details Job. dimensions of
and equipment are Applying 2. Proper use of Measuring sheathing and
selected, power tools dimensions stiffeners
inspected and mensuration Cutting
prepared Interpreting Squaring of sheathing and
consistent with job stock stiffeners
requirements. product manual Practicing 3R
1.4 Work area is and 5S
cleaned according
to safety and
environmental
regulations (e.g.
PD
1.5 Required
output is
completed as
specified by the
immediate
supervisor based
on work schedule.
1152 Section 6, 8
& 42)
1.1 Personal
protective
equipment (PPE)
is used in
accordance with
Rule 1080 of
Occupational
Safety and Health
Standards
1.2 List of
materials, hand
tools and
CARPENTRY NC II Date Developed: 3-20-20 Revision No.2
Issued by: FN LUNAG 2nd 3-20-20
TESDA-CAR- Fabricating, Installing Developed by: Page 54 of 63
PTC-IFUGAO and Removing Wooden Mr. Frazier N. Lunag
Formworks
equipment are
secured and
followed according
to job
requirements
1.3 Materials, tools
and equipment are
selected,
inspected and
prepared
consistent with job
requirements.
1.4 Work area is
cleaned according
to safety and
environmental
regulations (e.g.
PD 1152 Section
6, 8 & 42)
1.5 Required
output is
completed as
specified by the
immediate
supervisor based
on work schedule.
TESDA-CAR- CARPENTRY NC II Date Developed: 3-20-20 Revision No.2
PTC-IFUGAO Issued by: FN LUNAG 2nd 3-20-20
Fabricating, Installing
and Removing Wooden Developed by: Page 55 of 63
Mr. Frazier N. Lunag
Formworks