COMPETENCY BASED LEARNING MATERIAL
Sector: INFORMATION AND COMNMUNICATION TECHNOLOGY (ICT)
Qualification:
TELECOM OSP AND SUBSCRIBER LINE INSTALLATION
(Copper Cable/POTS and DSL) NC II
Unit of Competency: Perform Main Cable Installation
Module Title: :
Performing Main Cable Installation
Developed by:
Ramon L. Gonzales, Lead Training Officer
Network Access Technology
PHILIPPINE LONG DISTANCE TELEPHONE COMPANY
Technical Training Division
Table of contents
Contents page
Glossary of Terms………………………………………………………. 2
Introduction………………………………………………………………. 3
Information Sheet # 1…………………………………………………… 4
LO1.Prepare for Cable Jointing and Installation
Information Sheet # 2…………………………………………………… 8
LO2.Install Main Cable
Operation Sheet………………………………………………………… 30
Job Sheet………………………………………………………………… 32
Self – Check…………………………………………………………….. 38
Answer Key……………………………………………………………... 39
Performance Test……………………………………………………… 40
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 1
ICT724607
Glossary of Terms:
Core Competencies - are the specific skills and knowledge needed in a particular area
of work - industry sector/occupation/job role
Aerial Cable – suspended and attached on telephone pole for distribution porposes.
Communication Cable – is used for the distribution and small copper wires for voice
and data signals
Copper cable -- Electric power cables made from twisted pair copper wire.
Environment - The area surrounding the work site which can be directly or indirectly
affected by occurrences at the work site. It includes the atmosphere, soils, drains,
underground water tables, and the ecosystem. Protection of the environment would
require the proper disposal of waste materials, restriction of burning off, the correct
handling of toxic substances, the containment of CFCs and the like.
Hazardous Materials - Flammable gases and vapors and combustible dusts.
Pre-cautions:
A measure taken in advance to avert possible evil or to secure good results
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 2
ICT724607
Program/Course: Telecom OSP and Subscriber Line Installation
Unit of Competency: Perform Main Cable Installation
Module Title: Performing Main Cable Installation
INTRODUCTION:
This module is designed to enhance the knowledge, skills and attitude of the trainees in
performing main cable installation usually done in team
LEARNING OUTCOMES
Upon completion of this module you should be able to:
1. Prepare for cable jointing and installation
2. Install main cable.
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 3
ICT724607
INFORMATION SHEET # 1
LO1.
Prepare for cable jointing and installation
Objective:
Upon completion of this topic participants should be able to identify, describe and
prepare the necessary tools, materials and equipment for cable jointing and installation
Aside from the previous list of tools, materials and equipment in installing pole hardware,
cable terminal, line wire and accessories, hereunder are the additional;
LIST OF TOOLS, MATERIALS and EQUIPMENT
1. POLYETHYLENE KNIFE
Or slitting knife is used for cutting polyethylene cable sheath so as to make cable
openings, also for cutting lead sheath.
2. TABBING SHEARS
Used for cutting tabs in the ends of the polyethylene jacket to permit placement of bullet
bond clip.
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 4
ICT724607
INFORMATION SHEET # 1
3. ELECTRICIAN SCISSORS
Is a nickel plate finish tool used for stripping and cutting small wires.
4. TARPAULIN
Or manhole tent 10’ x 15’ lightweight or black with canvass, used on underground works or
trenches especially during inclement weather.
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 5
ICT724607
INFORMATION SHEET # 1
5. LEATHER TOOL POUCH
Used as side pouch of light tools such as a side cutters, pliers, screwdrivers etc. and is
supported by a leather belt.
6. AERIAL HANDLINE
Consist of 60 ft. of ½” rope. A one sleeve block, a ring spliced in one end of the rope and a
hook in the hand end, used on aerial cable work to raise and lower tools and materials.
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 6
ICT724607
INFORMATION SHEET # 1
7. CANVASS BUCKET
Or tool bag used for conveniently transporting all necessary tools and equipments used by
cable splicer is mad of canvass materials and pocket on its sides for small tools.
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 7
ICT724607
INFORMATION SHEET # 2
LO2.
Install main cable
Objective:
Upon completion of this topic participants should be able to install main cable prior to
splicing.
AERIAL (TERMINALS)
OLD DESCRIPTION NEW
Proposed Strand Mounted Terminal N/A
11 A terminal to be installed on strand Messenger N/A
A1-11 ST (ST) N/A
N/A
26 Existing Fixed Terminal (Pole Mounted) N/A
A1-26 T A terminal installed on pole(T) N/A
26 Proposed Fixed Terminal (Pole Mounted) W
A1-26 T A terminal to be installed on pole(T) 20
16 Existing Cable Terminal to be Removed W
B1-16 A cable terminal for removal and recovery(//) 20
51-24 Re-splicing Cable Terminal
A(a1-616)T-21 (Change Count A1-16 to A16-21)
6-21
Existing terminal to be recovered indicating
11 complement, pair count and terminal size.
A1-11 Already installed
Existing 20 pairs distribution point
N/A (DP) cable terminal on wall.
Already installed
Proposed 20 pairs distribution point
N/A (DP) cable terminal on wall.
Already installed
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 8
ICT724607
INFORMATION SHEET # 2
Existing 20 pairs distribution point
N/A (DP) cable terminal on wall to be recovered. 20 W
OLD Already installed
N/A
N/A DESCRIPTION NEW
Existing 10 pairs distribution point
N/A (DP) cable terminal on wall to be recovered.
N/A Already installed
N/A
N/A Proposed 10 pairs distribution point
N/A (DP) cable terminal on wall to be
Recovered.
Already installed
Existing 10 pairs distribution point
(DP) cable terminal on wall to be recovered.
Already installed
Existing 20 pairs distribution point
(DP) cable terminal on pole to be recovered.
Already installed
Proposed 20 pairs distribution point
(DP) cable terminal on pole.
Already installed
Proposed 30 pairs distribution point
(DP) cable terminal on pole.
Already installed
Existing 30 pairs distribution point
(DP) cable terminal on pole.
Already installed
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 9
ICT724607
INFORMATION SHEET # 2
AERIAL (POLE LINE)
OLD DESCRIPTION NEW
Existing 113.03 cm extension arm to be
Recovered
Already installed
Proposed 66.04 cm extension arm
To be installed smaller than 113.03 also used
to maintain cable span alignment on poles.
Existing 66.04 cm extension arm
To be installed smaller than 113.03 also used
to maintain cable span alignment on poles.
Existing 66.04 cm extension arm to be
recovered
Already installed for recovery
Existing pole to pole guy to be recovered.
Already installed messenger wire with guy and
anchor on each pole.
Proposed pole with extended suspension
strand.
To be installed between two poles
Existing poles with extended suspension
strand.
Already installed between two poles.
Recovery of poles and extended suspension
strand
For recovery
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 10
ICT724607
INFORMATION SHEET # 2
OLD DESCRIPTION NEW
Do not attach
DA
Electric pole.
35’-4
Proposed PLDT pole (wood) (pole size and PT#1001
number indicated)
To be installed 35’-4
PT#1001
Existing PLDT pole (wood) (pole size and
number indicated) w
Already installed
35’-4
Existing PLDT pole (wood) to be PT#1001
recovered.
Already installed w
w 35’-4
PT#1001
Existing PLDT pole (concrete) (pole size
and number indicated) cc
Already installed
cc Proposed PLDT pole (concrete) (pole size 35’-4
and number indicated) PT#1001
cc Already installed
Proposed Electric Pole cc
To be installed concrete or
Creosotd Meralco pole
Existing Jointly owned Pole
Already installed PLDT & Meralco
Joint pole
Proposed Jointly owned Pole
To be installed PLDT & Meralco
pole
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 11
ICT724607
INFORMATION SHEET # 2
OLD DESCRIPTION NEW
Existing Storm Guy
SW An already installed four guy and anchor on SW
SW one pole for storm protection 10M
SW
Proposed Storm Guy 10M
To be installed four guy and anchor on one
pole for storm protection
Existing Side Walk Guy
An already installed guy and anchor on pole
towards side walk
Proposed Side Walk Guy
To be installed guy and anchor on pole
towards side walk
Existing Pole to Pole Guy
An already installed messenger wire with guy
and anchor on each pole
Proposed Pole to Pole Guy
To be installed messenger wire with guy and
anchor on each pole
Existing 10 Pin Alley Arm
Used to maintain cable span alignment made
of 4” x 4” wood with a standard length of arm
usually attached to pole
Proposed 10 Pin Alley Arm
To be installed
Existing Cable Ext. Arm 44 ½”
Used to maintain cable span alignment on
poles with 44 ½” arm
Proposed Cable Ext. Arm 44 ½”
To be installed
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 12
ICT724607
INFORMATION SHEET # 2
OLD DESCRIPTION NEW
Existing Guy and Anchor
SW Already installed guy wire SW
10M with anchor and log 10M
10M 10M
Proposed Guy and Anchor
Already installed guy wire
With anchor and log
Existing sidewalk guy to be recovered
Already existing for recovery
Proposed down guy to be attached to
existing anchor (size indicated)
To be installed Guy and Anchor
Existing overhead / down guy
Already installed Guy and Anchor
Proposed overhead / down guy
To be installed Guy and anchor
Existing overhead / down guy to be
recovered
Already installed Guy and Anchor
Existing 10-pin alley arm to be recovered
Already installed for recovery
Proposed down guy (size indicated)
10M To be installed Guy and Anchor 10M
Existing down guy (size indicated)
10M Already installed Guy and Anchor 10M
Existing down guy to be recovered
10M Already installed / for recovery 10M
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 13
ICT724607
INFORMATION SHEET # 2
AERIAL (CABLES)
OLD DESCRIPTION NEW
N/A
N/A Stumps outside the joint (Aerial) (cable-pair 10X 0.4 30 S
N/A count indicated) 100X 0.4
N/A Proposed stumps-30 pairs to be short at the far 70x0.4(10)FSF
N/A end testing purposes.
N/A
Stumps within the joint (Aerial) (cable-pair 10X 0.4
count indicated) 89-1994 (underground) 30 S
(cable pair count indicated) 70x0.4(10)FSF 100X 0.4
Existing stumps-30 pairs to be short within the
splice for testing purposes.
Proposed stumps within the joint 10X 0.4 10x0.4
(underground) (cable pair count indicated) 20x0.4 100X 0.4
Proposed stumps-10 pairs to be short within 70x0.4(10)FSF
the splice for testing purposes.
Existing stumps within the joint 10X 0.4 10x0.4
(Underground) (cable pair count indicated) 20x0.4
100X 0.4
Existing stumps-10 pairs to be short within the70x0.4(10)FSF
splice for testing purposes.
Proposed aerial cable on wall (cable pair
count indicated)
Foam skinned filled aerial. 50 x 0.4 FSF (wall)
Existing aerial cable on wall (cable pair 50 x 0.4 PIC (wall)
count indicated)
Plastic insulated cable.
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 14
ICT724607
INFORMATION SHEET # 2
OLD DESCRIPTION NEW
N/A Proposed aerial cable to be installed on
Fieldside (cable pair count indicated) 50 x 0.4 FSF
N/A x
100 pairs 0.4 mm gauge proposed aerial FSF FS
CABLE (cable pair count indicated)
100 x 0.4 FSF
200 pairs 0.4 mm gauge existing aerial PIC
N/A CABLE (cable pair count indicated) 200 x 0.4 PIC
200 pairs 0.4 mm gauge proposed aerial 200 x 0.4 FSF
N/A FSF
CABLE (cable pair count indicated)
400 pairs 0.4 mm gauge existing
N/A underground PIC CABLE (cable pair count 200 x 0.4 PIC
indicated)
50 pairs 0.4 mm gauge aerial cable to be 50 x 0.4
N/A recovered (cable pair count indicated)
Cable splice joint on proposed cable (cable
N/A Pair count indicated)
70x0.4 4(10)FSF 100 x 0.4
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 15
ICT724607
INFORMATION SHEET # 2
OLD DESCRIPTION NEW
N/A
101-24 / Cable Block N/A
Cable plugging blocking (/) N/A
701-24 Y Pressure Testing Valve x 1x01-24 x x x x
Cable pressure valve for testing (Y)
51-26
101-24 Loading Coil
An amplification cable equipment usually N/A
x 1x01-24 x x x x useful for trunking cable ( ∆)
51-24
Cable to be removed
Cable for removal & recovery (x) N/A
N/A
Cable to be cut
Cut cable (//)
51-26
51-24 Re-splicing Cable Terminal
16 T-21
A(1-16) (Change Count A1-16 to A6-21)
6-21
51-24 Cable Bond and Ground
A cable with existing bonding & grounding
51-24—51-224 Existing cable showing straight splice
Same size and gauge
51-24 Cable of different Size and Gauge with
26-1.9 Spliced at Mid-Span
(Sub-standard procedure)
Proposed bond and ground
Bonding and grounding to be installed
Existing bond and ground
Bonding and grounding already installed
Proposed bond
Bonding and grounding to be installed
Existing bond utilizing existing ground
Bonding already installed with bonding
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 16
ICT724607
INFORMATION SHEET # 2
OLD UNDERGROUND NEW
CC (MANHOLES & CONDUIT) 35’-4
PT#1000
DESCRIPTION
Existing PLDT pole (concrete) to be CC
recovered
Already installed MH1
TYPE SRH 4
Proposed manhole (number and type
indicated) MH 1234
Already installed prefabricated type TYPE J4C
Existing manhole (number and type SB#1
indicated)
Already installed prefabricated type SB#1
Proposed service box (number indicated) HH
To be installed between a manhole and panel
box of a building used for sewing entrance HH
cable.
Existing service box (number indicated)
Already existing between a manhole and panel
box of a building used for sewing entrance
cable.
Proposed handhole
To be installed smaller than manhole more like
a service box used for emergency testing point
purposes
Existing handhole
Already installed
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 17
ICT724607
INFORMATION SHEET # 2
OLD DESCRIPTION NEW
Proposed conduit route number of PVC
4R conduit, length indicated 4PCV
4R To be installed 100.0M
4R 4PCV
4R Existing conduit route number of conduit, 100.0M
type and length indicated 4R
N/A Already installed
4R
Proposed lateral conduits toward pole
(no. of conduit indicated) 4R
A conduit to be installed within the ground
towards pole (4R) four conduits. 4R
Existing lateral conduits toward pole
(no. of conduit indicated)
A conduit already installed within the ground
towards pole (4R) four conduits.
Proposed lateral conduits toward wall
(no. of conduit indicated)
A conduit to be installed within the ground
towards pole (4R) four conduits.
Existing lateral conduits toward wall
(no. of conduit indicated)
A conduit already installed within the ground
towards pole (4R) four conduits.
Existing three (3) subducts inside 100mm
Diameter main duct
Already installed
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 18
ICT724607
INFORMATION SHEET # 2
UNDERGROUND
(CABLE SPLICES)
OLD DESCRIPTION NEW
N/A Proposed underground cable showing the
N/A following: 400 x 0.4 (50)(89)
400 pairs 0.4 mm gauge 50 dead pairs to be
N/A implemented in 1989 400 x 0.4 (50)(89) DEF
N/A
Proposed underground cable showing the 200
N/A following: 400
N/A 400 pairs 0.4 mm gauge 50 dead pairs to be
implemented between 1989-1994 within 5 200
years when development are completed 400
Initial Primary Pairs
This is the number of feeder cable pairs to be
installed during the first year of project
implementation.
Ultimate Primary Pairs
Ultimate Secondary Pairs
The number above of feeder cable pairs and
below is the number of cable pairs on the
secondary on ultimate.
Filled subjects
Already installed with 3 conduit pipes
Proposed subducts and proposed one (1)
fiber optic cable inside 100 mm diameter
main duct
To be installed
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 19
ICT724607
INFORMATION SHEET # 2
OLD DESCRIPTION NEW
N/A Proposed fiber optic cable
To be installed – a cable which is made of XXX
N/A silica glass and uses light wave as a medium of
transmission
N/A
N/A Existing fiber optic cable
Already installed – a cable which is made of
silica glass and uses light wave as a medium of
transmission
Existing fiber optic cable to be recovered
Already installed / for recovery
Proposed fiber optic splice
To be splice (fusion)
Existing fiber cable splice
N/A Already splice
Fiber optic cable no./8 fiber with fibers 1 &
N/A 2 working and fiber 3 to 8 spare for Makati F.O. CA. 1/8 F (1-2)+S(3-
8)
to Sampaloc route 1
MKT. SPC ROUTE 1
Already installed
Proposed duct assignment
N/A To be installed cable duct
Duct – a hole for passage of conduit pipe.
Filled duct
N/A Already installed cable duct with conduit pipe.
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 20
ICT724607
INFORMATION SHEET # 2
OLD DESCRIPTION NEW
N/A Subscriber pole
Creosoted or concrete pole used for subscriber S
access.
Existing loading coil
To be installed Loading coil
(amplifications equipment) usually installed
for trunking cable.
Proposed loading coil
To be installed Loading coil
(amplification equipment) usually installed for
trunking cable.
Existing loading coil to be recovered
Already installed for recover.
Existing build-out capacitor (BOC)
Already installed an amplification sub-
equipment for loading coils.
Proposed build-out capacitor (BOC)
To be installed an amplification sub-equipment
for loading coils.
Existing build-out capacitor (BOC)
Already installed an amplification sub-
equipment for loading coils.
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 21
ICT724607
INFORMATION SHEET # 2
OLD DESCRIPTION NEW
River
Ravine or Cliff
Canal or Ditch
QCUAELZOOONCACNITY Boundary mark QCUAELZOOONCACNITY
aerial limits Exchange Boundary aerial limits
Represent central office or exchange area
N/A limits
Cabinet Boundary
N/A Represent cross connect cabinet area limits.
Distribution Point Boundary
N/A Represents cable terminal or distribution point
area limits.
Block Boundary
N/A Represents block area limits.
Zone Boundary
N/A Represents block area limits.
Study Area
N/A Represent Area of project.
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 22
ICT724607
INFORMATION SHEET # 2
OLD DESCRIPTION NEW
Central office or Exchange Building
Recharge office
Indoor Cabinet Cross Connect Deferred
N/A This is a cross connect cabinet installed indoor
which is not yet for used.
Outdoor Cabinet Cross Connect Deferred
N/A This is a cross connect cabinet installed indoor
which is not yet for used.
Proposed Outdoor Cross Connect Cabinet
N/A An outdoor cross connect cabinet to be
installed.
Existing Outdoor Cross Connect Cabinet
N/A An outdoor cross connect cabinet already
installed.
Existing Outdoor Cross Connect Cabinet To
N/A Be Recovered
This is an outdoor cross connect Cabinet
already installed and for recovery.
Proposed 20 pairs internal distribution
N/A point (DP)
To be installed indoor terminal
Existing 20 pairs internal distribution point
N/A (DP)
Already installed indoor terminal
Existing 20 pairs internal distribution point
N/A (DP) to be recovered
Already installed indoor terminal
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 23
ICT724607
INFORMATION SHEET # 2
Outside Plant Cable Types
According To Usage & Installation
Aerial CA
Switch Board
Stub
U.G.
IOT
Buried
Exchange CA. CA. Vault
Distribution
Feeder
Terminating
COMMUNICATION CABLE
Are small copper wires, properly insulated, twisted together placed in a casing to provide
communication channels.
1. AERIAL CABLE
Cable suspended in the air usually in utility poles.
2. BURIED CABLES
A cable that is buried directly in the ground without being placed in under ground conduits.
3. DISTRIBUTION CABLE
A cable used for distribution of telephone service to subscribers.
4. EXCHANGE CABLE
Used to provide service in the local area around an exchange.
5. STUB CABLE
A short length of cable attached at the factory to a set of terminal block, loading coil case,
and other apparatus.
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 24
ICT724607
INFORMATION SHEET # 2
6. SWITCHBOARD CABLE
Used for connection central office equipments.
7. TERMINATING CABLE
A multi-paired cable usually with thin conductors and always with fire resistant insulator
that is used primarily between the cable vault and the main distribution frames.
8. TRUNKING CABLE
Used to connect or link central offices.
CABLE TYPES
ACCORDING TO CONDUCTOR INSULATION
1. PAPER INSULATED CABLE
Cable in which the conductors are insulated with paper ribbon either spirally or
longitudinally applied.
2. PLASTIC INSULATED CABLE
Cable wherein the conductors are insulated with plastic.
3. FOAM SKIN INSULATED CABLE
A cable is which the conductors are insulated directly with foam skin
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 25
ICT724607
INFORMATION SHEET # 2
ACCORDING TO SHEATH CONSTRUCTION
A. ALPETH CABLE – Aluminum Polyethylene
1. MECHANICAL CHARACTERISTICS:
a. Heavy Molecular Weight black polyethylene, heath resistant for the thermosetting.
b. Mylar Tape
Provides die-electric materials and placed over the core in a half-lapped manner,
the purpose of which is to hold the core firmly to prevent disarrangement.
c. Corrugated Aluminum
0.08 thick, flexible during cable formation and serves as primary ground.
d. Cable Core
Color Coded conductors for identification proposes.
e. Twisted Pairs
To eliminate Crosstalk and to maintain pairing.
f. Allowable moisture contents of air introduced to the core is 2% maximum.
2. Electrical Characteristics:
a. Insulation Resistance
1,000 megaohm-mile.
b. Capacitance per Mile
0.083 microfarad
c. Resistance Unbalance of the pair
± 10%
d. Breaking Voltage
10,000 VDC/10 secs.
e. Gauges
19, 22, 24, & 26 awg
f. Sizes
6, 11, 16, 26, 51, 101, 202, 303, 404, 606, 909, 1111, 1212, 1515, & 1818 pairs.
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 26
ICT724607
INFORMATION SHEET # 2
POLYETHELENE ALUMINUM MYLAR TAPE CABLE CORE
B. JELLY FILLED CABLE
1. Sheath and Core composition is identical to Alpeth Cable
2. Difference between Alpeth and Jelly Filled cable
Jelly is forced or injected to the core purposely to prevent moisture entrance.
C. STALPETH CABLE
1. Mechanical Characteristics:
a. Heavy molecular weight black Polyethylene flooded with black compound to
achieve adhesion between the sheath and the corrugated steel tape or ternaplate
serving as dual mechanical sheath.
b. Paper Core Wrap
Dielectric separator between electrical sheath and conductors.
c. Corrugated Aluminum
Primary electrical sheath lay under and in parallel with the corrugated steel to
achieve maximum resistance of electrical sheath.
d. Corrugated Steel Ternaplate
Secondary electrical sheath.
e. Cable Core
Insulated with paper applied spirally or longitudinally
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 27
ICT724607
INFORMATION SHEET # 2
2. Electrical Characteristics:
a. Insulation Resistance
500 megaohm-mile
b. Capacitance per mile
0.83 microfarad
c. Resistance unbalance of the pair
± 10%
d. Gauges
22, 24, & 26 awg
e. Sizes
1111, 1212, 1515, 1818, 2121, 2727, 3030, & 3636 pairs
POLYETHELENE STEEL ALUMINUM PAPER WRAP CABLE CORE
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 28
ICT724607
--------Blank page-----
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 29
ICT724607
OPERATION SHEET
PURPOSE: • Is to prepare the required tools, materials and equipment
prior to installation.
• To install pole hardware, cable terminal, line wire and
accessories
PROCEDURE: 1. Arrange tools, materials and equipment needed..
PRECAUTIONS: 2. Extend ladder to pole.as per manufactures specifications
and techniques.
3. Wear safety gadgets to prevent accident
4. Ascend and descend on pole with care
5. Sheath opening of main cable
6. Bonding and grounding are installed per outside plant
standards
7. Loop and bends are made to ensure standards are
followed.
1. Practice placement or installation of collapsible sign to
prevent accident.
2. For body belt and safety traps, look for the following
defects:
A. Leather cracks, cut tears, broken stitches and
loose rivets.
B. Defective buckles, snap hooks, keepers and d-ring.
Should there be any defect, correct them before
using the equipments.
C. If the defect can be corrected change the
equipment into new ones.
QUALITY CRITERIA: 1. Extended ladder should be properly in placed
2. Completeness of tools and materials are necessary
3. Proper usage of tools and materials must be
observed
4. Correct installation of main cable and groundings.
5. Measurements and supports are observed to
protect sagging.
.
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 30
ICT724607
----- blank page-------
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 31
ICT724607
JOB SHEET
Objective:
Upon completion of the job/task participants should be able to prepare and install
main cable
Materials, Tools and Equipment
1. Tabbing shears
2. Poly/lineman’s knife
3. Meter tape
4. Cable puncher
5. Wrench
6. Extension/manhole ladder
7. PPE
Instructions:
CABLE PREPARATION
1. Sheath Opening
Measure 12 inches opening and using a polyethylene knife cut the cable sheath
by ringing it on the marked portion, apply a little force in ringing until it reaches the
aluminum shield and be sure that the polyethylene knife does not touch the cable
core, do this on the other side of the cable.
Opening
12”
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 32
ICT724607
JOB SHEET
2. Choker Installation
Next in the installation of chocker to prevent from cutting or damaging the cable
core. Do this by applying an S.T. 22 x 1 sticky side up and sticky side down
manner around the mylar tape. Make a slit by using the tabbing shear at the end
of the opening for at least 1 ½ inches then inserting it in between the mylar tape
and aluminum shield, do this on the other side of the cable.
Slit Choker
1½
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 33
ICT724607
JOB SHEET
3. Bonding & Grounding
After the chocker has been installed on both sides, insert a yellow shoe of the
spring clip in between the cable sheath and the choker then the spring clip by
hammering both sides to hold it firmly. The purpose of this is to provide
continuous grounding of the telephone cable.
Spring Clip
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 34
ICT724607
JOB SHEET
4. Final Wrapping of Chocker
This is the final wrapping of choker including the spring clip by applying it with
S.T. 22 x 1. Wrap it until it reaches the slit portion to hold and tighten up the end
of the opening.
ST 22 x 1
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 35
ICT724607
JOB SHEET
5. Mylar Tape Removal:
Cut the mylar tape by an electrician scissor to expose the cable core. Do it slowly
and safely to avoid cutting the conductors, then remove the mylar tape. Again on
the other side, do this as safe as it was previously done
Mylar Tape
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 36
ICT724607
JOB SHEET
6. Securing Bunch End
Expose the end of the cable by pulling out the sheath then wrap the end with S.T.
22 x 1 to maintain the pairing and binding of each bunch. Then get all the end of
the cable and tighten it up with S.T. 22 x 1.
Bunch End Bunch End
Upon cable preparation, may now proceed to the next job….
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 37
ICT724607
SELF-CHECK
Directions:
ENUMERATE STEP BYSTEP CABLE PREPARATION
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 38
ICT724607
ANSWER KEY
1. SHEATH OPENING
2. CHOCKER INSTALLATION
3. BONDING AND GROUNDING
4. FINAL WRAPPING OF CHOCKER
5. MYLAR TAPE REMOVAL
6. SECURING BUNCH END
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 39
ICT724607
PERFORMANCE TEST
Learner's Name Date
Competency:
Test Attempt
1st 2nd 3rd
Directions: OVERALL EVALUATION
CALL INSTRUCTOR, ask Level PERFORMANCE LEVELS
instructor to assess your Achieved
performance in the
following critical task and 4 - Can perform this skill without supervision and with
performance criteria below initiative and adaptability to problem situations.
You will be rated based on 3 - Can perform this skill satisfactorily without
the overall evaluation on assistance or supervision.
the right side.
2 - Can perform this skill satisfactorily but requires
some assistance and/or supervision.
1 - Can perform parts of this skill satisfactorily, but
requires considerable assistance and/or supervision.
Instructor will initial level achieved.
PERFORMANCE STANDARDS
For acceptable achievement, all items should receive a "Yes" Yes No N/A
or "N/A" response.
Code No. Module Title – Performing Main Cable Installation Date: Developed Date: Revised Page #
Oct. 18, 2011 40
ICT724607