For Engineering, Procurement, Construction and Commissioning (EPCC) of
Telok Gong Loop Pipeline (TUAH) Project, Melaka
6th March 2019
TUAH Project Office, Simpang Ampat, Melaka
Main Contractor: Client:
No. 18 & 18-1, Persiaran Metro Sendayan 1, PETRONAS GAS BERHAD
Sendayan Metropark,
Bandar Sri Sendayan, 71950 Seremban, N. Sembilan Level 49, Tower 1, Petronas Twin Towers,
Phone : 06-7922154 / 06-7922451 Kuala Lumpur City Centre,
50088 Kuala Lumpur, Malaysia
Internal
Project
1 Briefing
Introduction to EPCC of Telok Gong
Loop Pipeline (TUAH) Project
Internal
The Engineering, Procurement, Construction and Commissioning (EPCC) of Telok
Gong Loop Pipeline Project (TUAH) has been awarded to Axianergy (M) Sdn Bhd
on 30 March 2018 by PETRONAS Gas Berhad (PGB)
Contract Mechanical Gas In Date: Initial
Duration: Completion: 1 January 2020 Acceptance:
25 months 9 December 2019 29 April 2020
Internal
The new NPS28 TUAH pipeline will be laid within 20m wide Right-Of-
Way, alongside the existing NPS18 Telok Gong Lateral pipeline
Internal Metering TOV Station TOV Station Block Valve Scraper Hot Tap
Station (KP 19) (KP 16) Station Launcher Station Station
The Telok Gong Loop Pipeline project will have 21 months from award to complete
the pipeline and its facilities installation in order to meet the critical Gas In date of
1 January 2020
Construction Survey Pre‐Commissioning
1 month 2 months
Melaka EPCC Award Site Preparation Mechanical Completion (MC)
1 month Commissioning
1 month
Line Pipes Delivery
Pipeline Construction Gas In Initial
13 months Acceptance (IA)
Station Construction
12 months
Mar Apr May Jul Aug Sept Sept Nov Dec Jan Apr
‘18 ‘18 ‘18 ‘18 ‘18 ‘18 ‘19 ‘19 ‘19 ‘20 ‘20
Jakarta Contractual
Gas In Date
Detailed Engineering
5 months Contractual
Mechanical Completion
21 months
25 months
Internal
Progress
2
Updates
Overall Project Activities
Internal
As of 20th February 2019, TUAH project has achieved progress
of 54.26% and is on track to meet its contractual Gas In Date on
1 Jan 2020
Actual: 54.26% vs Plan: 45.68%
Variance: +8.58%
Internal
Legend: Scraper Progress
Launcher Summary
Site Clearing
Stringing KP 1
Welding
Lowering KP 2
Backfill KP 3
KP 4
3 KP 5
KP 9 KP 8 KP 7 KP 6
KP 10
KP 11
KP 12 Activities Required Cumulative Balance %
KP 13 1. Clearing & Grading 22,000 Completed 732 100%
1,100 984 60%
GMS KP 16 KP 14 2. Stringing 1,832 850 1,091 46%
KP 17 KP 15 3. Welding 1,834 743 1,366 40%
4. NDT 1,834 468 16,149 25%
KP 18 5. FJC 1,834 5,851 16,149 26%
6. Holiday Test 22,000 5,851 16,149 26%
KP 19 7. Trenching 22,000 5,851 16,149 26%
5,851 26%
KP 20
8. Lowering 22,000
9. Backfilling 22,000
3 Gallery
Progress Video & Site Photos
Internal
Solat Hajat & Doa Selamat Site
Photos
CSR Badminton Game
CSR at JAPERUN Taboh Naning CSR Bowling Game
Internal
Training
Photos
AutoCAD CAESAR II
CSWIP Primavera
Site
Photos
Resistivity Test for CP Soil Investigation via SSPT & Bore Hole Method
Pegging & Demarcation at ROW Trial Hole Topographic Survey
Site
Photos
Pipe Received at Laydown Hot Bend Production Cold Bend Production
(Total: 1,852 pcs) Completed (Total: 6 pcs)
MPI/UT & Gauging Activity Pipe Coating for Hot Bend Hot Bend Received at Laydown
Site
Photos
Clearing and grading activity Stringing activity
Fit up activity Welding activity
Site
Photos
Field Joint Coating activity Trenching activity
Lowering activity Survey activity Backfilling activity
End of Presentation
Main Branch Address THANK YOU Website & Email
No. 18 & 18‐1, Persiaran Metro By Axianergy (M) Sdn. Bhd. www.axianergy.my