The words you are searching are inside this book. To get more targeted content, please make full-text search by clicking here.
Discover the best professional documents and content resources in AnyFlip Document Base.
Search
Published by Effa Eroza Esmawi, 2019-03-05 12:08:10

TUAH: Project Briefing and Status Update

Progress Update as of 20th Feb 2019

Management
Walkabout

For Engineering, Procurement, Construction and Commissioning (EPCC) of
Telok Gong Loop Pipeline (TUAH) Project, Melaka

6th March 2019
TUAH Project Office, Simpang Ampat, Melaka

Main Contractor: Client:

No. 18 & 18-1, Persiaran Metro Sendayan 1, PETRONAS GAS BERHAD
Sendayan Metropark,
Bandar Sri Sendayan, 71950 Seremban, N. Sembilan Level 49, Tower 1, Petronas Twin Towers,
Phone : 06-7922154 / 06-7922451 Kuala Lumpur City Centre,
50088 Kuala Lumpur, Malaysia

Internal

Project
1 Briefing

Introduction to EPCC of Telok Gong
Loop Pipeline (TUAH) Project

Internal

The Engineering, Procurement, Construction and Commissioning (EPCC) of Telok
Gong Loop Pipeline Project (TUAH) has been awarded to Axianergy (M) Sdn Bhd
on 30 March 2018 by PETRONAS Gas Berhad (PGB)

Contract  Mechanical  Gas In Date:  Initial 
Duration:  Completion: 1 January 2020 Acceptance:

25 months 9 December 2019 29 April 2020

Internal

The new NPS28 TUAH pipeline will be laid within 20m wide Right-Of-
Way, alongside the existing NPS18 Telok Gong Lateral pipeline

Internal Metering  TOV Station  TOV Station Block Valve  Scraper  Hot Tap 
Station (KP 19) (KP 16) Station Launcher Station Station

The Telok Gong Loop Pipeline project will have 21 months from award to complete
the pipeline and its facilities installation in order to meet the critical Gas In date of
1 January 2020

Construction Survey Pre‐Commissioning
1 month 2 months

Melaka EPCC Award Site Preparation Mechanical Completion (MC)
1 month Commissioning
1 month
Line Pipes Delivery
Pipeline Construction  Gas In Initial
13 months Acceptance (IA)

Station Construction 
12 months

Mar  Apr  May  Jul  Aug  Sept  Sept  Nov  Dec  Jan  Apr 
‘18 ‘18 ‘18 ‘18 ‘18 ‘18 ‘19 ‘19 ‘19 ‘20 ‘20

Jakarta Contractual 
Gas In Date
Detailed Engineering
5 months Contractual 
Mechanical Completion

21 months
25 months

Internal

Progress

2

Updates

Overall Project Activities

Internal

As of 20th February 2019, TUAH project has achieved progress
of 54.26% and is on track to meet its contractual Gas In Date on
1 Jan 2020

Actual: 54.26% vs Plan: 45.68% 
Variance: +8.58%

Internal

Legend: Scraper  Progress
Launcher Summary
Site Clearing
Stringing KP 1
Welding
Lowering KP 2
Backfill KP 3

KP 4

3 KP 5

KP 9 KP 8 KP 7 KP 6

KP 10

KP 11

KP 12 Activities Required Cumulative Balance %

KP 13 1. Clearing & Grading 22,000 Completed  732 100%
1,100 984 60%
GMS KP 16 KP 14 2. Stringing 1,832 850 1,091 46%
KP 17 KP 15 3. Welding 1,834 743 1,366 40%
4. NDT 1,834 468 16,149 25%
KP 18 5. FJC 1,834 5,851 16,149 26%
6. Holiday Test 22,000 5,851 16,149 26%
KP 19 7. Trenching 22,000 5,851 16,149 26%
5,851 26%
KP 20

8. Lowering 22,000

9. Backfilling 22,000

3 Gallery

Progress Video & Site Photos

Internal

Solat Hajat & Doa Selamat Site
Photos

CSR Badminton Game

CSR at JAPERUN Taboh Naning CSR Bowling Game

Internal

Training
Photos

AutoCAD CAESAR II
CSWIP Primavera

Site
Photos

Resistivity Test for CP Soil Investigation via SSPT & Bore Hole Method 

Pegging & Demarcation at ROW Trial Hole Topographic Survey

Site
Photos

Pipe Received at Laydown  Hot Bend Production  Cold Bend Production
(Total: 1,852 pcs) Completed (Total: 6 pcs)

MPI/UT & Gauging Activity Pipe Coating for Hot Bend Hot Bend Received at Laydown

Site
Photos

Clearing and grading activity Stringing activity

Fit up activity Welding activity

Site
Photos

Field Joint Coating activity Trenching activity

Lowering activity Survey activity Backfilling activity

End of Presentation

Main Branch Address THANK YOU Website & Email

No. 18 & 18‐1, Persiaran Metro  By Axianergy (M) Sdn. Bhd. www.axianergy.my
Sendayan 1, Sendayan Metro Park,  [email protected]
71950 Bandar Seri Sendayan, Seremban,  Phone & Fax

Negeri Sembilan Office Line: +6067922154
Fax: +6067922451


Click to View FlipBook Version